ML17158A063
| ML17158A063 | |
| Person / Time | |
|---|---|
| Site: | Susquehanna |
| Issue date: | 12/08/1993 |
| From: | Temps R, Jason White NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML17158A062 | List: |
| References | |
| 50-387-93-80, NUDOCS 9312300017 | |
| Download: ML17158A063 (79) | |
See also: IR 05000387/1993080
Text
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
Docket No.
Report No.
License No.
Facility Name:
Inspection At:
Inspection Dates:
50-387
50-387/93-80
Susquehanna
Steam Electric Station (SSES)
Berwick, Pennsylvania
October 29, 1993 through November 9, 1993
Inspectors:
Robert Summers, Project Engineer, DRP
Carl Sisco, Operations Engineer, DRS
Human Factors Specialist, NRR
Scott Morris, Reactor Engineer, DRP
David Mannai, Resident Inspector - Susquehanna,
Observer:
David Ney, Commonwealth of Pennsylvania
Team Leader:
R.R. Temps, Project
Division of Reacto
oj
Date
Approved By:
J.R.
'te, Section C
ef, B
2A
D'sion of Reactor Projects
.D
Inspection Summary:
See Executive Summary
9312300017
9'31208
ADOCK 05000387
Q
EXECUTIVESUMMARY
Between October 6 and 28, 1993, while the plant was shut down for a refueling outage, four
events occurred during fuel handling operations at Unit 1 ofPennsylvania Power and LightCo.'s
(PP&L's) Susquehanna
Steam Electric Station (SSES).
These events are described below.
Event
1 occurred on October 6, 1993, when a peripheral fuel bundle was incorrectly removed
from core location 31-56 (instead of from core location 29-55).
Upon discovery of the error,
the bundle was inappropriately returned to its original location in the core.
Further fuel moves
were suspended
while PP&L developed
and implemented corrective actions.
Core offload
recommenced
three hours later and was completed on October 9.
Event 2 occurred on October 26, 1993, the same day that PP&L commenced core reload. While
lowering a fuel bundle into the core, a 10-inch section of the telescoping mast "hung up" and
subsequently slipped, creating a loud noise. Afterdetermining that the fuel bundle had not been
affected, the operator's completed lowering the bundle into its core location and then secured fuel
handling activities. Maintenance personnel examined the mast and determined that the mast was
unusable because of a bend in the 10-inch section.
Event 3 occurred on October 27,
1993, after resumption of refueling activities and while using
the Unit 2 refueling bridge. While a double blade guide was being moved from the core to the
spent fuel pool, it hit the inner wall of the reactor pressure vessel.
Bridge operators, who noted
.that the mast was not high enough to allow the blade guide to clear the vessel flange, had
stopped bridge movement; however, momentum allowed the blade guide to hit the vessel's inner
wall. The mast was then fully raised and the blade guide was taken to its designated
location
in the fuel pool.
After comprehensive
inspection and testing of the mast (which revealed no
observable problems with the mast) and the institution of new procedural controls, refueling
activities were resumed.
Event 4 occurred on October 28, 1993, while the mast was being lowered in preparation for
grappling a new fuel bundle in the fuel pool. While lowering the mast, a section of the mast
"hung up" and then unexpectedly released.
PP&L suspended all further fuel movements pending
completion of an internal Event Review Team (ERT) investigation.
Subsequent
inspection
revealed that a section of the mast was bent.
An Augmented Inspection Team (AIT) was dispatched by the NRC to determine and assess
the
circumstances,
causes,
corrective actions, safety significance, and generic implications of the
events.
The AIT began its inspection on October 29,
1993, and completed
onsite review
activities on November 9, 1993. PP&L met with Region I management on November 18, 1993,
and presented the findings ofits internal reviews and its plans for resuming refueling operations.
The AITpresented its preliminary findings in a public exit meeting on November 22, 1993 (see
Attachments 7 and 8).
The AITconcluded that operator errors were the immediate causes of Events 1, 2 and 3. Event
4 was caused
by operation of the refueling bridge, with the mast in a weakened
condition
following Event 3.
The AITfound that several of the short-term actions taken by PP&L prior to resumption of fuel
handling activities after each event were inadequate.
Further, the AITdetermined that Events
1 through 4 were all repetitions of similar events going back to at least
1984.
The AIT
determined
that the root-cause
evaluations for these previous events were not thorough and
lacked independence of review, and that corrective actions were generally directed toward
counseling individuals, adding procedural precautions,
and reviewing the events in operator
training, rather than implementing proscriptive procedural
controls.
Consequently,
these
corrective actions were ineffective in preventing recurrence.
In reviewing PP&L's response
to previous events,
the AIT noted that PP&L had not treated
some fuel handling activities as safety-significant operations.
The AIT observed
repeated
instances where evaluations had stated "no safety significance" or "increased outage time" as the
consequence
of the event reviewed.
PP&L's response
to the repeated
maintenance
and
replacement of bent mast sections appeared
to be more concerned with economic factors (i.e.,
maintaining the timeliness of core offioad/reload) than in treating the problem as one affecting
a safety-significant activity.
The most. telling evidence of this was that for recent refueling
outages,
a spare mast was routinely kept on the refueling floor due to PP&L's history of mast
problems and the expectation that a spare would probably be needed.
The AITwas particularly concerned by PP&L's response to recommendations
made in 1986 and
1987 as a result of an engineering review of problems involving fuel handling equipment.
Although the recommendations
were designed to reduce the wear and tear on the fuel handling
equipment, PP&L did not adopt them.
Had PP&L paid attention to the recommendations,
many
of the problems encountered
recently may have been prevented.
The AITconcluded that operations management's
oversight of fuel handling activities was weak
and their failure to take more rigorous corrective actions from previous events allowed the
problems to recur.
In the past, senior operations management
has delegated oversight of these
activities to the refueling floor senior reactor operator (SRO).
This decision was apparently
made under the belief that having a higher management
presence on the refueling bridge would
distract the operators from their duties. However, although the desire to reduce distractions was
commendable,
senior managers did not hold their people accountable,
nor obtain feedback,
so
the managers
remained unaware of concerns
and practices known at the working level.
For
example,
senior
operations
managers
stated
they
had
never
heard
of complaints
from
maintenance
personnel that fuel handling equipment problems were caused by the manner in
which operators were operating the equipment, yet many operations personnel at the level of
Shift Supervisor and lower knew of this complaint.
Senior managers
were unaware of the fact
that double blade guide handles could be hit when double blade guides were moved in the spent
fuel pool, although this fact was reported by two operators during the AITinterviews.
Lastly,
human performance problems during fuel handling operations have repeatedly occurred over the
years, yet operations management
oversight of these activities remained unchanged.
TABLEOF CON'H<WTS
Introduction
1.1
AITScope and Objectives ..
1.2
AITProcess
Desc
~
~
rlptlon of Events
Assessment of Pennsylvania Power and Light Co.'s (PP&L's) Response
to, and
Corrective Actions Following, Each Event.......................
3.1
. Assessment of PP&L's Short-Term Corrective Actions for Each Event .
3.2
Adequacy of Short-Term Actions in Light of Previous Similar Events
3.2.1.
Previous Events Involving Impact to the Mast/Grappled
Components............................
3.2.2.
Fuel Bundle and Blade Guide Movement Errors......
3.2.3.
Mast Damage Attributed to Unknown Causes
3.3
Final Actions Taken Prior to Resumption of Fuel Loading
~
~
~
~
~
~
~
~
~
~
~
~
3
3
6
6
7
8
8
rator TralnHlg
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
Ope
Fuel Handling Procedures...................................
Schedule, Staffing, and Overtime ............................
~ .
7.5
7.6
7.7
Maintenance/Surveillance
Issues
Identified During the Outage
Related
to the
Refueling Bridge Main Grapple (Mast)...........................
7.1
Installation of Non-Q Grapple............................
7.2
Failure To Perform Required Surveillance Test .............
~ ..
7.3
Bridge Travel Interlock Failure..........................
7.4
Summary of Concerns
on Maintenance
and Troubleshooting
on the
MaSt
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
Review ofthe Maintenance History of the Refueling Bridge Main Grapple
(MaSt)
~
~
o
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
Summary of Concerns on Maintenance History
Potential Generic Concerns
7.7.1
Operational Concerns
7.7.2
Design Concern...............................
9
10
11
11
12
13
14
15
15
16
Human Factors Issues ..................
16
Safety Significance and Management
Oversight and Control of Fuel Handling
ACtlVltleS
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
16
lV
TABLEOF CONTENTS (CONTIMH~W)
Attachment 1:
Attachment 2:
Attachment 3:
Attachment 4:
Attachment 5:
Attachment 6:
Attachment 7:
Attachment 8:
AIT Charter
Personnel
Contacted
Detailed Timelines for Events
1 through 4
Previous Impact Events Since 1984
Bundle/Blade Guide Movement Errors
Human Factors Concerns
Slides Shown at the PP8cL Management Meeting
Slides Shown at the AITExit Meeting
DETAILS
1.
Introduction
Because of the series of fuel handling events which occurred in October
1993 at Unit 1 of
Pennsylvania Power and Light Co.'s (PP&L's) Susquehanna
Steam Electric Station (SSES), the
Nuclear
Regulatory
Commission
(NRC)
Region I Regional
Administrator,
and
senior
management
from the Office of Nuclear Reactor Regulation and the Office for Analysis and
Evaluation of Operational Data, determined that an Augmented Inspection Team (AIT) should
review the events and evaluate their significance.
The reasons for sending the AITcentered on
understanding the cause(s) of these events, the fact that the events were. repetitive in nature, and
that there may have been generic implications.
The AITwas assembled
and sent to the site on
October 29, 1993.
1.1
AITScope and Objectives
The charter for the AIT(Attachment 1) was issued on October 29, 1993.
The charter directed
the team to conduct an inspection that accomplished
the following objectives:
ao
Review and evaluate
the adequacy of PP&L's corrective measures,
in concert with
Region I management, prior to agreeing to resumption of refueling activities.
b.
Conduct.a thorough and systematic review of the circumstances
surrounding each of the
refueling events which occurred since October 1, 1993, and develop a detailed sequence
of events for each occurrence.
C.
Collect, analyze,
and document relevant factual information to determine the causes,
conditions, and circumstances
pertaining to each event.
d.
Review qualifications of the refueling operators
and training they received
on fuel
handling operations.
e.
Evaluate PP&L's review of and response
to each event and implemented corrective
actions, as well as their plans for resumption of refueling activities.
Review and assess
the adequacy of PP&L's refueling, surveillance, and test procedures
as they existed before these events; and review and assess
the changes
made in these
procedures after each event.
g.
Evaluate PP&L's procedures
regarding
senior reactor
operator
(SRO)
and reactor
operator (RO) responsibilities during fuel handling operations.
h.
Determine ifthere were any generic implications that should be considered for further
review or evaluation by the NRC staff.
i.
Determine the adequacy of management
oversight and control of refueling activities.
j.
Assess
the
safety
significance of each
event
and
communicate
to regional
and
headquarters
management
the facts and safety concerns related to problems uncovered.
1.2
AIYProcess
From October 29 to November 9, 1993, the AIT performed an independent
inspection and
review of the circumstances
associated
with the fuel handling events.
