ML17158A023

From kanterella
Jump to navigation Jump to search
Insp Repts 50-387/93-08 & 50-388/93-08 on 930816-20.No Violations Noted.Major Areas Inspected:Design Engineering Organization & Activities,Site Technical Support, Installation & Testing of Plant Mods
ML17158A023
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 11/16/1993
From: Drysdale P, Eapen P, Kenny T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17158A022 List:
References
50-387-93-08, 50-387-93-8, 50-388-93-08, 50-388-93-8, NUDOCS 9312070091
Download: ML17158A023 (19)


See also: IR 05000387/1993008

Text

U. S. NUCLEAR REGULATORY COMMISSION

REGION I

REPORT/DOCKET NOS.

50-387/93-08

50-388/93-08

LICENSE NOS.

NPF-14

NPF-22

LICENSEE:

FACILITYNAME:

INSPECTION AT:

Pennsylvania Power and Light Company

2 North Ninth Street

Allentown, Pennsylvania

18101

Susquehanna

Steam Electric Station

Allentown,, Pennsylvania

Salem Township, Pennsylvania

King of Prussia,

Pennsylvania

INSPECTION DATES:

August 16 - 20, 1993

INSPECTORS'ichard

S. Paroby, Reactor Engineer Co-op

=~

P.

Peter D. Dry

e, Sr. Reactor

ngineer

Systems Section, EB, DRS

ll(I( (93

Date

Thomas J. Kenny, Sr. Reactor

ngineer

Systems Section, EB, DRS

I< Jtgi$ 3

Date

APPROVED BY:

Dr. Plackeel K. Eapen, Ch ef

Systems Section, EB, DRS

i( /Q

Date

931207009'i

931126

PDR

ADOCK 05000387

8

PDR

2

A~PM: Th

'

'

dPP&L

h>>

d

Ig

g

g

d

and activities, site technical support, installation and testing of plant modifications, and the

motor-operated valve program for both units.

l~l:Th

II

h

ly

pl

I*

g

'

Ig gg'

g

Department.

This has improved the department's efficiency and reduced its overall

workload.

Also, some reduction in personnel was involved.

Engineering programs and

issues are well integrated with the PP&L Nuclear Department strategic goals and business

plans.

A revised Engineering Deficiency Report system has shown improvements in areas

related to operability and reportability determinations.

The licensee's GL 89-10 program was

put on hold in early 1993, in order to revise the engineering methodology used to perform

thrust calculations and to determine correct switch settings.

DETAILS

1.0

ENGINEERING AND TECHNICALSUPPORT PROGRAM ACTIVITY

(37700)

1.1

Engineering Organization

A two year planned transition was being implemented in accordance with the Organizational

Effectiveness Review (OER) to restructure the engineering organizations into functional

category groups and eliminate the alignment along basic engineering disciplines.

The

realigned engineering organization consists of the System Engineering, Nuclear Technology,

Modifications, and Nuclear Fuels groups.

This realignment is designed to improve utilization of engineering resources,

reduce the

overall engineering workload, increase work efficiency, and increase individual ownership

and technical responsibility of engineering tasks.

Before the reorganization,

the system

engineers were working approximately 25-30% overtime.

After the reorganization was

substantially completed, system engineers

averaged

about 5-8% overtime.

The

reorganization also increased interactions between the engineering organizations and the site

and improved the level and effectiveness of communications between those groups.

There is

improved engineering support of site activities and an increased

safety perspective on the part

of both engineering and site groups.

The engineering programs and issues within the

reorganized department are well integrated with the PP&L Nuclear Department strategic

goals and business plans.

As of August 1993, the reorganization was physically in place.

The OER implementation

plan projected two years to complete the reorganization and to make final adjustments

as

necessary.

On November 9, 1993, the licensee indicated that the reorganization was

structurally in place.

However, minor organizational enhancements

willbe ongoing as

necessary

to adjust to changing work loads and functional requirements.

Ongoing procedure

revisions and upgrades willrequire organizational effectiveness reviews that may result in

additional refinements in the engineering organization.

1.2

Self Assessment

Processes

The licensee conducted a Self-SALP in May 1993, and made a formal presentation of the

results to Region I management.

This self-assessment:

~

reviewed the licensee's own assessments,

audits, significant events, third party

reviews, and past NRC inspections to determine strength and weaknesses;

~

focused on management;

0

4

~

acknowledged the need to manage employee concerns,

and;

~

acknowledged

need to pursue better engineering training, improvements in system

performance,

and in management of deficiency resolutions.

