ML17055B747
| ML17055B747 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 05/28/1986 |
| From: | Anderson C, Cheung L, Paolino R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML17055B746 | List: |
| References | |
| 50-220-86-05, 50-220-86-5, NUDOCS 8606100074 | |
| Download: ML17055B747 (28) | |
See also: IR 05000220/1986005
Text
(
U.S.
NUCLEAR REGULATORY COMMISSION
REGION I
Report
No.
50-220/86-05
- Docket No.
50-220
License
No.
Priority
Category
C
Licensee:
Nia ara
Mohawk Power Cor oration
300 Erie Boulevard West
S racuse
13202
Facility Name:
Nine Mile Point
Unit
1
Inspection At:
S racuse
Inspection
Conducted:
A ri 1 14-18
1986
Inspectors:
eonard
S.
Cheung,
Reactor
gineer
date
Ralph
P olino,
R
tor Engineer
da
e
Cliff A erso,
Chief
Plant Systems
Section,
EB
Mark Jacobus,
Sandia National
Lab.
Steve Alexander,
Engineer
s
2.x
P'4
date
Approved by:
Cliff A d rson,
hief
Plant Systems
Section,
EB
date
Ins ection Summar:
Ins ection
on A ril 14-18
1986
Re ort No. 50-220/86-05
~d:,>>
i
- i
i
i
lid
tial enforcement/unresolved
items
and open
items (50-220/86-05-01
through -11)
and corrective actions
taken
by Niagara
Mohawk Power Corporation with regard to
meeting the requirements
of 10 CFR 50.49.
Also included
as
a part of this inspec-
tion was review of additional
environmental qualification (Eg) files of Limitorque
Valve motors,
Rosemount transmitters
and
Fenwal
temperature
switches.
8606100074
860603
ADaCZ 05000aa0
G
,
,
Results:
Status of Previousl
Identified Items
The inspection
determined that the licensee
had completed all but two
corrective actions resulting
from the findings of the
NRC Eg team inspection
of August 15-23,
1985,
as follows:.
Potential
Enforcement/Unresolved
Items
Item Numbers
Status
1.
gualification file deficiencies
2.
Static-0-Ring pressure
switches
3.
4.
General
Electric EB-25 terminal
blocks
5.
General
Electric
EB-5 terminal
blocks
6.
Fisher
304 position switches
7.
Rosemount
1151 transmitters
50-220/85-13-01
50-220/85-13-02
50-220/85-13-03
50-220/85-13-04
50-220/85-13-05
50-220/85-13-06
50-220/85-13-07
Cl osed
Closed
Closed
Cl osed
Cl osed
Closed
Closed
~oee
Items
1.
Implementation of Eg procedures
2.
Closed
loop cooling motor
lubrication
3.
Acoustic monitor coaxial
cable
4.
Laurence
50-220/85-13-08
Open
50-220/85-13-09
Open
50-220/85-13-10
Closed
50-220/85-13-11
Closed
b.
Newl
Identified Items
Two unresolved
items were identified as
a result of a review of additional
E(} files:
1.
gual ification of Limitorque Valve motor wiring
2.
gualification Status of Kerite Cables
d
DETAILS
1.0
Ke
Persons
Contacted
Nia ara
Mohawk Power Cor oration
1.2
A. Athelli, Senior
EQ Engineer
W. Connolly,
QA Program
Manager
T.
Egan,
Engineer
- P. Francisco,
Lead Licensing Engineer
- G. Gresock,
Manager,
Nuclear Design
- J. Janas,
Associate
Senior
QA Engineer
- J. Jirousek,
EQ Manager
K.
Lampman, Assistant Generation
Engineer
~T.
Lempges,
Vice President,
Nuclear Generation
- S. Loveland,
EQ Engineer
R. Main, Generation Specialist
- C. Mangan,
Senior Vice President
"M. Mosier, Associate
Senior Nuclear Engineer
~T. Perkins,
General
Superintendent,
Nuclear
T.
Roman, Station Superintendent,
Unit
1'K.
