ML17059B645

From kanterella
Jump to navigation Jump to search
Insp Repts 50-220/97-05 & 50-410/97-05 on 970310-0418.No Violations Noted.Major Areas Inspected:Engineering
ML17059B645
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 07/17/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17059B644 List:
References
50-220-97-05, 50-220-97-5, 50-410-97-05, 50-410-97-5, NUDOCS 9707290167
Download: ML17059B645 (44)


See also: IR 05000220/1997005

Text

U.S. NUCLEAR REGULATORY COMMISSION

REGION

I

Docket Nos.:

50-220; 50-410

Report No.:

97-05; 97-05

Licensee:

Niagara Mohawk Power Corporation

Facility:

Nine Mile Point

Location:

Oswego, New York

Dates:

I

March 10 - April 18, 1997

Inspectors:

L. S. Cheung, Sr. Reactor Engineer

Electrical Engineering Branch, DRS

'R. A. Skokowski, Resident Inspector

Projects Branch No. 5, DRP

Approved by:

illiam H. Ruland, Chief

Electrical Engineering Branch, DRS

9707290167

970717

PDR

ADQCK 05000220

8

PDR

TABLE OF CONTENTS

PAGE NO.

E1

Conduct of Engineering ................ ~.................

~

~

~

~

~

~

1

E1.1

E1.2

E1.3

Unit 1 Motor-Operated Valve Hot Short Issues .........

~ ..

Unit 2 Motor-Operated. Valve Hot Short Issues ......"...

~ ..

Inadequate

Isolation of Unit 2 Remote Shutdown Panel Control

Circuits from the Control Room

.

~

~

~ ..

~

~ ..

~ . ~... ~,

. ~...

~

0

1

5

9

E8

Miscellaneous

Engineering

Issues (92903)

. ~... ~....... ~..........

~ .

12

E8.1

E8.2

E8.3

E8.4

E8.5

E8.6

E8.7

E8.8

(Closed) Unresolved Item 50-410/95-24-02

.

(Closed Unresolved Item 50-220/96-13-04

(Closed) Unresolved Item 50-410/96-14-01

(Closed) Unresolved Item 50-220/96-15-01:

(Updated) Unresolved Item 50-410/96-15-01

(Closed) Violation 50-220/95-24-01

(Closed) LERs 50-410/96-15 and 96-15-01

(Closed) LERs 50-220/96-10 and 96-10-01

12

15

15

15

15

15

15

16

E9

UFSAR Reviews

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

1 6

X1

Exit Meeting.......................

PARTIAL LIST OF PERSONS CONTACTED .......

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

1 6

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

1 7

0

EXECUTIVE SUMMARY

Nine Mile Point Units

1 and 2

NRC Inspection Report Nos. 50-220; 50-410/97-05

This engineering inspection was conducted:

1) to review licensee's corrective actions

following their identification that certain motor-operated

valves (MOV) in the safe

shutdown systems at both Units

1 and 2 were vulnerable to valve damage

caused

by fire-

induced hot shorts during a postulated control room fire; 2) to assess

licensee's

performance

in response to their identification, on two separate

occasions, that isolation

switches were not provided for Unit 2 Division I and II emergency diesel generator

(EDG)

service water outlet valves; 3) to review licensee's corrective actions in resolving the issue

associated

with Unit 2 Agastat GP relay service lives; and 4) to close out several

previously identified inspection items and licensee event reports (LER).

Encnineerinq

~

The licensee's review in 1992 failed to identify that certain motor-operated

valves in

Unit 1 shutdown cooling systems were vulnerable to valve damage

caused

by a fire-

induced hot short. The licensee's review at that time was narrow in scope

in that it

restricted the potential damage to the valve motor only and did not include potential

mechanical damage to the valve by the excessive torque of the valve motor.

~

The licensee revisited the 1992 review following a request by the NRC and

identified that two safe shutdown MOVs in Unit 1 were vulnerable to valve damage

caused

by a fire-induced hot short during a postulated control room fire. The

damage of any one of these two valves could cause the Unit 1 shutdown cooling

system to be inoperable.

This condition constituted

an apparent violation of 10 CFR 50.48(b).

~ 'fter identifying the multiple wiring number and termination point errors in Unit,1

valve repair procedures,

the licensee promptly revised the affected procedures

and

initiated a corrective action to preclude recurrence,

This condition constituted

a

non-cited violation, consistent with Section VII.B.1 of the NRC Enforcement Policy.

The licensee identified similar MOV problems (hot short issues)

in Unit 2 shutdown

cooling system and the reactor core isolation cooling (RCIC) system.

The licensee

promptly corrected the deficient conditions following their identification.

However,

these conditions constituted

an apparent violation of Unit 2 operating license No.

NPF-69, Item 2.G, Fire Protection Program.

The licensee's failure to identify and correct the deficient conditions at Units

1 and

2 (valves vulnerable to hot short issues) during the 1992 review constituted

an

apparent violation to 10 CFR 50, Appendix B, Criterion XVI, Corrective Action,

which requires conditions adverse to quality are promptly identified and corrected.

On two separate

occasions,

the licensee initiated good efforts in identifying the

discrepancies

within the control circuitry (lack of isolation switches for short-to-

ground protection) for Unit 2 EDG service water outlet valves.

The licensee's

actions to minimize EDG's unavailable time during the repairs were also good.

However, this deficient condition could have caused

a loss of cooling water to the

EDGs during a control room fire and adversely affected the safe shutdown of the

plant from the remote shutdown panel

~ This condition constituted

an apparent

violation of Unit 2 operating license No. NPF-69, Item 2.G, Fire Protection Program.

A weakness was identified in the licensee's reportability evaluation for

discrepancies,

as evidenced by the numerous questions from the inspectors

and

excessive time required for the licensee to determine that the above condition was

reportable under 10 CFR 50.72.

The licensee's

program for calculating the service lives of Unit 2 normally energized

Agastat relays was poor.

Calculation methods were not based

on sound

engineering judgement.

The licensee was in the process of revising the program

and developing

a better calculation method.

The original unresolved

item is closed.

A new unresolved

item is open for this issue.

Three previously identified unresolved items and one violation were closed.

Re ort Details

I. En ineerin

E1

Conduct of Engineering

E1.1

Unit 1 Motor-0 crated Valve Hot Short Issues

a.

