ML17122A072

From kanterella
Jump to navigation Jump to search
Annual Non-Radiological Environmenta! Operating Report - 2016
ML17122A072
Person / Time
Site: Watts Bar  Tennessee Valley Authority icon.png
Issue date: 05/02/2017
From: Simmons P
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML17122A072 (12)


Text

Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 May 2,2017 10 cFR 50 4 ATTN. Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Units 1 and2 Facility Operating License Nos. NPF-90 and NPF-96 NRC Docket Nos. 50-390 and 50-391

Subject:

Watts Bar Nuclear Plant - Annual Non-Radiological Environmenta!

Operating Report -2016 ln accordance with Section 5.4.1, "Routine Reports," of Appendix B, "Environmental Protection Plant (Non-Radiological)," to the Watts Bar Nuclear Plant (WBN) Units 1 and 2 Operating Licenses, enclosed is the 2016 Annual Non-Radiological Environmental Operating Report for WBN. This report is required to be submitted to the Nuclear Regulatory Commission (NRC) within 90 days following the anniversary of the issuance of the WBN Unit 1 operating license (i.e., February 7, 1996). This report addresses the period from February 7,2016 through February 6,2017.

There are no new regulatory commitments in this letter. lf you have any questions concerning this matter, please contact Gordon Arent, WBN Licensing Director, at (423) 365-2004.

Respectfully, Paul Simmons Site Vice President Watts Bar Nuclear Plant

Enclosure:

Tennessee Valley Authority Watts Bar Nuclear Plant Annual Non-Radiological Environmental Operating Report February 7,2016 Through February 6,2017

U.S. Nuclear Regulatory Commission Page 2 May 2,2017 cc (Enclosure):

NRC Regional Administrator - Region ll NRC Project Manager - Watts Bar Nuclear Plant NRC Senior Resident lnspector - Watts Bar Nuclear Plant U.S. Fish and Wildlife Service

TENNESSEE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT AN N UAL NON.RADIOLOGIGAL ENVI RON MENTAL OPERATING REPORT FEBRUARY 7, 2016 THROUGH FEBRUARY 6,2017 E-1 of 10

TABLE OF CONTENTS

l.

lNTRODUCTlON...............

..... E-3 II.

REPORTS PREVIOUSLY SUBMITTED AS SPECIFIED IN THE WBN NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) PERMIT

... E-3 III.

SPECIAL BIOLOGICAL MONITORING REPORTS

........,,,,,.,,,..E-4 IV.

ENVIRONMENTAL PROTECTION PLAN NONCOMPLIANCES.........,...... E.6 V.

CHANGES MADE TO APPLICABLE STATE AND FEDEML PERMITS AND CERTlFICATlONS..............

............ E_8 VI.

CHANGES IN FACILITY DESIGN OR OPERATION...........

...... E-8 vil.

NoN-ROUTINE REPORTS..........

......... E_10 VIII. CHANGES IN APPROVED ENVIRONMENTAL PROTECTION PLAN SPECIF]CATIONS

..... E.1O E-2 of 10

I.

INTRODUCTION The Tennessee Valley Authority (TVA) Watts Bar Nuclear Plant WBN) Annual Non-Radiological Environmental Operating Report is provided for the period of February 7,2016 through February 6,2017. This reportwas prepared in accordance with Appendix B to facility operating licenses NPF-90 and NPF-96, "Environmental Protection Plan (EPP),' Section 5.4.1, "Routine Reports." This report includes a summary of:

A.

Reports previously submitted as specified in the WBN National Pollutant Discharge Elimination System (NPDES) Permit Number TN0020168.

B.

All special reports submitted per EPP Section 4.1, "Environmental Monitoring."

C.

All EPP noncompliances and the corrective actions taken to remedy them.

D.

Changes made to applicable state and federal permits and certifications.

E.

Changes in station design or operation that could involve a significant environmental impact or changes to the findings of the Final Environmental Statement (FES).

F.

Non-routine reports submitted per EPP Section 4.2, "Unusual or lmportant Environmental Events."

