ML17191A673

From kanterella
Jump to navigation Jump to search
Forwards Insp Rept 50-249/98-15 on 980409-17.No Violations Noted.Purpose of Insp,To Assess Info Re 980409 Inadvertent Closure of All Unit 3 Main Steam Isolation Valves & Subsequent Reactor Scram
ML17191A673
Person / Time
Site: Dresden Constellation icon.png
Issue date: 05/13/1998
From: Grant G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Kingsley O
COMMONWEALTH EDISON CO.
Shared Package
ML17191A674 List:
References
50-249-98-15, NUDOCS 9805270267
Download: ML17191A673 (3)


See also: IR 05000249/1998015

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION Ill

Mr. Oliver D. Kingsley

President, Nuclear Generation Group

Commonwealth Edison Company

ATTN: Regulatory Services

Executive Towers West Ill

1400 Opus Place, Suite 500

Downers Grove, IL 60515

801 WARRENVILLE ROAD

LISLE, ILLINOIS 60532-4351

May 13, 1998

SUBJECT:

NRC INSPECTION REPORT NO. 50-249/98015(DRP)

Dear Mr. Kingsley:

On April 17, 1998, a special inspection was completed at the Dresden Nuclear Power Station.

The purpose of the inspection was to assess information regarding the April 9, 1998, inadvertent

closure of all Unit 3 main steam isolation valves and the subsequent reactor scram. The

enclosed report presents the results of that inspection.

On April 9, 1998, Dresden Unit 3 experienced a full closure of all main steam isolation valves

(MSIVs) from full power which resulted in a reactor scram. Initially, the cause of the MSIV

closure was unknown. Dresden Station's Root Cause Analysis Team, established to evaluate

this event, concluded that the most probable cause for the MSIV closure and resultant scram

was a combination of two factors. The first factor was the discovery of a failed main steam line

high flow switch during surveillance testing. Technical Specifications then required* the MSIV trip

channel associated with this failed flow switch be placed in a trip condition. Therefore, the

A portion of the MSIV trip system was placed in the tripped condition, thus satisfying one half of

the MSIV closure logic. The second factor involved a loss of continuity for a contact associated

with a time delay relay in the B MSIV trip system. This satisfied the second half of the MSIV

closure logic and resulted in all MSIVs closing. The inspectors concluded the root cause effort

was thorough and agreed with the licensee's conclusion.

During recovery from the scram, reactor water level reached +60 inches on medium range

indication and subsequently entered the steam lines for the high pressure coolant injection

(HPCI) system. Operators closed the steam isolation valve to the HPCI system, making the

system inoperable. This consequence of scram recovery, water in the HPCI steam lines, was

experienced following the Unit 2 scram in December 1997, and resulted in the development of

. feedwater level control contingencies to prevent recurrence. The contingencies did not prevent

recurrence of water entering the HPCI steam lines during this event, partly due to the specific

circumstances of the event. We understand modifications to the feedwater level control system

to prevent recurrence of this condition have been installed on Unit 2 and are planned for Unit 3.

While the safety consequences were minimal in this case, overfill of the reactor vessel following

a scram resulting in an inoperable HPCI system is an undesirable condition. You should carefully

re-examine your feedwater level control contingencies until the modifications are installed and

monito'r performance following installation of the modifications to ensure actions to prevent

recurrence are effective.

9805270267 980513

PDR

ADOCK 05000249

G

PDR

0. Kingsley

-2-

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be placed in the NRC Public Document Room.

Sincerely,

/s/ G~ E. Grant

Geoffrey E. Grant, Director

Division of Reactor Projects

Docket No.: 50-249

License No.: DPR-25

Enclosure:

Inspection Report

.

No. 50-249/98015(DRP)

cc w/encl:

M. Wallace, Senior Vice President

D: Helwig, Senior Vice President

G. Stanley, PWR Vice President

J. Perry, BWRVice President

D. Farrar, Regulatory

  • Services Manager

I. Johnson, Licensing Director

DCD - Licensing

M. Heffley, Site Vice President

P. Swafford, Station Manager

F. Spangenberg, Regulatory Assurance

Manager

Richard Hubbard

Nathan Schloss, Economist

Office of the Attorney General

. State Liaison Officer

Chairman, Illinois Commerce

Commission

DOCUMENT NAME: G:\\DRES\\DRE98015.DRP

To receive a copy of this document, indicate in the box "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure

"N" = No co

OFFICE

Riii

~ Riii

NAME

RLerch\\ml ~**

GGrant

DATE

0517 /98

05~/9

OFFICIAL RECORD COPY

o.*Kingsley

Distribution:

SAR (E-Mail)

Project Mgr., NRR w/encl

A. Beach w/encl *

J. Caldwell w/encl

B. Clayton w/encl

SRI Dresden w/encl

DRP w/encl

TSS w/encl

DRS (2) w/encl

Riii PRR w/encl

PUBLIC IE-01 w/encl*

Docket File w/encl

  • GREENS

IEO (E-Mail)

DOCDESK (E-Mail)

n '"

.,.-;.() l . r:.

,

'

- ...,

I

  • ' '-

-3-