Ins ection Sco

e

On November 1, 1996, Niagara Mohawk Power Corporation (NMPC) identified that

two motor-operated

valves (MOV) in the shutdown cooling system were vulnerable

to valve damage if a fire-induced hot short (short circuit between control wiring and

a power source) bypass the control, limit and torque switches during a postulated

control room fire. The licensee promptly notified the NRC of this event and issued

a

Licensee Event Report (LER). The inspectors reviewed the licensee's corrective

actions in response to their identification of this issue.

b.

Observations

and Findin s

Back round

On February 28, 1992, the NRC issued Information Notice (IN) 92-18, "Potential for

Loss of Remote Shutdown Capability During a Control Room Fire," to alert all

operating licensees to conditions found at several reactors that could result in the

loss of capability to maintain the reactor in a safe shutdown condition in the unlikely

event that a control room fire forced reactor operators to evacuate the control room.

The control room fire could cause hot shorts that could bypass the control

switches, torque switches, and limit switches of the MOV control circuits, and

initiate spurious operations of the MOVs which were required for safe shutdown.

These spurious operations could cause the valve motor to be continuously

energized,

resulting in excessive torque and current, causing mechanical damage to

the valve or electrical damage to the motor.

In response

to IN 92-18, the licensee issued Deviation/Event Report (DER) 1-92-Q-

0881 on March 17, 1992, to determine its applicability to Unit 1.

Because of their

narrow scope of review and a misinterpretation that spurious maloperations

were

limited to functional failure only, the licensee failed to identify and correct the

potential problem of valve damage

(mechanical damage due to excessive torque

from the valve motor) at that time.

The Event

During a recent (October 7, 1996) MOV inspection by the NRC, the licensee was

requested to revisit their review of IN 92-18.

The licensee reviewed the 1992

disposition of DER 1-92-Q-0881, recognized potential valve damage

in spite of

thermal overload protection, and identified that two valves in the shutdown cooling

system could be damaged

mechanically if a fire-induced hot short bypasses

certain

control, limit and torque switches of the valves.

These two valves, IV 38-01 and IV

38-13, were normally closed, were both inside the drywell, and were in the

common suction and the common discharge paths of the shutdown cooling system.

Any one valve that became inoperable would cause the shutdown cooling system to

be inoperable.

Subsequently,

the licensee issued

LER 96-10 on December 2, 1996,

to report this issue to the NRC. The licensee also noted that the circuit breakers for

these two valves, IV 38-01 and IV 38-13, had been administratively locked open

'since'April 12, 1995, because

of an unrelated modification (for 10 CFR 50,

Appendix J water seal issue).

This administrative control (circuit breakers locked

open) would preclude spurious maloperations

of these valves during a control room

fire. The licensee also issued, on February 28, 1997, Supplement

1 to the LER.

Supplement

1 included the result of the root cause evaluation.

The licensee

attributed the root cause for not identifying these problems earlier (during the 1992

review) to be a misinterpretation that the effects of the spurious operations were

limited to functional failures (electrical failure of the valves), without the assessment

of mechanical failure. The licensee also acknowledges that NMPC personnel failed

to recognize, at that time, that valve actuators could develop sufficient thrust to

mechanically damage the valves.

/

Review of the LER

The inspectors reviewed the LER, including Supplement

1, and found the LER

properly described the event.

The inspector agreed with the licensee for the root

cause of the event.

Short term corrective actions taken by the licensee included:

1) performing

additional detailed reviews for all other motor-operated

valves in the safe shutdown

systems,

including the hot shutdown system, and found that the other valves were

not affected; 2) starting promptly a similar review of Unit 2 motor-operated

valves

in the safe shutdown system and found many valves that were susceptible to this

fire-induced hot short issue, as discussed

in Section E.2 of this report.

Long term corrective actions planned by the licensee included: 1) revising Appendix

R safe shutdown analysis in the FSAR to require that the valve breaker be locked

open to preclude spurious maloperation,

by May 30, 1997; 2) training by December

31, 1997, of NMPC technical staff of the details of this LER to preclude future

occurrences

of inadequate

failure mode effect analyses

relative to motor-operated

valve spurious actuations.

The inspectors determined that the licensee's short-term and long-term corrective

actions for'this event to be appropriate.

The inspector also determined that for the

period from March 3, 1983, when the 10 CFR 50 Appendix R program was

implemented to April 12, 1995, when the circuit breakers for motor-operated

valves

IV 38-01 and -13 were administratively locked open, Unit 1 was in apparent

violation of 10 CFR 50.48(b) as follows:

3

10 CFR 50.48(b) requires, in part, that all nuclear power plants licensed prior to

January

1, 1979, shall satisfy the applicable requirements

of Appendix R to 10 CFR 50, Section III.G, including the requirements of Section III.L, alternative and

dedicated shutdown capability, which, according to the NRC's response

to Question

5.1.3 for Generic Letter 86-16, applies to the alternative safety shutdown option

under Section III.G, as follows:

Although 10 CFR 50.48(b) does not specifically include Section III.Lwith Sections

III.G, J, and 0 of Appendix R'as a requirement applicable to all power reactors

licensed prior to January

1, 1979, the Appendix, read as a whole, and the Court of

Appeals decision on the Appendix, Connecticut

Li ht and Power, et al. v. NRC, 673

F2d. 525 (D.C. Cir1982), demonstrate

that Section III.Lapplies to the alternative

safe shutdown option under Section III.G if and where that option is chosen by the

licensee.

The alternative shutdown capability had been chosen by the licensee (two

alternative shutdown panels were provided)

~ Appendix R,Section III.L.5 requires

that equipment and systems comprising the means to achieve and maintain cold

shutdown conditions shall not be damaged

by fire; or the fire damage to such

equipment and systems shall be limited so that the systems can be made operable

and cold shutdown can be achieved within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.- Materials for such repairs

shall be readily available on site and procedures

shall be in effect to implement such

repairs.

During the period from March 3, 1983, to April 12, 1995, the licensee did not have

written evidence, including repair procedures that if valves IV 38-01 and -13 were

damaged

mechanically due to a fire-induced hot short during a postulated control

room fire, the damaged

valves could be repaired and still achieve the cold shutdown

function within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.