The team inspected the
fuel handling equipment and observed associated troubleshooting and repair activities; conducted
formal interviews with the personnel involved in the events; held discu'ssions with operations,
maintenance,
and
engineering
personnel;
reviewed
fuel handling procedures
and training
documents; reviewed documents pertaining to previous occurrences ofrefueling events; reviewed
operators'ogs;
and reviewed management oversight of fuel handling activities.
Attachment 2
lists personnel contacted by the AIT.
2.
Description of Events
The following information is a brief synopsis of the four events that were the focus of the
inspection.
Attachment 3 contains detailed timelines for each event, as constructed
from the
team's review ofoperating logs, and also provides relevant details and circumstances
developed
through interviews with various personnel involved in the events.
Relevant technical information
resulting from PP&L's review.of the events has also been factored into the timelines for Events
2 and 4. Other issues were identified concerning maintenance and surveillance practices on the
refueling equipment, and these are discussed
in Section 7.
On September 25, 1993, PP&L shut down Unit 1 and entered a refueling outage.
On October
1, 1993, core off-load to the spent fuel pool commenced.
Event
1 occurred on October 6, 1993,
when a peripheral fuel bundle was incorrectly removed from core location 31-56 (instead of
from 29-55, adjacent to 31-56). When the error was discovered, the bundle was inappropriately
returned to its original location in the core.
Further fuel moves were suspended
while PP&L
developed and implemented corrective actions.
Core off-load recommenced
three hours later
and was completed on October 9.
Event 2 occurred on October 26, 1993, the same day that PP&L commenced core reload. While
.'owering a fuel bundle into the core, a 10-inch section of the telescoping mast "hung up" and
subsequently slipped, creating a loud noise.
Operators on the refueling bridge finished lowering
the bundle into its core location and then secured fuel handling activities.
Surveillances were
performed
on the mast and maintenance
personnel
determined
that the mast was unusable
because there was a bend in the 10-inch section.
Consequently, PP&L decided to use the Unit
2 refueling bridge to complete the Unit 1 refueling activities.
Event 3 occurred on October 27,
1993, after resumption of refueling activities and while using
the Unit 2 refueling bridge. While moving a double blade guide from the core to the spent fuel
pool, the blade guide hit the reactor pressure vessel inner wall. Bridge operators noted that the
mast was not high enough to allow the blade guide to clear the vessel flange and had stopped
bridge movement; however, momentum allowed the blade guide to hit the vessel inner wall.
The mast was then fullyraised to clear the flange and the blade guide was subsequently
placed
into its designated location in the fuel pool. After comprehensive
inspection and testing of the
mast, which revealed no problems with the mast, and the institution ofnew procedural controls,
refueling activities were resumed.
Event 4 occurred on October 28, 1993, while the Unit 2 refueling bridge mast was being
lowered in preparation for grappling a new fuel bundle in the fuel pool.
While lowering the
mast, a section of the mast "hung up" and.then unexpectedly released.
PP&L suspended
all
further fuel movements
pending
completion of an
internal
Event Review Team
(ERT)
investigation.
Subsequent
inspection revealed that a section of the mast was bent.
3.
Assessment
of Pennsylvania
Power and Light Co.'s (PP&L's) Response
to, and
Corrective Actions Following, Each Event
The AITreviewed and assessed
the actions that PP&L took for each event before resuming'fuel
handling activities.
The AIT also reviewed
the adequacy of these actions in light of the
historical record of numerous similar events which have occurred at SSES since at least 1984.
The AITidentified deficiencies,
as described below.
3.1
Assessment of PP&L's Short-Term Corrective Actions for Each Event
In the following discussions,
refer to Attachment 3 for details about each event.
VENT 1'
1 Bun l Err r
PP&L's immediate corrective actions to this event included "Hot Box" training (guidance which
must be read before operators assume their shift duties) which discussed
the requirements for
the bridge operators to communicate to each other the cell orientation of the fuel bundle and to
confirm correct mast orientation/alignment, with respect to core location, before grappling the
bundle.
The training also clarified that once a bundle clears the top guide, during offloads, then
the bundle must not be reloaded into the core.
Operations
management
also counseled
the
individuals involved in the event regarding proper communications
practices.
Defueling
activities resumed
within three hours, with operations
management's
understanding
that a
procedure
change approval form (PCAF) would be issued by the next day to formalize the
information in the Hot Box training memorandum regarding cell orientation of the bundle and
mast orientation before grappling a bundle.
The team assessed
that these actions were inadequate for the following reasons:
(1)
PP&L's corrective actions did not address
the serious breakdown in the command and
control of fuel handling activities that occurred during this event .
Procedure RE-081-
032, "Refueling Operations," states that shift supervision is responsible for directing fuel
handling activities; however, the bundle was improperly placed back in the core without
the knowledge or concurrence of the shift supervisor (SS).
Instead, the central figure
directing the recovery actions for this event was the outage supervisor.
By procedure
RE-081-032, this individual is not responsible for directing fuel handling operations,
especially recovery actions.
No training emphasizing
the command
and control of
refueling activities, especially when unexpected events occur, was given to the operators
preceding the resumption of defueling.
(2)
The outage supervisor was counseled by operations management
on his responsibilities
during fuel handling activities, yet after two interviews with the individual by the AIT,
it was apparent that the counseling he received,
as to his responsibilities,
had not been
clearly communicated or understood.
(3)
Defueling was allowed to resume without a PCAF in place, under the assumption that
it would be issued by the following day.
The AITfound that the PCAF was not issued
until 12 days later.
Therefore,
the remaining 3 days of defueling were performed
without the PCAF in place.
Operations management
was not aware that the PCAF had
not been issued on time until the AITtold them.
VE
2
M
n "Hn
Following this event, PP&L maintenance
personnel
determined
that the Unit
1 mast
was
unusable
and the Unit 2 bridge and mast were readied
to support refueling.
Operations
management interviewed all refueling operators to determine ifthe operators had hit anything.
All of the operators interviewed replied they had not hit anything.
Refueling recommenced,
once the Unit 2 equipment was verified operable.
The AITidentified that these corrective actions were inadequate for the following reasons:
(1)
PP&L did not fullyexplore the physical evidence of the markings on the flange protector
before resuming fuel reload.
Subsequent evaluation (a week later) by PP&L determined
that the mast's grapple had been dragged across the reactor vessel flange protector and
that this most likely bent the mast.
(2)
PAL proceeded
with refueling without resolving how the mast was damaged.
Even
though the operators said they had not hit anything, considering the bent mast section and
flange marking, operations management
suspected
that the mast had hit something,
All
operators involved in the current refueling outage were interviewed and all stated they
had not hit anything with the mast.
The interviews were then expanded to include all
operators who had participated in refuelings in the past.
During one of these interviews,
an operator,
responsible for an impact event in 1992, stated that when that incident
occurred, he did not feel any impact.
From this, PP&L concluded that an impact might
have occurred during Event 2 and that operators could have been unaware of it. Reactor
Engineering then proceeded to prepare a PCAF for the refueling procedures which would
have been more proscriptive concerning
mast elevation; however, Event 3 occurred
before the PCAF was implemented because refueling had recommenced before all of the
interviews were completed.
(3)
The fault lockout on the bridge which occurred while traversing
the transfer canal
("cattle chute") was never fully explained prior to resumption of refueling.
VE 'l
i
Im
n R
ctor V
l Inn rW 11
Following this event, refuel activities were temporarily halted.
A PCAF was subsequently
issued to place restrictions on the mast elevation before movement through the transfer canal,
Maintenance personnel checked out the bridge and mast and saw no observable damage to the
mast.
Operations
management
also assigned
an SS to monitor refuel floor activities and to
report his observations
to them.
The AITconsidered
these actions inadequate
because:
(1)
The PCAF, specifying that the mast be in the normal up position before proceeding past
the central area of the core,
was only issued
to one of the two affected refueling
procedures.
The PCAF was entered in Procedure RE-081-032, "Refueling Operations,"
the reactor engineer's procedure,
but Procedure OP-181-001,
"Refueling Operations,"
the one used by the operators,
did not receive the PCAF.
The AITnoted this fact.
(2)
The SS assigned by operations management to review and report on refuel flooractivities
only observed 20 minutes'of actual refueling operations before he left the refuel floor.
This, apparently,
was the extent of management
oversight over the resumption of
refueling for this event.
3.2
Adequacy of Short-Term Actions in Light of Previous Similar Events
The events of October 6, 26, 27, and 28, 1993, had all happened
before at SSES.
The AIT
assessed
that PP&L's root-cause evaluations for these earlier events, and the corrective actions
implemented, were inadequate
because
the same events recurred.
The AITdivided these past
events into three areas
as described
below.
The AIT's assessment
of PP&L's root-cause
analyses
and corrective actions for these events follows:
3.2.1.
Previous Events Involving Impact to the Mast/Grappled Components
Events of this type are safety significant because they can occur while irradiated fuel bundles
are being moved, or while components
are being moved over irradiated fuel bundles,
and
damage to irradiated fuel can result in significant radiation exposure.
Fortunately, none of the
impact events, reviewed by the AITat SSES, have involved irradiated fuel bundles.
However,
several other impact events have occurred at SSES in the past; these are listed in Attachment 4.
The AIT assessed
that PP&L's corrective actions for these past events were inadequate,
as
evidenced by their recurrence.
The AITfound that PP&L's corrective actions consisted mainly
of discussing the events in training, counseling the individuals involved, and adding procedural
precautions to the fuel handling procedures,
but PP&L did not investigate why personnel
had
made
mistakes.
The reviews for these
events
were performed
by the line organization
responsible for the operation, and were not subjected to independent review or other assessment,
The AIT cited the following as examples of inadequate
investigation and independence
of
review:
(1)
There
appeared
to be
no followup to an
operator's
statement
made
during the
investigation of an event that occurred
on April 13,
1989.
In an attachment
to the
significant operating occurrence
report (SOOR) issued for this event,
the following
statement was made by the operator involved: "When moving a double blade guide from
the fuel pool to the Rx I bumped the blade guide in the cattle shoot (sic) but it didn'
seem very hard compared
to some bumps I'e seen...."
The AIT interviewed the
individual concerning that statement and learned of the concern about double blade guide
impact in the fuel pool as described
in Section 7.2.
The AIT had heard this same
concern from another operator.
PP&L senior operations management
had never heard
of this concern until the AITtold it to them.
(2)
An SRO involved in an event that occurred on October 16, 1992, was asked to review
the event and report to operations
management.
His report, attached
to the SOOR
documenting this event,
stated that "this was an isolated event" and "procedures
are
adequate."
These same words appear in the final resolution to the SOOR, which led the
AITto question the true independence of the review, especially since several events of
this type had occurred in the past.
Further, this was the same individual, who, when
interviewed following Event 2, stated that he detected no impact when he ran the mast
into the transfer canal in October 1992. A more thorough and independent review at that
time might have elicited this fact and could have affected PP&L's response to Event 2.
3.2.2.
Fuel Bundle and Blade Guide Movement Errors
The AIT assessed
that the safety significance of these
types of events
is relatively low.
Placement of a fuel bundle or blade guide in an incorrect location in the fuel pool has no safety
significance.
However, placement of a fuel bundle in an incorrect coie location, and reactor
operation
in this configuration if undetected,
could damage
the fuel and
thus
has
safety
significance.
The AIT documented
numerous
instances of previous
occurrences
of bundle/blade
guide
movement errors.
