ML17055B142
| ML17055B142 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 01/07/1986 |
| From: | Anderson C, Paolino R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML17055B140 | List: |
| References | |
| 50-410-85-42, NUDOCS 8601270160 | |
| Download: ML17055B142 (26) | |
See also: IR 05000410/1985042
Text
U.S.
NUCLEAR REGULATORY COMMISSION
REGION I
Report
No.
50-410/85-42
Docket No.
50-410
License
No.
CPPR-112
Priority
Category
B
Licensee:
Niagara
Mohawk Power Corporation
300 Erie Boulevard,
West
Syracuse,
NY
13202
Facility Name:
Nine Mile Point Nuclear Station - Unit 2
Inspection At:
Scriba,
Inspection
Conducted:
November 12-15,
and
December
4,
1985
Inspector:
R. J.
ino,
Lead Reactor
Engineer
date
Approved by:
7
Pk
C. J.
derson,
Chief, Plant Systems
Section
date
a
Ins ection Summar:
Ins ection
on November
12-15
and
December
4
1985
Re ort
~/
h
installation to determine whether the work performed
and the required documenta-
tion is in accordance
with established
procedures,
FSAR and licensee
commitments.
The inspection
involved 25 inspector
hours
on site
and
30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br /> in office
inspection.
Results:
Two violations were identified:
one violation pertains
to installation
of coaxial cable
by a method other
than that authorized,and
approved
by established
procedures.
The
second violation pertains to exceeding
minimum bend radius for
installed flex-conduit and coaxial cable.
(
8601270160
85000g10
6012~1
ADQCK 050
8
f
+
1
/y
~'I
DETAILS
1.0
Persons
Contacted
1.1
Nia ara
Mohawk Power
Com an
W.
RC
- 8W
G.
"W.
- D
L.
AE
- T
- T
)kM
J.
AJ
D. Baker,
Special
Projects
Beckham,
QA Project Manager
Dick, Quality Engineer
Donahue,
Senior Construction
Supervisor - Electrical
A. Griffith, Site Licensing
Hausen,
Manager Nuclear Operations
(QA)
Hess,
Supervisor
(QC)
D. Kassakatis,
Startup
and Test
R. Klein, Assistant
Manager Project Engineering
E. Kolceski, Special
Projects
Lee, Special
Projects
Matloc, Deputy Project Director
R. Morrison, Manager Quality Engineering
J.
Ray,
Manager Special
Projects
C. Sheppard,
QC Supervisor
White, Special
Projects
1.2
Stone
and Webster
En ineerin
Cor oration
- T
- J
B.
- A*E
- R.
%AD
%*M
AA*T
M.
L. Baumgartner,
Site
QA Supervisor
Beverage,
FQC Inspection Supervisor
R. Bulger, Project Advanced Engineering
Corso,Principal
Electrical
Engineer
W. Crowe, Assistant Superintendent
FQC
J.
Hubner, Assistant
Superintendant
Engineering
S. Hyslop, Jr., Site Licensing Engineer
Johnson,
Senior
QC Inspector
Jurmain,
Startup
Engineer
Landry, Senior Electrical
Engineer
Lapointe,
Senior
QC Inspector
1.3
L.
K. Comstock
RRD
8'*W
- M
1.4
U.
E.
Bateman,
General
Foreman
Carey,
Area Manager
L. Hayes,
Cable Pulling Foreman
E. Phillips, General
Foreman
S. Nuclear
Re ulator
Commission
A. Gramm,
Senior Resident
Inspector
"Denotes
personnel
present
at, exit meeting
" Denotes
personnel
present at demonstration
of method(s)
used to
install Neutron Monitoring System Coaxial
Cables
- Denotes personnel
present at both
P'
~Fatti
T
2.1
The inspector
observed
work activities in progress,
completed
work and
plant status
during general
inspection of the drywell and under the
pedestal
area of the reactor vessel.
The inspector
examined installed
instrument/cable
in the area for any obvious defects
or non-compliance
with regulatory requirements
or licensee
commitments.
Particular
note
was taken of gC personnel
observing
workmen in the area
assembling
coaxial
cable connectors
on the Neutron Monitoring System.
The inspector
noted that the craft were using the proper tools'and following appli-
cable
General Electric Procedures
(GEK-45754B and
SDDF 01.690-5036A)
for installing the connectors.
The inspector verified the connectors
were qualified for the environment in which they are required to func-
tion.
The inspector interviewed craft, supervisory
and
gC personnel
as they
were available in the area.
While inspecting
the Safety-Related
Neutron
Monitoring System
under the Reactor
Vessel
the inspector
observed that
the Systems
coaxial control cables
were installed in individual flexible
conduit.
The cables
had
been installed from the drywell penetration
through
2~ inch rigid conduit to
a junction box mounted outside of the
vessel
pedestal
wall.
At the junction box each coaxial
cable
then
entered
separate
flexible conduit anchored
to the junction box and
routed
under the reactor vessel
via
a
7 foot penetration
in the vessel
pedestal.
Underneath
the vessel
the flexible conduit is strung along
the wall supported
by unistrut hangers
welded to the inner pedestal
wall.
The use of flexible conduit was questioned
by the inspector
since specification
E-061A for Installation of Electrical
Equipment
specifies rigid conduit for all Safety Related
Category
1 Systems
unless
noted otherwise.
The inspector
reviewed the conduit layout
drawings
EE-570E,
D and
G which specifies stainless
steel flexible
conduit.
Where the specification
E-061A calls for the use of flexible
conduit it limits the length of flexible conduit to 48 inch whether
it is connected
at one
and or both ends.
However, the above drawings
placed
no limitations on length of flexible conduit that could be
used.