Therefore this condition constituted an apparent violation

of 10 CFR 50.48(b). (EEI 50-220/97-05-01)

Review of Re air Procedures

The inspectors reviewed two P&IDs (piping and instrumentation diagram) for two

systems:

C-18017-C for the emergency cooling system, Revision 46; and C-

18018-C for the reactor shutdown cooling system, Revision 23 to identify the

motor-operated

valves (MOV) that were used for hot and cold shutdown following a

postulated control room fire. The inspectors also reviewed the elementary wiring

diagrams for valves IV 38-01, IV 38-13, IV 39-05, -06, -07, and -08, and did not

identify any deficiencies.

The inspectors also reviewed Damage Repair Procedure

N1-DRP-GEN-004, "Emergency Damage Repair for Fire Zones C2 and C3" Revision

3, dated April 25, 1995.

This procedure was used to repair valves IV 38-01 and-

13 following a postulated control room fire. The licensee also checked the

procedure steps against the wiring diagrams for errors.

The licensee found several

steps containing wire numbers and termination point errors, which could hamper

valve repair process if left uncorrected.

The licensee promptly issued an immediate

PCE (procedure change evaluation) to correct these errors.

The licensee also issued

DER 1-97-0682 on March 12, 1997, to document this issue.

The corrective action

for this DER included expanding the procedure reviews to include the other four

repair procedures.

Additional errors were identified in three of the procedures

reviewed.

Subsequently,

the licensee issued additional PCEs to correct the

identified errors.

All four repair procedures

had not been actually used, therefore,

no hardware (repair) errors had been involved.

The licensee attributed the apparent

cause for these errors to be a failure to perform

verification of written documentation

by the procedure writer. The licensee also

stated that all these repair procedures

were special procedures

and had never been

used before.

To eliminate other possible errors, the licensee planned to perform a complete

walkdown of all five repair procedures

and label all accessible wires (for better

identification of wire numbers and termination numbers).

The licensee stated that

these corrective actions would be completed by July 1, 1997.

The inspector's

review of the resolution of DER 1-97-0682 indicated that these actions had been

documented

and tracked by the DER.

The inspectors determined that the completed and planned corrective actions for

this procedure deficiency were appropriate.

However, failure to establish

acceptable

repair procedures

constituted

a violation of 10 CFR 50, Appendix B,

Criterion V, "Instruction, Procedures,

and Drawings," which requires activities

affecting quality to be prescribed by documented

instructions, procedures,

or

drawings of a type appropriate to the circumstances.

However, this licensee-

identified violation is being treated as a Non-cited Violation, consistent with Section

VII.B.1 of the NRC Enforcement Policy.

Conclusion

In response to NRC Information Notice 92-18, the licensee issued

a DER (DER 1-92-

Q-0881) in 1992 to document their review for its applicability to Unit 1.

Because of

their narrow scope of review (restricting to potential electrical damage to the motor

only), the licensee failed to identify and correct at that time the potential problem of

valve damage

(mechanical damage due to excessive torque from the valve motor)

due to a fire-induced hot short.

During a recent MOV inspection, the NRC had asked the licensee to revisit their

review of IN 92-18.

The licensee's

re-review identified that two valves in the

shutdown coolin'g system could subject to mechanical damage,

due to high torque

'rom the valve motors, if a fire-induced hot short bypasses

certain control and

torque switches of the valves.

The licensee also noted that the circuit breakers of

the two affected valves had been administratively locked open since April 12,

1995, because

of an unrelated modification.

Locking the circuit breakers open

would preclude maloperations of these valves during a control room fire. The

licensee attributed the root cause for not identifying these problems earlier (during

5

the 1992 review) to be a misinterpretation that the effects of the spurious operation

were limited to functional failure (electrical failure of the motors), without the

assessment

of mechanical valve failure due to excessive torque.

The licensee also

acknowledges that NMPC personnel failed to recognize at that time (during the i

1992 review) that valve actuators could develop sufficient thrust at stall to damage

the valves.

The inspectors concluded that during the period from March 3, 1983, when the 10 CFR 50 Appendix R program"was implemented to April 12, 1995, when the circuit

breakers for the affected two valves were administratively locked open, Unit 1 was

in apparent violation of 10 CFR 50.48(b).

The inspectors concluded that the licensee's failure to identify these potential valve

damages

(during a postulated control room fire) during the 1992 review constituted

an example of an apparent violation of 10 CFR 50. Appendix B, Criterion XVI,

Corrective Action, which requires conditions adverse to quality such as failures,

malfunctions, and nonconformances,

to be identified and corrected promptly.

(EEI 50-220/97-05-02)

The inspectors'eview of LER 96-10, including Supplement

1 to the LER, indicated

that the LER properly described the event.

The inspectors concurred with the

licensee for the root cause of the event.

The inspector determined that the

licensee's short-term and long-term corrective actions, in response to this event,

were appropriate.

A non-cited violation was also identified in the area of valve repair procedures.

Unit 2 Motor-0 crated Valve Hot Short Issues

Ins ection Sco

e

On December 17, 1996, and January

15, 1997, the licensee identified that multiple

MOVs in the shutdown cooling system and the RCIC system were vulnerable to

v'alve damage if a fire-induced hot short bypass the control, limit and torque

switches during a postulated control room fire. The licensee subsequently

notified

the NRC of this event and issued

LER 96-15.

The inspectors reviewed the

licensee's corrective actions in response to their identification of this issue.

Observation

and Findin s

In response

to NRC IN 92-18, the licensee conducted

an applicability review in

1992 to determine whether similar problems existed at Unit 2. The licensee issued

DER 2-92-0-1056 on March 25, 1992, to document the review process

and review

results (disposition).

At that time, the licensee considered that the examples

provided in IN 92-18 only applied to MOVs of which thermal overload protections

were bypassed.

Since the thermal overload protections for Unit 2 were not

bypassed,

the licensee concluded at that time that IN 92-18 did not affect Unit 2

operation.

0

Shutdown Coolin

S stem Motor-0 crated Valves

Following Unit 1 engineering identification that two motor-operated

valves in the

shutdown cooling system were susceptible to valve damage caused

by a fire-

induced hot short during a postulated control room fire, NMPC management

questioned

Unit 2 engineering whether similar conditions existed on the Unit 2

design.

