ML17174B136

From kanterella
Jump to navigation Jump to search
Safety Insp Rept 50-237/91-36 on 910120-920114.No Violations Noted.Major Areas inspected:2A Recirculation Pump Discharge Valve Failure to Close on 910807
ML17174B136
Person / Time
Site: Dresden Constellation icon.png
Issue date: 02/10/1992
From: Burgess B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17174B135 List:
References
50-237-91-36, NUDOCS 9202180033
Download: ML17174B136 (8)


See also: IR 05000237/1991036

Text

"

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No.

50~237/91036(DRP)

Docket No.

50-237

Licensee:

Commonwealth Edison Company

Facility Name:

Dresden Nuclear Power Station, Unit 2

Inspection A~: Dresden'Site, ~orris, IL

License No.

DPR-19

Inspection Conducted: October 20, 1991, through January 14, 1992

Inspectors:

W. Rogers

M.

Peck

M.

Huber

Approved By:

&~ ~

fut.

B. L. Burgess, Chief,

Projects Section lB

Inspection Summary

Inspection from October 20. 1991 through January 14. 1992 (Report No.

50-237/91036CDRP}.

Areas Inspected: Special safety inspection conducted by resident and regional

inspectors concerning the 2A recirculation pump discharge valve failure to

close on August 7, 1991.

Results: *The low pressure coolant injection system was inoperable for

approximately seven months.

Several weaknesses were identified in the site.

management control system:

Limited root cause evaluation

Inadequate* documentation of qualification requirements for

personnel performing a special process

Use of a non-safety consultant for safety-related work

Inadequate test acceptance criteria

Lack of independence in analyzing VOTES traces

Inaccurate Licensee Event Report information

Several additional weakness were identified in the corporate engineering

management control system concerning:

Failure to perform a safety-related engineering evaluation under

rigorous management control

Failure of erigineering personnel to recognize and document a

condition adverse to quality

9202180033 920210

"* .

PDR

ADOCK. 0500.0327 ____ _

O

PDR

1.

  • 2.

DETAILS

Persons Contacted

Commonwealth Edison Company

  • C. Schroeder, Station Manager
  • J. Kotowski, Production Superintendent
  • D. Van Pelt, Assistant Superintendent - Maintenance
  • K. Kociuba, Nuclear Quality Programs Superintendent

W. Kapinus, Motor Operated Valve Coordinator

  • D. Pool, Corporate Motor Operated Valve (MOV) Group
  • R. Radtke, Regulatory Assurance Supervisor
  • W. Morgan, BWR Nuclear Operations Supervisor
  • R. Kyrouac, Nuclear Quality Programs Supervisor
  • E. Zebus, Project Manager

.

  • L. Gerner, Technical Superintendent
  • R. Meadows, Maintenance Staff Supervisor
  • G. Smith, Assistant Superintendent, Operations
  • D. Booth, Master Electrician
  • H. Mulderink, BWR MOV Coordinator
  • R. Ungeran, Corporate MOY Administrator
  • Denotes those attending the exit interview conducted on

January 14, 1992 .

The inspectors also talked with and interviewed several other licensee

employees including members of the technical and engineering staffs.

Background

a.

System Operability Requirements

At Dresden, the low pressure emergency core cooling system is

comprised of the two core spray trains and the low pressure

  • coolant injection (LPCI) system. Technical Specification (TS)

3.5.A requires LPCI to be operable during power operation to

ensure adequate heat removal capability in t~e event of a loss of

coolant accident (LOCA).

The TS limiting condition for operation

prohibits continued reactor operation beyond seven days if LPCI is

inoperable.

For LPCI to be operable, the system must be able to determine in

which reactor recirculation (RR) loop the LOCA occurred, isolate

the faulted loop, and inject water into the reactor vessel via the

non-faulted RR loop .. Isolation of a faulted loop occurs when .the

associated RR discharge valve closes.

b.

VOTES Testing Methods

The licensee tests motor operated valves using the Liberty

Technologies Valve Operation Test Evaluation System (VOTES).