G.

Changes in the approved EPP.

II.

REPORTS PREVIOUSLY SUBiIIITTED AS SPECIFIED IN THE WBN NATIONAL POLLUTANT DISCHARGE ELttUtNATION SYSTEM (NPDES) pERtUtT The following reports were submitted as specified in the WBN NPDES Permit Number TN0020168 and the Tennessee Storm Water Multi-Sector General Permit (TMSP)

Numbers TNR051343 and TNR050000:

A.

As required by the NPDES permit, Discharge Monitoring Reports (DMRs) were completed and submitted monthly to the Tennessee Department of Environment and Conservation (TDEC) no later than 15 days after the completion of the reporting period.

B.

WBN submitted to the TDEC the "Compliance Survey for Watts Bar Nuclear Plant Outfall 113 Passive Mixing Zone" for "Winter 2015". As summarized in the report, the compliance surveys confirms the adequacy of the passive mixing zone and the adequacy of the thermal model to evaluate the operation of Outfall 113.

C.

The annual Biocide/Corrosion Treatment Report was completed and submitted to TDEC prior to the February 15, 2016 deadline.

D.

The annual sampling and analysis required by the 2016 and 2017 TMSP for storm water was performed and the annual reports were submitted to the TDEC within 30 days after the sample results were obtained.

E-3 of 10

II.

REPORTS PREVIOUSLY SUBMITTED AS SPECIFIED IN THE WBN NATIONAL POLLUTANT DISC HARGE ELIMINATION SYSTEM (NPDES) PERIUIIT (continued)

E.

DMR Quality Assurance (QA) Laboratory Performance Evaluation Study 36 was completed by and submitted to Environmental Resource Associates, the TDEC, and the Environmental Protection Agency (EPA) prior to the August 26,2016 deadline. The cadmium, selenium, and total suspended solids value for DMR-QA Study 36 analyses performed and reported by our contract analytical laboratory - Test America were 'Not Acceptable'. After a careful investigation, the probable root cause was undetermined. Corrective action measures to ensure the current analysis process produces reliable and repeatable results were determined to be unnecessary as no reproducible issue was detected.

SPECIAL BIOLOGICAL IUIONITORING REPORTS A.

EPP Section 4.1.1, "Aquatic Monitoring"

1.

Routine semi-annual Whole Effluent Toxicity WET), a.k.a. chronic biotoxicity tests, were conducted on plant effluents and the appropriate reports were submitted as part of the DMR for Outfall Serial Numbers (OSNs) 101 and 113, in May and October 2016 as required by the NPDES permit. All TVA test results were valid for all sampling outfalls and dates and for both lC25 tests (P. promelas and C. dubia).

2.

A report on the "Biological Monitoring of the Tennessee River near the Watts Bar Nuclear Plant 2012" is not required in accordance with Part lll,Section I of the WBN NPDES Permit, but was a recommendation in the "Watts Bar Nuclear Plant Supplemental Condenser Cooling Water System Fish Monitoring Program, 2001" report to be consistent with other required annual reporting programs at Tennessee and Alabama nuclear plants. TVA determined in January 2013 that these reports, or an equivalent, would be submitted with the permit renewals versus the historical annual basis (last submitted December 29,2015 as a component of the NPDES permit renewal application).

3.

ln accordance with the provisions of Tennessee Code Annotated Section 69-7-301 et seq., the Water Resources lnformation Act, WBN submitted the Water Withdrawal Registration Form for Calendar Year (CY) 2016 to the TDEC prior to the February 15, 2017 deadline. Although federal agencies are not subject to laws and regulations promulgated by state governments unless Congress has clearly waived the federal government's sovereign immunity, in 2003 TVA voluntarily agreed as a matter of policy to provide the registration information in order to assist both TVA and TDEC in carrying out their water management responsibilities.

III.

E-4 of 10

l!!.

SPECIAL BIOLOGICAL IUONITORING REPORTS (continued)

B.