An initial evaluation by Unit 2 engineering

indicated that similar problems

existed in the shutdown cooling mode of the residual heat removal (RHR) system.

At Unit 2, there were two sh'utdown cooling trains (two pumps and two heat

exchangers)

sharing

a common suction path, containing 2RHS" MOV-112 and -113

in series.

At that time, the power supply circuit breaker for 2RHS" MOV-113 was

administratively controlled in the open position.

Therefore, this valve was not

vulnerable to the hot short problem.

However, the power supply breaker for

2RHS" MOV-112 was closed, and was susceptible to the hot short problem, if the

fire-induced hot short bypassed

the control, limit and torque switches.

The licensee

also found that 2RHS "MOV-112 had sufficient torque that could cause mechanical

damage to the valve.

Subsequently,

the licensee notified the NRC of this issue on

December 17, 1996, and issued

DER 2-96-3379 to document this deficiency.

Since the opening of 2RHS" MOV-112 was required for the plant to achieve cold

shutdown, the inspectors determined that the above condition constituted

an

example of an apparent violation of the Unit 2 operating license as follows:

Nine Mile Point Unit 2 operating license No. NPF-69, Item 2.G requires the licensee

to implement and maintain in effect all provisions of the approved fire protection

program as described

in the Final Safety Analysis Report (FSAR) for the facility.

Nine Mile Point Unit 2 FSAR, Section 9B.8.2, which is part of the approved fire

protection program, states that the main control and relay rooms fire protection

analysis postulates

a fire in the main control or relay rooms that necessitates

evacuation of the main control room and verifies that capability for safe shutdown

of the plant exists from the remote shutdown room and other local control stations

outside the main control or relay rooms.

This analysis was based

on the

assumptions

which include that a single, spurious maloperation,

in addition to the

loss of all automatic signals, is considered for evaluation purposes for components

controlled from the main control room.

Section 9B.8.2.2 of the FSAR identified that

the cold shutdown under these conditions could be achieved within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.

In

addition, Unit 2 FSAR Section 9B.8.2-4, Conclusion, states that necessary

administrative procedures,

operating instructions, and operator training are provided

for the main control and relay rooms fire event.

However, the operating conditions described below was not based

on the above

assumptions:

As of December 17, 1996, a potential fire-induced hot short in the control circuit of

shutdown cooling motor-operated

valve NRHS "MOV-112, which is located in the

common suction path inside the drywell, could cause damage to the valve and

prevent the shutdown. cooling system from achieving its cold shutdown function

within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.

Specifically, the fire-induced hot short could bypass the valve

0

7

k

control, limit, and torque switches, and the excessive torque generated

by the

motor could cause mechanical damage to the valve, making the valve inoperable.

At that time, there. was not written evidence, including administrative procedures

and operating instructions, that the potentially damaged

valve could be repaired and

still achieve cold shutdown within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (EEI 50-410/97-05-03).

'Following the identification of the above deficiency, the licensee promptly

deenergized

the control circuits for valve 2RHS "MOV-112 and administratively

controlled its power supply circuit breaker in the open position during normal plant

operation, to preclude spurious operation during a control room fire. Two other

motor-operated

valves (2RHS "MOV-142 and -149) in the shutdown cooling system

also had their control circuits deenergized,

and their power supply circuit breakers

administratively controlled in the open position.

These two valves were used to

flush the stagnant water upstream of the residual heat removal heat exchanger

and

to provide pre-warming of piping system before the start of shutdown cooling.

Reactor Core Isolation Coolin

RCIC Motor-0 crated Valves

During the review of the preliminary LER 96-15, which was intended to report the

condition discussed

above, Unit 2 Station Operations Review Committee (SORC)

questioned

Unit 2 engineering if the RCIC system motor-operated

valves (MOV)

were subject to the same deficiency.

The results of Unit 2 engineering's

reviews indicated that there were multiple motor-

operated valves in the RCIC system that were vulnerable to the fire-induced hot

short problem.

These valves included 2ICS" MOV-121, -126, -128. A failure of any

of these valves would render the RCIC system inoperable.

On January

15, 1997,

the licensee notified the NRC of these deficient conditions.

The licensee also issued

DER 2-97-0118 to docu'ment and track the resolution of this deficiency.

Because

an inoperable

RCIC system, at that time, would cause the remote shutdown panel

to be unable to provide a safe shutdown path, the licensee entered

a seven-day

LCO (limiting condition for operation) on January

15, 1997, in accordance

with Unit

2 Technical Specification Section 3.3.7.4.

- The licensee immediately contracted

Generic Electric (GE) to conduct an analysis for an alternate success

path using

safety relief valves (SRV) in the automatic depressurization

system (ADS) mode in

conjunction with the RHR system, the "Pseudo LPCI" path.

The GE analysis results

indicated that hot shutdown could be achieved by manually reducing the reactor

vessel pressure through ADS and the Pseudo

LPCI paths.

The licensee also issued

the applicable procedures for using the alternate safe shutdown path.

Subsequently,

the licensee exited the seven-day

LCO on January 22, 1997.

The

Pseudo

LPCI paths consisted of two (redundant)

loops.

Each loop took suction from

the suppression

pool through manual valves, passed through the RHR heat

exchanger,

and injected coolant into the reactor vessel through the recirculation

line. The licensee stated that appropriate. sections of the Unit 2 fire protection

program (FSAR Section 9B) would be updated to incorporate the alternate shutdown

path when the RCIC system was inoperable following a postulated control room fire.

Review of Unit 2 LER 96-15

The licensee issued

LER 96-15 on January

16, 1997, to report the two issues

(potential shutdown cooling system MOV damages

and RCIC system MOV

damages) to the NRC. The licensee also issued Supplement

1 to LER 96-15 on

March 27, 1997, to include the result of their root cause evaluation.

The licensee

'attributed the root cause of the design deficiencies to be a failure to fully evaluate

hot short vulnerability of safe shutdown valves by the design organizations

(the

Architect Engineer) responsible forthe initial plant design.

The licensee also

attributed that the root cause for not identifying these deficiencies during the 1992

evaluation

(in response

to IN 92-18) was a mindset that information contained

in IN 92-18 was outside the design basis of NMP Unit 2.

The short term corrective actions taken by the licensee was prompt as discussed

in

various parts of this report (Section E1.2.b).