Sweet, Electrical
Maintenance
Superintendent
~C. Terry, Manager,
Nuclear
Engineering
and Licensing
- G. Wilson, System Attorney
- S.
Wilczek,
Manager,
Nuclear Tech.
NMPC Consultants
J. Anderson,
Senior Qualification Engineer,
Wyle Lab.
- R. Bennett,
Engineering Supervisor,
Wyle Lab.
"T. Brewington,
Engineering
Program Manager,
Wyle Lab.
- J. Gleason,
Manager,
Nuclear Engineering Service,
Wyle Lab.
- L. Price,
EQ Engineer,
Gasser
Associates
~J.
Vaden,
Mechanical
Engineer,
Gasser
Associates
1.3
United States
Nuclear
Re ulator
Commission
~J. Kelly, Project Manager
- W. Johnston,
Deputy Direct,
DRS,
Region I
"Denotes those
present at the exit meeting
on April 18,
1986.
The
and
team members
also contacted
other managers,
supervisors,
engineers
craftsmen
during the inspection.
2.0
Status of Previousl
Identified Items
2.1
Closed
Potential
Enforcement/Unresolved
Item 50-220/85-13-01
pertain-
ing to generic qualification file deficiencies.
The inspector
reviewed
NMPC procedure
NT 100.C,
"Equipment Qualification," Revision 0, dated
January
29,
1986.
Paragraph
6.5. 19 of this procedure
requires
use of
4I
an "Environmental Qualification Checklist" (also called
an
EQ File
Review Checklist) to document
"program implementation."
This checklist
also
shows the claimed level of qualification and
a statement
that
the item is qualified for its "environment."
The 'inspector
checked
approximately six
EQ files and noted that they
contained
the signatures
and the checklists described
above.
The
master list did contain the entry "yes" in the "Action Completed"
column
for line items the licensee
considered qualified.
The inspector
found
that proper qualification level
was checked
on the checklist.
The inspector
checked four
EQ files and noted that functional perform-
ance
requirements
were properly defined.
The inspector also reviewed
Wyle Report
17655-PERF-1,
which was
used to specify and demonstrate
compliance with the functional performance
requirements
for the appli-
cation of the qualified equipment.
The inspector considers
the licensee's
corrective actions
on this
item adequate
for its closure.
This item is considered
closed.
2.2
Closed
Potential
Enforcement/Unresolved
Item 50-220/85-13-02
pertain-,,
ing to the environmental qualification of Static-0-Ring pressure
switch,
(pc.
No. PS-70-279).
This item included three deficiencies:
1) the
licensee
did not demonstrate
that the equipment
performance
observed
during .the type testing
was adequate
for the application,
2) the inspec-
tion revealed
dependence
on
a cable
seal
internal to the conduit,
however,
the seal
was not qualified,
and 3) the specified qualified
life is 40 years,
however,
no
EQ maintenance
was specified.
Wyle Laboratory report "Nuclear Environmental
Assessment
Report
on
Performance
of Safety-Related
Equipment at Nine Mile Point Unit
1
Nuclear Power Plant"
specifies
acceptable
performance
levels within
which safety-related
equipment
must operate.
The report includes four
categories
of equipment
performance.
The Static-0-Ring pressure
switch
was included in Category
2 Performance
Determined
by Operating
History.
For this equipment
which is only subject to higher-than-normal
radiation,
the effects of radiation
have
been
addressed
and the equip-
ment has
been
shown to not be adversely affected.
The qualification of the switch was originally classified
as
HELB plus
LOCA.
Based
on the location of the switch, its qualification has
been reclassified
to
LOCA only.
Because
the switch is located
outside the drywell, it needs
only to be qualified for radiation
environment.
Under these conditions, qualification of the seal is
not required.
The inspector
reviewed the revised
SCEW sheet,
the
environmental
qualification checklist
and the qualification file
review check to confirm that the switch was reclassified
to
alone.
The inspector also reviewed the pressure
switch to confirm
that the reclassification
is justified.
