Informs That NRC Does Not Plan to Continue Insp of 881115 Allegation Re Employees Sleeping on Shift.Inspectors Will Continue to Conduct Random Unannounced Insps During Day Shift & Backshifts
ML17055E480
Person / Time
Site: Nine Mile Point  
Issue date: 01/25/1989
From: Wenzinger E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Burkhardt L
NIAGARA MOHAWK POWER CORP.
References
NUDOCS 8902010298
Download: ML17055E480 (6)


Text

Docket No. 50-220 50-410 Niagara Mohawk Power Corporation ATTN:

Mr. Lawrence Burkhardt, III Executive Vice President Nuclear Operations 301 Plainfield Road

Syracuse, New York 13212 Gentlemen:

Subject:

Allegation Regarding Employees Sleeping on Shift On November 15,

1988, our office received an anonymous allegation through Mr.

Charles Donaldson, Assistant Attorney General of the State of New York.

Mr.

Donaldson stated that the alleger had indicated that he had personally observed persons who perform safety-related work at Nine Mile Point Unit 1 (possibly licensed operators) who were sleeping while on duty.

Subsec. ent discussions directly with the alleger revealed that he had once observeo a control room operator who appeared to be sleeping.

Based on the facts given us by the alleger and inspections conducted by NRC inspectors, the event appears to be an isolated incident of little consequence.

Therefore, we do not plan to continue our inspection of this specific issue.

However, our inspectors will continue to conduct random unannounced inspections during day shift and backshifts.

It is our understanding, from discussions with you, that your management staff will also conduct such inspections to ensure that all personnel performing safety-related activities are properly attentive to and performing their duties.

Please provide us the details of your program to prevent or detect and correct concerns such as this.

As part of our review of your Unit 1 Restart Plan actions we intend to closely monitor your self assessment initiatives.

Mr. Donaldson has i'ndicated a willingness to discuss this issue with you in your review of this matter.

He can be contacted at (212) 341-2348.

8902010298 890i25 PDR ADQCK 05000220 P

PNU 0001.0.0 OFFICIAL RECORD COPY 2Ylf NMP/ALLEG-SLEEPING ON SHIFT-01/05/89

1

Niagara Mohawk Power Corporation 25 PAN 8:9 If you have any additional questions with regard to this -matter, please contact Mr. Jon Johnson of my staff at (215) 337-5234.

Sincerely, GE Edward C. Wenzinger, Chief Projects Branch No.

2 Division of Reactor Projects 0001.1.0 OFFICIAL RECORD COPY

'MP/ALLEG-SLEEPING ON SHIFT-01/05/89

h

Niaga'ra Mohawk Power Corporation

>> JAf> i989 CC:

J.

Perry, Manager, Nine Mile Point Unit, 1 Restart Task Force C; Mangan, Seni'or Vice President D. Palmer, Acting Manager - Quality Assurance Operations W. Hansen, Manager Corporate Quality Assurance K. Dahlberg, Unit 1 Station Superintendent R. Randall, Unit 1 Superintendent, Operations C.
Beckham, Manager Nuclear Quality Assurance Operations J. Willis, General Station Superintendent C. Terry, Vice President Nuclear Engineering and Licensing J.

F. Warden, New York Consumer Protection Branch Troy B. Conner, Jr.

Esquire Conner

& Wetterhan John W. Keib,. Esquire R.

G. Smith, Unit 2 Superintendent, Operations R.

B. Abbott, Unit 2 Station Superintendent

Director, Power Division State of New Yor'k, D'epartment of Law Licensing Project Manager, NRR Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center.(NSIC)

NRC Resident Inspector State of New York bcc:

Region I Docket Room (with concurrences)

Management Assistant, DRMA (w/o encl)

DRP Section Chief PAO (2)

SALP Reports and All Inspection Reports Robert J.

Bores, DRSS M. Johnson, EDO A.sbapsh>>.

<LuqW 4n.

I:DRP Barkley/rhl 1/l~ /89 end ARP Johnson 1/iD/89 cc 7o Sk.pygmy>re le nger uy49 ne 1/ +9 0002.0.0 OFFICIAL RECORD COPY NMP/ALLEG-SLEEPING ON SHIFT-01/10/89

)

\\

I