The long-term corrective action was to

provide training to the engineering

support staff, on LER 96-15, to preclude

improper evaluation of NRC Information Notices in the future.

The licensee

expected to complete this training by September 30, 1997.

The inspectors reviewed LER 96-15, including Supplement

1, and concluded that

the LER appropriately described the event.

The root causes

and corrective action

discussed

in the LER were determined to be appropriate.

Violations

The inspectors determined that before a successful

alternate safe shutdown path

was fully established

and proceduralized,

the potential loss of the RCIC system due

to a potential valve damage caused

by a fire-induced hot short following a

postulated control room fire constituted another example of an apparent violation of

Unit 2 operation license No. NPF-69, Item 2.G, Fire Protection Program, is as

follows:

As described

in Section E1.2(b) of this report, Unit 2 fire protection analysis for

c'ontrol room fire protection was based on the assumptions

which include that a

single, spurious maloperation,

in addition to the loss of all automatic signals, is

considered for evaluation purposes for components

controlled from the main control

room.

Section 9B.8.2.2 of the FSAR identified that the hot shutdown under these

conditions could be achieved within 10 minutes.

However, the operating conditions described below were not based

on the above

assumptions:

As of January

15, '1997, a potential fire-induced hot short in any one of the control

circuits of multiple motor-operated

valves (2ICS" MOV-128, -121, and -126) could

prevent the RCIC system from achieving its hot shutdown function within 10

minutes.

Specifically, the fire-induced hot short could bypass the valve control and

limit switches and the motor torque switch, and the excessive torque generated

by

the motor could cause mechanical damage to the valve, making the affected valve

inoperable.

The RCIC system would be inoperable when any one of the multiple

motor-operated

valves was inoperable

(EEI 50-410/97-05-04).

The inspectors

also determined that the licensee's failure to identify, during the

'1992 review in response to IN 92-18, that the shutdown cooling motor-operated

valve 2RHS" MOV-112 and multiple motor-operated

valves (2ICS" MOV-128, -121,-

and -126) in the RCIC system were susceptible to mechanical damage when their

control circuits were subjected to a fire-induced hot short during a postulated

control room fire, constituted an apparent violation of 10 CFR 50, Appendix B,

Criterion XVI, Corrective Action, which requires conditions adverse to quality, such

as failures, malfunctions, and nonconformances

to be identified and corrected

promptly.

The licensee failed to identify the deficient conditions at that time

because

a mindset existed at NMPC that the information contained

in IN 92-18 was

outside the design basis of the plant (EEI 50-410/97-05-05).

Conclusion

On two separate

conditions, the licensee had identified that there were motor-

operated valves in the shutdown cooling system (for cold shutdown) and in the

RCIC system (for hot shutdown) that were vulnerable to valve damage when

subjected to a fire-induced hot short during a postulated control room fire.

The inspectors concluded that these deficient conditions 'constituted two examples

of an apparent violation of the Unit 2 operation license No. NPF-69.

The inspectors also concluded that the licensee's failure to identify the above

deficient conditions, during the 1992 review in response to IN 92-18 cohstituted

an

apparent violation of 10 CFR 50, Appendix B, Criterion XVI, Corrective Action,

which requires conditions adverse to quality, such as failures, malfunctions, and

nonconformances

to be identified and corrected promptly.

Inade

uate Isolation of Unit 2 Remote Shutdown Panel Control Circuits from the

Control Room

Ins ection Sco

e

On two separate

occasions

during the week of April 7, 1997, the licensee identified

deficient condition within the control circuitry for the Unit 2 emergency diesel

generator

(EDG) service water valves.

The inspectors assessed

the licensee's

performance

in response to the associated

events.

Included in the

inspectors'ssessment

were discussions with the on-duty station shift supervisors

(SSSs),

operations

and licensing department management,

and system and design

engineers.

0

Observations

and Findin s

Service Water Valves Vulnerable to Short-to-Ground

Dama

e

During a review of an operating experience report from another facility regarding

a

deficiency that could potentially result in damage to plant EDGs during the

'performance of the alternate shutdown procedure,

NMPC identified a different

deficiency that could damage both Division I and II EDGs during a control room fire.

Specifically, the licensee identified that the remote shutdown panel (RSP) control

circuits for EDG service water outlet valves 2SWP"MOV66A and 668 were not

completely isolated from the control room.

Therefore, during a postulated control

room fire, the potential existed that a short-to-ground

in the control circuits could

result in a loss of control power to 2SWP" MOV66A and 668.

This deficiency

placed the plant in a condition outside the design basis, as described

in Unit 2 fire

protection program.

On April 7, 1997, the licensee notified the NRC in accordance

with 10 CFR 50.72.

Additionally, the SSS declared the RSP inoperable

and entered

a seven-day

LCO per Technical Specifications (TS) 3.7.4.b.

The licensee

documented

the deficiency in DER 2-97-1092.

This deficiency is discussed

below.

Although the additional fuses were in place, because

of lack of isolations, portions

of the control circuits for 2SWP" MOV66A and 668, located in the control room,

would have remained connected to RSP even after the transfer switches were

operated.

Therefore,

a short-to-ground within the control room could result in

blowing the fuses at the RSP panel, rendering the valves inoperable.

Since a loss of

off site power (LOOP) is postulated

in conjunction with a control room fire, the loss

of 2SWP" MOV66A and 668 would cause

a loss of cooling water to both EDGs.

This could cause

a station blackout condition and adversely affect the safe

shutdown capability of the plant from the RSP.

The inspectors reviewed DER 2-97-1092, and discussed

related issues with the

SSS.

The inspectors considered the licensee identification of the deficiency to be

good, and the immediate actions taken to address the deficiency were appropriate.

however, the deficient condition described above constituted

an apparent violation

of Unit 2 operation license No. NPF-69, item 2.G, Fire Protection Program, as

follows:

Nine Mile Point Unit 2 FSAR Section 98.8.2.3, which is part of the approved fire

protection program, states that in case of a fire in the main control or relay rooms,

the design modifications necessary to maintain availability and controllability of

systems required for safe shutdown and to prevent spurious maloperations

included

the provision of disconnect switches outside the main control or relay rooms for

certain safe shutdown equipment, which included two motor-operated

valves

2SWP" MOV-66A and B.

