Forwards IE Insp Repts 50-335/79-27 & 50-389/79-17 on 791002-04.No Noncompliance Noted
ML17207A619
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 10/22/1979
From: Sutherland J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Uhrig J
FLORIDA POWER & LIGHT CO.
Shared Package
ML17207A620 List:
References
NUDOCS 7912100260
Download: ML17207A619 (3)


See also: IR 05000335/1979027

Text

~8 REoy

"o

Cy

A0O

I

Cy

~O

++*a+

In Reply Refer To:

RII:WWP

50-335/79-27

50-389/79-17

UNITEDSTATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100

ATLANTA,GEORGIA 30303

OCT 8 2 1979

Florida Power and Light Company

Attn:

R. E. Uhrig, Vice President

Advanced

Systems

and Technology

Post Office Box 529100

Miami, Florida

33152

Gentlemen:

This refers to the inspection

conducted

by W.

W. Peery of this office on

October 2-4,

1979 of activities authorized

by NRC License

No. DPR-67 for the St.

~

~

tucie facility, and to the discussion of our findings held with C.

M. Wethy at the

conclusion of the inspection.

Areas

examined during the inspection

and our findings are discussed

in the enclosed

inspection report.

Within these

areas,

the inspection consisted

of selective

examinations of procedures

and representative

records,

interviews with personnel,

and observations

by the inspector.

Within the scope of this inspection,

no items of noncompliance

were disclosed.

We have

examined actions you have taken with regard to previously identified

enforcement matters.

These

are discussed

in the enclosed

inspection report.

In accordance

with Section 2.790 of the NRC's "Rules of Practice", Part 2, Title 10,

Code of Federal Regulations,

a copy of this letter and the enclosed

inspection

report will be placed in the NRC's Public Document

Room. If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary

that you make

a written application within 20 days to this office to

withhold such information from public disclosure.

Any such application must include

a full statement

of the reasons

on the basis of .which it is claimed that the

information is proprietary,

and should be prepared

so that proprietary information

identified in the application is contained in a separate

part of the document.

If

we do not hear from you in this regard within the specified period,

the report will

be placed in the Public Document

Room.

~@0

V9 as1 00

Florida Power and Light Company

-2-

OCT 2 2 1979

Should you have any questions

concerning this letter,

we will be glad to discuss

them with you.

Sincerely,

J.

T. Sutherland,

Chief

Fuel Facility and Materials

Safety Branch

Enclosures:

Inspection Report Nos. 50-335/79-27

and 50-389/79-17

cc w/enclosures:

C.

M. Wethy, Plant Manager

Post Office Box 128

Ft. Pierce, Florida

33450

Nat Weems, Assistant

QA Manager

Post Office Box 128

Ft. Pierce, Florida