1.3

Control of Design Changes and ModiTications

1W

r Level In trumen

i n M ifi ti n In

la i n

PP&L recently developed a plant modification to install new reactor vessel level

instrumentation designed. to overcome potential water level indication inaccuracies

caused by

the evolution of non-condensible

gases from the level instrument reference legs.

The inspectors reviewed the modification package and observed the progress of equipment

installation.

System engineers were knowledgeable on details of the modification and closely

monitored its installation.

An appropriate level of QA/QC inspections were designated

to

observe the installation and to verify that the specified levels of work quality were present.

The work practices observed by the inspectors were well controlled and the installed

equipment met the specifications and requirements contained in the modification work

packages.

Post installation tests were included with the modification package and they

specified the appropriate functional and preoperational

tests for the new instrumentation.

1.4

Engineering Deficiency Reports (EDRs)

As detailed in NRC inspection reports 50-287;288/92-14, 50-287;288/92-28 and

50-287;288/93-04,

the licensee's EDRs lacked detailed information related to plant events,

did not identify potential generic implications of events, and did not directly address

the

potential impact of EDRs on technical specifications operability criteria.

Also, the

reportability evaluation process for nonconforming conditions was not adequately defined.

In recognition of these concerns, PP&L formed an Engineering Discrepancy Management

Task Group to examine the EDR process in depth and to make recommendations

for

improvement.

This task group identified improvements in the processes of reporting,

resolving, tracking, and closing EDRs.

A new Nuclear Department Administrative

Procedure, NDAP-QA-0740, was issued to document the improved Engineering Deficiency

Report process.

Since many EDRs are resolved through the installation of a plant modification, the licensee

allows one refueling cycle to close an EDR after it is issued.

The goal was not to extend

more than 5% of the EDRs beyond one refueling outage.

A small number of EDRs were

extended beyond this goal.

The licensee documented justifications for extending these EDRs.

In all cases,

these justifications were reasonable for extending the due date.

The inspectors

verified that the modifications associated

with the extended EDRs were being prepared and

were scheduled for installation the following refueling outage,

In most cases,

these

extensions involved minor modifications; however, some major modifications were also

extended.

For example, modifications associated with EDR ¹610091, "Single Failures that

Affect Operability of Equipment Required for Accident Mitigation and Cause Degraded Bus

Voltages," were extended twice; once to November 19, 1993, and then again to the end of

the sixth refueling outage in Unit 2 to allow for installation.

Although delayed,

modifications associated

with EDR ¹G00088, "Recirculation Pipe Jet Impingement on MSIV

Operator and Other Targets," were still within the deadline for a commitment made to the

NRC, and modifications associated with EDR ¹G10112, "Maximum Allowable Torque

Switch Settings," still met the licensee's

schedule for implementing their Generic Letter 89-10 program.

The licensee also has a goal to have less than.20% of all EDRs open for more than 180 days.

The inspectors noted that approximately 60% of all open EDRs were more than 180 days

old.

The inspectors also noted that 80% of the EDRs opened in the past 12 months and 43%

of those opened in the previous 12 months were open primarily due to the unavailability of a

refueling outage to facilitate installation.

However, this situation is not consistent with the

goal to expect only 20% of the EDRs to be open for more than 180 days.

Overall, the

licensee is making an effort to close EDRs as soon as possible and the process for processing

and resolving engineering deficiencies appears

adequate

and timely.

The inspectors interviewed SSES control room personnel to obtain an onsite perspective of

the new EDR process.

One Shift Supervisor noted that improvements have been noticed

under the revised system, especially with the way EDRs are now communicated to the

control room supervisors.

Operability concerns are communicated more quickly to the

control room from PP&L headquarters

and Shift Supervisors are brought into EDR problems

at a much earlier point in order to get SRO insights.

2.0

NRC BULLETIN93-02, "DEBRIS PLUGGING OF EMERGENCY CORE

COOLING SUCTION STRAINERS"

NRC Bulletin 93-02 required licensees

to examine their practice of using fibrous materials in

temporary filters within the containment during refueling, and the storage of temporary filters

during operation when the containment is closed.

Immediately following a LOCA, fibrous

materials could become dislodged and be transported to the suppression pool where a

sufficient accumulation of fibre could contribute to a partial loss of net positive suction head

(NPSH) in emergency core cooling system (ECCS) pumps during the post-LOCA

recirculation phase of containment cooling. PP&L responded to the Bulletin stating that they

did not use temporary filters and, therefore, would not have this problem.