2

,,

3.

After recording the VOTES data, maintenance technicians select a

zero reference point from the latter of two transition points in a

closed-to-open-to-closed trace. The transition points occur when

all stem compression and tension is relieved as the stem nut turns

freely through the thread clearance.

The VOTES computer software

then uses data collected by a strain gage, located on the valve

yoke, to calculate valve thrust by referencing the force

coordinate events to the zero refer*ence point. Based upon the

calculated thrusts a torque switch setting is then established.

Reactor Recirculation Valve Failure

In December 1990, during the 12th refueling outage on Unit 2, the

licensee performed VOTES testing on the 2A reactor recirculation loop

discharge valve, 2-202-5A.

The technician was unable to determine the

zero reference point due to anomalies in the VOTES trace.

One of the

technicians sent the digital test data to a recognized VOTES industry

expert, employed with Babcock and Wilcox Nuclear Technologies {BWNT},

and requested guidance in identifying the zero reference point.

On December 14, 1990, the recognized industry expert telephoned the

technician and assisted in identification of the zero reference point.

This zero reference point was entered into the VOTES analysis program

and the valve thrusts were calculated.

Fro~ this calculation, the valve

On August 6, 1991, the 2A reactor recirculation pump tripped on over

excitation due to a failed resistor in the motor generator voltage

regulator circuit. After replacing the resistor~ operations personnel

attempted to restart the pump.

In accordance with the procedure, the

operator tried to close the loop discharge valve prior to restarting the

pump.

However, the valve would not close beyond the intermediate

position.

Investigation showed that the valve motor was prematurely

tripping due to an improper torque switch setting. The incorrect torque

switch setting corresponded to a valve operator thrust between 19,000

  • and 20,000 pounds.

The required thrust window, based on a design

differential pressure of 200 pounds per square inch, was between 48,280

and 56,517 pounds.

On August 10, 1991, the torque switch was reset to 3.25, based on a

motor current trace, and the valve was declared operable.

On August 20, 1991, as part of the corrective action for the wrong

torque switch setting, the corporate nuclear engineering department

(NED} motor operated valve (MOV} group performed a reanalysis of the 39

remaining safety-related VOTES tests from the D2Rl2 outage.

The

reanalysis concluded that all the other valves were within their design

thrust windows.

3

I,

4.

Event Contributors

a.

Cause of the Event and. Root Cause Evaluation

The licensee determined the cause of the event to be a

misinterpretation of the zero reference point on the force versus

time VOTES trace. The zero reference point identification was

hampered by the unusual characteristics of the trace and the

limitation of the VOTES computer software {Version I.I) to expand

the force axis portion of the trace. The licensee event report

(LER) indicated the newer edition of the software {Version 2.I)

,provided enhanced resolution as well as other features to ensure

proper zeroing interpretations.

The inspector concluded the root cause of the event was a

limitation in the VOTES process.

The determination of the zero

reference point for the discharge valve was consistent with the

VOTES methodology, as described in the formal VOTES training

program and the VOTES manual.

The reactor recirculation discharge

valve yoke exhibited a bending moment when the valve was cycled.

The bending effect resulted in abnormal running loads and a

discontinuity between the first and second transition points of

approximately 50,000 pounds force {lbf) compared to 200 lbf in a

typical trace. The VOTES testing program, including the

methodology, training, and software, was not equipped to properly

evaluate the reactor recirculation discharge valve data, due to

the bending yoke effect. Both versions of the VOTES software

provided expansion capability of the time axis.

The expansion

feature ~llowed for clear identification of both transition points

on the valve trace; however, expansion of the time axis may not

have identified the torsional bending yoke effect to the

uninformed individual. Therefore, the use of version I.I instead

of version 2.I did not contribute to the misidentification of the

zero reference point.

b.

