ML17191A896
| ML17191A896 | |
| Person / Time | |
|---|---|
| Site: | Dresden |
| Issue date: | 09/24/1998 |
| From: | Grant G NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Kingsley O COMMONWEALTH EDISON CO. |
| Shared Package | |
| ML17191A898 | List: |
| References | |
| 50-237-98-21, 50-249-98-21, NUDOCS 9810020051 | |
| Download: ML17191A896 (5) | |
See also: IR 05000237/1998021
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION Ill
Mr. Oliver D. Kingsley
President, Nuclear Generation Group
Commonwealth Edison Company
ATTN: Regulatory Services
. Executive Towers West Ill
1400 Opus Place, Suite 500
Downers Grove, IL 60515 *
Dear Mr. Kingsley:
801 WARRENVILLE ROAD
LISLE, ILLINOIS 60532-4351
Septem~er 24, 1998
SUBJECT:
DRESDEN INSPECTION REPORT 50-237/98021(DRP); 50-249/98021(DRP)
Dear Mr. Kingsley:
On July 14, 1998, through August 25, 1998, the NRC performed an inspection at your Dresden
Nuclear Power Station. The enclosed report presents the results of this inspection.
During the inspection per-iod, a safety-conscious approach characterized the overall conduct of
- activities at the Dresden station ... However, several issues showed that challenges to smooth
operation remained at the station.
Twice during this inspection period, operators failed to recognize conditions that required entry
into Technical Specification Limiting Conditions for Operation (LCOs). These failures
represented an emerging negative trend in operator performance, first documented in our prior
Inspection Report (50-237/98019; 50-249/98019). *These failures were of concern because
they represented a breakdown In the fundamental expectation that operators be able to
correctly maneuver through the Technical Specifications as conditions warrant. In our prior
'(,
report, we documented examples where although the operators failed to recognize entry into a
particular Technical Specification, the requirements themselves were not violated. However,
. during this inspection period, one of the failures to recognize an entry condition directly
... resulted in a failure to comply with the requirements of the Technical Specification.
Based on the results of this Inspection, the NRC has determined that violations of NRC
requirements occurred. These violations are cited in the enclosed Notice of Violation (Notice)
- and the circumstances surrounding them are described in detail in the subject inspection
report.
The first violation is of concern because it represents a continuing trend of operators failing* to
recognize and manage Technical Specifieations and LCOs. *Our previous inspection report,
issued August 7, 1998, treated this issue as a noncited violation because we understood that
the Dresden staff had Identified the Issue and had developed corrective actions to prevent
further occurrences. On August 6, 1998, the first of the two examples of operators not
recognizing Technical Specification LCOs occurred. At this point, we had not yet issued the
inspection report documenting the noncited violation and your corrective actions may not have
9810020051 980924
ADOCK 05000237
8
-,-
..
~**
0. Kingsley
-2-
been in place for sufficient time to be fully effective. Therefore, the NRC is refraining from
issuing a violation in this case. However, the problem of operator recognition and
management of Technical Specification LCOs caused the failure to comply with Technical
Specifications on August 21, 1998. In addition to addressing the violation of Technical
Specifications, your response to this violation should address why your corrective actions did
not prevent the events of August 6 and 21, 1998, and the larger issue of operator recognition
and management of Technical Specifications and LCOs.
The second violation is of concern because it resulted in an unexpected half scram, disabled a
protective system input, and was not prevented by your independent verification practices. We
are also concerned with the potential generic aspects of this issue. We recognize that your
staff identified the potential generic independent verification concerns prior to NRC
identification of the specific example cited in the enclosed report. However, this violation is
being cited consistent with NRC Enforcement Policy (NUREG 1600) which states that licensee
identification credit is not warranted when a .licensee identifies a violation as a result of an
event where the root cause of the event is obvious. In addition, the inspectors concluded your
investigation of the event was inadequate and initial corrective actions defaulted to the easy fix
of coaching individuals. Subsequent corrective actions were considered acceptable. The
NRC has concluded that information regarding the reason for this violation and the corrective
actions taken and planned to correct the violation and prevent recurrence is already
adequately addressed on the docket in this inspection report. Therefore, you are not required
to respond to this violation unless the description the.rein does not accurately reflect your
corrective actions or your position. In that case, or if you choose to provide additional
information, you should follow the instructions in the enclosed Notice.
Your are required to respond to this letter and should follow the instructions specified in the .
enclosed Notice when preparing your response. In accordance with 10 CFR 2. 790 of the
NRC's "Rules of Practice," a copy of this letter, the enclosures, and your response will be
placed in the NRC Public Document Room.
Docket Nos.: 50-237; 50-249
Enclosures:
1.
Sincerely,
- ~ ?. J
GJ~Y k ~ire
1
- ~
Division of Reactor Proj~
2.
Inspection Report 50-237/98021(DRP);
50-249/98021 (DRP)
See Attached Distribution
0. Kingsley
-2-
been in place for sufficient time to be fully effective. Therefore, the NRC is refraining from
issuing a violation in this case. However, the problem of operator recognition and
management of Technical Specification LCOs caused the failure to comply with Technical
Specifications on August 21, 1998. In addition to addressing the violation of Technical
Specifications, your response to this violation should address why your corrective actions did
not prevent the events of August 6 and 21, 1998, and the larger issue of operator recognition
and management of Technical Specifications and LCOs.