These previous occurrences
are listed in Attachment 5 to this report.
In
reviewing PP&L's corrective actions to these events, the AITnoted that the actions usually were
directed toward training and counseling.
No concerted effort was made to look for ways to
improve the procedures or implement practices to prevent recurrence of the events,
The AITdetermined that this was due to a "mind set" that first appeared
in SOOR 2-88-091,
dated April 15, 1988.
In the section of the SOOR titled "Resolution and Actions to Prevent
Recurrence,"
the following statement appeared:
"In light of the measures
presently in place to
preclude a refueling error, combined with the inconsequential repercussions ofsuch an error due
to the plans being implemented, Reactor Engineering concludes that no further actions to prevent
recurrence are required." That same SOOR contained a quantitative analysis ofrefueling errors
which appeared
to accept that an average of 2 or 3 occurrences
out of 2000 component moves
during a core offload/reload was acceptable because the occurrences
were minor in nature and
the errors would likely be detected during Reactor Engineering verification.
This same thought process appeared again in a SOOR (1-89-127) dated April 13, 1989, in which
a Human Performance Evaluation System (HPES) report attached to the SOOR stated in part:
"The number of errors, 2 to 3, is acceptably low, considering the number of moves" and in
reference
to achieving a goal of zero defects
that "Zero defects
is a goal, but, as stated
previously, core offload or reload has been analyzed such that a minimal number of errors is
tolerable."
In the resolution section of the SOOR, Reactor Engineering stated that: "Allsteps
known to prevent errors have been taken and no further actions to prevent recurrence are known
or being taken."
Because ofthis mindset, the AITconcludes that operations management chose to accept not only
that these errors would occur during refueling outages but also that errors were acceptable.
PP&L's lack of effective corrective actions indicates this.
3.2.3.
Mast Damage Attributed to Unknown Causes
The AITnoted that PP&L performed excessive repetitive maintenance on the refueling masts.
This maintenance
history and the AIT's assessment
of PP&L's response
to the repetitive
maintenance are discussed
in detail in Section 7.5.
3.3
Final Actions, Taken Prior to Resumption of Fuel Loading
Afterthe AITconcluded its site activities, PP&L undertook an exhaustive review ofits handling
of these issues,
as well as an expanded review ofits handling ofsimilar issues involving human
error or design deficiencies.
PP&L developed
short, intermediate,
a'rid long-term corrective
actions to address its findings in these areas.
A public meeting was held in the Region I office
on November
18,
1993, in which PP&L managers
presented
their findings and plans for
resuming refueling operations to senior NRC managers.
Attachment 7 contains PP&L's slides
used at the meeting.
After the meeting, regional management
and the team members met again to discuss PP&L's
presentation.
On the basis of the information submitted, and after factoring in the AIT's and
resident inspector staff's independent reviews of the corrective actions, regional management
agreed that PP&L's actions were sufficient to resume refueling on November 19, 1993.
4.
Operator Training
The AIT determined that all refueling bridge operators
and refueling bridge supervisors
had
successfully completed the facilities refueling bridge training program and that the program was
adequate.
The AITreviewed the refueling bridge training program.
The program is described in facility
procedures
OP-O20, "Refueling Bridge Training and Qualification," and OP-O11, "Operator
Refuel Training." The program consists ofclassroom instruction followed by on-the-job training
conducted on the refueling floor. The classroom training is followed by a written examination.
The refueling bridge training was conducted about one month before refueling activities.
In
addition, several refueling bridge operators
had attended refueling bridge operations training
conducted by the General Electric (GE) Company at the GE training facilities in San Jose,
California, about a month before refueling activities were started.
5.
Fuel Handling Procedures
The AIT determined
that operator actions concerning refueling activities were contained in
procedures RE-081-032, "Refueling Operations," and OP-181-001, "Refueling Operations." The
AITverified that these procedures were present on the refueling bridge and in the control room.
The AITdetermined that the procedures concerning refueling activities were generally adequate
as far as the mechanics of fuel handling were concerned.
While there were precautions in the
procedures that addressed
confirmation of fuel bundle location and movement of the mast so as
to avoid contact with objects, the procedures were not proscriptive enough to prevent the human
errors which occurred.
Despite past occurrences of human error and recommendations
made
in 1986 on operation of fuel handling equipment,
the procedural
methodologies
remained
essentially unchanged until the occurrence of Event 3.
Section 7. of the report contains details on inadequacies
identified in certain fuel handling
equipment maintenance
and surveillance procedures.
The responsibilities ofthe Refueling Floor SRO and Refuel Bridge Operator during refueling are
contained in procedure RE-081-032 "Refueling Operations" Section 4. The AITconcluded that
the procedure adequately described the necessary responsibilities ofthe Refueling Floor SRO and
the Refuel Bridge Operator.
6.
Schedule, Staffing, and Overtime
The AIT,determined
that refueling activities were conducted
with sufficient numbers of
personnel
that PP&L did not have to use overtime.
The work schedule
during refueling
consisted of three hours on the refueling bridge and three hours elsewhere in the plant for the
Refueling Floor, SRO.
The Refuel Bridge Operators worked four hours on the refueling bridge
and four hours elsewhere in the plant.
7.
Maintenance/Surveillance
Issues
Identified During the Outage
Related
to the
Refueling Bridge Main Grapple (Mast)
The AITreviewed records of work authorizations for the plant refueling equipment, including
the bridge and main grapple (or mast).
The AIT found that PP&L had been performing
preventive and corrective maintenance,
applying appropriate priority to these activities.
Prior to commencing refueling activities, PP&Lperformed appropriate mechanical and electrical
pre-operational checks ofthe refueling bridge and its attendant equipment using procedures. MT-
081-001,"Refueling Platform (Mechanical Inspection)," and MT-081-002, "Refueling Platform
(Electrical Inspection)."
As required by technical specifications (TS), appropriate
tests of the
refueling equipment interlocks and liftingcapabilities were also performed using surveillance test
procedures SO-1(2)81-001, "WeeklyRefueling Platform," and SO-1(2)81-002, "Refueling Bridge
Main and AuxiliaryHoist." The AITnoted that PP&L encountered difficultyin calibrating the
load cell for the main mast.
A recent modification of the load cell necessitated
that a new
methodology be performed.
Prior to commencing
the refueling activities, this method was
conducted using an approved work plan in lieu of an approved calibration procedure.
The AIT
determined that the method was appropriate; however, use of a work plan was inconsistent with
normal calibration or surveillance activities performed by PP&L since the work plan had not
been reviewed by PORC nor approved by station management.
However, the work plan was
10
performed in accordance
with an approved work authorization,
and the load cell calibration
methodology
had received
a technical review by both electrical
maintenance
and
system
engineering before implementation.
Afterreviewing the events that occurred during the present
refueling outage, PP&L made a formal procedure change to the electrical inspection maintenance
procedure which formally adopted the steps in the aforementioned work plan into the procedure
to calibrate the various load cells used on the refueling bridge.
Subsequently, PP&L found that the surveillance procedures were inadequate because the portion
ofthe tests that demonstrate the interlock features ofthe bridge travel and reactor manual control
system (to prevent inadvertent insertion of a fuel bundle and simultaneous
withdrawal of a
control rod) failed to require special operator controls as stated in the'plant TS.
Specifically,
the surveillance test required placing the reactor mode switch in the run or startup/hot standby
mode; and the TS required that a second licensed operator or other qualified individual verify
that all control rods remained fullyinserted at that time. This second verification process was
not incorporated into the procedures and, therefore, the TS requirement was never met until the
present change.
During the current refueling outage, the AITdetermined that a number of maintenance-related
activities associated
with the fuel handling equipment were not fully adequate.
These issues
were also identified by PP&L during its concurrent investigations.
The AIT reviewed the
proposed corrective actions and found that PP&L was appropriately addressing
the root causes
of these issues as described below in Sections 7.1 through 7.4.
7.1
Installation of Non-Q Grapple
During core offload on October 4, 1993, the Unit 1 grapple began to leak air.
On October 5,
mechanical maintenance removed the grapple from the Unit 1 mast and replaced it with a spare
grapple that was available on the spare mast present on the refueling floor. This work was done
using a "generic" support work authorization (WAH20382) that was approved for maintenance-
supporting activities for refueling.
Mechanical maintenance
was aware that there had been a
quality control (QC) hold on the spare mast since it was non-Q; but found no hold tag on the
spare mast and assumed
that the matter had been resolved and the materials had been released
for installation.
Unknown to mechanical maintenance,
QC had removed the hold tag from the
equipment to ensure that the tag would not be lost on the refuel floor; and assumed
that any
work to install the equipment would require a specific work authorization that QC would review
and thereby ensure that the non-Q issue was appropriately resolved before use.
The AITwas concerned about PP&L's failure to adequately control materials not approved for
use.
Specifically, for this piece of equipment, it was subsequently
determined
by safety
evaluation on October 22, 1993, that the non-Q grapple was acceptable for use.
Before that,
on October 5, 1993, an operability assessment
was completed per Non-Conformance Report 0
(NCR)93-112 that concluded that the grapple could be used pending final resolution of the non-
Q issue.
However, the equipment had already been placed in service prior to an appropriate
11
operability determination or adequate
resolution of the QC hold on use.
PP&L has taken
corrective actions to prevent recurrence including: use ofa specific WA for this type ofactivity,
additional controls to prohibit release of components for use when under QC hold, and revision
to the Final Safety Analysis Report to change the design criteria for refueling equipment.
The
AITconsidered these corrective and preventive actions adequate.
The AITconcluded that better
interdepartmental communications and management oversight could have prevented this problem.
7.2
Failure To Perform Required Surveillance Test
After mechanical maintenance replaced the grapple on the Unit 1 refueling mast on October 5,
1993, a post-maintenance
operability test was performed to prove proper equipment function
prior to commencing fuel handling activities, As previously stated, the grapple repair work was
accomplished
per a generic support WA.
A work plan was developed
and included EFR
R40382, which specified that the post-maintenance
test would be SO-181-002.
Subsequently,
a discussion was held between operations,
maintenance,
and the refueling manager in which a
change was made to the post-maintenance
testing so as to perform SO-181-001 in lieu of SO-
181-002.
SO-181-002 is a more rigorous test of the equipment's
load lifting capacity and
confirms operability of the refueling platform (bridge), its respective hoist, and some of the
bridge interlocks also tested in SO-181-001, which tests the interlock features of the refueling
platform and reactor manual control system.
After completing the post-maintenance
test, refueling activities recommenced
at 3:40 a.m. on
October 5, 1993.
Approximately 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> later, after noting that the grapple was still not
"qualified," a decision was made to perform SO-181-002.
This test was then performed, at
which time the interlock feature that prevents bridge travel over the reactor vessel while control
rods are withdrawn was found inoperable (see Section 7.3).
PP&L has since determined that
because a load-bearing component had been changed, SO-181-002, which tests the load capacity,
should have been performed before commencing refueling activities.
As a result, PP&L failed
to adequately test the operability of equipment after maintenance.
PP&L has
proposed
several
corrective
and preventive
actions
including:
modifying the
surveillance procedures
to have a specific procedure for each refueling bridge hoist; assessing
the adequacy of guidance for post-maintenance
testing for the refueling bridge; and providing
specific work instructions and proper post-maintenance
testing for refueling bridge work. The
AIT considered
these actions adequate.