Failure to Document Personnel Qualification

Nuclear Operations Directive NOD-MA.I, "Guidelines For Motor-

Operated Valve {MOV) Testing, Maintenance'and Evaluation,

September I990," delineated the special training requirements for

the Station Motor Operated Valve {MOV) Coordinator, the Corporate

MOV Coordinator, and engineering personnel performing work for the

Corp~rate MOV Coordinator.

The.inspector determined that the licensee had not maintained

records documenting station and corporate personnel qualification

to NOD-MA.I requirements.

The Nuclear Quality Programs group had

previously identified this concern for corporate personnel as

documented in .Audit Report CE-9I-04, November IS, I99I.

The inspector confirmed, through interview, that personnel

performing VOTES analysis were qualified and that the lack of

4

as-left torque switch sittings, or the valve thrust windows.

(2)

The MOV coordinator's concerns about selecting the zero

point on the valve and use of industry expert services were

not documented.

For example, no notations were made in the

work package nor was a condition adverse to quality record

initiated.

(3)

No independent analysis or evaluation was required by the

test procedure. Additionally, no independent verification

of conformance to the thrust windows was required.

The inspector determined through interview that the technicians

performing the testing ~nderstood management's expectations that

the valve torque switch settings would be set consistent with the

design thrust windows.

Therefore, the inadequacies in the test

procedure were not a contributor in the event.

5.

Corporate Engineering Involvement

a.

Reanalysis of the VOTES Traces by NED

The corporate motor operated valve (MOV) group completed a

reanalysis of the 39 safety related VOTES tests performed during

the outage on August 20, 1991.

The MOV Program Administrator

i~sued a letter to the station concluding that all the valves,

except the reactor recirculation discharge valve, were within the

currerit design thrust window.

The inspector determined that five of the re-evaluated valves were

actually outside the design thrust window.

Two of the five valves

had been identified during the outage and had been found

acceptable, as documented in an engineering transmittal (CHRON No.

161468, January 15, 1991, to E. Eenigenburg).

Based upon

engineering judgement, NED MOV personnel determined that the

  • operability of the other three valves was not affected by the

degraded torque switch settings. The engineers involved failed to

document either the reanalysis effort or the discrepancies between

the plant configuration and design documentation.

Further, the

NED organization did not communicate to the station that

discrepancies were found or how they were resolved.

b.

MOV Design Thrust Window Data

The licensee contracted with Bechtel Corporation to provide MOV

thrust windows for worst ca~e differential pressure and minimum

  • terminal voltage.

The NED MOV group adjusted the Bechtel thrust

window values as a function of torque switch tolerance, valve

lubrication history and measured equipment uncertainty. The

adjusted thrust values were sent to the site via letter. Station

personnel used the letter to determine the acceptable valve thrust

in *the VOTES analysis.

6

c.

documentation did not contribute to the incorrect torque switch

setting.

Use of a Non-Safety-Related Consulting Service

Prior to the outage, the licensee contracted with Babcock and

Wilcox Nuclear Technologies (BWNT} to provide consulting services

for VOTES data analysis (Purchase Order Number 333188}.

In

accordance with the contract, BWNT was to issue a formal analysis

report within five days of receipt of valve data.

The purchase

order was issued as non-safety related.

Under this purchase order, a site technician sent the reactor

recirculation discharge valve digital test data to BWNT for

analysis, as described in section 3 above.

Assisted by the BWNT

recognized industry expert, the technician selected a zero point

for the trace.

When the BWNT industry expert participated in

selecting the zero reference point for this safety related valve,

he performed safety related work.

During the review of the valve trace, the BWNT industry expert

determined a problem existed with the valve. This observation was

not communicated to the site during the zero reference point

dialogue.

As stated in the contract, the industry expert wrote a

VOTES summary report.

The report concluded the valve might not

shut off flow under actual operating conditions and recommended

that the valve be disassembled and deficiencies corrected.

However, BWNT failed to forward the summary report to the

licensee.

The site MOV coordinator failed to recognize that the

summary report was not received.

The inspector concluded that the procurement of the consultant

services under a non-safety purchase order was not a contributing

factor to the event. All practical aspects of a safety related

program were met.