However, they

reported their ongoing assessment

of the impact on ECCS suction strainers of debris and

corrosion products adhering to permanently installed fibrous material (e.g., insulation) that

could become dislodged as a result of a pipe break.

PP&L issued a voluntary licensee event report (LER) 93-007-00, regarding the potential

blocking of ECCS suction strainers from containment debris.

Within the LER, PP&L

explained the methodology and assumptions

used to analyze "jet impingement" conditions

inside containment after a pipe break.

The analysis concluded that some amount of fibrous

insulation could find its way to the suppression pool and cause partial plugging of the ECCS

suction strainers.

The inspectors discussed

the scenario outlined in the LER and the licensee

demonstrated

how the event described was plausible.

The licensee subsequently

issued a modification to replace fibrous insulation considered

susceptible to shredding during a steam line break in the most vulnerable areas of the

containment.

The modification would replace. the old material with a mirror-type canned

metal insulation.

The inspector observed several areas where the insulation had been

replaced inside the containment and noted that the new insulation contained no fibrous

material.

Discussions with PP&L engineers

and a review of modification package 93-3058E

indicated that all the fibrous insulation would be replaced in the containments buildings at

both Units

1 & 2.

This work is expected to be completed over the next several outages.

The licensee is also in the process of issuing a procedure to backflush potentially blocked

ECCS strainers with nitrogen from a 2400 psig source during an accident.

The procedure is

to be issued when the fittings needed to connect the nitrogen bottles are received on site.

3.0

NRC Gk<2%FMC LETI'ER (GL) 89-10, SAFETY-RELATED

MOTOR-OPERATED VALVETESTING AND SURVEILLANCEPROGRAM

UPDATE

During September 23-27, 1991, the NRC conducted a team inspection (report 50-287/91-80;

50-288/91-80) to assess

the GL 89-10 program at the Susquehanna

Steam Electric Station

(SSES).

In general, the team found the existing MOV program to be acceptable.

However,

there were unresolved and open items related to specific aspects of the program.

PP&L has assessed

their program in light of some of the questions raised during the team

inspection and several

10 CFR Part 21 issues that were identified after the team inspection.

This inspection identified that PP&L has completely changed the MOV program to address

the NRC questions and to address

issues such as the Part 21 identified by Liberty

Technologies that affected MOV test results and VOTES equipment inaccuracies.

In February 1993, PP&L recognized that their MOV program would not meet the entire

intent of GL 89-10, and began to revise the program.

In March 1993, a new program was

started to address

the following significant issues:

1.

2.

3.

4.

VOTES 10 CFR 21 Notification on test equipment inaccuracies

SSES Power Update

MOV Weak Link Evaluations

Degraded Voltage Calculations

,

6.

7.

8.

9.

10.

11.

12.

New Allowable Thrust Methodology

Spring Pack Deficiencies

Torque Measurements

Trending by VOTES

Limitorque 10 CFR 21 Notification on High Temperature Effects on AC Motors

Valve Design Factors

Rising Rotating Stem Torque

Detailed Valve-By-Valve Schedule

PP&L deferred all GL 89-10 testing during the period from about November 1992, through

April 1993, for the following reasons:

There were a significant number of design and implementation-related

issues.

These

issues affected both the allowable thrust range and the determination of the actual

thrust developed.

Therefore, the program

as it existed did not provide a conclusive

measure of valve performance.

2.

There was minimal testing during this time period (6 VOTES &4 dynamic tests).

During this period of time, the program was in transition.

The design methodology,

VOTES software, method of applying VOTES tolerances,

and method of assessing

VOTES test results was changed.

Not testing during this transition period eliminated

the possibility of using wrong criteria for testing and analyzing the results.

3.

Allavailable manpower was spent revising the Program (rather than performing

testing and analyzing tests results).

4

The new program now in place at Susquehanna

provides answers to the aforementioned

open

items.

The following delineates

problems identified by the team inspection and the

licensee's current method for resolving each item, in accordance with PP&L's new GL 89-10

program.

Section numbers in parenthesis

below refer to the sections in NRC inspection

report 50-387/91-80; 50-388/91-80 where each item appears.

I

BA I

REVIEW

E TI N22

om I

etailed eval

i n of minim m volta eav ila le

M V

u

1

2

The degraded grid voltage analysis that was in place at the time of the team inspection has

been replaced by a newer version (as a result of the EDSFI).

The degraded voltage

calculated had concluded that the voltage at the motor terminals were very low. The

degraded voltage calculations were revised using the new degraded grid analysis that

removed excess conservatism.