7.3
Bridge Travel Interlock Failure
It was determined by PP&L that while the bridge was technically inoperable due to failing the
surveillance
test
and
fuel-bearing
components
had
been
moved
during
that period of
inoperability, the interlock would have prevented bridge motion over the core if a real fuel
assembly had been grappled in the main mast.
The test weight used for the surveillance activity
weighs between 350 and 400 pounds (ib). Electrical maintenance found that the interlock reset
12
value, while acceptable,
was set too high (close) to the interlock setpoint.
This resulted in the
interlock resetting with the test weight still loaded on the mast.
Since fuel elements
weigh
approximately 600 lb, the interlock should have performed acceptably ifbridge movement had
taken place with a fuel element instead of the test weight. The problems encountered by PP&L
in demonstrating
the operability of the bridge interlocks indicates a weakness
in developing
appropriate acceptance criteria. This may require PP&L to take action to pursue changes to the
plant TS in order to have sufficient margin in the operability tests.
PP&L plans to revise the
operability tests and the TS, as necessary,
to support appropriate acceptance
criteria.
7.4
Summary of Concerns on Maintenance and Troubleshooting on the Mast
(1)
After completing a modification to the load cells on the refueling bridge, calibration
procedures were not formally updated and approved by station management prior to use
of the equipment, resulting in the use ofa "work plan" instead of a station procedure for
calibration.
Updating of station procedures
due to facility modifications should be
completed before using the equipment.
(2)
A "non-Q" component
(grapple)
was installed in a "Q" system
and used
to move
irradiated
fuel.
Positive separation,
identification, and control of nonconforming
components
should prevent such use such for activities that are important to safety.
(3)
A generic or supporting WA was
used
to perform corrective
maintenance
on the
refueling equipment.
Corrective maintenance activities on components that are important
to safety provides valuable failure and performance data, as well as an opportunity for
QA/QC to observe
activities that are important to safety.
Use of a generic WA
potentially results in lost valuable information on the work performed and the practices
employed.
(4)
Ineffective interdepartmental communications on the refueling floor twice resulted in less
than
acceptable
conditions.
The first involved the installation
(and
use) of the
nonconforming component (grapple) on the refueling mast, and the second involved the
change to the post-maintenance
test requirement following that same activity.
(5)
Insufficient
guidance
exists
for
determining
appropriate
post-maintenance
test
requirements for the refueling equipment.
This led to using the wrong post-maintenance
test following the replacement of the grapple.
(6)
Surveillance activities, especially those used to determine the operability of the refueling
bridge interlocks required by facilityTS, have acceptance
criteria that appear to be too
restrictive for the instruments and test weights being used.
The refueling bridge TS, the
facilityprocedures,
and the standards (weights) used to calibrate and test the operability
of the required interlocks should be reviewed to ensure that the appropriate acceptance
criteria are established and achievable and that all requirements of the "Refuel Mode" TS
are being met.
13
7.5
Review of the Maintenance History of the Refueling Bridge Main Grapple (Mast)
The AITreviewed prior maintenance activities on the refueling mast to ascertain ifuncorrected,
repetitive conditions were present.
On the basis of this review and discussions with PP&L staff,
it appeared
that PP&L had not treated the fuel handling equipment with the care and attention
commensurate with equipment used for the safety-related activity of fuel handling.
PP&L had not, until these recent events, tracked or trended any corrective maintenance for the
refueling platform and fuel handling equipment.
In addition, the'SOOR, NCR, EWR and WA
history files all contained valuable information regarding the repeated
failures of the main
grapple (mast); however, PP&L apparently did not use this information in an effort to better
understand
the root causes
of the problems
and
then determine
effective corrective
and
preventive actions.
The AIT was concerned
that PP&L had sufficient information at least in
1986 or early 1987 that should have led to corrective actions at that time, and that may have
prevented these repeated failures.
On the basis ofPP&L trends that were performed during the AITinspection, the refueling masts
have been bent, or similarly damaged, about 15 times at SSES.
By independent review, the AIT
was aware of 13 such events.
On each occasion, PP&L repaired or replaced the bent sections
ofthe mast.
When damage was caused by operator error, additional corrective actions consisted
of training and counseling the operators involved, as described in Section 3.2.
These actions
were generally ineffective.
Moreover, during interviews with both maintenance
and operations staff, it became evident to
the AITthat craft personnel were aware of, and expressed concern to station management about,
the ineffective corrective actions.
Further, maintenance personnel stated that the mast problems
were caused by the way operators performed refueling activities. Similarly, operations personnel
stated that the masts were "weak" or improperly maintained.
The AIT found no evidence that
these
concerns
were
known by senior
operations
managers
or effectively addressed
by
maintenance
managers.
In 1986, five masts were damaged or bent during two separate refueling outages.
PP&L was
concerned about the high frequency offailure, and coincident costs, and began investigation into
the causes
so it could determine how to make the equipment more reliable.
An independent
assessment,
conducted by GE, at that time indicated that the masts were failing as a result of
operator actions.
GE proposed corrective actions to PP&L that included better barrier controls
to prevent operators from accidently hitting the mast or carried loads into objects along the path
of travel.
New operator actions were proposed to minimize the wear of the mast by restricting
travel, both in terms of acceleration
and deceleration,
and by limiting the degrees of motion.
Atthe time, and until the present, operators were permitted to move the mast/refueling platform
in three directions simultaneously and at any speed.
While the 1986 recommendations
clearly
stated that one of the root causes
was due to impact, the recommended
corrective actions also
reduced the operational stresses
resulting from the unrestricted bridge/mast movement methods
14
used by the operators
during refueling.
As stated
earlier,
had PP&L implemented
these
recommendations,
additional similar failures in 1987, 1988, 1989, 1992, and 1993 could have
been prevented.
No basis was found for PP&L's failure to implement GE's recommendations.
As a result of the failures in 1986, PP&L attempted to improve the reliability of the mast for
critical path refueling activities.
PP&L established
a reliability task team to improve the
performance of the equipment.
This team attempted to quantify the reliability of the type of
mast/refueling bridge used at SSES and elsewhere in the industry and to compare that with other
possible designs.
A pilot barrier control system was studied; however, it was determined that
it was subject to a high rate of "downtime" due to high humidity on the refuel floor affecting
the system's processor.
The barrier control system was not pursued." Having compared
the
performance of different mast designs, it was not clear to PP&L that a modification to a
different type of mast would prove beneficial.
During the 1990-1991 period, the reliability of
the equipment seemed
to improve.
As a result, the activities of the reliability task team were
given a low priority.
To reduce the schedule and cost impact of fuel handling equipment failures during refueling
outages, PP&L made it a practice to have both refueling platforms ready during unit outages,
and for the last two outages,
stored a spare mast on the refueling floor in case it would be
needed.
Their history of mast problems apparently indicated that masts would be bent and
PP&L wanted to be able to replace them in a timely manner.
The AITwas concerned
that in
spite ofevidence available to PP&L regarding more effective corrective actions to prevent mast
failures, management,
by its inaction, condoned the practices leading to repeated failures of this
equipment.
7.6
Summary of Concerns on Maintenance History
(1)
Ineffective failure data trending forimportant-to-safety equipment resulted in management
not being aware that its expectations were not being met in the area ofcorrective actions.
In a memorandum
to various plant managers,
contained
in an EWR package
that
documented
the investigation of the 1986 mast failures,
management
clearly expected
that corrective actions recommended
by GE were to be implemented.
However, these
actions were not implemented and no formal mechanism existed to ensure feedback of
performance
data to management
to show the effectiveness
(or in this case the lack
thereof) of the actions.
(2)
PP&L management
should have been aware of the staff concerns regarding the repeat
failures of the refueling
equipment.
In addition, PP&L management
apparently
considered
the failures to be nothing more than a financial loss, due to lost time on
critical path, rather than indicative of a potential concern of safety significance.
15
7.7
Potential Generic Concerns
While there are a number of potential causal
factors,
the AIT considered
that two failure
mechanisms of the mast bending/binding problems are highly probable.
The most likely cause
is either striking an object while in transit or movement of the bridge while the grapple is still
engaged
to a load that has been seated in its respective core or spent fuel pool location.
The
second likely cause is excessive moment forces caused by drag and unusual wear of the bearing
points, causing the structure to become
less rigid, and resulting in subsequent
failure with
continued use.
7.7.1
Operational Concerns
Preliminary AITinspection findings indicated that the vendor stress analysis is bounding only
for specific conditions, such as movement of the mast in the "X" or "Y" directions with a fuel
assembly load in the normal up position.
However, vendor-supplied information on the use of
the equipment does not specifically prohibit different operations, such as simultaneous movement
in three directions or fast acceleration/deceleration
while the mast is extended either loaded or
unloaded.
In addition, vendor-supplied training information on refueling operations also does
not specifically prohibit certain types of operations nor does it specify design restrictions or
limitations.
On the basis of this information, the AIT identified the following three potential operational
concerns:
(1)
acceptability of simultaneous three direction motion
(2)
acceptability of "fast" acceleration or deceleration with the mast fully extended
(3)
acceptability of the drag forces when moving double blade guides
PP&L surveyed the industry regarding the experience of refueling equipment failures.
found that while this information is hard to find, other utilities have also experienced
similar
failures; although, not to the extent ofSSES.
PP&L also found that some utilities have very few
such problems.
The plants with better performance records had one or more of the following
attributes:
(2)
(3)
(4)
some form of boundary protection, either by electrical interlock or through operational
procedure limitation on movement
short shifts for operators performing fuel maneuvers
(1.5 to 3 hr.)
, significant pre-outage preventive maintenance inspection program for the bridge and mast
fuel moves performed by a dedicated team or contractors
This information is still preliminary in nature.
At the conclusion of the inspection, PP&L was
still engaged in extensive engineering discussions with the refueling equipment vendor.
16
V.7.2
Design Concerns
The design of the spent fuel pool at SSES and its storage cells results in inadequate clearance
between the bottom ofa double blade guide suspended from the grapple at its normal up position
and the top of the bail handles for stored double blade guides.
This results in obstructions in
the spent fuel pool that can be accidently struck during refueling operations.
This can result in:
(1) bending the mast; (2) damage to the load that could cause a loss of debris into the reactor
vessel;
(3) or bent blade guide handles,
which could result in improper grappling and a
subsequent drop of the load onto fuel or interference with the proper insertion of a fuel bundle
into a fuel cell in the core.
Although the apparent damage to equipment at SSES is limited to
bent masts, possibly bent double blade guide bail handles, and superficial marks on the reactor
vessel wall and the reactor vessel flange protector due to impacts, it appears fortuitous that no
irradiated fuel has apparently been damaged,
according to PP&L records.
8.
Human Factors Issues
During the inspection, the AITidentified several instances in which human factors issues played
a role in the events.
These
included
concerns
on coordination of refueling
tasks
and
communications between the operators,
and operation of the refueling equipment.
A summary
of issues identified is contained in Attachment 6 to the report.
9.
Safety Significance and Management
Oversight and Control of Fuel Handling
Activities
Refuelings
are
relatively infrequently
performed
activities
which involve unusual
plant
conditions, potentially significant radiation exposures,
the opportunity to introduce. foreign
material into vital reactor plant systems,
and the need for well-defined and well-coordinated
responsibilities among several organizations.
