ML17056C045

From kanterella
Jump to navigation Jump to search
Insp Repts 50-220/92-18 & 50-410/92-20 on 920727-0807 & 0831-0901.No Violations Noted.Major Areas Inspected:Response to GL 88-14,corrective Actions for NOV 50-410/91-12-02 & Actions to Address Unresolved Item 50-410/91-12-04
ML17056C045
Person / Time
Site: Nine Mile Point  
Issue date: 09/25/1992
From: Drysdale P, Eapen P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17056C044 List:
References
50-220-92-18, 50-410-92-20, GL-88-14, NUDOCS 9210080003
Download: ML17056C045 (14)


See also: IR 05000220/1992018

Text

'

U. S. NUCLEAR REGULATORY COMMISSION

REGION I

REPORT NOS.

~

50-220/92-18,

50-410/92-20

DOCKET NOS.

LICENSE NOS.

50-220

50-410

DPR-63

NPF-69

LICENSEE:

FACILITYNAME:

INSPECTION AT:

Niagara Mohawk Power Corporation

301 Plainfield Road

Syracuse, New York 13212

Nine Mile Point, Units

1 and 2

Scriba, New York

INSPECTION DATES:

July 27 - August 7; and August 31 - September

1, 1992

INSPECTOR:

P. Drysdale, Sr.

eactor Engineer,

Systems Section, EB, DRS

Date

APPROVED BY:

Dr. P. K. Eapen, Chic

Systems Section,

Engineering Branch, .DRS

Date

~Ah

d:

Th

R

'

G

'

<<88-14

dU

f

actions for the Instrument Air System in Unit 1;

the licensee's corrective actions for

violation NOV 50-410/91-12-02 (inadvertent isolation of a secondary containment unit

cooler); and the licensee's actions to address

unresolved item URI 50-410/91-12-04 (reduction

in cooling capability in certain unit coolers).

9210080003

920930

PDR

ADOCK 05000220

8

PDR

c$

~

~

~

~

~

~

~

~

~

~

~

2

~RSgllr.

The licensee is nearing completion on Phase IIof a three phase response to Generic Letter 88-14 for Unit 1.

As a result of the design basis reconstitution effort for the

Instrument Air system, several design issues remain open.

The significance and priority for

resolving these items remain as concerns to the NRC. The initial schedule committed by the

licensee for this GL was not met due to changes in operating cycle and the resulting

postponement of the outage required to complete the actions.

The licensee agreed to provide

a revised schedule and the status of open engineering issues by September 3, 1992.

The licensee's corrective actions for violation 50-410/91-12-02 was adequate.

Therefore this

violation is closed.

However, complete and documented engineering bases for current service

water cooling capabilities were not available.

Consequently,

unresolved item URI

50-410/91-12-04 remains open.

3

1.0

UNIT 1 RESPONSE TO NRC GENERIC LETTER 88-14, "INSTRUMENTAIR

SUPPLY SYSTEM PROBLEMS AFFECTING SAFETY-RELATED

EQUIPlVH<JitT"

The inspector reviewed Niagara Mohawk's response and progress on actions imposed through

NRC Generic Letter (GL) 88-14.

The GL was issued in August of 1988 as a result of NRC

concerns about instrument air system failures which have caused adverse effects upon

safety-related equipment.

The letter requested

licensees to verify that safety-related

instrument air "systems are operated,

maintained, and tested in accordance with design basis

requirements and that system components would perform as expected in all design basis

events.

Niagara Mohawk responded

to the GL in April 1989.

This response outlined the following

three phase evaluation of plant air and gas systems (Instrument, Service, and Breathing Air):

Phase I:

Short term actions to verify the systems'peration,

testing, and maintenance

are performed in accordance with the original design basis.:

Phase II:

Long term,* complex operational considerations involving testing, analysis, and

evaluation of system aging and degradation to assure continued performance

and fulfillmentof mtended functions.

Phase III:

Implementation of corrective actions and system improvements.

The response letter indicated that an engineering evaluation was performed in Phase I to

determine that the IAS system was being operated within its design, operational basis and its

safety evaluation.

The design and operational bases were also verified by a detailed

evaluation of the engineering documentation.

The Phase I reviews concluded that all air systems were operated,

maintained, and tested in

accordance with the design basis requirements.

Phase II work was ongoing during this

inspection and a separate project was undertaken to reconstitute the design bases for the

plant's air systems as part of the licensee's efforts to reestablish the design bases for

safety-related

systems at Unit 1. This work has proceeded in parallel with the Phase II work

to evaluate IAS performance.

A contractor was hired to establish the design basis for the air

systems and to produce a System Design Basis Document (SDBD). This work was nearing

completion at the time of this inspection.