0

11

As of April 7, 1997, disconnect switches (isolation) located outside the main control

room were not provided to the control circuits for these two valves as necessary to

prevent spurious maloperations.

These two valves controlled the cooling water

supplies to emergency diesel generators

EG1 and EG3.

Because of this lack of

isolations,

a potential short-to-ground

in certain parts of the control circuits during a

control room fire could render the associated

valves inoperable.

(EEI 50-410/97-05-

'06)

To address this deficiency, f4MPC completed Design Change N2-97-049 to add

transfer switch contacts to isolate the RSP from the control circuits for

2SWP" MOV66A and 66B, located in the control room.

The inspectors reviewed

portions of this design change,

including the associate

10 CFR 50.59 applicability

review, and found them appropriate.

Additionally, the design change was discussed

with the responsible

engineers, with no concerns identified.

During implementation

of the design change, the inspectors observed that the licensee properly entered TS

limiting conditions for operations

(LCOs) for the EDGs and the service water

system, and performed appropriate post-modification testing.

Additionally, the

licensee's actions to minimize EDG unavailability, during the design change

implementation, was considered

good.

Additional Deficient Condition

On April 11, 1997, during the post-modification testing for the design change to the

2SWP" MOV66A control circuit, the licensee discovered

eleven drawing

discrepancies.

These discrepancies

consisted of both editorial and deviations

between the drawing and plant configuration, and were documented

in DER 2-97-

1136.

Nine of the eleven discrepancies

were minor in nature, including several

typographical errors, which were to be resolved with the closeout of the design

change.

However, two discrepancies

involved a wire that jumpered one of the

contacts associated

with the RSP transfer switch, and a lifted lead.

The

combination of the jumper and the lifted lead effectively voided the protection that

the transfer switch was to provide the RSP control circuit for 2SWP" MOV66A.

The SSS informed the inspectors of these discrepancies

at 4:34 p.m..

Subsequently,

the inspectors discussed

the discrepancies

in detail with the SSS and

was satisfied that only the jumper and lifted lead impacted the operation of the RSP

or other equipment.

The resident inspectors

also verified that the applicable TS

LCOs for the affected equipment were being implemented.

The initial reportability determination made by the SSS, as indicated on the DER

reviewed by the resident inspector the evening of April 11, 1997, was that the

event was only reportable under 10 CFR 50.73 (a 30-day written report).

The

resident inspectors questioned

the SSS as to why this event was not reportable

under 10 CFR 50.72 (a one-hour telephone notification) for a condition outside

design basis, as was the case on April 7. Subsequently,

the SSS included the

General Manager of Operations,

and eventually the Licensing Manager into the

discussion.

At 6:58 p.m., NMPC determined that the event was reportable under

10 CFR 50.72 for a condition outside the design basis, and notified the NRC at 7:37

12

p.m. Although NMPC eventually determined the event was reportable under 10 CFR 50.72, the inspectors considered their evaluation to be weak.

This weakness

was evidenced

by. the numerous questions from the inspectors

and excessive time

required by the licensee to determine that the event was reportable under 10 CFR 50.72.

'The licensee corrected the wiring discrepancies

under a work order.

Additionally,

the licensee compared the as-installed configuration to plant drawings for five other

valve control circuits associated

with the RSP.

No additional discrepancies

were

identified during this comparison.

The inspectors considered the licensee's

actions

taken to correct the discrepancies

and the performance of the precaution checks for

similar discrepancies

to be appropriate.

However, this failure to meet the design

basis was considered the second example for the apparent violation of Unit 2

operation license No. NPF-69, item 2.G, as discussed

above.

(EEI 50-410/97-05-06)

C.

Conclusions

On two separate

occasions,

during the week of April 7, 1997, NMPC identified

discrepancies

within the control circuitry for the Unit 2 Division I and II EDG service

water outlet valves.

These discrepancies

could have caused

a loss of cooling water

to the EDGs during a control room fire and adversely affect the safe shutdown of

the plant from the RSP.

The licensee's identification of the discrepancies

and the

actions to minimize EDG unavailability time during the repairs were good.

However,

on both occasions,

the plant failed to meet the design basis, as described

in the

Unit 2 Fire Protection Program, and were considered

additional violation of Unit 2

operation license No. NPF-69, item 2.G. Also, a weakness was identified in the

licensee's reportability evaluation for discrepancies

identified on April 11, as

evidenced

by the numerous questions from the inspectors and excessive time

required for the licensee to determine that the event was reportable under 10 CFR 50.72.

E8

Miscellaneous Engineering Issues (92903)

.

E8.1

'Closed

Unresolved Item 50-410 95-24-02:

This item pertained to the calculations

of the service lives of Unit 2 Agastat relays.

During the November 1995 inspection

when this item was identified, the licensee stated they had performed various aging

calculations using test data from Southwest

Research

Institute Report 04-1738-

001, the measured temperatures

at the relay locations, and the mechanical

activation energy of 0.84 eV. Their calculations indicated that the service lives of

the normally energized

(NE) Agastat GP relays in the control building were greater

than 14 years.

The licensee also stated that they had a preventive maintenance

program in place to replace the relays before their service lives expired.

Since all Agastat GP relays at Unit 2 were located in mild environment areas, they

were not covered by Unit 2 environmental qualification (EQ) programs.

13

Review of Rela

Service Life Calculations

During this inspection, the inspectors reviewed the licensee's

program for

calculating the service lives of normally energized relays and the program for relay

replacement.

The licensee had developed

Nuclear Engineering

Report NER-2E-007,

entitled, "Agastat Relay Service Life." This document was used by the licensee to

calculate the service lives of all NE Agastat GP relays and to schedule the

replacement of those relays.

The inspectors reviewed Revision

1 of this document, dated March 10, 1997, and

noted the following:

Section 4.2.1 discussed

a Grand Gulf document,

No. 04-1738-001, entitled, "Grand

Gulf Nuclear Station Test Report for Agastat Relays," dated'December

1988.

Based

on the Grand Gulf test, the licensee established two sets of curves, designated

as

Attachment 1, "Ambient Temperature

vs. Coil Temperature,"

and Attachment 2,

"Coil Temperature

vs. Relay Service Life." The licensee also stated

in this section,

that: "the ambient temperature

surrounding the relay and the inside coil temperature

were the two key elements in determining the service life of the relay; the Grand

Gulf document established

these relationships

based

on actual thermal aging tests.

