Denies 830902 Request for Extension to Submit Formal Response to Generic Ltr 83-28 Re Salem ATWS Event.Info Must Be Submitted by 831105.Participation in Owners Group for Issues Requiring long-range Planning Acceptable
ML17194B749
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 10/26/1983
From: Crutchfield D
Office of Nuclear Reactor Regulation
To: Farrar D
COMMONWEALTH EDISON CO.
References
GL-83-28, LSO5-83-10-059, LSO5-83-10-59, NUDOCS 8310310052
Download: ML17194B749 (3)


Text

I,--

Docket Nos. 50-237/249 LS05.-83-10-059

/

Mr. Dennis L. Farrar Director of Nuclear Licensing Commonwealth Edison Company Post Office Box 767 Chicago, Illinois 60690

Dear Mr. Farrar:

October 26, 1983

SUBJECT:

CLARIFICATION OF REQUIRED ACTIONS BASED ON GENERIC IMPLICATIONS OF SALEM ATWS EVENTS (GENERIC LETTER 83-28)

Re:

Dresden Nuclear Power Station~ Unit Nos. 2* and 3 The staff is {n *receipt bf your letter dated September 2, 1983 regarding a request for extension of time to submit your formal, 120 day, response to Generic Letter 83-28.

We understand that your participation with an owners group, INPO or other industry group will require additional time to fully complete your.planning and scheduling of activities as requested in GL 83-28.

  • However, to allow the staff to plan reviews and ensure timely implementation, we believe a gene*ral.overall status regarding the industry posture is warranted and therefore we are not granting your request for an extension.

We therefo~e, reques~ t~at you submit the infqrmation requested, to the

  • extent practical, by November 5, 1983.

Where commitments and schedules for final implementation are*possible they should be provided.

Where additfonal planning is need.ed, before *the final implementation schedules can be established, you should prdvide a description of your plans and schedules for developing -t_he program in question.

The Salem*ATWS Events have-far reaching safety implications.

For those

~issues requiring long range planning we believe that your participation with an owners group, INPO or other industry group is desirable and commendable, however, it is important that the staff be able to assess the status of the industry response regarding the implementation of the required actions, as sobn BS possible.

8310310052 831026 PDR ADOCK 05000237 p

PDR OS'->

SEO/

use ~e.

Ila

Mr. Dennis October 26, 1983 This request for information was previously approved by the Office of Management and Budget under clearance number 3150-0011 which expires April 30, 1985.

cc:

See next page DISTRIBUTION Docket File NRC PDR Local PDR NSIC ORB #5 Reading DCrutchfield HSmith RGilbert OELD ELJordan JMTaylor-ACRS (10)

DL:~#5 RGiYB~~:cc

/ol~tf./83 DL:~Jlr:;

Dcr?It1'h'f.ie 1 d

p!U/83 Sincerely, Original signed by Dennis M. Crutchfield, Chief Operating Reactors Branch #5 Division of Licensing

Mr. Denni':S L. Farrar

.) -

cc Isham, Lincoln & Beale Counselors at Law One First National Plaza, 42nd Floor Chicago~ Illinois 60603 Mr. Doug**-Scott Plant Superintendent Rural Route #1 Morris, Illinois 60450 U. S. Nuclear Regulatory Corranission Resident Inspectors Office Dresden Sta ti on RR #1 Morrisr lllinois 60450 Chainnan Board of Supervisors of Grundy County Grundy County Courthouse Morris, Illinois 60450

u. S. Environmental Protection Agency Federal Activities Branch
  • Region V Office ATTN:

Regional Radiation Representative

'230 South Dearborn Street Chicago, Illinois 60604 James G. Keppler, Regional Administrator Nuclear Regulatory ColTITlission, Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 Mr. Gary N. Wright, Manager Nuclear Facility Safety Illinois Department of Nuclear Safety 1035 Outer Park Drive, 5th Floor Springfield~ Illinois 62704 October 26, 1983