EPP Section 4.1.2, "Maintenance of Transmission Line Corridors' Listed below are the 500 kV transmission lines associated with WBN and information regarding the maintenance that was performed on each line:

500 kV Line ldentifier Maintenance Performed Bull Run - Watts Bar (Note Below)

There was not any Chemical or Herbicide utilized on these lines within the period.

Watts Bar - Roane The following methods were used to treat the 4.9 acres June 16, and 18, 2016.

A. Backpack Sprayer:

o Arsenal (EPA 241-346) 40.81 oz.

Escort XP (EPA 432-1 549) 1.24 oz.

o Milestone VM (EPA 62719-537) 32.31 oz.

o Rodeo (EPA 62719) 27 1.94 oz.

Watts Bar - Volunteer No chemical or herbicide was utilized on these lines within the period.

Watts Bar - Sequoyah 1 (Note Below)

No chemica! or herbicide utilized on these Iines within the period.

Watts Bar - Sequoyah 2 (Note Below)

No chemical or herbicide utilized on these lines within the period.

Note:

The transmission line designated as Bull Run - Sequoyah in previous versions of this report has been split into the following transmission lines: 1) Watts Bar - Sequoyah 1, and 2) Bull Run -

Watts Bar.

E-5 of 10

IV.

ENVIRONMENTALPROTECTIONPLANNONCOiiPLIANCES WBN received two Notice of Violations (NOVs) from February 2016 to February 2017.

A.

On November 8, 2016, the TDEC issued the WBN Compliance Evaluation lnspection (CEl) report and issued two NOVs:

i. According to comments made by TVA personnel and the calibration report, Wafts Bar Nuclear Plant Dye Test Calibration for 0-FlT-27-98, January 26,2016, the flowmeter 0-FlT-27-98 may not maintain calibration between scheduled calibrations and should be calibrated on a more frequent basis. By failing to ensure that the flowmeter at OSN 101 maintains a tolerance of +1go1o, TVA WBN is not in compliance with Part llA.4 of its permit.

ii. By failing to repair the permanent temperature sensing system at OSN 101 in a timely manner, TVA WBN is not in compliance with Part A.4 of its permit and Note 4 in Part 1.

ln accordance with the NPDES permit, the following noncompliances were reported to the TDEC.

ln accordance with Part 1 of the NPDES permit, daily temperature monitoring at OSN 101 was conducted on January 01-22, February 12, May 13 through 31, June 1, 2, 26 through 30, July 3, 6, 9, 12,16,20,23,29, and 31, September 1 through 12 and the 29th, 2016 due to temperature monitoring equipment failure. WBN notified the TDEC on the applicable DMR cover letters.

On February 18, 2016 WBN reported to TDEC that WBN exceeded the benchmark monitoring requirement for iron at storm water monitoring outfall SW-g on January 15,2016.

Due to constraints on the OSN 101 flow meter, flows in excess of 80,000 gallons per minute (gpm) were calculated for the months of February 2016 through September 2016.

Due to meter fouling, flows were calculated at IMP 103 April 5 through 7, 11, 15, 20, 22 through 26, 28, 2016 and May 1, 3 through 16, 1 8, 22, 24 through 26, and 29 through 31,2016.

On June 18,2016, TVA notified the National Response CenterthatWBN had an oil sheen on the Cooling Tower Basin. Estimate of oil released into the cooling tower basin is less than one quart. Notifications were also made to Tennessee Emergency Management Agency (TEMA), the CDO, ODS, the National Response Center, the NRC (NRC event#520211, and the TDEC.

On July 11,2016 WBN reported to the TDEC in the June DMR cover letter that due to Turbine Building Station Sump (TBSS) pump failure on June 24,2016, the TBSS effluent was discharged on June 25 and 26, 2016 to the Yard Holding Pond via a storm water drain. This effluent was analyzed daily for OSN 101 parameters at the NPDES monitoring point and IMP 103 parameters at the discharge point. The results were included in the June DMR.

c.

D.

A.

B.

E.

F.

E-6 of 10

IV, Atr.