Attachment

1 provided the relationships between ambient temperature

and coil

temperature

based on Grand Gulf's actual test results."

Attachment 2 consisted of

three curves, providing the relationships between the relay coil temperatures

and

the expected

service lives, for 24 Vdc, 125 Vdc, and 120 Vac relays.

Attachment

1 indicated that for ambient temperature

above 86

F, the coil temperature

and the

ambient temperature

had a linear relationship.

However, for ambient temperature

below 86

F, the coil temperature

stayed above 186

F.

In Section 4.2.2, the licensee used another means to estimate the relay coil

temperatures.

The licens'ee used thermography

readings,

aiming at the target relay,

and added 40

F. The licensee claimed that the result represented

the relay coil

inside-temperature.

Typically, the 'temperature of the energized relay coil and that

of the relay base differed substantially.

In addition, the relay coil was covered by a

thick plastic cover.

Therefore, it was not clear that the thermographic

reading

represented

the temperature of which part of the relay.

This method was not based

on actual testing, and the result was in conflict with Attachment

1 described

in

Section 4.2.1, which was in the same document.

The licensee calculated the service life of 120 Vac relays E31A-K029B and K024B

in panel

2CEC "PNL642, relays 3X-2HVCA05, 42X-HVCA02, 42X-HVCA05, 3-

2HVYA16, and 3-2-2HVRA90, in panel 2CEC" PNL859, using the thermographic

reading method to.be 40 years.

However, if the Attachment

1 method was used,

the calculated service life would be 10 years.

There was a 30-year-life difference

for the same relays.

The inspector concluded that the licensee's calculations for the

relay service life were unacceptable.

0

0

14

Review of Rela

Failure Re orts

The inspector also. reviewed two DERs (DER 2-96-2038, dated August 28, 1996;

DER 2-97-0391, dated February 12, 1997).

Both DERs documented

problems due

to failed, normally-energized

relays.

The licensee later sent th'ese failed relays to

PECo Energy Laboratories in Valley Forge, Pennsylvania,

for testing to determine the

'root cause.

The test results, as documented

in PECo report No. 9700406, dated

April 2, 1997, indicated that all relays had brittle, cracked relay coil bobbins,

indicating excessive thermal'aging,

The licensee calculated the service lives for

these two relays, using thermography

reading, to be 12 years and 15 years.

Again,

if the Attachment

1 method was used, the service lives for both relays would be 10

years.

If these relays were replaced within 10 years, relay failure could have been

avoided.

Licensee's

Corrective Actions

The licensee stated that they had contracted

PECo Laboratories to perform more

tests and to establish

a more reliable methodology to determine the relay coil

temperatures

based

on measured

ambient temperatures.

Ori April 28, 1997, the

licensee transmitted, for the inspector's review, a preliminary schedule for

developing

a new methodology to calculate all Unit 2 NE Agastat relay service lives.

This schedule

indicated that they could complete the new calculations, based on the

test results from independent

laboratories

(PECo Laboratories), by June 30, 1997.

On a telephone call on June 2, 1997, the licensee stated that the PECo test report

was just completed and was being reviewed by the licensee.

The licensee also

stated that they would start promptly to establish the new calculation methodology.

During the inspection, the inspectors emphasized

the importance of replacing the

safety-related

relays on time to prevent relay failures due to over-aging, because

all

of these relays perform important functions, including initiating reactor trip, starting

and stopping engineered

safety feature pumps, and opening and closing important

valves for accident mitigation.

Since relay failure normally could not be detected

until the system testing following the failure, common mode failure could result if

over-aged relays were not replaced on time.

The inspector asked the licensee why the Attachment

1 method was not used in

their calculations, but did not get a satisfactory answer.

However, the licensee did

state that:

1) they intended to replace all normally energized safety-related Agastat

relays, that had not been previously replaced, by the next refueling outage, even if

the new calculated service lives were greater than 13 years; 2) for second round

relay replacement,

all normally energized

and safety-related Agastat relays would be

scheduled for replacement within a 10 year interval even if the calculated service

lives were longer.

The inspectors considered this replacement

schedule acceptable.

The original item is closed:

However, the relay service life calculation issue remains

unresolved

pending further NRC review of licensee's corrective actions. (URI 50-

41 0/97-05-07)

15

Closed Unresolved Item 50-220 96-13-04:

This item pertained to hot short

vulnerability of Unit 1 shutdown cooling motor-operated

valves IV 38-01 and -13.

The details of this.issue and the licensee's corrective actions were discussed

in

Section E1.1 of this report.

This item is closed.

Closed

Unresolved Item 50-410 96-14-01:

This item pertained to hot short

vulnerability of three motor-operated

valves (2RHS" MOV-112, -142, and -149) in

the Unit 2 shutdown cooling system.

The details of this issue and the licensee's

corrective actions for this issue were discussed

in Section E1.2 of this report.

This

item is closed.

Closed

Unresolved Item 50-220 96-15-01:

This item pertained to the motor-

operated valves that were vulnerable to fire-induced hot short damage during a

control room fire. For Unit 1, the detail and the resolution was discussed

in Section

E1.1 of this report.

Therefore, this item is closed.

U dated

Unresolved Item 50-410 96-15-01:

For Unit 2, the design basis for their

fire protection program only postulates

a single maloperation (involving mechanical

valve damage)

during a postulated control room fire. The design basis assumptions

regarding multiple hot short scenarios were not discussed

in the fire protection

program.

Region

I will request the Office of Nuclear Reactor Regulation

(NRR) to

conduct

a review of this issue.

Therefore, this item remains open pending review

results from NRR.

Closed

Violation 50-220 95-24-01:

pertained to inadequate

corrective actions for

replacing over-aged,

normally energized Agastat GP relays and for replacing

commercial-grade Agastat time-delay relays.

During this inspection, the inspector

reviewed the licensee's corrective action taken to resolve these two issues,

including the licensee's

expanded

review of Wyle Laboratories

EQ test reports.

Corrective actions were discussed

in NMPC letters NMPIL1035, dated February 22,

1996, and NMPIL1066, dated April 29, 1996, in response to the Notice of

Violation. The inspector determined that the licensee's corrective actions were

adequate to prevent recurrence.

