ML17055D434

From kanterella
Jump to navigation Jump to search
Insp Rept 50-220/87-23 on 871103-06.No Deviations,Violations or Unresolved Items Noted.Major Areas Inspected:Licensee Followup Actions in Response to Previously Identified Violations & Unresolved Items
ML17055D434
Person / Time
Site: Nine Mile Point 
Issue date: 12/04/1987
From: Chaudhary S, Strosnider J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17055D433 List:
References
50-220-87-23, NUDOCS 8712140253
Download: ML17055D434 (12)


See also: IR 05000220/1987023

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION I

Report

No.

50-220/87-23

Docket

No.

50-220

License

No.

DPR-63

Pri or ity

Category

C

Licensee:

Niagara

Mohawk Power Corporation

301 Plainfield Road

Syracuse,

New York

13212

Facility Name:

Nine Mile Point, Unit

1

Inspection At:

Scriba,

New York; and Syracuse,

New York

inspection

Conducted:

November 3-6,

1987

Inspectors:

%A.ctcc.

S.

K.

C audhary,

Senior Reactor

Engineer

tz<

6'ate

Approved by:

R. Strosnider,

Chief,

MPS,

EB,

DRS

ru~i~r

date

Ins ection

Summar

Ins ection Conducted

November 3-6

1987

Ins ection

Re ort No. 50-220/87-23)

Areas

Ins ected:

A routine

unannounced

inspection

was conducted

by a region

based

inspector of the licensee

follow-up actions

in response

to previously

identified violations

and unresolved

items.

Results:

No deviations, violations or unresolved

items were identified.

87 lQ fQQ253 B~ppp+2p

87ippa

p,gOCK

pDR

DETAILS

1.0

Persons

Contacted

Nia ara

Mohawk Power

Cor oration

"T.

W.

Roman, Station Superintendent

"T.

R.

Egan, Associate

Senior

NC&V Engineer

  • L. 'Wolf, Site Licensing Engineer

P. Francisco,

Lead Licensing Engineer

P.

George,

Assistant

Manager - Structural

Engineering

R. Oleck, Acting Manager of Consulting

A. Chiu, Associate Structural

Engineer

C. DiNatelli, Senior Structural

Engineer

New York State - Public Service

Commission

  • P. Eddy, Site Representative

U.S. Nuclear

Re ulator

Commission

'.

Schmidt,

Resident

Inspector

Review of Licensee Actions in Res

onse to Previousl

Identified Items

The inspector

reviewed documentation

and held discussions

with licensee

engineers

and other management

personnel

to assess

the adequacy

and/or

resolution of previously identified unresolved

items, violations and

deviations.

The review consisted

of examination of pertinent engineering

records,

licensee

submittals to the

NRC, discussions

with cognizant

personnel,

and visual examination of completed

works in the plant.

The follow-up actions

in response

to violations were specifically reviewed

against

the commitments

made

by the licensee

in his submittal to the

NRC.

The resolutions

of unresolved

items were reviewed for technical

adequacy

and

use of accepted

engineering principles.

The documents

reviewed for

this effort are listed in paragraph

3.0 of this report.

The following items were reviewed:

(Closed) 86-07-06, Violation:

This item pertains to inaccurate

as built

drawings of modified supports

and failure to issue

change

requests

for

other supports.

The licensee

has

documented

the current design configura-

tion of supports

SCR1-3

and SCRl-6 in the final as-built drawing issued

as

revision

1

on January

9,

1987.

Also, the personnel

in the engineering

department

were re-advised of the necessity of documenting

engineering

changes

in support design,

even if the changes

are minor.

This item is

closed.

(Closed) 84-01-02,

Unresolved

Item:

This item is related to the design

accuracy of core spray pipe supports

at

RCS

pump ¹122.

The licensee

has

reanalyzed

the

system to demonstrate

the seismic qualification of the

piping system.

The reanalysis

is documented

in calc.

¹S14-81-P001,

Revision 0.

The inspector

reviewed the above analysis

and determined that

the analysis

is consistent with the plant

FSAR.

It has

been

performed

with the response

spectra

method described

in the

FSAR.

From the current

analysis it is determined that the system piping meets the code allowable

stresses

in the support for seismic

loading.

This item is closed.

(Closed} 84-15-04,

Unresolved

Item:

This item pertains

to

a lack of

documented

and consistent criteria for the seismic design

and qualifica-

tion of safety related piping systems.