The inspector
reviewed the licensee's
basis for not specifying
Eg
related
maintenance
to confirm that the specified corrective maintenance
was adequate
to preserve
the qualification of this equipment.
This item is considered
closed.
2.3
Closed
Potential
Enforcement/Unresolved
Item 50-220/85-13-03 pertain-
ing to the environmental qualification of Valcor solenoid valve, (pc.
No. SOV-39-14.7).
This item included two deficiencies:
1)
no conduit
seal
was
used in the plant installation,
however,
a conduit seal
was
used in the type test
and 2) the licensee failed to identify required
Eg maintenance
for a 40 year qualified life.
The qualification of the Valcor solenoid valve was originally classi-
fied as
HELB plus
LOCA.
Based
on the location of the solenoid valve,
its qualification has
been reclassified
to
LOCA only.
Since this
valve is located outside the drywell, it needs
only be qualified for
radiation environment.
Under these conditions,
the installation
need
not include
a conduit seal.
The inspector
reviewed the revised
SCEW
sheet,
the environmental qualification checklist
and the qualifica-
tion file review check to confirm that the solenoid valve was re-
classified to
LOCA alone.
The inspector
also reviewed the 'licensee's
technical
basis for excluding the
HELB environment.
Since these
valves are in the emergency
condenser
system,
they would not be
called
upon to mitigate
a
HELB.
With regard to the issue of E(j required maintenance,
the licensee
noted
that they planned
near
term replacement
of these
The
inspector confirmed the licensee
plans to replace
the specified Valcor
solenoid valves with ASCO solenoid valves during the current outage.
However, the inspector
noted that other Valcor solenoid valves
on the
master list will continue to be used in the facility.
The inspector
reviewed the required
Eg maintenance
sheets
to confirm that the speci-
fied maintenance
for these
valves
was adequate
to preserve
the qualifi-
cation of the equipment.
The inspector
reviewed the licensee's
disposition of Information Notice 86-65,
"Improperly Rated Field Wiring to Solenoid Valves," as it per-
tains to Valcor Solenoid valves.
This notice relates
to
a potential
deficiency involving field installed electric cables with low tempera-
ture rated insulation being terminated
inside solenoid valves housing
which are subject to high temperatures
caused
by selfheating.
It was
determined that all affected Valcor solenoid valves
were provided
with pigtails which were qualified with the valves.
The inspector
observed
Yalcor solenoid valves
SOV 39-12C,
SOV 39-14C
and
SOV 39-11C
during the plant walkdown and verified the exi stance
of the pigtails.
This item is considered
closed.
I
P
2.4
Closed
Potential
Enforcement/Unresolved
Item 50-220/85-13-04 pertain-
ing to the qualification of GE EB-25 terminal blocks.
The licensee
had identified that all EB-25 terminal blocks were
used for on-off
functioning only.
The operating
time requirement for terminal blocks
inside the drywell had
been
revised
from 28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br /> to
1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />
(SCEW sheet
711)
~
The tested insulation assistance
during the first hour was very
high and therefore
leakage
current
was not
a problem.
The terminal
blocks located outside the drywell still require
an operating time of
28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br />.
However,'he
temperature
and pressure
profiles after
an
accident
decay quickly.
The insulation resistance
of the terminal
blocks did not change substantially.
The inspector
reviewed pertinent
EQ documents for the
EB-25 terminal
blocks
and did not identify any more concerns
about the qualification
of the terminal blocks.
This item is considered
closed.
2.5
Closed
Potential
Enforcement/Unresolved
Item 50-220/85-13-05
per tain-
ing to the qualification of GE EB-5 terminal blocks.
The licensee
had determined all EB-5 terminal blocks located inside the drywell
were for on-off functions only.
The operating
time requirements
for
these
terminal blocks
had
been
revised
from 28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br /> to
1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />
(SCEW
sheet
042).
The tested insulation resistance
during the first hour
remains
high and therefore
leakage current would not create
a problem.