In April 1992, the contractor notified Niagara Mohawk getter 1120-140-SYR-199, 4/7/92) of

twenty nine outstanding engineering and design basis issues for Unit 1 air systems and

provided a description of all plant equipment and documents affected by each issue.

Also in

April 1992, Niagara Mohawk Engineering and the contractor conducted a formal meeting and.

addressed

sixteen of the above issues.

The meeting identified the potential safety significance

of all sixteen open items and the actions required to resolve them.

The licensee determined

that each of the sixteen items was not a technically significant discrepancy.

Niagara Mohawk

4

Evaluation engineers performed a preliminary evaluation of all design-related

open items in

accordance with procedure DBGR-012, "Discrepancy Evaluation Guideline"; however, the

classification of their significance was preliminary since the issues were not completely

evaluated and their resolution remained open.

Engineering evaluations were performed by

the contractor on 16 of the current 29 outstanding open items.

The inspector reviewed the current status of engineering and design reconstitution efforts for

the Unit 1 IAS and the unresolved engineering issues against the licensee's response letter.

Niagara Mohawk's initial response to the GL was based upon the existing body of

engineering and design basis information available within the company in 1989;

The original

architect-engineer (AE) for Unit 1 was not involved with the initial response to the GL and

the current design basis reconstitution is supported by the contractor.

The response letter

indicated that completion of the Phase II work was dependent on the next scheduled refueling

outage which was then scheduled for Spring of 1991.

However, the operating cycle was

delayed and the refueling outage was postponed until 1993.

The letter also indicated that the

results of Phase IIwould be submitted after the next refueling outage (initiallyplanned for

Spring of 1991) and Phase IIIresults would be submitted by January 1992,

The delayed

operating cycle affected Phase

11 and Phase IIIand the licensee has not established new

completion dates for these activities.

The inspector discussed

the above inconsistencies in the

response letter with the licensee.

The licensee agreed to document the revised schedule for

the completion of the required actions in a letter to the NRC by September 30, 1992.

Out of the total twenty nine unresolved items, the inspector observed that four were

significant as they had a potential impact upon operation and testing (see ABB letter of

4/7/92, items OI-506-'S020, -S021, -S022, and -S027).

These items were:

1) lack of design

basis information for safety relief valve setpoints; 2) unable to determine cooling water

requirements for instrument air compressors;

3) pipe and pipe support design load and stress

analyses do not exist; and 4) analysis of the instrument air capability under a 50% duty cycle

does not exist.,The inspector discussed

the status of these items with the licensee and noted

the licensee had only completed a preliminary evaluation of these and other items.

The

formal classification of all of the open engineering issues for the IAS was pending at the time

of this inspection.

Therefore, this issue remains unresolved pending the licensee's completion

of the formal evaluation of the IAS and resolution of all open engineering issues

(URI 50-220/92-18-01).

2.0

FOLLOWUP TO PREVIOUS NRC CONCERNS (92702)

l

V

-41

1-12- 2'F il r

F

11 wPr

r

n

RI

-41

1-12-

'

il u

f il

rr

i n Pr

uct in

ervi

W ter

ni

1 r

In NRC inspection report 50-410/91-12, a violation was issued to address the inadvertent

valving out of SW unit cooler 2HVR*UC404D for an extended time.

Preventive

Maintenance work and testing were initiated on the cooler and an isolation tag permit

("markup") was approved by the operations staff.

The maintenance work was interrupted

prior to completion as the cooler's SW discharge throttle valve could not be positioned

properly to provide the required SW outlet flow. The markup was voided and tags were

removed from the cooler.

However, the SW inlet valve was not returned to the open

position, thus making the cooler unavailable.

The condition was noted approximately two

weeks later when a confirmatory valve lineup was performed by operations personnel and the

valve was noted to be out of its required position.

This situation was reported by the licensee

in LER 91-16 on August 1, 1991, and its supplements

dated September 3, 1991, and

November 21, 1991.

The initial violation addressed

the apparent inoperability of this cooler

from a technical specifications point of view.

After an engineering review of the cooling capacity provided by this heat exchanger,

Niiagara

Mohawk concluded that the reduction in heat removal capability did not represent a loss in

capacity below the required minimum for post-accident cooling of the secondary containment.

Under the analyzed worse case conditions in the SW system (maximum heat loading in

containment and minimum temperature difference between SW and containment), the

minimum time required to meet secondary containment drawdown to -1/4" water gauge could

still be achieved.

This information was presented to the NRC during an enforcement

conference on October 17, 1991.

Based on this enforcement conference,

the NRC concluded

that the reduction in heat removal capability for cooler 2HVR*UC404D was not a violation

of technical specifications as previously stated.