The second violation is of concern because it resulted in an unexpected half scram, disabled a
protective system input, and was not prevented by your independent verification practices. we*
are also concerned with the potential generic aspects of this issue. We recognize that your
staff identified the potential generic independent verification concerns prior to NRC
identification of the specific example cited in the enclosed report. However, this violation is
being cited consistent with NRC Enforcement Policy (NUREG 1600) which states that licensee
identification credit is not warranted when a licensee identifies a violation as a result of an
event where the root cause of the event is obvious. In addition, the inspectors concluded your
investigation of the event was inadequate and initial corrective actions defaulted to the .easy fix
of coaching individuals. Subsequent corrective actions were considered acceptable. The
NRC has concluded that information regarding the reason for this violation and the corrective
actions taken and planned to correct the violation and prevent recurrence is already
adequately addressed on the docket in this inspection report. Therefore, you are not required
to respond to this violation unless the description therein does not accurately reflect your
corrective actions or your position. In that case, or if you choose to provide additional
information, you should follow the instructions in the enclosed Notice.
Your are required to re~pond to this letter and should follow the instructions specified in the
enclosed Notice when preparing your response. In accordance with 10 CFR 2.790 of the.
NRC's "Rules of Practice," a copy of this letter, the enclosures, and your response will be
placed in the NRC Public Document Room.
Docket Nos.: 50-237; 50-249
Enclosures:
1.
Sincerely,
/sf Geoffrey E. Grant
Geoffrey E. Grant, Director
Division of Reactor Projects
2.
Inspection Report 50-237/98021(DRP);
50-249/98021 (DRP)
See Attached Distribution
See Previous Concurrences
DOCUMENT NAME: G:\\DRES\\DRE98021.DRP
To receive a copy of this document, Indicate In the box "C" = Copy without attachment/enclosure "E" = Copy with attechment/enclo1ure
"N" = No co
OFFICE
Riii
Riii
Riii
Riii
NAME
RLerch:co
MRin
Cla
on/Heller
DATE
09/ /98
09/ /98
09/ /98
OFFICIAL RECORD COPY
0. Kingsley
-2-
been in place for sufficient time to be fully effective. Therefore, the NRC is refraining from
issuing a violation in this case. However, the problem of operator recognition and
management of Technical Specification LCOs continued and manifested itself in the failure to
comply with Technical Specifications on August 21, 1998. In addition to addressing the
violation of Technical Specifications, your response to this violation should address the failure
of your corrective actions to prevent the events of August 6 and 21, 1998, and the larger issue
of operator recognition and management of Technical Specifications and LCOs.
The second violation is of concern because it resulted in an unexpected half scram, disabled a
protective system input, and was not prevented by your independent verification practices. We
are also concerned with the potential generic aspects of this issue. We recognize that your
staff identified the potential generic independent verification concerns prior to NRC
identification of the specific example cited in the enclosed report. However, this violation is
being cited consistent with NRC Enforcement Policy (NUREG 1600) which states that licensee
identification credit is not warranted when a licensee identifies a violation as a result of an
event where the root cause of the event is obvious. In addition, the inspectors concluded your
investigation of the event was inadequate and initial corrective actions defaulted to the easy fix
of coaching individuals. Subsequent corrective actions were considered acceptable. The
NRC has concluded that information regarding the reason for this violation and the corrective
actions taken and planned to correct the violation and prevent recurrence is already
adequately addressed on the docket in this inspection report. Therefore, you are not required
to respond to this violation unless the description therein does not accurately reflect your
corrective actions or your position. In that case, or if you choose to provide additional
information, you should follow the instructions in the enclosed Notice.
Your are required to respond to this letter and should follow the instructions specified in the
enclosed Notice when preparing your response. In accordance with 10 CFR 2. 790 of the
NRC's "Rules of Practice," a copy of this letter, the enclosures, and your response will be
placed in the NRC Public Document Room.
Sincerely,
/s/ Geoffrey E. Grant
Geoffrey E. Grant, Director
Division of Reactor Projects
Docket Nos.: 50-237; 50-249
Enclosures:
1.
2.
Inspection Report 50-:237/98021(DRP);
50-249/98021 (DRP)
See Attached Distribution*
See Previous Concurrences
OOCUMENT NAME: G:\\DRES\\DRE98021.DRP
To receive 11 copy of this document, Indicate In the box *c* = Copy without attachment/enclosure *e* = Copy with attachment/enclosure
"N" = No co
OFFICE
Riii
(f Riii
NAME
DATE
OFFICIAL RECORD COPY
0. Kingsley
-3-
cc w/encls:
M. Wallace, Senior Vice President
D. Helwig, Senior Vice President
G. Stanley, PWR Vice President
J. Perry, BWR Vice President
Distribution:
SAR (E-Mail)
D. Farrar, Regulatory Services Manager
I. Johnson, Licensing Director
DCD - Licensing
M. Heffley, Site Vice President
P. Swafford, Station Manager
F. Spangenberg, Regulatory
Assurance Manager
R. Hubbard
N. Schloss, Economist
Office of the Attorney General
State Liaison Officer
Chairman, Illinois Cor:nmerce Commission
Project Mgr., NRR w/encls
J. Caldwell, Rill w/encls
C. Pederson, Rill w/encls
B. Clayton, Riii w/encls
- SRI Dresden w/encls
DRP w/encls
TSS w/encls
DRS (2) w/encls
Riii PRR w/encls
PUBLIC IE-01 w/encls
Docket File w/encls
GREENS
IEO (E-Mail)
DOCDESK (E-Mail)