Forwards IE Inspec Rept 50-335/78-21 on 780831-0901 During Which No Items of Noncompliance Were Noted
ML17206A499
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 09/28/1978
From: Sutherland J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
Shared Package
ML17206A498 List:
References
NUDOCS 7811030231
Download: ML17206A499 (3)


See also: IR 05000335/1978021

Text

~PR RfC0,

(4

+>>*<<+

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30303

SEP'8

1978

In Reply Refer To:

RII:GTG

50-335/78-21

Florida Power and Iight Company

Advanced

Systems

8 Technology

Attn:

Robert E. Uhrig, Vice,President

P. 0. Box 52910d

Miami, Florida

33152

Gentlemen:

This refers to the inspection

conducted

by Mr.

G. T. Gibson of this

office on August 31 - September

1,

1978, of activities authorized

by NRC

Operating License No. DPR-67 for the St. Lucie

1 facility, and to the

discussion of our findings held with Mr. C. Wethy at the conclusion of

the inspection.

Areas

examined during the inspection

and our findings are discussed

in

the enclosed

inspection report.

Within these

areas,

the inspection

consisted of selective

examinations of procedures

and representative

records,

interviews with personnel,

and observations

by the inspector.

Within the scope of this inspection,

no items of noncompliance

were

disclosed.

We have examined actions

you have taken with regard to previously

identified enforcement matters

and unresolved

items.

The status of.

these

items is discussed in the enclosed

report.

In accordance

with Section 2.790 of the NRC's "Rules of Practice",

Part 2, Title 10,

Code of Federal Regulations,

a copy of this letter and

the enclosed

inspection report vill be placed in the NRC's Public

Document Room. If this report contains

any information that you (or

your contractor) believe to be proprietary, it is necessary

that you

make

a written application within 20 days to this office to withhold

such information from public disclosure.

Any such application must

include

a full statement of the reasons

on the basis of which it is

claimed that the information is proprietary,

and should be prepared

so

that proprietary information identified in the application is contained

in a separate

part of the document.

If we do not hear from you in this

regard within the specified period,

the report will be placed in the

Public Document Room.

gE,P 28 1978

Florida Power and Light Co.

"2-

Should you have any questions

concerning this letter,

we will be

glad to discuss

them with you.

Sincerely,

J. T. Sutherland,

Chief

Fuel Facility and Materials

Safety Branch

Enclosure:

Inspection Report No.

50-335/78-21

cc w/encl:

Mr. C.

M. Methy, Plant Manager

St. Lucie Plant

P. 0.

Box 128

a t

Ft. Pierce, Florida

33450

Mr. Mat 1'ec-s, Assistant

QA Manager

P. 0.

Box 128

Ft. Pierce, Florida

33450