As such, refueling operations constitute a safety-
significant activity, with the concomitant responsibility that it be treated
as such by plant
management
and personnel.
In reviewing PP&L's response
to previous events,
the AIT noted that some
areas of fuel
handling activities had not been treated
as safety-significant operations.
The AIT observed
repeated
instances where past evaluations stated "no safety significance"
or "increased outage
time" as the consequence
of the event reviewed.
In reviewing PP&L's response
to repeated
maintenance or replacement of bent mast sections, PP&L appeared to be more concerned with
economic factors (i.e., maintaining the timeliness of core offload/reload) than in treating the
problem as one affecting a safety-significant activity. The most telling evidence of this was the
fact that for recent refueling outages, PP&L routinely kept a spare mast on the refueling floor
in response
to the history of mast problems and the expectation that the spare would probably
be needed.
Although a contractor was hired to review mast bending problems in 1986, the
contractor's recommendations
for reducing wear and tear on the refueling equipment were not
implemented by PP&L.
17
The AITconcluded that operations management's
oversight of fuel handling activities was weak
and their failure to take more rigorous corrective actions from previous events allowed them to
reoccur.
Senior operations management
has always delegated oversight of these activities to the
refueling floor SRO.
The Operations Manager stated that this decision was made under the
belief that having a higher management
presence
on the refueling bridge would distract the
operators from their duties. However, while the desire to reduce distractions was commendable,
senior managers did not hold their people accountable,
nor communicate with them, so senior
managers
remained
unaware of concerns
and practices
known at the working level.
For
example,
senior
operations
managers
stated
they
had
never
heard of complaints
from
maintenance
personnel that fuel handling equipment problems were caused by the manner in
which operators were operating the equipment, yet many operations personnel at the level of
shift supervisor and lower were aware of this complaint.
Senior managers were unaware of the
fact that double blade guide handles could be hit when moving double blade guides in the spent
fuel pool, although this fact was learned from two operators during the AITinterview process.
Lastly, human performance problems during fuel handling operations have repeatedly occurred
over the years, yet operations management
oversight of these activities remained unchanged.
Other examples of the lack of senior operations management
oversight included:
(1) a PCAF
which was supposed
to be issued within a day after Event
1 was not issued until 12 days later,
a fact which the AITidentified to the operations senior managers;
and (2) a Shift Supervisor
assigned to observe and report back on refueling activities following Event 3 only observed 20
minutes of refueling activities before he left the refuel floor. The AITconcluded that this was
an inadequate amount oftime to verify the effectiveness ofprocedure changes implemented after
Event 3.
~
~$ REgy
c<
P
~4
O
O
I
X
~0
e+
++**+'ocket
Nos.
50-387
MEMORANDUMFOR:
FROM:
SUBJECT:
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION I
475 ALLENDALEROAD
KING OF PRUSSIA, PENNSYLVANIA19406-1415
October 29,
1993
Richard W. Cooper, II, Director, Division of Reactor Projects
Thomas T. Martin, Region Administrator
AUGMENTEDINSPECTION TEQvfCHARTER FOR REVIEW
OF REFUELING ACITVITIESAT SUSQUEHANNA
Over the last two weeks, multiple problems have been encountered during refueling operations
at Susquehanna Unit 1 involving fuel handling equipment.
Because the cause(s) of these events
is uncertain, there were repetitive instances of problems,
and there may be possible generic
implications, I have determined that an Augmented Inspection Team (AIT)inspection should be
conducted to review and evaluate the circumstances,
safety significance, and generic implications
that are associated with these problems.
The NRC staff needs to fullyunderstand the cause(s)
of these events and determine whether further actions willbe required.
This is consistent with
AITselection criteria 05.02, b, c, e and fin NRC Inspection Manual 0325.
Accordingly, the DivisionofReactor Projects (DRP) is assigned the responsibility for the overall
conduct of this Augmented Inspection.
Rob Temps, Project Engineer, DRP, is appointed as
Augmented Inspection'Team Leader (Other AITmembers are identified in Enclosure 2). The
Division of Reactor Projects
(DRP) is assigned
the responsibility for resident and clerical
support, as necessary;
and the coordination with other NRC offices, as appropriate.
Further,
the Division of Reactor Projects is responsible for the timely issuance of the inspection report,
the identification and processing
of potentially generic
issues,
and
the identification and
completion of any enforcement action waiTanted as a result of the team's review.
Enclosure
1 represents
the charter for the Augmented Inspection Team and details the scope of
the inspection.
The inspection shall be conducted
in accordance
with NRC Management
Directive (MD)8.3, NRC Inspection Manual 0325, Inspection Procedure 93800, Regional Office
Instruction 1010.1, and this memorandum.
Thomas T. Martin
Regional Administrator
Enclosures:
1.
Augmented Inspection Team Charter
2.
Team Membership
Richard W. Cooper, II
cc wlencls:
J. Taylor, EDO
J. Sniezek, OEDO
T. Murley, NRR
J. Partlow, NRR
J. Calvo, NRR
C. Rossi, NRR
L. Nicholson, Acting PD I-2, NRR
F. Miraglia, NRR
C. McCracken, NRR
F. Rosa, NRR
W. Russell, NRR
J. Richardson, NRR
A. Thadani, NRR
.
B. Grimes, NRR
J. Roe, NRR
E. Jordan, AEOD
D. Ross, AEOD
V. McCree, OEDO
W. Kane, DRA, RI
R. Cooper, DRP, RI
W. Lanning, DRP, RI
J. White, DRP, RI
W. Hehl, DRSS, RI
S. Shankman, DRSS, RI
S. Barber, SRI, Susqeuhanna
C. Sisco, DRS, RI
I.. Bettenhausen,
DRS, RI
W. Hodges, DRS, RI
E. Wenzinger, DRP, RI
K. Abraham, PAO, RI
M. Miller, SI.O, RI
ENCLOSURE 1
AUGMENT%) INSPECTION TEAM (AIT) CHARTER
The general objectives of this AITare to:
Review and evaluate the adequacy of the licensee's corrective measures,
in concert with
Region I management,
prior to agreeing to resumption of refueling activites
2.
Conduct a thorough and systematic review of the circumstances
surrounding each of the
refueling events which have occurred since October 1, 1993, and develop a detailed
seqqence of events for each occurrence.
3.
Collect, analyze,
and document relevant factual information to determine the causes,
conditions, and circumstances pertaining to each event.
Review qualifications of the refueling operators and training they received on refueling
operations.
5.
Evaluate the licensee's review ofand response to each event and implemented corrective
actions, as well as their plans for resumption of refueling activities.
6.
Review and assess the adequacy oflicensee s refueling, surveillance, and test procedures
as they existed before these events; and review and assess
the changes recently made in
these procedures.
'I
7.
Evaluate
the licensee's
procedures
regarding
during
refueling operations.
8.
9.
Determine ifthere are any generic implications that should be considered for further
review or evaluation by the NRC staff.
Determine the adequacy of management oversight and control of refueling activities.
10.
Assess
the
safety
significance of each
event
and
communicate
to Regional
and
Headquarters
management
the facts and safety concerns related to problems identified.
Prepare
a report documenting the results of this review for signature of the Regional
Administrator within thirty days of the completion of the inspection.
ENCLOSURE 2
AITMHHBKRSHIP
Robert Temps, AITLeader, Project Engineer, Division of Reactor Projects (DRP), Region I
(Rg
Robert Summers,
Assistant AITLeader, Project Engineer, DRP, RI
Carl Sisco, Operations Engineer, Boiling Water Reactor Section, OB, Division of Reactor
Safety, RI
Human Factors Assessment
Specialist, HHIFB, NRR
Scott Morris, Reactor Engineer, DRP, RI
Other NRC personnel,
consultants, or contractors willbe engaged in this AIT, as needed.
ATTACHMENT2
PERSONS CONTACTED
Pnn
lv
i Pwr
Liht
C. Boudman, Jr.
R. Byram
K. Chambliss
T. Dalpiaz
A. Dominguez
A. Fitch
T. Gorman
R. Heim
G. Jones
D. Karchner
J. Kenny
G. Kuczynski
V. Kelly
R. Lengel
D. Marinos
T. Markowski
K. Mattern
D. McGann
J. Miltenberger
L. O'eil
H. Palmer
D. Roland
D. Roth
A. Sabol
R. Saccone
H. Stanley
H. Woodeshick
P. Zabawa
Asst. Foreman, Mechanical Repairs
Senior Vice President - Nuclear
Supervisor, Maintenance Production/Outage
Manager, Nuclear Maintenance
NSAG Site Supervisor
Operator Training
Senior Engineer, Systems Analysis
Senior Quality Control Specialist
Vice President - Engineering
Power Production Engineer
Supervisor, Nuclear Licensing
Manager, Nuclear Plant Services
Sr. Maintenance Project Eng., Maintenance Technology Group
Project Engineer, Nuclear Steam Supply Systems
Senior Nuclear Plant Specialist
Supervisor, Dayshift Operations
Supervisor, NSS Maintenance
Supervisor, Nuclear Compliance
Manager, Nuclear Safety Assessment
Special Assistant, Sr. Vice President - Nuclear
Manager, Nuclear Operations
Operations Shift Supervisor
NSSS Supervisor, NSE
Manager, Nuclear Quality Assurance
Manager, Nuclear Systems Engineering
Vice President, Nuclear Operations
Special Assistant to the President
Electrical Maintenance
ene
1 Electric
D. Rousal
Senior Engineer
ATTACHMPfT3
DETAILEDTIIVKLINESFOR EVENTS 1 THROUGH 4
Unit 1 reactor shutdown.
Refueling outage commenced.
+1~/1 Q
Surveillances SO-181-001 (Weekly Refuel Platform Operability) and SO-181-002
(Unit
1 Main/Aux Hoist Operability) completed
satisfactorily on the Unit
1
refueling bridge.
2117
Core offload commenced with the Unit 1 refuel bridge.
Mtt94L92
Unit 1 refuel mast grapple developed an air leak. A spare, "non-Q" grapple was
installed on the mast as a replacement (NCR 93-112 had been initiated previously
to make the component "Q").
The spare grapple had been pre-staged
on the
refuel floor prior to the start of the outage.
(See Section 7.0.)
0320
Completed a partial SO-181-001 surveillance (i.e., did not perform the Control
Rod Out & Bridge Travel Interlock test) on the repaired Unit 1 mast.
0340
The bridge operator was "uncomfortable" with the refuel bridge mast because SO-
181-002 was not conducted as post maintenance testing, so he grappled and lifted
the 1200 pound test weight to verify mast integrity before continuing fuel moves.
Defueling operations were then resumed.
0826
Stopped defueling to accommodate
a manual scram in support of CRD activities
under the reactor vessel.
Surveillance procedure
SO-181-002 was performed
because of questions raised about the operability of the Unit 1 mast after the new
grapple was installed.
1500
Unit 1 mast failed SO-181-002 when the interlock which prevents bridge travel
over the core with a load on the mast and with a control rod withdrawn one notch
failed.
Operators
prevented
actual movement over the core.
Maintenance
personnel were called in to troubleshoot.
(See Section 7.0.)
AIN683
Electrical Maintenance personnel recalibrated the load cell on the Unit 1 bridge
hoist.
Surveillance SO-181-002 complete.
0115
0220
Surveillance SO-181-001 complete.