ENvIRoNiIENTAL PRorEcrloN PLAN NoNcoilPLlANcEs (continued)

On July 26,2016 at 1536 EDT, TVA notified the National Response Center that Watts Bar Nuclear Plant had noted an oilsheen on the Cooling Tower Basin. An oil sheen was observed within the U1 Cooling Tower basin at WBN. The sheen did not cover the entire Cooling Tower basin. The sheen covered approximately two square feet. Estimate of oil released into the Cooling Tower basin is less than four ounces.

No oil sheen was visible in the Tennessee River from the bank above the diffuser pipes. Notifications were also made to TEMA the NRC (NRC event#52126), and the TDEC.

On August 09, 2016, TVA notified the National Response Center that Watts Bar Nuclear Plant had noted an oil sheen on the Cooling Tower Basin. No oil sheen was visible in the Tennessee River from the bank above the diffuser pipes. Notifications were also made to TEMA the NRC (NRC event#52163), and the TDEC.

On August 30, 2016, TVA reported a Notice of Unusual Event - Fire in a Main Bank Transformer (NRC event#52210). A fault occurred on the unit 2 "B" main bank transformer resulting in an oil fire and the loss of approximately 15,000 gallons of oil to the site drainage system and ponds. The main turbine tripped resulting in a reactor trip. The fire began at2110 EDT and was reported out at2228. Unit 1 continued operation. Notifications were also made to the DHS SWo, FEMA ops Center, DHS NICC, FEMA NationalWatch Center (E-mail) and Nuclear SSA, the NRC, and the TDEC.

WBN notified the TDEC on the September 2016 DMR cover letter of the Mussel Relocation Zone (MRZ) average calculation for September 1 through 18 and27 through 30, 2016 due to a failure in the temperature monitoring equipment failure.

The NRC event#52400 involved the release of a GE BETZ Chemical Flogard*

MS6237 (ratio of materials 2O-4Oo/o for both Zinc Chloride and Phosphoric Acid) on November 29,2016. The release of approximately 525 gallons was reported in the National Response Center report 1 165106 (total volume of the container was 2,500 gallons). From the total spilled and the percentage estimations from GE BETZ, the material exceeded the Zinc chloride Reportable Quantity (Ra) of 1,000 pounds.

TVA demonstrated that Phosphoric Acid did not exceed its RQ of 5,000 pounds. A notification was given to the National Response Center, Rhea County LEPC, Tennessee Emergency Management Agency, and the TDEC.

H.

t.

J.

K.

E-7 of 10

V.

CHANGES MADE TO APPLICABLE STATE AND FEDERAL PERTUIITS AND CERTIFICATIONS A.

NPDES Permit Number TN 0020168

1. The Environmental Protection Agency (EPA) issued the final rule requiring all NPDES Permitees to utilize electronic reporting instead of the former paper-based reporting. This rule became effective on December 21,2015. The TDEC instituted the NetDMR for submitting the monthly DMRs. This rule does not change the information required to be reported nor does it change NPDES requirements. lnformation regarding the rule can be obtained under Docket lD No. EPA-HQ-OECA-2009-0274 at the www.reoulations.oov web site.
2.

On December 6, 2016, TVA submifted comments to the draft NPDES permit dated November 17,2016.

3.

TVA requested an update to the Tennessee Storm Water Multi-Sector General Permit (TMSP) TNR051343 to add coverage under Sector AF on December 16, 2016. TVA recently completed construction projects under TNR190741 and elected to maintain the spoils area underthe TMSP as a borrow area. The runoff from the borrow area drains to an existing storm water outfall, SW-13.

B.

Air Permits Number 463822

1. On March 31, 2016 TVA applied for a source No. 72-0029, DG-g Construction Permit for a TSOB Building Replacement Emergency Generator Diesel Engine.

VI.

CHANGES IN FACILITY DESIGN OR OPERATION ln accordance with EPP Section 3.1, "Plant Design and Operation," facility design and operational changes were reviewed for potential effect on the environment as described below. A review of facility design and operational changes proposed from February 7, 2015, through February 6, 2016, was performed. Projects considered as having potential impact on the environment included those that:

Could have caused waste stream generation/alteration.