For terminal blocks located outside the drywell, five were
used for
analog signal transmission,
four for Rosemount transmitters
(FT 81. 1-01
and
02 and
LT 68-28
and 29)
and
one for temperature
sensor
TE-36-29.
The rest were for on-off function only.
The licensee
performed
an engineering
analysis for each of the
EB-5
terminal blocks
used for analog signal transmission,
and demonstrated
that. the resultant
loop error was within the allowable limit.
The re-
sults of these
analyses
were documented
in their report
No.
17655-PERF-1.
The inspector
reviewed pertinent
EQ documents
and considered this item
closed.
2.6
Closed
Potential
Enforcement/Unresolved
Item 50-220/85-13-06 pertain-
ing to the environmental qualification of Fisher model
304 position
switch, part
No. 39-ll-1LSC.
The switch has
been qualified to
DOR
guidelines
as noted in licensee
assessment
report
No.
17655-LSW-16,
Revision A, dated
September
14,
1985;
EQ reference
No.
246 and
Deficiency Resolution
Report
No.
17655-LSW-16. 1, Revision
B, dated
October 8,
1985.
The
SCEW sheet indicates
the position switch is located outside
the
containment
and is subjected
to only a radiation environment.
This
item was included by the licensee
in the listing of changes
from HELB
to
LOCA radiation only made to equipment qualification records
as
a
result of the licensee
post-audit (¹85-13) reevaluation.
This change
was reported to the
NRC in a Narch 4,
1985 letter (NMP1L-0032) from
the licensee.
e i~
+p >r
In reviewing the position switch qualification package,
the inspector
noted that
an internal
memo,
dated
December
5,
1985,
has
been
issued
by the
EQ engineer to the
EQ coordinator stating that the Fisher model
304 position switch is being replaced with a qualified
NAMCO Model
EA-180 switch.
Switches
scheduled for replacement
during the
1986
outage
are listed in
SCEW sheet
Nos.
582,
583,
584,
585,
401,
402,
403
and 404.
This item is closed.
2.7
Closed
Potential
Enforcement/Unresolved
Item 50-220/85-13-07 pertain-
ing to the qualification status of Rosemount
1151 transmitters'he
licensee
completed
a retest of Rosemount
1151DP transmitters
in 1985
and
had developed
a
new qualification file for this equipment.
The
inspector
noted that the
new file now contained
QC inspection report
No. 79-589A dated April 6,
1979 for the installation of the transmitters.
This report established
the beginning of qualified life and justified
the
DOR guideline
as the basis for qualification.
The
new test report (prepared
by Wyle Lab.) indicated that partial type
testing
and
new analysis
had been
done using
a Rosemount
1151DP
4E
transmitter with one
BUNA-N and one
EPR 0-ring installed.
Qualified
lives for both 0-rings
as limiting components
were calculated
using
actual
service temperature
historical data weighted for time at that
temperature
and using
a summation of degradation
intervals technique.
All BUNA-N 0-rings
had
been
replaced with EPR 0-rings which have
much
longer qualified life.
0-ring replacement
intervals were verified to
have
been
less
than their qualified life.
The transmitters
as
a whole
were evaluated
to have
a qualified life greater
than
40 year s.
This item is closed.
2.8
0 en
0 en item 50-220/85-13-08
pertaining to the implementation of
EQ procedures
and control of the
EQ program.
This item covers
several
areas.
Each area is discussed
separately
as follows:
2.8. 1
E
rocedures
and
rocedure
im lementation
The licensee
issued
top tier document
NT-100.C,
"Equipment Quali-
fication," Revision 0, in January,
1986.
The licensee
considered
thi s document contains sufficient detail to be used for various
categories.
Procedure
NT-100.C establishes
methods
which can
be used
by
licensee
engineering
and licensing,
in conjunction with site
technical
support,
to satisfy the requirements
of 10 CFR 50.49.
This document is used to determine
environmental qualification
criteria; identification of design
requirements
and control;
installation requirements,
EQ maintenance
requirements,
and
file requirements.