Resumed fuel offload.
0744
K
NT
1: A peripheral bundle was incorrectly removed from core location
31-56 (vice 29-55, adjacent to 31-56).
Contrary to procedural
requirements
(Precaution 6.2.1 ofOP-AD-107), the bundle was returned to its original location
in the core after the SRO on the bridge received direction from the outage
supervisor to place it there.
The bridge SRO was under the assumption that the
outage
supervisor's
decision
had
the concurrence
of the reactor
engineer.
However,
due
to miscommunication
by the outage
supervisor,
the reactor
engineer thought the bundle had already been placed back in the core and he
stated that he was going to check procedures to see ifany requirements had been
violated as a result ofplacing the bundle back in the core.
The outage supervisor
thought he had permission from the reactor engineer to place the bundle back in
the core and relayed this to the bridge SRO. The Shift Supervisor was not aware
of any of these activities until after the fact, although by procedure,
he is
responsible for directing fuel handling activities.
1033
Defueling resumed following corrective actions by operations management.
M/99LB
0113
Core offload completed.
ML22K
1755
Completed surveillance procedures
SO-181-001
and SO-181-002 on the Unit 1
refuel bridge.
ML22l93
0737
Commenced core reload.
=0950
While moving the unloaded refuel bridge from the reactor cavity to the spent fuel
pool, the mast grapple head contacted the reactor vessel flange protector, bending
the mast (deterinined by PP&L 1 week after the event) causing a "Fault Lockout"
on the bridge and leaving a distinct scrape marking on the reactor vessel flange
protector.
Operators were unaware of the cause of the lockout: the lockout was
reset and refueling continued.
1008
~NT:
D
U* * Rl
- ,
Ill
1
g.*f lb
dl
location
13-48,
a 10-inch
section of the telescoping
mast
"hung up" and
subsequently dropped 10-15 inches.
Operators stopped lowering the mast at 375
inches and verified that there was no slack cable alarm p'resent (i.e., the bundle
itselfdid not move during the event).
Operators on the bridge checked the bundle
and core top guide for interference, then lowered the fuel bundle into its intended
location. The operators then moved the mast to a defueled region of the core and
attempted to recreate the event by extending and retracting the mast.
On the third
cycle of the mast, the condition was reproduced.
The operators
reported the
incident to the Shift Supervisor and fuel handling activities were suspended.
=1100
Mechanical
maintenance
personnel
identified a bend
in the mast following
inspection of it. Maintenance recommended
the use of the Unit 2 bridge for the
completion of refueling.
ML2ZLM
0630
0850
Surveillances SO-181-001 and SO-181-002 completed on Unit 2 bridge.
Commenced refueling with the Unit 2 bridge.
1538
EVENT¹: A double blade guide (removed from core locations 37-22 &39-
24) impacted the pressure vessel wall during its movement from the core to the
fuel pool. Just prior to impact, the SRO on the bridge realized that the mast was
not raised high enough for the blade guide to pass through the transfer canal
(grapple height was 150 inches which is satisfactory for mast movement without
a load attached).
The bridge was stopped (and its direction actually reversed)
prior to the mast impacting the wall, but the momentum of the blade guide
allowed it to swing forward and strike the vessel wall. The mast was then raised
to the proper height and the blade guide moved to its intended location in the fuel
pool.
1945
Mechanical Maintenance
personnel
conducted
a visual inspection of the mast
using a video camera
and identified a distinct "bow" in the 10-inch section;
however, they did not identify any contact/friction points or other observable
damage.
The mast was cycled up and down several times without any abnormal
indications.
The 1200 pound test weight was lifted to ensure
mast structural
integrity. After concurrence by operations and maintenance personnel,
the mast
was cleared for use.
The vessel wall was also inspected using the video camera
and no non-conforming conditions were noted.
2349
Resumed fuel reload after plant management
modified the refueling procedures
(e.g. requiring the mast to be fullyraised prior to moving the bridge between the
reactor cavity and the fuel pool, raising the mast in "slow" speed only) and
implemented other short term corrective actions.
ML2E93,
0231
Refueling operations were suspended
when operators were unable to seat a fuel
bundle in core location 13-24 due to interference from a bent blade guide handle
in the adjacent cell.
The fuel bundle was returned to the fuel pool at position
DD-29 per reactor engineer direction.
The interfering double blade guide (in positions 13-22 and 15-24) was moved to
the fuel pool.
Refueling operations resumed.
0707
2 more bundles moved into the core (within 9 minutes).
0710
EVENT
4: While lowering the mast in preparation for grappling a new fuel
bundle in the fuel pool, one of the telescoping mast sections "hung up" and then
suddenly dropped. A large amount ofbubbles were observed in the pool for 5-10
seconds followingthe event. Final mast conditions indicated a normal air system,
mast position of 206 inches, load cell reading of 193 pounds, and no slack cable
alarm.
No radiation alarms were received.
Refueling operations were stopped.
Inspection of the mast revealed
that the 10-inch section
was bent,
(PP&L
subsequently determined that the cause of this event was due to weakening of the
mast from EVE%I'
and subsequent
mast weakening and eventual bending from
hydrodynamic forces on the mast as a result of rapid bridge movements.)
Preparations were made to replace the mast on the Unit 1 bridge in order to ready
it for refueling.
1130
The SSES Vice President - Operations directed a halt to'fuel loading pending the
completion of an'vent
Review Team
investigation
and implementation of
comprehensive corrective actions.
1700
The previously
damaged
Unit
1
mast
was
removed
from its bridge.
By
agreement with Region I management,
PP&L agreed to curtail further refueling
activities.
~1/2
$Q
1200
NRC Augmented Inspection Team arrived on site.
ATTACHMENT4
PREVIOUS IMPACT EVENTS AT SSES SINCE 1984
(1)
3/29/84; Unit 2: A fuel bundle hit the transfer canal ("cattle chute"). PP&L attributed
the root cause to one oftwo possibilities; slippage of the fuel hoist or a stuck downbutton
on the hoist.
The bundle was inspected,
no problems
were noted,
and no other
corrective actions were taken beside maintenance activities.
(2)
3/31/84; Unit 2:
An operator forgot to retract the hoist after releasing
a blade guide.
The bridge was moved and the mast was bent when the grapple caught on a blade guide
bail handle.
Cause of the event was attributed to the operator's
overzealousness
and
inexperience.
Corrective actions comprised improving training and ensuring that any
operator moving fuel for the first time would be supervised by someone who had actual
fuel handling experience.
(3)
3/22/86; Unit 1:
The mast
experienced
binding while lowering
a fuel bundle.
Maintenance
determined
the binding was due to an "external force" which bent the
sections.
The mast was replaced with Unit 2's mast.
No explanation of the "external
force" was given, nor did the SOOR issued for this event address or explain what the
force was. (See Section 7.)
(4)
4/13/89; Unit 1:. Operators were unable to release a double blade guide from the hoist.
The blade guide had to be physically pried from the grapple.
The cause was attributed
to a bent bail handle.
Before this event, the bridge operator had banged the blade guide
into the transfer canal.
The SOOR for this event stated that how or when the handle was
bent could not be determined.
The SOOR discounted the impact as the cause for the bent
handle.
(5)
10/16/89; Unit 2: An operator was heading for the transfer canal when he realized his
Y coordinate was wrong.
He stopped bridge movement and moved the mast in the Y
direction.
However, he ran the mast into the side railing of the chute and damaged
the
mast.
Root cause was attributed to the operator being tired and anxious for turnover and
inattention to detail.
Corrective actions were administrative in nature.
(6)
10/16/92; Unit 2:
The mast was damaged
when it contacted the transfer canal.
The
bridge was being moved to the spent fuel pool.
The root cause
was attributed to
inattention to detail.
The SOOR for the event stated that it was an isolated instance.
ATTACHMI<2lT5
BUNDLE/BLADEGUIDE MOVEMENTERRORS
The following history of bundle/blade guide mis-manipulations
was compiled from various
SOOR's.
SOOR numbers appear in parentheses.
m r2
1
2-
1
EVENT:
Fuel bundle found in incorrect position in the core.
CAUSE:
Operator error.
ACTION:
Incorporate lessons learned into training before the next outage.
S
tern
r 27
1
7
1- 7-27
and 271
EVENT:
CAUSE:
ACTION:
3 double blade guides removed from wrong location.
Failure to follow procedure; operator error.
Issued management letter to all licensed operators.
EVENT:
CAUSE'CTIO¹
Fuel bundle removed from wrong location in the core.
Failure to follow procedure;
operator error.
Issued management letter to all licensed operators.
A
11
1
2- -1
EVENT:
CAUSE'CTION:
Wrong fuel bundle placed in the core.
Operator error.
Incorporated lessons learned into operator training; purchased
a new "sight box"
to aid in peripheral vision; Reactor Engineering revised RE-TI-004 (to provide
copies of all changes
to the core component movement sheets to Operations
so
that it can trend the number of mispositioning occurrences).
1-
-127
EVENT:
CAUSE'CTION:
Fuel bundle placed in wrong location in the fuel pool.
Operator error.
Essentially none. In the SOOR analysis, Reactor Engineering stated that all steps
known to prevent errors were taken and no further actions were needed to prevent
recurrence.
m
r
1
1
2-
-12
EVENT:
Wrong fuel bundle moved during core reload.
CAUSE:
Operator error.
ACTION:
Counseled operators.
7
EVENT:
CAUSE:
ACTION:
Moved fuel bundle without verifying all initial conditions.
Operator error.
Address
in
operator
training;
Enhanced
procedures
regarding
suspending/reinitiating
fuel movements.
2
1
2
1- 2-
EVENT:
CAUSE'CTION:
3 fuel bundles found in wrong position in the fuel pool.
Lack of attention to detail; operator error.
Verified accuracy of position counters; permanently label trolley beams.
ATTACHMENT6
HUMANFACTORS CONCERNS
1.
COMMUNICATIONS
During Event I, the operators'esponse
to an incorrect fuel bundle being pulled from the core
was compromised by a communication error between
the outage supervisor and the reactor
engineer.
The reactor engineer understood that an incorrect bundle had been removed from the
core, and replaced in the core, in its original position.
In reality, the bundle had not yet been
returned to the core.
As a result, the reactor engineer did not state that the bundle should not
be replaced in the core. The outage supervisor believed that he had communicated to the reactor
engineer that he intended to return the fuel bundle to that location from which it had been
removed.
In the absence ofreceiving any prohibition from the reactor engineer concerning this
action the outage supervisor directed the fuel to be returned to the core.
The SRO on the bridge in charge ofrefueling activities, having recognized that an incorrect fuel
bundle had been withdrawn from the core, terminated the fuel movement and communicated to
the control room his recommendation
that the fuel be placed in a location in the fuel pool that
had been reserved for placement of fuel in emergency conditions.
When the outage supervisor
directed
the fuel to be returned
to the location within the core from which it had
been
withdrawn, the SRO understood this decision to have been made based upon consultation with
Reactor Engineering and as a result he did not question the decision.
2.
OPERATOR VIGILANCE
Interviews with operators
involved in the four events
revealed
that the majority of. these
individuals described their refueling bridge duties as "boring" and "monotonous."