IZ

A

WIT H

SECTI

2 4

m le

r m inin

r izin

wih

n

I 'n

rin

f 1

2

This has not yet been completed by PP&L; however, it is addressed

within engineering

deficiency report (EDR) ¹630034, which consolidated all known EDR's pertaining to

GL 89-10 in April 1993, due to the revision of the GL 89-10 program.

EDR ¹630034 was

written to address

and resolve all of the significant program issues delineated above.

Evaluat

the

v lv f ct r

urin

d

i n

asi

t

tin

and m

e chan

a r

ir

This item is not yet completed; however, PP&L has evaluated the 0.3 valve factor and has

concluded that industry and SSES data suggests

that the use of a valve factor of 0.3 may not

be conservative in all cases.

Their study recommended

that a valve factor of 0.5 should be

used for all flex wedge gate valves.

mn

'fi infr

in

1

mfri in

ffiiin

This item is not yet completed; however, after PP&L reviewed three test programs, "EPRI

MOV Flow Test Project RP-3433-15," "EPRI Rate of Loading Effects Testing Program

RP-3433-12," and "EPRI Stem to Stem Nut Lubrication Test Report RP-3433-10," they

concluded that programs identified a coefficient of friction for their lubricant (Moly 101) was

in the range of 0.10 to 0.13, and, therefore, the use of 0.15 friction factor was conservative

for sizing motor operators.

vel

ificati n

r

r

tructural limit an I

is f r

L

-1

v lv

Specification M-1509, "Specification for MOV Weak Link Analysis," has been issued to

address

the procurement of the analysis on aU valves installed at SSES.

Also, a Design

Standard, MDS-05, "MOVWeak LinkEvaluation Criteria," has been issued to specify the

requirements when determining MOV maximum allowable thrust/torque and accelerations

that includes the valve, actuator, and motor.

Ad'u t tor ue switch se tin s t

account for rate of loadin

oad sensitive behavior

as

gg)~r~ri ~

After reviewing SSES and industry testing, PP&L has concluded that an allowance of 5%

should be included in the MOV sizing calculation to compensate for rate of loading.

R view

h

r

i

h ein

fllwin d in

i

in

n mk

ad

men

if

~ruired

This is part of EDR 630034, and willbe incorporated when the EDR is complete.

R

lv

iffr n

nv1

e

m fr

inM

in

AR

nr

lvedIemN

-

7

-

/ 1-

-

1

Licensing Document Change 1879, revised Section 8.3.1.9 of the UFSAR to allow the use of

voltages greater than 80% in mechanical sizing evaluation of MOVs. This now conforms

with the guidance of GL 89-10, and this item is considered

closed.

Revi w the Limit r

e

tud

n am ien

em

ture effects

n

c m

rs an

inco

in

wi h

'n

lc lation

ifa

li

le

The inspector reviewed PP&L study, VE-010, "Assessment of Elevated Temperature Effects

on AC MOVs," which concluded that all MOV motors at SSES have an inherent torque

reduction, based on the 10 CFR 21 condition identified by the Limitorque Corporation.

The

results of this study, along with other emerging issues,

have been incorporated into MDS-01

actuator sizing calculations.

To date, Unit 1 has been completed and Unit 2 is being

addressed.

Approximately twenty modifications have been identified for MOVs at Unit 1.

R vi w h

ff

fv I

r ketim limi

ndecr

0-

7

0-

1-

- 2.

m

r

nr

lv

I m

There are 24 dc MOVs at SSES.

16 are equipped with Reliance motors and the remaining 8

are equipped with Peerless

motors.

PP&L plans to replace 4 of the Reliance motors with

Peerless.

The inspector reviewed Service Order ¹S-16098-5 that was issued to Limitorque

Corporation on April 15, 1992, to supply information to PP&L, regarding dc motor speed at

reduced voltages.

The current status is that Limitorque has provided the results of the

completed motor tests conducted by Peerless;

however, Reliance has not yet completed

testing.

This item remains open pending incorporation of the motor speed data into the

stroke time calculation.

M V TESTIN

E TION 2

In inspection reports 50-387/91-80 and 50-388/91-80 the NRC requested

the licensee to

provide a justification for the use of the parent/candidate

approach to testing for valves that

are not practicable to test prior to using this approach.

PP&L has developed VE-009, "MOV Dynamic Test Scope," that delineates the definition of

a testable or non-testable valve and explains the criteria for how a prototype test may be used

to demonstrate

the operability of an identical valve.

The procedure is comprehensive

and

discusses

the rationale for the parent/candidate

approach to testing of valves that are not

practicable to test.