For example,
section
6. 10. 1 states
that
"zonal
maps shall
be maintained
as control documents,
and
include
peak values of temperature,
pressure
and relative
humidity that would be experienced
in each
area of the plant
analyzed for High Energy Line Break (HELB)."
JI
The licensee
has developed
individual zonal
maps
based
on
a study
by NUS (NUS-1961-SAAl).
The zonal
maps contain the required infor-
mation
as stated
in the procedure.
The procedure
(NT-100.C) references
24 documents
which may be used
in conjunction with the procedure.
Of the 24 documents
referenced,
all have
been
issued
except
seven.
The
seven
have
been written
and approved,
ready to be issued.
Their i ssuance
is pending
formal
training of personnel
in use of the procedures.
This training is
scheduled for May 1986.
The inspectors
considered this area
completed
except for the
maintenance
requirements
which are discussed
below.
E
Re uired Maintenance
and Site Maintenance
Procedures
U dates
The
EQ maintenance
requirements
are defined in paragraph
6.7 of
NT-100.C.
The
EQ required maintenance
(EQRM) for each type of
equipment is listed in the
EQRM form and transmitted to the site
for implementation.
The site personnel
are responsible
for
scheduling,
performing, inspecting,
and tracking the required
maintenance activities.
A computer
program
has
been developed
by the licensee
to track the status of each maintenance activity.
The site personnel
are also responsible
to update their site
maintenance
procedures
to include the
EQ requirements.
Two groups
are involved in these activities.
The Electrical
Equipment group
and the
18C group.
The Electrical Maintenance
supervisor
indicated that
28 electrical
maintenance
procedures
need to be updated.
Five of them are to
be used for the
EQ maintenance
during the current outage.
These
five procedures
(Nl-EPM-Cl and C2,
Nl-EPM-R1, Nl-EPM-C14 and
Nl-EPM-122-R135)
have
been drafted
and will be issued
before plant
restart
from the current outage.
The rest of the
28 procedures
will be updated
and issued
before the end'of this year.
Twenty-three
IKC mai'ntenance
procedures
need to be updated to in-
clude the
EQ requirements.
Of these
23 procedures',
all but one
have
been written and are in the review process.
One of these
has
been
approved
and is ready to be issued.
Four have
been
reviewed
and are in process for corrections prior to release.
These four
are
scheduled for issue
on April 19,
1986.
The remainder (in
various
stages
of approval) will be issued
before the
end of the
current outage.
In the interim, work is being done per Work Requests
and
EQRMs
based
on existing procedures
which form the basis for the
18C
maintenance
procedures.
The
EQ maintenance
activity involving replacement
of Rosemount
Transmitter 0-rings was confirmed by reviewing Work Request
Nos.
10100,
11009,
11010
and
11011,
dated
March 24,
1986.
2..
EttTEii
P
2.8.3.1
Site Personnel
Trainin
The inspector
reviewed
and discussed
the licensee's
training program
and implementation of training proce-
dures relating to equipment qualification.
Topics
covered in the training program will enable
licensee
personnel
to utilize a
SCEW sheet,
Environmental
Maps
from the Equipment Qualification Procedure
NT-100.C
and the
EQ Master Equipment List.
The training program is in effect for Electrical
and
Instrumentation
and Control personnel.
Training records
indicate the program
has
been in effect since
September,
1985.
The records
also indicate that personnel
are
tested
on the material
presented
and must demonstrate
an understanding
of the equipment qualification program
as evidenced
by an achievement
of 80 percent or better
in the examination.
2.8.3.2
Cor orate
Personnel
Trainin
Corporate training has
been delayed.
The Corporate
training program originally scheduled for February,
1986
has
been delayed to May, 1986.
Corporate
EQ personnel
have
been
given copies of the
EQ material
(NT-100.C, i.e.)
to read
and acknowledge receipt of this material.
The
EQ function has
been
supported
to date
by experienced
contract personnel.
Licensee
personnel will gradually
move in to perform the
EQ function as training is com-
pleted.
