ML17138B762

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-387/80-06 & 50-388/80-04 on 800401-04 & 09-10 & Notice of Violation
ML17138B762
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 07/21/1980
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Curtis N
PENNSYLVANIA POWER & LIGHT CO.
Shared Package
ML17138B760 List:
References
NUDOCS 8102040305
Download: ML17138B762 (2)


See also: IR 05000387/1980006

Text

6>II Pe6I

0

p0

IVlp

Y/

0

++*<<+

Docket Nos.

50-387

50-388

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA19406

J91 ZX LSM

Pennsylvania

Power

5 Light Company

ATTN:

Mr. Norman

W. Curtis

Vice President

Engineering

and Construction

(Nuclear)

2 North Ninth Street

Allentown, Pennsylvania

18101

Gentlemen:

Subject:

Combined Inspection 50-387/80-06;

50-388/80-04

This refers to'the inspection

conducted

by Mr.

R. Paolino of this office on

April 1-4 and 9-10,

1980 at the Susquehanna

Steam Electric Station,

Units

1 and

2, Salem Township, Pennsylvania of activities authorized

by

NRC License

Nos.

CPPR-101

and

CPPR-102

and to the discussions

of our findings held by Mr. Paolino

with Mr. A. Sabol

and other members of your staff at the conclusion of the

inspection.

Areas

examined during this inspection are described

in the Office of Inspection

and Enforcement Inspection

Report which is enclosed with this letter.

Within

these

areas,

the inspection consisted of selective

examinations of procedures

and representative

records,

interviews with personnel,

and observations

by the

inspector.

Based

on the results of this inspection, it appears

that certain of your activi-

ties were not conducted in full compliance with

NRC requirements,

as set forth

in the Notice of Violation, enclosed

herewith

as Appendix A.

These

items of

noncompliance

have

been categorized

into the levels

as described

in our corres-

pondence to you dated

December

31,

1974.

This'notice is sent to you pursuant to

the provisions of Section

2.201 of the NRC's "Rules of Practice,,"

Part 2, Title

10,

Code of Federal

Regulations.

Section

2.201 requires

you to submit to this

office, within thirty (30) days of your receipt of this notice,

a written state-

ment or explanation in reply including:

(1) corrective steps

which have

been

taken by you and the results

achieved;

(2) corrective steps

which will be taken

to avoid further items of noncompliance;

and (3) the date

when full compliance

will be achieved.

In addition to the need for corrective action regarding

these

specific items of noncompliance,

we are concerned

about the implementation of

your quality assurance

program that permitted

them to occur.

Consequently,

in

your reply, you should describe

in particular,

those actions taken'or

planned to

improve the effectiveness

of your quality assurance

program.

In accordance

with Section 2.790 of the

NRC's "Rules of Practice,"

Part 2, Title

10,

Code of Federal

Regulations,

a copy of this letter and the enclosed

inspection

report will be placed in the

NRC's Public Document

Room.

If this report contains

Pennsylvania

Power and Light

Company

any information that,you

(or your contractor) believe to be proprietary, it 'is

necessary

that you make

a written application within 20 days to this office to

withhold such information from public disclosure.

Any such application must be

accompanied

by an affidavit executed

by the owner of the information, which

identifies the document or part sought to be withheld, and which contains

a

statement of reasons

which addresses

with specificity the items which will be

considered

by the Commission

as listed in subparagraph

(b) (4) of Section

2.790..

The information sought to be withheld shall

be incorporated

as far as

possible into a separate

part of the affidavit. If we do not hear from you in

this regard within the specified period, the report will be placed in the Public

Document

Room.

Should you have

any questions

concerning this inspection,

we will be pleased

to

discuss

them with you.

Sincerely,

Robert T. Carlson,

Chief

Reactor Construction

and Engineering

- Support Branch

Enclosures:

l.

Appendix A, Notice of Violation

Z.

Office of Inspection

and Enforcement

Combined

Inspection

Report

Numbers 50-387/80-06;

50-388/80-04

cc w/encls:

A.

R. Sabol,

Manager,

Nuclear guality Assurance

H.

E. Barberich,

Licensing Engineer

S.

H. Cantone,

Superintendent of Plant