Although
reflecting
a professional
attitude regarding
their responsibilities,
most of the individuals
interviewed indicated that they generally did not look forward to assignments on the bridge. The
novelty and enjoyment of working on the bridge quickly was supplanted by boredom, and it
became difficultto maintain the level ofconcentration required by the task. In contrast, a small
minority of the operators
interviewed stated that they enjoyed refueling bridge assignments.
Most of the interviewees indicated that they had been assigned
to refueling bridge activities.
Many of them also indicated that they would like refueling bridge assignments
to be voluntary.
The opinions of the individuals regarding refueling activities did not appear to be affecting the
professionalism
of the staff in completing
refueling activities.
However,
the boredom
experienced by the operators
can be a direct precursor to lapses in attention.
Whereas
lapses
in attention due to the repetitive nature of the task did not appear to be causal factors in these
recent events, such lapses in attention can be reasonably expected to degrade the performance
of the operators in conducting refueling activities.
3.
WORK SCHEDULES
Many operators noted that the length of time that individuals were assigned to refueling bridge
operations had been decreasing in recent years and that during the current refueling outage Ros
were assigned to be on the bridge for two 3-hour stints during their 12-hour shift. Time offthe
bridge was considered
rest periods.
SROs are now assigned 4-hour stints on the bridge.
The
reduced number of consecutive hours on the bridge was viewed positively by the individuals
interviewed, considering their views concerning the repetitive nature of the job.
4.
HUMANSYSTEM INTERFACE
The inspector examined the refueling bridge controls while the bridge was under quarantine and
consequently not operating and displays not illuminated.
The inspector interviewed an RO and
SRO on the bridge regarding their tasks during bridge operations,
and
the controls
and
indications used to perform these tasks.
4.1
Uncontrolled Operator Aid
The inspector observed a placard hung at the controls ofthe refueling bridge which had numbers
written in grease pencil that gave the operators information, including mast height required for
clearing the transfer canal with no load on the mast,
and mast extension
points at which
operators need to slow down. However, derivation and controls on the use of this operator aid
could not be determined.
4.2
Team Work
Events 2 and 3, and an event from the 1992 Unit 2 refueling outage (SOOR 2-192-127) in which
the mast struck the flange protector, all demonstrated
inadequate team work. In these cases, the
were performing activities related
to fuel movement,
but failed to provide timely
verification that the Ros were operating the bridge and mast clear of obstructions.
4.3
Task Design/Equipment Configuration
Events have occurred while using the other unit's refueling bridge. For example, a Unit 2 1992
refueling outage event (SOOR 2-192-127) involved the Unit 1 bridge "backing" into the transfer
canal with the mast extended.
Using the bridge of the opposite unit for fuel movement activities results in the operator
"backing" a bridge from the reactor vessel into the transfer canal.
As a result, operators turn
their attention from the mast (Z coordinate) to verify proper X and Y coordinate alignment with
the transfer canal.
Consequently,
such configurations increased
the probability that the bridge
operator
could lose track of mast
status
and approach
the transfer
canal with the
mast
inadvertently extended.
A GENDA
PPdkL/NRC IVD&AGKMKNTMEETING:
FUEL HANDLINGAIT
November 18, 1993
1VRQMGEMENTPERSPECTIVE.......
R. G. Byram,
LESSONS LEARNED/
CON%ECTIVE ACTIONS ..........
H.G. Stanley
SUMMARY ......................
R. G. Byram
MANAGEMENTPERSPECTIVE
The NRC AIT provided a valuable independent
perspective.
Recurring problems with fuel handling practices
have caused us to examine the effectiveness of our
assessment
and corrective action programs.
We'e
completed
a
comprehensive
review
to
identify issues and take corrective actions.
Short term corrections, including generic issues,
have been implemented.
Intermediate
(by March,
1994
Unit
2
RFO)
corrections
have
been
identified
and
are
in
progress.
~
A long term evaluation ofthe broader implications
is being performed.
We are confident that the results will be effective
for the long term, and as a result will strengthen
our organization.
MANAGEMENTPERSPECTIVE
PPd'cL has a strong record regarding the resolution of
issues
related
to
the
design
and
operation
of
Susquehanna.
We
take
aggressive
measures
where
safety
is
challenged.
Our people do high quality work
Our management
is involved.
MANAGEMENTPKRSPKCTA"E
PPckL
recognizes
that
our
actions
have
been
ineffective in resolving long standing problems with
fuel handling activities.
The
individual
events
had
broader
safety
implications.
Our actions were inconsistent with our phi1osophy
on shutdown risk.
We did not provide our people with the tools they
needed to succeed.
We have not met our values in this area; we are changing
our standards.
MANAGEMENTPKRSPKCTA'K
The duration ofa refueling outage is defined by the
time it takes to ensure the safe performance of all
activities and safe operation for the next cycle.
Questioning attitudes will ensure safety remains
'our top priority.
Reinforcement of this expectation
is a required.
response to the internally driven pressure of highly
motivated people.
Management must lead by example, listen, and be
vigilant
to
ensure
that
critical
path
never
supersedes
safety.
MANAGEMENTPERSPECTIVE
'PPckL
is
taking
aggressive
actions
to
resolve
identified problems, and to continue to assess
the
broader implications.
We have analyzed the information both specifically
and generically.
Short
term
corrective
actions
have
been
implemented that address both the specific events
and their commonalities.
Intermediate
and longer term actions have been
identified.
Independent,
outside insight will be sought and
utilized.
R.G. BYRAM
Senior VP Nuclear
H.G. STANLEY
VP - Nuclear Operations
A.R. SABOL
Manager - Nuclear
Quality Assurance
G.J. KUCZYNSKI
Manager-
Nuclear Plant Services
J.R. MILTENBERGER
Manager - Nuclear
Safety Assessment
~ Verification Of Actions
~ NQA Performance
~ Refueling Floor Management
~ Event Commonalities
~ Station Culture
~ Department Culture
~ Self Assessment
~ Department Response to NRC AIT
~ NSAG Performance
MANAGEMENTPERSPECTA
"E
LESSONS LEAEUVED
~ Clearly set forth management
expectations.
~ Solve recurrent problems
~ Preserve
and
enhance
strong
Susquehanna
safety
culture.
October 6, 1993
Core Offload Error
October 26, 1993
Unit 1 Refueling Bridge Mast
Non-Load Bearing Telescoping
Section Dropped
October 27, 1993
Double Control Rod Blade Guide
Impacted Vessel Wall While Being
Moved
October 2S, 1993.
DifficultyExperienced With Aligning
Fuel Bundle In Core
Unit 2 Refueling Bridge Mast
Non-Load Bearing Telescoping
Section Dropped
V.P.- Nuclear Operations Stopped
AH Refueling Activities
(Later, Same Day) AITAnnounced
By NRC Region I With
Confirmatory Action Letter
EATTSTIGA2VONAl'G)ANALFSIS
~
Seven Event Reviews
~
Station Management Review Of Each Event
~
NSAG Assessments During Event Reviews
h
~
Management Review Teams
Management Of Refuel Floor
Look For Commonalities With Other Station
Operating Events
Station Culture
Department Culture
Effectiveness Of Self-Assessment
REFUELING OPERATIONS HISTORICAL
PERSPECTEVE
~
Several
Previous
Occurrences
Of Bent Mast
Assemblies At Susquehanna
~
Higher
Frequency
Of
Occurrences
At
Susquehanna
Compared To Industry
~
Each Event By Itself Was Not Judged
To Be
Significant
Incomplete Determination Of Root
Causes
Did Not Identify Adverse Trends
Generic Implications Not Assessed
BASICROOT CAUSES
~
Management Oversight
Command and Control
Structured
Monitoring Of Fuel
Handling
Activities
Followup On Corrective Actions
Communication Of Management Expectations
Self Assessment
~
Procedures
Design Limitations/Operating Constraints
OffNormal Procedure
Comprehensiveness
(Operations
And
Maintenance)
User Friendliness
BASIC ROOT CAUSES (continued)
~
Training
Consistency With Management Direction And
Expectations
Monitoring
Significance Of Refueling Activities
~
Culture
Threshold For Taking Management Action
Acceptance Of Human Error As Root Cause
Without Further Inquiry
Perception Of Expectations For Critical Path
Activities
Integrated Management
Structure For 'Refuel
Floor Activities
Follow-Up On Implementation Of Corrective
Actions
'
COKRF<CTEVEACTIONS
~
Near Term (Prior To Commencing
Unit
1 Core
Reload)
~
Intermediate Term (Prior To Unit 2 6th Refueling
Outage - March '94)
~
Long Term
)VEER TERiVCOEREC17VE< ACTIONS
MANAGEMENT
~
Establish Refueling Floor Manager
SRO Certified
Recognized Leader
TechnicaHy Competent
Reinforces Chain of Command
~
Strengthen Engineering Support For Refueling Floor
Activities
System Engineer Assigned
Implement Short Term Recommendations
~
Leadership
Listening
Communication
Teamwork
Resolution of Concerns
1VEAR TERM CORRECTIVEACTIONS
PROCEDURES
~
Upgrade Maintenance
Procedures For Maintaining
The Refueling Bridge
~
Develop Integrated Single Procedure For Conducting
The Unit 1 '7th Refuel Outage Core Reload
~
Develop
Specific
Procedure
For
Off Normal,
Refueling Bridge Operations
N
~
Revise And Perform Specific Surveillance Procedures
For Refueling Bridge Operability
~
Institute
Refueling
Floor
Management
Administrative Procedure/Program
1VEAR TERM CORRECTIVE< ACTIONS
TRAINING
~
Complete Training For Operations
On Refueling
Bridge Operation And Procedure For Unit
1 7th
Refuel Outage Core Reload
1VEAR TEEiVCORRECTEVEACTIONS
CULTURE
~
Communicate Expectations To Station Personnel
High Standards
Zero. Defect Goals
Supervisory Follow-Up And Monitoring
Teamwork
Listening And Acting On Issues
Management Visibility
Schedule Pressure
~
Institutionalize
The
Concept
That
Root
Causes
Attributed To Human Error WillBe Probed Deeper
To Determine Why Human Error Occurred
IN)WRMZDJATETERM CORRECT?lVE ACTIO1VS
RJOR TO ANT2 6TH REEEJEL OUTAGE
MANAGEMENT
~
Critique Unit I 7th Refuel Outage Core Reload With
Refueling Floor Manager Concept/Adjust Program
For Unit 2
~
Select/Train
Permanent
Personnel
For Refueling
Floor Management
~
Assess
Operation
Support
Staff
Performance,
Training, Qualifications And Organization
~
Evaluate Actions Required On The List Of Other
Equipment/System
Issues
For Unit 2 6th Refuel
Outage Work
~
Implement
Short- Term
Engineering
Recommendations
On The Unit 2 Refueling Bridge
~
Communicate Lessons Learned To Industry
I1VTERMZDIATETERM CORRECTEVZ-ACTIONS
RIOR TO ANT2 6TH REFUEL OUTAGE
PROCEDURES
~
Review
Fuel
And
Core/Fuel
Pool
Handling
Procedures
To Be
Used For Unit 2 6th Refuel
Outage and Revise Accordingly
~
Enhance Refueling Bridge Test Weight Issues
Tech Spec Changes
Procedures/Work Controls For Weights
INTEMCZDIATETERM CORtK'CTEPZ ACTIONS
RIOR TO UlVET2 6TH REFUEI. OUTAGE
TRAINING
~
Identify
Specific
Training
Needs
For
Fuel
Handling/Core Component Handling Activities And
Adjust/Conduct Training Accordingly
INTEN/MEDIATETERM CORRECTIVE< ACTIONS
RlOR TO ZUVTT2 6TH REFUEL OUTAGE
CULTURE
~
Perform
A 'DACUM'rocess
For Supervisory
Training In.Areas Of:
Listening
Follow-Up
Monitoring
High Standards
include In Employee Concerns Module)
INTERMEDIATETERM CORRECTIVE ACTIONS
(PRIOR TO UNIT 2 6TH REFUEL OUTAGE)
Cu1ture (Cont.d)
~
Communicate
Expectations
To
Department
Personnel
High Standards
Zero Defect Goals
Supervisory Follow-Up And Monitoring
Teamwork
Listening And Acting On Issues
Management Visibility
Schedule Pressure
INTERMEDIATETERM CORRECTIVE ACTIONS
(PRIOR TO UNIT 2 6TH REFUEL OUTAGE)
Culture (Cont.d)
~
Lower The Threshold
For Writing SOORs
and
Improve Corrective Action For Repeat Events
~
Lower
The
Threshold
For
Conducting
NSAG
Investigations
~
Revise Scheduling 'Terminology'
Conduct Thorough Human Factors Review Of SSES
Refueling Platforms
LONG TERM COEtK'CTIlVE ACTIONS
MANAGEMENT
~
Benchmark The Industry For The Be'st Refueling
Floor Management
~
Conduct/Host An INPO Assist Visit On Refueling
Floor Management
~
Institutionalize
Refueling
Floor Assessment
And
Monitoring
~
Strengthen The Operations Staff Support Function
~
Implement The Results Of Evaluation Performed
For List Of Other Equipment/System
Issues
~
Implement
The
Long
Term
Engineering
Recommendations
On The Refueling Bridges
~
Review Root Cause/Corrective
Action Process
and
Recommend Changes
LONG TENN COP/K'CTIME ACTIONS
PROCEDXH&S
~
Perform A Review Of Related
Refueling
Floor
Procedures And Upgrade Accordingly
~
Perform A Review Of Work Controls (Preventive
And Corrective) For Refueling Floor Work And
Upgrade Accordingly
LONG TERM COEtK'CTIjVEACTIONS
TRAINING
~
Review
And
Upgrade
Training
Programs
For
Personnel
Who Perform Work Activities On The
Refuel Floor
LONG TERR CO%)V<CTEVZACTIONS
CULTURE
~
Conduct Re-training For All Personnel On Nuclear
Department
Supervisory Training Matrix On The
Expectations Of:
Listening
Follow-Up
Monitoring
High Standards
Employee Concerns
~
Institutionalize A More Stringent Corrective Action
Program For Dealing VVith Repeat Events
~
Implement
Human
Factors
Review
Recommendations
On Both Refueling Platforms
fBK4THAVE PX LEANVED?