2.8.4
This item remains
open pending
NRC peview and evaluation of the
licensee's
completion of their
EQ maintenance
program
and Corporate
personnel
training.
2.9
0 en
0 en item 50-220/85-13-09
concerning
the oil spillage
under each
of the reactor building closed
loop cooling motors M70-01,
02 and 03.
The licensee
stated that this problem was due to lubricant overfill
during the routine maintenance.
The licensee
proposed
two steps to
prevent recurrence
of this problem:
1) to instruct the maintenance
personnel
not to overfill lube oil during the lubrication maintenance,
and 2) to adjust the motor lube oil filler level
such that any over-
filled oil will be drained to the drain pan.
The inspector verified
through training record that the first step
was completed in September,
1985.
However, the
second
step
had not yet been taken.
The licensee
stated that
one of the three motors
was being overhauled
and the other
two motors
had to run continuously.
Once the overhaul
is completed,
they would adjust the motor oil filler level.
This item remains
open.
10
2. 10
Closed
0 en item 50-220/85-13-10
pertaining to verification of procure-
ment documentation
to establish similarity for acoustic monitor coaxial
cable
and the Rockbestos
coaxial cable for which the file established
qualification.
The inspector
reviewed licensee
procurement
document
No. 52657, product
code
Nos.
?46-3422
(38/C ¹16XLPE/NED) and
146-0021
(2/C ¹16XLPE/NED)
verifying similarity of cable type
and size.
The document review
included certified test reports for the
above product
code
numbers,
cable
megger termination
and interconnecting wiring diagram
No.
3-N21-E21.5.
Thi s i tern i s cl osed.
2. 11
Closed
0 en item 50-220/85-13-11
pertaining to
a deformed
in
a conduit coupling for a related
switch and the seismic acceptability
of the valve (No. 50V-201.2-23) installation with respect
to
a steel
clamp.
The deformed gasket
has
been
replaced
and operator training provided
for replacement
and positioning of gasket
seals.
For the valve installation,
the licensee
has provided
an engineering
evaluation with supporting calculations
(No. S22.4-201.2-H24)
for the
installed configuration-( support
No. 201.2-H-24)
minus the steel
clamp.
The support
was analyzed
and designed for East/West
and Vertical loads.
The analysis
does not reflect
a north/south restraint of the valves
that would occur with the
use of a clamp.
The licensee
could not explain why the steel
clamp was installed.
The
clamp was
removed
and
a second
evaluation
and calculation
was performed
by the licensee
to determine if there
had been
any damage
as the result
of using the steel
clamp which would have prevented
thermal
expansion
in the north/south direction of the valve support.
The analysis
shows
that while the clamp was in place, it did not cause
overstress
in either
the piping or pipe support.
This item is closed.
3.0
Licensee
Post-Ins ection Reevaluation
of
E ui ment
uglification
Following the
NRC inspection of the licensee's
Equipment gualification
Program conducted
August 19-23,
1985,
the licensee
took steps
to correct the
identified deficiencies.
The licensee
corrective
actions
are described
in
three letters to the
NRC dated
September
30,
1985,
November
15,
1985 and
December
2,
1985.
Corrective actions related to specific file deficiencies
are evaluated
in section
2 of this report.
N '"
(4
k
With regard to programmatic deficiencies identified during the inspection,
the licensee
described their general
corrective actions during
an enforce-
ment conference
at the
NRC Region I office on February
5,
1986.
These
actions
included the following programmatic activities:
Reassessment
of EQ test Reports
Revision of
EQ test Reports
Addition of Page/Paragraph
References
Qualification File Review Checklist
Traceabi lity Matrix (Summary Table)
Functional
Performance
Reassessment
During the current inspection
each of these
programmatic activities were
reviewed both programmatically
and
as they related to specific equipment
qualification files reviewed during the inspection.
No programmatic defi-
ciencies
were identified.
The licensee
discussed
the results of their post-inspection
reevaluation
during the February
5,
1986 conference call with the
NRC and in their letter
dated
March 4,
1986 to the
NRC.
