Forwards IE Insp Repts 50-335/80-23 & 50-389/80-09 on 800715-18. No Noncompliance Noted
ML17208B012
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 08/05/1980
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
Shared Package
ML17208B014 List:
References
NUDOCS 8009240066
Download: ML17208B012 (3)


See also: IR 05000335/1980023

Text

gA~ REGS

P0

Cy

C

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I I

101 MARIETTAST., N.W., SUITE 3100

ATLANTA,GEORGIA 30303

AUG -5 1980

In Re

1

Refer To:

PKV

50-335/80-23

50"389/80"0

Florida Power and Light Company

ATTN:

R. E. Uhrig, Vice President

Advanced Systems

and Technology

=. P. 0., Box 529100

'iami, FL

33152

Gentlemen:

This refers

to the

inspection

conducted

by P. K. VanDoorn of thi's office on

July 15-18,

1980, of activities authorized

by NRC Operating License

No. DPR-67

and

Construction

Permit

No.

CPPR-144 for the St. Lucie facility, and to the

discussion

of our findings held with B. J.

Escue

at the

conclusion of the

inspection.

Areas

examined

during the inspection

and

our findings

are

discussed

in the

enclosed

inspection

report.

Within these

areas,

the inspection

consisted

of

selective

examinations

of procedures

and representative

records,

interviews with

personnel,

and observations

by the inspector.

Within the scope of this inspection,

no items of noncompliance

were disclosed.

Two new unresolved

items resulted

from this inspection

and are discussed

in the

enclosed report.

These items willbe examined during subsequent

inspections.

In accordance

with Section 2.790 of the

NRC's

"Rules of Practice",

Part 2,

Title l0,

Code of Federal

Regulations,

a

copy of this letter and the enclosed

inspection report will be placed in the

NRC's Public Document

Room. If this

report

contains

any information that you (or your contractor)

believe to be

proprietary, it is necessary

that you make

a written application within 20 days

to this office to withhold such information from public disclosure.

Any such

application must include

a full statement

of the reasons

on the basis of which

it is claimed that the information is proprietary,

and

should

be prepared

so

that proprietary information identified in the application is contained in a

separate

part of the document. If we do not, hear from you in this regard within

the specified period, the report willbe placed in the Public Document Room.

Should you have any questions

concerning this letter,

we will be glad to discuss

them with you.

Sincerely,

C. E. Murph

, Chief

Reactor Construction

and Engineering

Support Branch

Enclosure:

(See

Page

2)

80002g0

.,C'g

0

h

V

Florida Power and Light Company

RUG "5 1980

Enclosure:

Inspection Report Nos. 50-335/80-23

and 50-389/80-09

cc w/encl:

C.

M. Wethy, Plant Manager

Nat Weems, Assistant

QA Manager