Text

In Reply Refer To:

RII:JJL

50"389/79-15

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100

ATLANTA,GEORGIA 30303

SEP 2 11979

Florida Power and Light Company

ATTN:

R. E. Uhrig, Vice President

Advanced Systems

and Technology

P. 0. Box 529100

Miami, FL

33152

Gentlemen:

This refers

to the inspection

conducted

by J. J.

Lenahan of this office on

September

5-6,

1979,

of activities authorized

by

NRC Construction

Permit No.

CPPR-144 for the St. Lucie facility, and to the discussion of our findings held

with B. J. Escue at the conclusion of the inspection.

Areas

examined

during the inspection

and

our findings

are

discussed

in the

~

~

enclosed

inspection

report.

Within these

areas,

the inspection

consisted

of

selective

examinations of procedures

and representative

records,

interviews with

personnel,

and observations

by the inspector.

Within the scope of this inspection,

no items of noncompliance

were disclosed.

t

We

have

examined

actions

you have

taken with regard

to previously reported

unresolved items.

The status of these items is discussed in the enclosed report.

In accordance

with Section 2.790 of the NRC's "Rules of Practice", Part 2, Title

10, Code of Federal Regulations,

a copy of this letter and the, enclosed inspection

report will be placed in the NRC's Public Document Room. If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary

that you make

a written application within 20 days to this office to

withhold such information from public disclosure.

Any such application must

include

a full statement of the reasons

on the basis of which it is claimed that

the information is proprietary,

and

should

be prepared

so that proprietary

information identified in the application is contained in a separate

part of the

document. If we do not hear from you in this regard within the specified period,

the report willbe placed in the Public Document Room.

>911 020~~

P, flI

Florida Power and Light Company

sv a >1979

Should you have any questions

concerning this letter,

we will be glad to discuss

them with you.

Sincerely,

C. E. Murphy, Chi

Reactor Constru tion and Engineering

Support Branch

Enclosure:

Inspection Report No. 50-389/79-15

cc w/encl:

C.

M. Wethy, Plant Manager

P. 0. Box 128

Ft. Pierce,

FL

33450

Nat Weems, Assistant

QA Manager

~

~

~

P. 0.

Box l28

Ft. Pierce,

FL

33450