The NRC also concluded that the inadvertent

isolation of this cooler was an indication of inadequate configuration control which was a

violation of NRC requirements.

The violation was therefore reissued to reflect inadequate

procedure controls over the implementation and voiding of equipment markups as discussed

in the NRC letter dated October 23, 1991, and in inspection report 50-410/91-17.

The inspector reviewed the licensees actions in response to this violation.

Generation

Administrative Procedure GAP-OPS-02, "Control of Equipment Markups" was revised on

November 11, 1991, to specify additional requirements for voided markups.

These included

instructions to retain all voided markups for accountability.

The inspector reviewed the file of equipment markups maintained in the Unit 2 control room

and randomly selected ten voided markups to examine them for conformance with

GAP-OPS-02.

Allof these files contained complete records of markup sheets and tags as

required by the procedure.

In addition, necessary approval signatures for voiding the markup

were appropriately documented.

Two of the files examined involved markup tags which had

been applied to plant equipment before they were voided.

As required by the procedure,

these files contained all of the tags that had been removed; however, a notation that all the

tags had been accounted for was not entered into the file as required by the GAP., The

inspector performed a complete accounting for these markup files and confirmed that all tags

had been removed and retained.

No tags were noted to be missing and all tag identification

numbers corresponded

to the numbers listed in the file. The operations manager was

informed that two voided markups had not been annotated

as required by the procedure and

that'operations personnel responsible for performing an accounting of tags might not fully

understand the procedure requirements.

The operations manager issued an instruction to all

station shift supervisors on August 11, 1992 to assure that a complete tag accounting is

performed and documented.

The inspector considered that the revised procedure

~

'

'

requirements to retain all voided markup files and tags provided the necessary

administrative

controls to complete necessary corrective actions for the violation.

The additional actions

taken by the operations manager to assure that voided tags are inventoried and documented

are also considered adequate to address the inspectors concerns.

Based upon the above

review, this item is closed (NOV 50-410/91-12-02).

'he inspector noted that additional actions were taken by the licensee to provide a

methodology for operations personnel to interpret technical specifications requirements and to

determine the operational status of serviceable unit coolers when one or more coolers are

removed from service for maintenance or testing.

The interpretation provided a means to

assure that the available cooling capacity was adequate to provide minimum post-accident

containment cooling and drawdown.

The inspector reviewed the licensee's evaluations of

cooler performance and noted that the interpretation was based upon an assumed

average

cooler degradation of 30% under worse case conditions.

However, detailed and formalized

engineering calculations were not available at the time of this inspection to substantiate

the

validity of this assumption.

This is of particular concern to the NRC since some coolers

(2HVC*UC407C and 2HVC*UC407E) were demonstrated

by testing in May 1991 to have

less than 63% design capacity available.

Therefore, the assumed

average of 70% available

capacity may not be valid for all situations where some unit coolers are permitted to be

removed from service.

The potential safety significance of these concerns were expressed

to

the licensee within the context of unresolved item 50-410/91-12-04,

"Build-up of

Silt/Corrosion Products in Unit Coolers," and willbe tracked for resolution under that item.

3.0

EXIT INTERVIEW

The inspector held a preliminary exit interview with Unit 2 management

on August 4, 1992

to review the results of the follow-up to the violation. A final exit interview was conducted

on September

1, 1992 with corporate engineering and Unit 1 licensing personnel to conclude

the review of the Unit 1 response to Generic Letter 88-14.

Attachment

1 contains a list of

personnel attending the exit meetings.

~

'

'

ATTACHMENT1

P~d

i

MhwkP wr

+

P. Bartollini, Lead Mechanical Engineer

G. Brownell, Site Licensing

J. Conway, Technical Support Manager

A. DeGracia, Operations Manager

+

P. Francisco, SDBD Control Point Manager

M. Friedman, Mechanical Design Engineer

S. Godamunne,

Mechanical Design Engineer

D. Green, System Engineer

M. Jaquin, Operations Support

E. Klein, Engineering Project Manager

B. Magnant, Site Licensing

M. McCormick, Plant Manager

+ R. Oleck, Design Basis Reconstitution Program Director

D. Rathbun, Operations Support

+ ¹ Spangoletti, I.icensing Program Director

. G. Thompson, Supervisory System Engineer

+ W. Yeager, Engineering Manager

T. Zannick, Site Licensing Manager

nit

e Nucl

r Re ulat

mmi

i n

W. Schmidt, Senior Resident Inspector, NMP

R. Laura, Resident Inspector, NMP Unit 1

B. Mattingly, Resident Inspector, NMP Unit 2

C. Beardslee,

Inspector Intern

Present at the preexit meeting on August 4, 1992

+

Present at the exit meeting on September

1, 1992

0'