The licensee

has developed

and

documented

the design criteria for seismic design

and qualifications of

piping system.

The inspector

reviewed the procedure

MDC-2, Revision 3.

The documented criteria appears

to meet the

ASME Code requirement for load

combinations

and the analysis

methods.

This item is closed.

(Closed) 86-07-13,

Unresolved

Item:

This item is related to

a damaged

hanger

in

a drain line in main

steam

system.

A work request

was initiated

and the hanger

was repaired

(LIR ¹010410)

on June

20,

1986.

The licensee

was not sure

as to how the actual

damage

to the hanger occurred,

but the

personnel

were re-advised

to be careful

when working in the vicinity of

safety related

equipment not to damage

equipment.

This item is closed.

(Closed) 86-07-07, Violation:

This item pertains to modification of

existing drain pipe supports

05-SCR1-3,

05-SCR1-6,

05-SCR1-7

where field

welds were undersized

( 1/4 inch to 3/8 inch less

than design).

The

inspector

reviewed the licensee's

evaluation of this discrepancy

documented

in Calc. ¹S14-39-Al.

The evaluation indicates that the

maximum unit load

on the welds (pounds

per inch) is only 2925 lbs per

inch in spite of the

reduction in weld size.

The actual

load is considerably

smaller than the

allowable load

on welds in question.

No safety concern exists.

This item

is closed.

(Closed) 86-07-05,

Unresolved

Item:

This item pertains to the design

and

analysis of piping and support

systems for emergency

condenser

system

modifications.

The licensee

has

used design

and acceptance

criteria that

were significantly different from the

FSAR descriptions

of the analytical

method.

In the modification design

and analysis:

1) the development of

ground motion was based

on probabilistic ground motion hazard analysis;

2) the allowable limits for pipe stresses

were based

on the

ASME Code,

Section III, 1980 instead of ASA 1331,

1955 as referenced

in the

FSAR;

and

3)

ASME Code

case

N-411 was

used in the analysis.

The licensee

has reanalyzed

the piping and supports

in the

Emergency

Condenser

(EC) system.

The

new analysis is documented

in calculation

package

No. 514-39-LBP0012

A through

D, Revisions 0.

The

new analysis,

although still based

on

1980

ASME Code,

conforms to the ground motion

referenced

in the

FSAR.

The

Code case

N-411

has not been utilized.

The

use of the later code

(ASME-1980) is permitted under Section

NI of the

ASME Code.

The inspector'reviewed

the analysis

and evaluation of the

system for technical

adequacy,

and conformance to the code requirements

and determined that the analysis

and design of the system

conforms to the

applicable

code

and the

FSAR descriptions.

Thi's item is closed.

(Closed) 84-15-01, Violation:

This item pertains to the lack of control

procedures

and functional specifications

during work related to IEBs 79-02

and 79-14.

In response

to this violation, the licensee

committed to

upgrade

his engineering

assurance

program to provide better procedural

control

and consistency

in design

and analysis

work.

The inspector

reviewed the following documents

to verify the adequacy

of the engineering

assurance

program.

System Descriptions;

Volumes

1 5 2 (Controlled Copy No. 25)

Design Criteria;

Volumes

1

& 2

Standard Specifications

(Controlled Copy No.

15)

Nuclear

Engineering

and Licensing Procedures;

Volumes 1, 2,

and

3

(Controlled

Copy No. 66)

Based

on the

above review and discussions

with responsible

engineers,

the

inspector

determined that controls

have

been

provided to assure

consis-

tency

and technical

accuracy

in the area of design

and analysis.

This

item is closed.

(Open) 84-15-05,

Unresolved

Item:

This item pertains to

a lack of

procedures

for the evaluation of increased

loads

on concrete

expansion

anchors

due to seismic reanalysis

required

by IEB 79-14.

The licensee

has

made progress

in this area;

however,

the actual

comparison of the original

design

loads

and the

IEB 79-14 loads

have not been

completed.

This effort

was included in the

scope of general

seismic

upgrade

program which has not

been

completed yet.

This item, therefore,

remains

open pending the

evaluation

and comparison of loads,

and determination of current factors

of safety for concrete

expansion

anchors.