Required the acquisition/modification of permits.

o lnvolved the use of hazardous material.

Required physical construction.

E-8 of 10

A.

CHANGES lN FACILITY DESIGN OR OPERATTON (continued)

The review, performed in accordance with the guidelines of TVA's National Environmental Policy Act (NEPA) Program, documented that design and operational changes did not involve an unreviewed environmental question. The following criteria were used to identify those projects with a potential for environmental effects:

A.

Waste stream generation/alteration:

Air, Hazardous Waste, Solid Waste, Polychlorinated Biphenyls, Asbestos, or Wastewater B.

Permit Acquisition/Modification:

NPDES, Air, lnert Landfill, or Other C.

Hazardous Materials:

Hazardous Materials that are environmentally unfriendly and are likely to generate a Resource Conservation and Recovery Act (RCRA) hazardous or Toxic Substances ControlAct (TSCA) waste.

D.

Physical Construction lnvolved:

E rosion/Sedi mentation Effects, Tra nsportation Effects, N oise Effects, Groundwater Effects, Surface Water Effects, Floodplain Effects, Wetland Effects, Prime Farmland Effects, Unique Natural Features Effects, Aquatic Ecology Effects, Terrestrial Ecology Effects, Protected Species Effects, Sensitive Habitat Effects, Visual Effects, Historical, Cultural and Archeological Effects, Changes in Site Land Use, or Controversy.

1.

TemporaryAlterations:

There were no temporary alterations conducted during this period that met the environmental impact criteria.

Desion and Operational Chanoes Most of the design and operational changes conducted during this period did not meet the environmental impact criteria. There were 15 facility design and operational changes made during this reporting period with a potential impact on the environment. The appropriate environmental reviews were completed and all changes were found to be within the scope of existing environmental permits and in compliance with NEPA regulations.

E-9 of 10

VII.

CHANGES lN FACILITY DESIGN OR OPERATTON (continued)

Those Categorical Exclusion Checklists (CECs) written to document the review of site changes are as follows:

(1) 34413 Provide supplemental condenser cooling water from Unit 2 Supply Weir to Unit 1 Cooling Tower Basin WBN Pond lmprovement Plan WBN Tritium Monitoring Wells WBNP System 027 Diffuser Pipe Repair-Near Vatve WBN-0-FCV-O27-0101 and WBN-0-FCV-027-0100, Work Order # 112809151 (5) 34989 Repair of diffusers at Watts Bar Nuclear via epoxy (6) 35163 Agrekko Chillers 2016 (7) 35192 Watts Bar Transmission Service Center Truck Canopy (8) 35244 wBN MET Tower grounding upgrade (Fp610266 two 429124)

(9) 35252 WBN U2 Steam Generator Replacement Core Borings (10) 35313 Replacement of existing Molar Ratio Skid with a Polyacrylic Acid (PAA) skid (1 1) 35370 lnstallation of 2500 gallon Flogard (Corrosion I nhibitor) double-walled tank (12) 35472 U2 Switchyard Clean-Up Foilowing U2 MBT Fire (13) 35931 Construct BoricAcid Mixing Station inside BoricAcid Mixing Building (14) 36259 Replace Cooling Tower Blowdown Flow Sensor O-FE-027-0098 and Transmitter (15) 36292 Replacement of Main Bank Transformers 2A,28,2C and Spare at WBN All other facility design and operational changes made during this reporting period with a potential impact on the environment were found to be within the scope of existing environmental permits and in compliance with regulations.

ln summary, there were no facility designs or operational changes from February 7,2016 to February 6,2017, which resulted in an unreviewed environmental question.

VII. NON.ROUTINE REPORTS No non-routine reports for EPP Section 4.2were issued during this reporting period.

VIII. CHANGES IN APPROVED ENVIRONMENTAL PROTECTION PLAN SPECIFICATIONS No changes were made to the wBN operating license, Appendix B, Epp during the reporting period.

(2) 34437 (3) 34767 (4) 34812 E-10 of 10