- 1 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 August 2, 1988 Docket Nos.:
50-237/249 50-254/265 Mr. Henry E. Bliss Nuclear Licensing Manager Commonwealth Edison Company P.O. Box 767 Chicago, Illinois 60609
Dear Mr. Bliss:
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION RELATED TO FLUED HEAD ASSESSMENT PROGRAM AT DRESDEN STATION UNITS 2 AND 3 AND QUAD CITIES STATION UNITS 1 AND 2 (TAC NOS. 66160, 66161, 66162, AND 66163)
References:
- 1.
Letter from I. M. Johnson to Thomas E. Murley on Flued Head Assessment Program, dated June 6, 1988.
- 2.
Letter from Kamal Banydypadhyay to P. T. Kuo on Flued Head Anchor Design, dated February 10, 1988.
- 3.
Letter from I. M. Johnson to Thomas E. Murley on Continued Operation Criteria for LPCI Piping, dated June 9, 1988.
Your response to concerns raised by the staff in a teleconference between Commonwealth Edison Company (CECo) and the staff on May 12, 1988, regarding the Dresden and Quad Cities Flued Head Assessment Program, was provided in Reference 1. These concerns were originally raised by members of Brookhaven National Laboratories {BNL) during a January 26-28, 1988 NRC audit of the program (Reference 2).
Our consultants at BNL have reviewed CECo's response contained in Reference 1 and found that some of the staff's concerns are still not satisfactorily resolved. This latest evaluation by BNL is sunmarized in the enclosure and requires an additional CECo response in order for the staff to complete its review.
Upon receipt of CECo's response the staff will conduct another audit of your program, particularly in the area of the calculations which were perfonned for the current reassessment.
The operability issue of the Dresden Unit 2 Low Pressure Core Injection (LPCI) piping is addressed in Reference 3. As you are aware, this issue is being reviewed together with the above flued head anchor program.
The corresponding calculations of the LPCI piping will also be audited with the rest of the program.
August 2, 1988 Henry It is requested that this infonnation be provided within 30 days of receipt of this letter.
The reporting and/or recordkeeping requirements continued in this letter affect fewer than ten respondents. therefore, OMB clearance is not required under
- p. L.96-511.
Enclosure:
As stated Sincerely, L":, ie l<oject Manager
~ject D rectorate 111-2 Division of Reactor Projects - III, IV, V and Special Projects l
/
- ~
Mr. Henry E. Bliss Conrnonwealth Edison Company cc:
Mr. Stephen E. Shelton Vf ce President Iowa-Illinois Gas and Electric Company P. 0. Box 4350 Davenport, Iowa 52808 Michael I. Miller, Esq.
Sidley and Austin One First National Plaza Chicago, Illinois 60603 Mr. Richard Bax Station Manager Quad Cities.Nuclear Power Station 22710 206th Avenue North Cordova, Illinois 61242 Resident Inspector U. S. Nuclear Regulatory Comnission 22712 206th Avenue North Cordova, Illinois 61242 Chainnan Rock Island County Board of Supervisors 1504 3rd Avenue Rock Island County Offfice Bldg.
R,ock Isldnd, Illinois 61201 Mr. Michael E. Parker, Chief Division of Engineering Illinois Department of Nuclear Safety 1035 Outer Park Drive, Springfield, Illinois 62704 Regional Administrator, Region III U. S. Nuclear Regulatory Conrnission 799 Roosevelt Road, Bldg*. #4 Glen Ellyn, Illinois 60137 Quad Cities Nuclear Power Station Units 1 and 2
4 "--
August 2, 1988 Henry It is requested that this information be provided within 30 days of receipt of this letter.
The reporting and/or recordkeeping requirements continued in this letter affect fewer than ten respondents, therefore, OMB clearance is not required under
- p. L.96-511.
Enclosure:
As stated Distribution:
r.Do-c:kets-**
NRC & Local PDRs PDIII-2 r/f BSiegel LLuther DMuller A. Lee J. Richardson G. Holahan T. Ross PDIII-2:PM BSiegel -~
1 /J.y/88,.,/
'/( /88 Sincere_ly, Byron Siegel, Project Manager Project Directorate III-2 Division of Reactor Projects - III, IV, V and Special Projects PDIII-2?£::~...RJPDIII-2:PD LLuther;,.Z:_]
~DMuller
?'/ / /8
.8 I 1.,/88
~ugust ~' l~
Henry It is requested that this information be provided within 30 days of receipt of this letter.
The reporting and/or recordkeeping requirements continued in this letter affect fewer than ten respondents, therefore, OMB clearance is not required under p.L.96-511.
Enclosure:
As stated Distribution:
Dockets NRC & local PDRs POI II-2 r/f BSiegel lluther DMuller A. lee J. Richardson G. Holahan T. Ross PDIII-2:PM BSiegel ~
1 /J!t'/88,-,/
. PDII I-2 :.PM TRossf/l..
, /( /88 Sincerely, Byron Siegel, Project Manager Project Directorate III-2 Division of Reactor Projects - III, IV, V and Special Projects PDIII-2f£.::~ ~PDIII-2:PD lluther,Z:....1 =.Ji!DMuller
?/I /8
. EI 1../88