ES-301 Administrative Topics Outline Form ES-301-1 Facility: Monticello Nuclear Generating Plant Date of Examination: November 2016 Examination Level: RO SRO Operating Test Number: 2016-301 Administrative Topic (see Note) Type Describe activity to be performed Code*
Conduct of Operations D Bulk Drywell Temperature Manual Calculation 2.1.45 Ability to identify and interpret (JPM-001) diverse indications to validate the response of another indication.
IMPORTANCE RO 4.3 SRO 4.3 Conduct of Operations N Demonstrate Electrical Safety Practices for 2.1.26 Knowledge of industrial safety Racking Out a 4160 KV Breaker procedures (such as rotating equipment, (JPM- FP-MA-ES-01-001) electrical, high temperature, high pressure, caustic, chlorine, oxygen and hydrogen).
IMPORTANCE RO 3.4 SRO 3.6 Equipment Control N Independent Verification of RHR following 2.2.15 Ability to determine the expected shutdown of Torus Cooling.
plant configuration using design and (JPM-4 AWI-04.04.02-005) configuration control documentation, such as drawings, line-ups, tag-outs, etc.
IMPORTANCE RO 3.9 SRO 4.3 Radiation Control D Expected Dose Determination to Inspect 2.3.4 Knowledge of radiation exposure Equipment (JPM-4 AWI-08.04.01-006) limits under normal or emergency conditions.
IMPORTANCE RO 3.2 SRO 3.7 Emergency Plan N/A N/A N/A NOTE: All items (five total) are required for SROs. RO applicants require only four items unless they are retaking only the administrative topics (which would require all five items).
- Type Codes & Criteria: (C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs; 4 for SROs & RO retakes)
(N)ew or (M)odified from bank ( 1)
(P)revious 2 exams ( 1; randomly selected)
ES-301 Administrative Topics Outline Form ES-301-1 Facility: Monticello Nuclear Generating Plant Date of Examination: November 2016 Examination Level: RO SRO Operating Test Number: 2016-301 Administrative Topic (see Note) Type Describe activity to be performed Code*
Conduct of Operations D, P SRO - NRC License Maintenance 2.1.4 Knowledge of individual licensed Responsibilities (JPM-OWI-01.08-002) operator responsibilities related to shift l staffing, such as medical requirements, no-solo operation, maintenance l of active license status, 10CFR55, etc.
IMPORTANCE RO 3.3 SRO 3.8 Conduct of Operations N Pre-Job Brief for APRM Heat Balance 2.1.1 Knowledge of Conduct of Calibration (JPM-FP-PA-HU-06-001)
Operations Requirements IMPORTANCE RO 3.8 SRO 4.2 Equipment Control N LCO 3.0.9 Application Determination - Blocked 2.2.40 Ability to apply Technical Open HELB Door (JPM-OWI-02.07-002)
Specifications for a system.
IMPORTANCE RO 3.4 SRO 4.7 Radiation Control N Authorization to exceed Administrative Dose 2.3.4 Knowledge of radiation exposure Limit. (JPM-4-AWI-08.04.01-008) limits under normal or emergency conditions.
IMPORTANCE RO 3.2 SRO 3.7 Emergency Plan D EAL Classification (JPM A.2-101-002) 2.4.41 Knowledge of the emergency action level thresholds and classifications.
IMPORTANCE RO 2.9 SRO 4.6 NOTE: All items (five total) are required for SROs. RO applicants require only four items unless they are retaking only the administrative topics (which would require all five items).
- Type Codes & Criteria: (C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs; 4 for SROs & RO retakes)
(N)ew or (M)odified from bank ( 1)
(P)revious 2 exams ( 1; randomly selected)