The licensee's
re-inspection
of accessible
qualified equipment
was initiated in April 1985.
This re-inspection
did not
identify any substantial
deficiencies.
The licensee
conducted
a re-evalua-
tion of all the equipmert qualification files in light of the deficiencies
identified during the August 19-23,
1985 inspection
and the programmatic
activities listed above.
As
a result of this re-evaluation
three-hundred
five (305) changes
were
made to the files as of February
17,
1986.
Of
this number,
17 affected the qualification status of qualified equipment.
The licensee
stated that
none of these
changes
required testing or additional
analyses
to establish qualification.
Furthermore,
no unqualified equipment
or required
hardware
changes
were identified.
the inspector
reviewed the
details associated
with a sample of the
17 file changes
affecting qualified
status.
Specifically, the inspector
reviews
changes
associated
with the
D.G. O'rien electrical penetrations.
The licensee
increased
the specified
operating
time from 28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br /> to 100 days.
the inspector
confirmed that these
changes
in the specified operating
time were enveloped
by the qualification
of the equipment.
A summary review of several
other file changes
affecting
qualified status
by the inspector
confirmed the licensees
conclusion that
equipment specifications
were enveloped
by the equipment qualification.
No significant deficiencies
were identified by the inspector
in the licen-
see's
post-inspection
reevaluation
of Equipment Qualification.
4.0
Review of Additional
E
Files
4. 1
The inspectors
reviewed the
EQ files and
SCEW sheets
for three selected
equipment-types
to verify the qualification status
of the equipment
within the
scope of 10 CFR 50.49.
In addition to comparing plant
service conditions with qualification test conditions
and verifying
the bases for these conditions,
the inspectors
selectively reviewed
areas
such
as required post-accident
operating
time compared to the
duration of time the equipment
has
been
demonstrated
to be qualified;
12
similarity of tested
equipment to that installed in the plant (e
~ g.,
materials of components
of the equipment,
tested configuration
compared
to installed configuration,
and documentation
of both); evaluation of
adequacy
of test conditions;
aging calculations
for qualified life
and replacement
interval determination;
evaluation of test anomalies;
and applicability of EQ problems reported
in IE INs/Bulletins and
their resolution.
4.2
The following equipment-types
were selected
for review:
a)
Rosemount
Model
1153D transmitters.
(SCEW sheets
062,
063,
064,
343 and 344).
b)
Limitorque Model
SMB-3 valve actuations
(SCEW sheets
078,
079,
080
and 185).
c)
Fenwal
Model
17002-40 temperature
switches
(SCEW sheets
20 through
35).
4.3
~Findin
Within the
scope of this review,
no unacceptable
conditions were iden-
tified.
.0
n ii
i
.
i
E
The inspector
reviewed the licensee's
method of verifying that generic equip-
ment installed in the plant is included in the Equipment (}ualification master
list and backed
by Equipment gualification files supporting
the qualification
of the equipment.
Examples of generic
equipment
are cables,
terminal blocks,
switch gear
and splices.
The methods
used
by the licensee
to verify installed generic
equipment vary.
For several
of the generic
items
on the master list such
as switch gear
and
power supplies,
the licensee
conducted
a walkdown of the items.
For the
cable splices,
the licensee
recently replaced
most of the cable splices with
qualified splices.
The verification methods
used for other items are not as
definitive as the above methods
and the verification methods
are not clearly
documented.
An example of an item in the latter category is cable.
Verifi-
cation of installed cable is accomplished
through
a combination of licensee
and vendor records relating to site cable procurement
and applications.
In
some,
but not all cases,
cable
can
be identified by walkdowns through cable
jacket markings,
SIS wire marking or samples
of unmarked cable
are returned
to the vendor for positive identification.
Additional information relating
to installed cable is available in the plant archives.
However, this infor-
mation is not computerized
or readily available for this purpose.
As
a
result of discussions
with the licensee,
they plan to document the various
methods
they used to verify installed generic
equipment at Nine Mile l.