(Closed) 86-07-11, Violation:

This item pertains

to anchor installation

(anchor 039-Al) where bolts

had

been installed

such that three bolts did

not meet the acceptance

criterion of two exposed

threads

beyond the

fastening

nut.

The licensee

has analyzed this condition and determined

(calculation

PS14-39-A1,

Rev.

0) that if the bolt is flush with the

surface of nut, the installation is acceptable.

Also, the jet impingement

load (the governing load)

has

been

reduced

from 200 kip to 149 kip due to

reanalysis.

Therefore

no safety concern exists regarding

the load

carrying capacity of the installed bolts.

This item is closed.

e

(Closed)

84-26-01,

Unresolved

Item:

This item pertains to lack of review

in the material requisition program of purchase

requisitions

(PR) by

the user organization to assure

the quality and adequacy

of items ordered

for service.

The licensee

has

revamped

the material requisition program

controls.

The old procedure

APN-14 has

been

superseded

and

a

new admin-

istrative procedure

AP-70,

Rev.

2, Sec-6.0,

has

been

implemented.

The

new

procedure

requires that all purchase

requisitions

must be reviewed

by

engineering

to assure their conformance

to

FSAR commitments,

codes

and

standards,

and the technical

requirements

of the application.

The material

management

system

manual

Section 5.0 also clearly establishes

the engineering

review requirement for all safety-related

purchase

requisi-

tions.

The inspector verified by

a review of some

PRs that this process

has

been

implemented

and is working.

A verification of this procedure

by

the licensee's

Compliance

and Verification Organization

was also reviewed

by the inspector.

This'tem is closed.

(Closed) 86-07-10, Violation:

Two braces for Emergency

Condenser

(EC)

steam piping anchor

No. 39-Al were connected

to wall embedded

plates

by

fin plates

and

use of a mixture of A-325 and A-490 bolts, whereas

A-490

bolts were required

by drawing No.

F-39831.

The licensee

provided records

to

show that at the time of NRC inspection,

the support

was still not

fully erected

and

was not ready for final inspection.

The A-325 bolts

were installed to temporarily hold the support, in place.

An in-process

gC inspection report

No. 21.6008

was presented

to the inspector to sub-

stantiate

that the support

had not been finally accepted

at the time of

the

NRC inspection.

This

gC report

was annotated

with a remark that A-325

bolts have

been

used to erect

the support.

The licensee

had replaced

the

bolts before the final inspection

and acceptance

of this support.

This

item is closed.

3.0

Documents

Reviewed

The following documents

were reviewed during the course of this

inspection.

APN-14, "Procedures

for Control of Material

and Services,"

Rev.

5

(Superseded)

AP-7.0,

"Procedures

for Control of Material

and Services,

Rev.

2

(current)

Material

Management

System

Procedures

Manual, Section

5

Safety Evaluation 85-043,

Rev.

2, "Installation of Perimeter Draining

System for Administrative Building"

'

Letters

from NMPC to

NRC

11/5/86

(NMPIL-0112); 1/7/85; 1/30/86

(NMPIL-0024); 3/31/86

(NMPIL-0040)

Design Standard

Manual, Section

MDC-1, MDC-2, MDC-5 (Mechanical

Design

Criteria)

Piping and Support Analyses

Calculation

Numbers

"Emergency

Condenser

System

condensate

Supply/Return"

Calc.

No. S14-81-P001,

"Core Spray

Pump ¹122 to Topping

Pump ¹122"

Cal c.

No.

S14-39-LBP0012A-MDC-2

S14-39- LBP0012B-MDC-2

S14-39- LBP0012C-MDC-2

S14-39- LBP0012D-MDC-2

Calc.

No. S14-39-A1,

"E.C.

Steam

Supply Lines"

Work Request

No.

WR010410,

"System

OS Hanger"

Drawing Change

Request

No. NIY83, M4043LG044

Verification and Examination Report

No. 21-6008

Drawings

4.

Unresolved

Items

Unresolved

items are matters

regarding which more information is needed

to

determine if they are acceptable

items, deviations or violation of

requirements.

5.

Exit Interview

At the conclusion of the inspection,

the inspector

met with the licensee

representatives

(denoted

by * in paragraph

1.0) where the inspector

summarized

the

scope

and findings of this inspection,

At no time during this inspection did the inspector provide written

material

to the licensee.

The licensee

did not indicate that any

proprietary material

was included in the

scope of this inspection.

l

~