This item is closed,

Closed

LERs 50-410 96-15 and 96-15-01:

This LER pertained to Appendix R fire-

induced hot shorts in remote shutdown system valves.

LER 50-410/96-15

described issued associated with fire-induced hot short potentially rendering valves

unable to perform the intended 10 CFR 50, Appendix R functions during a

postulated control room fire. Supplement

1 to LER 96-15 was issued by NMPC to

provide the root cause and corrective actions not included in the original LER. The

technical details pertaining to the events were described

in NRC Inspection Report

50-410/96-14 and 50-410/97-01.

The original LER, 50-410/96-15 was reviewed in

Inspection Report 50-410/97-01, but since the licensee had yet to complete their

root cause evaluation and determine the subsequent

corrective actions, the LER

review was left open.

The inspectors reviewed the root cause and corrective

16

actions provided in the LER supplement,

and they were determined to be

appropriate.

The details associated

with the root cause

and corrective actions are

provided in Section E1.2 of this report.

Therefore, based

on the inspectors'eview,

LERs 50-410/96-15 and 50-410/96-15-01

are closed.

E8.8

Closed

LERs 50-220 96-10 and 96-10-01:

This LER pertained to Appendix R fire-

'induced hot shorts in shutdown cooling valves.

LER 50-220/96-10 described

issues

associated

with fire-induced.hot shorts potentially rendering valves unable to

perform the intended

10 CFR'50 Appendix R functions during a postulated control

room fire. Supplement

1 to LER 96-15 was issued by NMPC to provide the root

cause and corrective actions not included in the original LER. The technical details

pertaining to the events were described

in NRC Inspection Report 50-410/96-13.

The LER and supplement were found to be timely and to satisfactorily describe the

event.

The inspectors reviewed the root cause and corrective actions provided in

the LER supplement,

and they were determined to be appropriate.

The details

associated with the root cause and corrective actions are provided in Section E1.2

of this report.

Therefore, based

on the inspectors'eview,

LERs 50-220/96-10 and

50-410/96-10-01

are closed.

E9

UFSAR Reviews

A recent discovery of a licensee operating their facility in a manner contrary to the

updated final safety analysis (UFSAR) description highlighted the need for a special,

focused review that compares plant practices, procedures

and/or parameters

to the

UFSAR descriptions.

While performing the inspections discussed

in this report, the inspector reviewed

the applicable portions of the UFSAR that related to the areas inspected.

Nonconformances

with the UFSAR for the unit fire protection program were

discussed

in Sections E1.2 and E1.3 of this report.

The inspector verified that other

reviewed sections of the UFSAR wording were consistent with the observed plant

practices, procedures

and/or parameters.

X1

Exit Meeting

The inspector met with the licensee personnel at the conclusion of the site inspection on

April 18, 1997, and summarized the scope of the inspection and the inspection results.

No

proprietary materials were reviewed during this inspection.

The licensee acknowledged

the

inspection findings at that meeting.

The inspector amended the exit meeting in a telephone

call on June 4, 1997, to Mr. D.

Baker of Niagara Mohawk.

The inspector stated that:

1) the violation that pertained to

Unit 1 repair procedures

would be changed to a non-cited violation; and 2) NRC

management

review resulted in an additional apparent violation 10 CFR 50, Appendix B,

Criterion XVI, Corrective Action, for the motor-operated

valves,,that were vulnerable to the

hot short issue at both Units

1 and 2.

17

PARTIAL LIST OF PERSONS CONTACTED

Licensee

R. Abbott, Vice President

and General Manager - Nuclear

C. Beckham, Manager, Quality Assurance

D. Bosnic, Operations,

Unit 2

J. Burton, Director, ISEG

W. Connolly, QA Audit Supervisor

"

R. Dean, Manager, Unit 2 Engineering

T. Fiorenza, Technical Support

G. Gresock, Licensing Engineer

G. Helker, Unit 2 WC/OMG

A. Julka, Supervisor, Unit 2 Electrical Engineering

M. Kalsi, Unit 2 Electrical Engineering

M. McCormick, Vice President,

Engineering

W. Pisand, Maintenance

Manager, Unit 2

N. Rademacher,

Plant Manager, Unit 1

A. Raju, Unit 2 Electrical Engineering

K. Sweet, Unit 1 Technical Support Manager

R. Tessier, Training Manager

C. Terry, Vice President NSAS

L. Vavra, MATS, Inc.

A. Vierling, General Supervisor,

Fuel and Analysis

C. Wave, Chemistry Manager

G. Whitaker, Engineer,

ISEG

D. Wolniak, Manager of Licensing

W. Yaeger, Unit 1 Engineering Manager

NRC

T. Beltz, Resident Inspector

B. Norris, Sr. Resident Inspector

18

ITEMS OPENED, CLOSED AND DISCUSSED

~Oen ed

50-220/97-05-01

VIO

Unit 1 failure to meet 10 CFR 50.48(b) requirements

50-220/97-05-02

VIO

Unit 1 failure to identify and correct the MOV deficiency earlier

50-410/97-05-03

VIO

Unit 2 failure to meet the fire protection program in achieving

cold shutdown

50-410/97-05-04

VIO

Unit 2 failure to meet the fire protection program in achieving

hot shutdown

50-410/97-05-05

VIO

Unit 2 failure to identify and correct the MOV deficiencies

earlier

50-41 0/97-05-06

VIO

Unit 2 failure to provide disconnected

switches to MOV control

circuits

50-41 0/97-05-07

URI

Unit 2 normally energized Agastat GP relay service life

calculations

50-410/95-24-02

URI

Unit 2 normally energized Agastat GP relay service life

calculations

50-220/96-13-04

URI

Unit 1 shutdown cooling MOVs susceptible to hot short issue

50-410/96-14-01

URI

Unit 2 shutdown cooling h/IOVs susceptible to hot short issue

50-220/96-15-01

URI

Unit 1 MOVs susceptible to hot short issue

50-220/95-24-01

VIO

Inadequate

corrective actions for replacing Agastat GP and

time delay relays

LER 50-410/96-1 5

and 96-15-01

LER

Unit 2 MOVs susceptible to hot short issue

LER 50-220/96-10

and 96-10-01

LER

Unit 1 MOVs susceptible to hot short issue

l