~
Clearly Set Forth Management Expectations
Communicate Individual Performance Objective
Of Zero Defects
,Conduct Verifications With Questioning Attitude
Provide Checks And Balances Through Effective
Oversight
Reinforce Teamwork
Lead By Example
~
Solve Recurrent Problems
Lower Threshold To Initiate Action
Identify True Root Causes - Particularly For
Human Performance
Strengthen AbilityTo Detect Recurring Problems
Generic Implications
Status Control
WHATHAVE WE LEARNED? (continued)
~
Preserve And Enhance Strong Susquehanna
Safety
Culture
Reconfirm Commitment That Safety Is Not
Compromised By Schedule
Better Utilize Assessment
Resources And Listen
To Their Messages
Strengthen Elements Of Defense-In-Depth
(Training, Procedures,
Design) Commensurate
With Expectations
MANAGEMENTPERSPECTA'E
PPdlL is committed to learning from these issues and
strengthening our organization for the long term.
We are taking a comprehensive, aggressive look
at ourselves.
We willlisten, and face the facts openly as they
unfold.
We are setting new standards,
and will take
steps to ensure behavioral changes occur.
The results will be effective for the long term,
and
ensure
an environment of cooperation,
communication, and teamwork.
V
U.S. NUCLEAR REGULATORY
COMMISSION
REGION I
REeg
~O
+
0
Cy
C
0
)'
i
C
Cl,
a
a
Yr
+n
~O
+~*~+
SUSQUEEDd~A
AUGMEXIEDINSPECTION TEAjM
EXIT
NOVEMBER 22, 1993
PURPOSE OF AN AIT
~
LOWEST LEVEL OF NRC INCIDENT
INVESTIGATIONPROGRM4 FOR RESPONSE
TO OPERATIONALEVENTS
~
CONDUCT A TIMELYAND THOROUGH
INSPECTION WITH THE EMPHASIS ON
FACT-FINDING
~
COLLECT AND ANALYZETHE FACTS TO
DETERlvtINE CAUSE(S) OI'HE EVENT
~
ASSESS THE SAFETY SIGNIFICANCE OF THE
EVENT
AN AIT~E
HQX:
~
DETERMINE WHETHER NRC RULES WERE
VIOLATEDOR RECOMMEND
ENFORCEMENT ACTION
~
ADDRESS THE APPLICABILITYOF GENERIC
CONCERNS TO OTHER PLANTS
EXIT AGENDA
~
AIT CHARTER
~
EVENTS DISCUSSION AND FINDINGS
~
ADEQUACY OF CORRECTIVE ACTIONS IN
LIGHT OF PREVIOUS SIMILAREVENTS
~
FUEL HANDLINGPROCEDUI&S
SAFETY SIGNIFICANCE OF FUEL HANDLING
ACTIVITIES
MANAGEMENTOVERSIGHT A2'G) CONTROL
OF FUEL HAM)LINGACTIVITIES
MAINTENANCEASSESSMENT
~
GENERIC IMPLICATIONS
~
POST AITACTIVITIES
AIT CHARTER
WEIY THE AIT%AS CONDUCTED
~
SCOPE AM) OBJECTIVES
(1) Determine the cause(s) of each event
(2) Determine the adequacy of PP&L's
response
to each of the events
~
ASSESS SAFETY SIGNIFICANCE
~
DETERMINE ADEQUACYOF MANAGEMENT
OVERSIGHT
~
REVIEW ADEQUACYOF PROCEDUI&S AND
TANNING
~
DETE
POSSIBLE GENERIC
IMPLICATIONS
AITMEMBERS
TEAM
LEADER
TEAM
MEMBERS
R. Temps
Project Engineer, DRP
R. Summers
Project Engineer, DRP
D. Desaulniers
Human Factors Specia1ist, NRR
D. Mannai
Resident Inspector, DRP
C. Sisco
Operations Engineer, DRS
S. Morris
Reactor Engineer, DRP
EVENTS DISCUSSION R FINDINGS
~
EVENT 1:
October 6, 1993
"FUEL MOVEMENTERROR"
~
EVENT 2:
October 26, 1993
"MAST DROP"
EVENT 3:
October 27, 1993
"BLADEGUIDE IMPACT"
~
EVENT 4:
October 28, 1993
"MAST DROP"
~
OTHER CONCERNS
THE FOLLOWINGWILLBE DISCUSSED FOR
EACH EVENT:
(1) Event Details
(2)
Cause
(3) Corrective Actions
(4) AIT's Assessment of Corrective Actions
ADEQUACYOF CORRECTIVE
ACTIONS IN LIGHT OF PREVIOUS
SIMILAREVENTS
~
MMEROUS EVENTS OF THIS KINDHAVE
OCCUIGXD AT SSES SINCE 1984
~
ADEQUACYOF CORI&CTIVEACTIONS
ASSESSED IN TMREE &AREAS:
(I) Events Involving Impact to the Mast/Grappled
Components
(2) Bundle and Blade Guide Movement Errors
(3) Mast Damage Due to Unknown Causes
~
INADEQUACIES IDENTIFIEDBY THE AITIN
PPEcL's ROOT CAUSE EVALUATIONS,
INDEPENDENCE OF REVIE%, AND
CORRECTIVE ACTIONS
SAFETY SIGNIFICANCE OF FUEL
LING ACTIVITIES
~
REFUELING OPERATIONS ARE SAFETY
SIGNIFICANT
~
TREATMENT OF FUEL HA2'G)LINGAS A
SAFETY SIGNIFICANTACTIVITY%AS
LACKINGIN PPEcL's RESPONSE TO FUEL
HANDLINGPROBLEMS
~
PAST EVALUATIONSSTATED "NO SAFETY
SIGNIFICANCE" OR "INCREASED OUTAGE
TIME" AS A CONSEQUENCE
~
RESOLUTION OF BENT MAST SECTIONS
MORE CONCERNED %ITH ECONOMIC
FACTORS;
i.e. MAINTAININGTIMELINESS
OF'CORE OFFLOADlRELOAD
~
SPARE MAST STAGED DURING REFUELINGS
DUE TO HISTORY OF PROBLEMS
~
CONTRACTOR's RECOMMENDATIONSMADE
IN 1986 ON REDUCING %"EAR A, TEAR ON
FUEL HANDLINGEQUIPMENT WERE NOT
IMPLEMENTED
MANAGEMENTOVERSIGHT OF FUEL
LINGACTIVITIES
~
OPERATIONS MANAGEMENTOVERSIGHT
OF FUEL HANDLINGASSESSED AS WEAK
~
DELEGATIONTO REFUELING BRIDGE
SENIOR REACTOR OPERATOR
~
UNAWARE OF BRIDGE OPERATOR's
PRACTICES AND CONCERNS
~
EXPECTATIONS NOT MET
~
DESPITE PERFORMANCE PROBLEMS OVER
THE YEARS, MANAGEMENTOVERSIGHT
REMAINED UNCHANGED
MAINTENANCEASSESSMENT
I.
CUIKWNTAC
~
NON-"Q" COMPONENT USE
~
INADEQUATEPOST MAINTENANCE
TEST
~
LOAD CELL CALIBRATIONAI'G)
RELATED ISSUES
NANCE HISTORY
~
AITFOUM) 13 EVENTS OF BENT MASTS
SINCE 1984
~
NO CO$3&CTIVEMAINTENANCE
TRENDING
~
INVESTIGATION
~
INTERVIEWRESULTS OF STAFF
POTENTIAL GENERIC CONCERNS
I.
OPERATIONAL CONCERNS:
ACCEPTABILITYOF THREE- DIRECTION
MOTION .
~
ACCEPTABILITYOF ACCELERATION4,
DECELERATION FORCES FOR FULLY
EXTENDED MAST
~
ACCEPTABILITYOF DRAG FORCES OF
DOUBLE BLADE GUIDE MOVEMENT
II. DESIGN CONCERNS:
U
~
INTERFERENCE %ITH DOUBLE BLADE
GUIDE HAP'G)LES IN SPENT FUEL POOL
NRC POST AITACTIVITIES
~
COMPREHENSIVE REVIE% OF REVISED
REFUELING MG) RELATED PROCEDURES
~
DIRECT OBSERVATION OF "DRY RUN"
WALKTHROUGHOF REVISED PROCEDMM
~
VERIFICATIONAND VALIDATIONOF
OPERATOR TANNINGAND QUALIFICATION
~
LICENSEE hGMAGEMENT MEETING TO
DISCUSS REFUELING EVENTS A5lD
CORI&CTIVEACTIONS