No significant deficiencies
were identified by the inspector in this review.
0
Ef
'4l
'I
13
6.0
Plant
Ph sical
Ins ection
6.1
The inspectors
selected
a sample of four Limitorque valve actuators
(Model
Nos.
SMB-O,
SMB-1 and SMB-2), four Rosemount
11530 transmitters,
and four cables for physical
inspection.
All these
items were located
outside the drywell and were accessible
at the time of the inspection.
One Limitorque valve actuator
(Model
No.
SMB-1) is
a
new actuator
not
yet installed.
The inspectors
examined
the characteristics
such
as
mounting configuration, orientation,
interfaces,
model
number,
ambient
environment,
and physical conditions.
For the Limitorque valve actua-
tors,
the inspector also
examined
the identity of the internal wiring.
6.2
~Findin
s
a)
For Limitorque valve actuators,
the
NRC inspectors
did not identify
any unacceptable
conditions other than those already identified
by the licensee.
The licensee
had established
a program in 1984
to identify and replace,
as necessary,
all jumper cables
from the
limit switches to the torque switches if the cables
were not
either
Raychem "Flamtrol" or'ockbestos
"Firewall III."
They
developed
Procedure
Nl-EMP-45.96,
"Equipment gualification of
Limitorque Yalve Actuators
and Associated
Motor Type
SMB and
SB"
in 1984 to implement this program.
According to the licensee,
there
are
39 Limitorque valve actuators
requiring environmental qualification.
They conducted
a reinspec-
tion during the week of April 7,
1986, of 35 of these
actuators
and found that
20 of the
35 contained
jumper cables
(from the limit
switches to the torque switches)
whose identify was
unknown
and
qualification status
could not be established.
Subsequently,
work requests
had
been
issued
to replace
the jumper cables of
these
20 actuators
with qualified cables.
As of April 14,
1986,
four had
been
completed.
The rest will be completed during the
current outage.
The other four actuators will be reinspected
for their jumper
cables.
The licensee
plans to replace
the cables
where necessary
with qualified cables prior to startup
from the current outage.
The licensee
stated that the cases
where identification of the wire
was not immediately possible is not necessarily
a condition of
non-qualification but rather
a case
where the qualification could
not be established
without additional
research
or additional
test/analysis.
Since the qualification status of the affected valve actuators
cannot
be determined for the period from November 30,
1985 to
the time when the jumper cables
are or were replaced, this is
considered
an unresolved
item pending further.NRC evaluation of
the issue
(50-220/86-05-01).
~'
i
b)
The inspector identified that two Kerite cables
(one Model
HTK
power cable wired to Limitorque valve actuator.
IV-31-07, one
Model
FR II FR control cable wired to Limitorque valve actuator
FCV-80-118) were not included
on the master list, nor were any
SCEW sheets
prepared for this type of cable.
The licensee indi-
cated that the cables
were previously covered in a Kerite splice
qualification file.
However,
the qualification file had
been
deleted
from the master list when all the splices
were replaced
by other qualified splices.
This item is unresolved
pending
NRC review of the licensee's
corrective action
on the qualification of these
types of Kerite
cables
(50-220/86-05-02).
7.0
Unresolved
Items
Unresolved
items are matters
which require
more information in order to
ascertain
whether they are acceptable
items, or violations.
Unresolved
items identified during this inspection
are discussed
in Details, in para-
graph 6.2.
8. 0
Exit Me~et i e
The inspector
met with licensee
and licensee
representatives
(denoted
in
paragraph
1.0) at the conclusion of the inspection
on April 18,
1986 at
the corporate office.
The inspector
summarized
the
scope of the inspection,
the inspection findings
and confirmed with the licensee
that the documents
reviewed
by the team did
not contain
any proprietary information.
The licensee
agreed that the inspec-
tion report
may be placed in the Public Document
Room with prior licensee
review for proprietary information ( 10 CFR 2.790).
At no time during this inspection
was written material
provided to the
licensee.
t