Requests Addl Info by 860307 Re 860131 Request to Defer Preoperational Tests Beyond 860505 Fuel Load Date.Info Should Include Justification for Not Completing Tests, Schedule for Test Completion & Exemption Requests
ML17055B296
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 02/21/1986
From: Adensam E
Office of Nuclear Reactor Regulation
To: Hooten B
NIAGARA MOHAWK POWER CORP.
References
NUDOCS 8602280780
Download: ML17055B296 (4)


Text

Docket No. 50-410 Mr. B. G. Hooten Executive Director of Nuclear Operations Niagara Mohawk Power Corporation 300 Erie Boulevard West

Syracuse, New York 13202

Dear Mr. Hooten:

Attorney, OELD JPar tlow EJordan BGrimes ACRS (10)

DISTR'UT ION'.~

Doc eel..

60~410 NRC PDR Local PDR PRC System BWD-3 r/f EAdensam EHylton MHaughey RBernero RBecker DVassall

Subject:

Review of Preoperational Tests to be Conducted after Fuel Load for Nine Mile Point, Unit 2 In a letter dated January 31, 1986, you indicated that, at this time, there are no preoperational tests planned to be deferred beyond fuel load.

You also included a list of preoperational tests which you believed could be deferred beyond fuel load and requested NRC review and concur rence of deferral of these tests.

In order to review the acceptability of deferral of these tests beyond fuel load for Nine Mile Point, Unit 2 (NMP-2) the following information should be provided; (1) justification for not completing these tests (2

schedule when these tests will be completed (3)

Niagara Mohawk's basis for concluding it is acceptable to delay these tests (4) an evaluation of whether each of these tests involves any exception to the technical specifications (5) exemption requests where required.

In order to support a May 5, 1986, fuel load date, we request this information be provided no later than March 7, 1986.

The above request was discussed with Mr. Don Hill of your staff on February 5, 1986.

Any questions concerning the above should be directed to the Licensing Project

Manager, Mary Haughey (301) 492-9422.

Sincerely, OggQTQ~T'ere121oe Zr gQ k

cc:

See next page

  • NOTE:

PREVIOUSLY CONCURRED Elinor G. Adensam, Director BWR Project Directorate No.

3 Division of BWR Licensing BWD-3:DBL LA:BWD-3:DBL

  • MHaughey/hmc
  • EHylton 2/19/86 2/19/86 8602280780 86022i PDR ADOCN, 050004i0 A

'DR BWR:FOB

  • RBecker 2/19/86 C:BWR:FOB
  • DVassallo 2/20/86 D.

-3:DBL EAdensam 2gjfi86

Ol u

44

Mr. B.

G. Hooten Niagara Mohawk Power Corporation d

Nine Mile Point Nuclear Station Unit 2 CC:

Mr. Troy B. Conner, Jr.,

Esq.

Conner 5 Wetterhahn Suite 1050 1747 Pennsylvania

Avenue, N.W.

Washington, D.C.

20006 Richard Goldsmith Syracuse University College of Law E. I. White Hall Campus

Syracuse, New York 12223 Ezra I. Bialik Assistant Attorney General Environmental Protection Bureau New York State Department of Law 2 World Trade Center New York, New York 10047 Resident Inspector Nine Mile Point Nuclear Power Station P. 0.

Box 99

Lycoming, New York 13093 Mr. John W. Keib, Esq.

Niagara Mohawk Power Corporation 300 Erie Boulevard West

Syracuse, New York 13202 Mr. James Linville U. S. Nuclear Regulatory Commission Region I 631 Park Avenue King of Prussia, Pennsylvania 19406 Norman Rademacher, Licensing Niagara Mohawk Power Corporation 300 Erie Boulevard West
Syracuse, New York 13202 Regi'onal Administrator, Region I U.S. Nuclear Regulatory Commission 631 Park Avenue Kinq of Prussia, Pennsylvania 19406 Mr. Paul D.

Eddy New York State Public Service Comoission Nine Mile Point Nuclear Station-Unit II Post Office Box 63

Lycoming, New York 13093 Don Hill Niagara Mohawk Power Corporation Suite 550 4520 East West HighWay
Bethesda, Maryland 20814