10

M V MAINTENAN E AND PO T-MAINTENAN E

TING

E TI N 2

Review fr

uenc f r

rea e sam lin

and MOV Overhaul

The inspector reviewed SSES's program for maintenance

and overhaul of MOVs. The

inspector concluded the following:

Stem and stem nut lubrication is routinely done during 18-month grease sampling.

The inspector examined several valves inside of containment and confirmed the stems

had been cleaned and relubricated.

PP&L conducted an 18-month interval lubrication program to identify trends and to

assess

the adequacy of the interval using new and better grades of grease.

The

licensee analyzed the grease

samples and also sent them to a contractor for

independent analysis.

The inspector reviewed the analyses of several grease

samples

and observed good agreement between the consultants'nalysis

and PP&L's analysis.

The inspector concluded that there is now a schedule in place for overhaul of

actuators based on the results of the grease analysis.

R vi

the maintenan

r

re t r

uir theuse

f

rin

ck e t r t

h

k f r

rin

ack r lax

'

durin

verhaul

PP&L is not using a spring pack tester; however, the procedure has been changed to make

more careful measurements

during overhaul periods.

These measurements

are recorded and

compared to an as-left condition of the spring pack.

u tif an

vi ti n

from ven

r-r

mmen

ed m intenance

ch

le

The inspector verified this has been done in draft procedure,

"Preventive Maintenance

Improvement Project," package number 130, "Limitorque Valve Motor Operators NRC GL 89-10 VOTES Tested."

PP&L stated this package would be issued within the next six

months.

FAIL

RRE TIVE A TI N

A

TRE

IN

E TI N 2.8

ml

h rviw fh Prevniv Min

n ceImrvmn

Pr

m

h

n

f

1991

The inspector reviewed package number 131, "Limitorque Valve Motor Operators Butterfly

Valve Type," and package number 132, "Limitorque Valve Motor Operators Incompatible

for VOTES Testing."

PP&L is making progress in issuing the Preventive Maintenance

Improvement Program, which was put on hold during the period while PP&L was rethinking

GL 89-10 requirements.

11

Q~nl i~in

The inspector concluded that PP&L recognized that the program that existed in

February 1992, did not meet the intent of GL 89-10 and halted the entire program and

revised it. However, they did not inform the NRC of their actions.

PP&L and NRC have

had discussions

on the extension of the GL 89-10 program at SSES.

It appears

that PP&L

willbe asking for an extension of their schedule in accordance with Supplement 6 of

GL 89-10.

The extension willbe to the end of 1995.

During this inspection the NRC was

informed of the changes.

Notwithstanding, PP&L used the correct approach to enhancing

their testing program for testing MOV's. The management involvement and an aggressive

approach toward completing the program by the end of 1995, ifthe extension is granted,

were evident.

4.0

EXITMEETING

An exit meeting was conducted August 20, 1993, at the Susquehanna

Steam Electric Station

to summarize the purpose,

scope, and findings of the inspection.

The inspector's findings

and conclusions were discussed

at this meeting.

Those in attendance

are listed in

Attachment 1. At that meeting, the NRC staff focused on its concern that the licensee did

not inform the NRC that significant changes were made in the implementation of the Generic Letter 89-10 MOV program, and some minor inconsistencies

in the implementation of EDRs

were noted.

The licensee acknowledged the inspection findings at the exit meeting.

0

ATTACHMENT1

Persons

Contacted

Pnn

lv

i Pwr

n Lih

m

H. Clarke, Design Basis Document Project Manager

  • T. Clymer, Nuclear Quality Assurance Coordinator
  • T. Dalpiaz, Manager, Nuclear Maintenance
  • J. Fritzen, Supervisor, Modifications Installation

M. Golden, Supervisor, System Engineering Programs and Testing

  • J. Gutshall, Supervisor, Valve Maintenance

J. Kenney, Supervisor, Nuclear Licensing

G. Kuczynski,

  • J. Maertz, Senior Results Engineer
  • D. McGann, Supervisor, Nuclear Compliance
  • J. Meter, Compliance Engineer

G. Miller, Manager, Nuclear Technology

~ B. Saccone, Acting Manager, Nuclear Systems Engineering

J. Stefanko, Manager, Nuclear Fuels

  • C. Smith, Senior Results Engineer

ni

1

rRe

1

mmis i n

  • S. Barber, Senior Resident Inspector
  • P. K. Eapen, Chief, Systems Section, DRS
  • D. Galvin, DOE Intern
  • R. Paroby, Co-op, Systems Section, DRS
  • Designates

those in attendance at the exit interview on August 20, 1993.