Advises That Util 920724 Response to NRC Bulletin 92-001, Failure of Thermo-Lag 330 Fire Barrier Sys Acceptable.Nrc Should Be Informed of Completion of Corrective Actions to Restore Fire Barrier Operability
ML17056B931
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 08/04/1992
From: Menning J
Office of Nuclear Reactor Regulation
To: Sylvia B
NIAGARA MOHAWK POWER CORP.
References
IEB-92-001, IEB-92-1, TAC-M83900, NUDOCS 9208110329
Download: ML17056B931 (4)


Text

PJP

'Docket No.

50-PRO Hr. B. Ralph Sylvia Executive Vice President, Nuclear Niagara Mohawk Power Corporation 301 Plainfield Road

Syracuse, New York 13212

Dear Mr. Sylvia:

August 4, 1992 DISTRIBUTION:

'ocket File

'DI-1 Reading JCalvo CVogan OGC AHasciantonio, 13/D/18

CCowgill, RGN-1 NRC

& Local PDRs SVarga RACapra JHenning

PHadden, 8/D/1 ACRS (10)

Plant File

SUBJECT:

RESPONSE

TO NRC BULLETIN 92-01, "FAILURE OF THERMO-LAG 330 FIRE BARRIER SYSTEM," NINE HILE POINT NUCLEAR STATION, UNIT 2 (TAC NO.

H83900)

By letter dated July 24,

1992, Niagara Mohawk Power Corporation (NHPC) provided a response to NRC Bulletin 92-01 for Nine Mile Point Nuclear Station, Unit 2.

NMPC's response stated that compensatory measures have been implemented consistent with the plant Technical Specifications and licensing basis.

The compensatory measures (roving fire watches and verification of the operability of fire detectors on one side of the suspect fire barriers) were implemented on July 1,

1992, and will continue until definitive corrective actions are taken to restore operability to the affected fire barriers.

NHPC also stated that appropriate corrective actions to restore fire barrier operability are being developed through an industry program being coordinated by NUHARC.

This program will include establishment of a test data

base, development of guidance for applicability of tests, development of generic installation guidance, and consideration and coordination of additional testing as appropriate.

The results of these efforts, when completed, will be applied to the Thermo-Lag installations within the scope of NRC Bulletin 92-01.

We have reviewed your response and find it acceptable.

Please inform us when all corrective actions have been completed.

Further NRC review, if any, will be performed by inspection or audit.

Sincerely, Original signed by:

John E. Menning, Project Manager Project Directorate I-l Division of Reactor Projects I/II Office of Nuclear Reactor Regulation cc:

See next page NAME DATE CVo an i (

92 0FFIGE PDI 1. LA PDI-1 'H JMennin

avl)'2 snL ig 92 PDI-1:D

'ACa ra 9/Ii 92 OFFICIAL RECORD COPY FILENAME: A: iI,NM283900. LTR 9208110329 920804 PDR ADOCK 05000410 8

PDR lC fop'gg )@~y

E C '

bl 1

k

i

, -~ Hr.

B. Ralph Sylvia Niagara Mohawk Power Corporation Nine Mile Point Nuclear Station Unit No.

2 CC:

Mark J. Wetterhahn, Esquire Winston 8 Strawn 1400 L Street, NW.

Washington, DC 20005-3502 Hr. Richard Goldsmith Syracuse University College of Law E. I. White Hall Campus

Syracuse, New York 12223 Resident Inspector Nine Mile Point Nuclear Station P.

O.

Box 126

Lycoming, New York 13093 Gary D. Wilson, Esquire Niagara Mohawk Power Corporation 300 Erie Boulevard West
Syracuse, New York 13202 Mr. David K. Greene Manager Licensing Niagara Mohawk Power Corporation 301 Plainfield Road
Syracuse, New York 13212 Hs.

Donna Ross New York State Energy Office 2 Empire State Plaza 16th Floor

Albany, New York 12223 Supervisor Town of Scriba Route 8, Box 382
Oswego, New York 13126 Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, New York 10271 Hr. Richard M. Kessel Chair and Executive Director State Consumer Protection Board 99 Washington Avenue
Albany, New York 12210 Hr. Hartin J.

McCormick Jr.

Plant Manager, Unit 2 Nine Mile Point Nuclear Station Niagara Mohawk Power Corporation P. 0.

Box 32

Lycoming, New York 13093 Hr. Neil S.

Cams Vice President - Nuclear Generation Nine Mile Point Nuclear Station Niagara Mohawk Power Corporation P. 0.

Box 32

Lycoming, New York 13093