The expert was qualified and the analysis was

documented in accordance with BWNT's QA program.

The report was

placed into the vendor's QA document control program.

Procuring

the consultant services under a non-safety related purchase order

had no bearing on the consultant's failure to submit the report to

the licensee.

d.

Test Procedure Quality

The inspector reviewed the work package (WR 091331} and testing

procedures for VOTES testing of the reactor recirculation

discharge valve.

The irispector identified the fol~owing

weaknesses associated with the documentation of the work

activities:

(l}

Neither the work package nor the testing procedure

delineated any quantitative or qualitative acceptance

criteria related to the VOTES diagnostic, the as-found or

5

6.

The inspector requested to review the NED adjustment calculations.

However, these calculations were not available since they were not

retained under a QA program.

Licensee Event Report Followup

(Open) LER-237/91-023, 2A Retirculatiori Pump Discharge Motor-Operated

Valve Failure to Close.

The inspectors identified that the LER

contained incorrect and misleading information.

The licensee committed*

to revise the LER, correcting inaccuracies, and to review the LER

  • information gathering process.

7.

IO CFR 21 Evaluation Followup

The station procedure for review and processing significant conditions

adverse to quality, Dresden Administrative Procedure (OAP) 2-8, provides

three Part *21 deviation screenings.

The first review is performed by

the Operation Engineer, the second by the deviation report coordinator

and a final review by the on-site review group.

When a deviation is

identified through the screening, the information is forwarded to the

corporate Part 21 coordinator.

The coordinator then ensures that an

evaluation for a defect, under IO CFR Part 21, is completed.

For the reactor recirculation discharge valve incorrect torque switch

setting, all three screenings concluded that a Part 21 evaluation was

not required;

However, the LER concluded that li~itations of the VOTES

computer software contributed to the improper zero reference point

identification.

The inspector inquired why a Part 21 evaluation was not performed beyond

the initial screenings. During the inspection, the licensee began a

10 CFR Part 21 evaluation of the VOTES process relating to the bending

valve yoke phenomenon.

8.

Analysis of Inspection Findings

  • ---

Several weaknesses associated with the VOTES testing program were

identified in the site management control system:

The management control system did not ensure an adequate

root cause evaluation was completed following the failure of

the RR discharge valve to close.

The management control system did not ensure the

qualification requirements, as outlined in NOD-MA.I, were

. documented for personnel performing VOTES testing.

The management control system did not ensure consultant

services used for safety-related work were procured on a

safety related purchase order.

7

The management control system did not ensure the VOTES testing

procedure/work package delineated quantitative or qualitative

acceptance criteria.

Given an emergent technology, the management control system did

not establish a commensurate level of review of the VOTES

analysis~

The management control system did not ensure the abnormal

VOTES trace was identified and documented as a condition

adverse to quality.

The management control system did not ensure that LER 91-023

contained factual information.

Several additional weaknesses w~re identified in the NED Management

Control System:

The management control system did not ensure the re-evaluation of

the remaining Unit 2 MOVs was performed and documented under

rigorous management controls.

The management control system did not ensure engineering personnel

recognized or documented the failure of three Unit 2 MOVs to meet

the design specification as a condition adverse to quality.

The original unresolved item, 50~237/91022-0S(DRP), issued on this

matter will remain open.

Closure of this item is dependent upon

completion of the licensee's 10 CFR 21 evaluation of the VOTES process

and further NRC review of the licensee's condition adverse to quality

system and licensee calculation controls.

An unresolved item is a

matter requiring more information to ascertain whether it is an

acceptable item, an open item, a deviation, or a violation.

9.

Exit Interview

The inspectors met'with licensee representatives (denoted in

paragraph l) during the inspection period and at the conclusion of the

inspection period on January 14, 1992.

The inspectors summarized the

scope and results of the inspection and discussed the likely content of

this inspection report .. The licensee acknowledged the information and

did not indicate that any of the information disclosed during the

inspection could be considered proprietary in nature.

8