Installed lengths varied from 4 feet to 80 feet.
Engineering
justification for using flexible conduit instead of rigid conduit and
lengths of flexible conduit, in excess
of 48 inches
was not available
for this inspections
This item is unresolved
pending
NRC review of licensee
evaluation
and
justification for deviating from specification
requirements.
(50-410/85-42-01).
During the inspection of the installed Neutron Monitoring System,
the
inspector
observed that the
bend radius of a number of flexible conduits
exiting out of the top of junction box 2JB0790
were smaller than the
required
bend radius for the cable in the flexible conduit.
E-061A
specifies
a bend radius of 3 inches for the NJP-29 cable installed in
the flexible conduit.
t
The conduit manufacturer
(American Boa) allows
a minimum bend radius of
1'," for this application.
As
a result of using the flexible conduit
allowable
bend radius the licensee violated the permanent
bend radius
allowed by the cable manufacturer.
Flexible conduits violating bend
radius include:
2CX998A thru H, J,
K,
M & P thru
R.
Additional bend
violations were identified in the drywell but outside of the Reactor
Vessel
Pedestal
area
as follows:
Flexible Conduit:
2XK997YH1, minimum required
bend radius
5 inch,
was
2 3/4 inch
2CK997YF, minimum required
bend radius
3 1/2 inch,
was
2 1/8 inch
2CC996YC5,
minimum required
bend radius
6 inch,
was
2 3/4 inch
2CK999YD, minimum required
bend radius
3 1/2 inch,
was
2 inch
2CK9997YG,
minimum required
bend radius
3 1/2 inch,
was
2 inch
The licensee
was informed that the above
bend radii were. examples of
failure to follow procedures
and in violation of 10 CFR 50, Appendix B,
Criteria
V which states,
in part, that:
"activities affecting quality
shall
be prescribed...and
shall
be accomplished
in accordance
with
these instructions..."
(50-410/85-42-02).
3.0
Instrumentation
Cable
and Termination
- Work Observation
3. 1
The inspector
observed
work activities in progress,
completed work and
partially completed
work relating to the installation of the Neutron
Monitoring System to ascertain
whether the installation
was performed
in accordance
with applicable
procedures,
the
FSAR and licensee
commitments.
Items examined for this determination
include:
Rigid Conduit Nos.
2CX999YH and
2CX999YG
'Electrical Junction
Box Nos.
and 2JB-0794
Coaxial
Cable
Nos.
2NMPAYX006, 2NMPAYX007, 2NMPAYX015, 2NMPAYX017,
2NMPAYX018, 2NMPAYX021, 2NMPAYX022, 2NMPABYX024 thru 030,
2NMPBYX031 thru 036
Cable Pull Tickets for the above referenced
cables
Cable
Reel
Nos.
and
Wiring Diagram Nos.
36A-9GA and
In reviewing the cable pull tickets for the above referenced
cables,
the
inspector
noted that the
maximum pull tension for the cable
had been
omitted.
Discussions with the licensee
regarding
the requirements
in
specification
E-061A and Appendix J for calculating
and verifying the
cable pull tension,
the licensee
stated that it was not necessary
to
calculate
or verify the cable pull tension for the Neutron Monitoring
System cable
because
the cable
was
pushed
not pulled through the flexible
conduit.
Since the specification
E-061A did not address
cable install-
ation by pushing,
the inspector
requested
that the licensee
produce
documented
instruction
and procedures
used
by the cable pull crews to
push the cable through flexible conduit.
Following additional di'scus-
sions with licensee/construction
engineering
and supervisory
personnel
it became
evident that there
were
no instructions or procedures.
Personnel
present
during these
discussions
could not agree
on the
method(s)
used in attaching
the lubricating tube to the cable or whether
the coaxial
cable
was pushed,
pulled or
a combination of both.
Figure
3 illustrates four methods of attaching
the lubricating tube to the
coaxial
cable thought to have
been
used for installing the coaxial
cable.
Conclusions
reached
following discussions
with licensee/construction
engineering
and supervisory
personnel
are
as follows:
a.
There are
no written procedures
or instructions for installing
cable
by pushing.
However, Section 4.3. 1B of Quality Standard
QA 10.52 for raceway
and cable installations
states
that:
"The
engineering
department
is responsible
for issuing specification
and drawings,
and reviewing and approving instructions required
for the installation of raceway
and cable...".
b.
Figure 3-C was finally agreed
upon by construction
and
QC personnel
as the method
used in attaching
the lubrication tube to the
coaxial cable.
c.
QC personnel
present
during the cable installation
say the cable
was
pushed
through the flexible conduit.
They claim to have
observed
personnel
at the lubrication end using two fingers to
guide the lube tube
as it was being
pushed
back out of the flexible
conduit from the opposite
end.
d.
Cable pulling craftsman
and foreman (day/night shifts) differ on
whether the cable
was pushed
or pulled.
Day shift personnel
say
cable
was pulled as evidenced
by 2-3 breaks
occurring during the
installation of the permanent
cable.
The breaks
were said to
have occurred in the coaxial center conductor
loop attachment
to
the lubrication tube (figure 3-C mark X).
Night shift personnel
say cable
was
pushed
through while using
two fingers to guide
the lube tube out of the flexible conduit.
e.
All personnel
agreed
to
some difficulty in installing the coaxial
cable.
Those that believe cable
was pulled claim
a pulling force
of 3-5 lbs
on the lubricating end
and at least
20-25 lbs pushing
at the
same time.
Others,
claiming the cable
was pushed,
say the
lube tubing was held by two fingers
and used in gui'ding tube out
while force of 30 lbs or more
on the other end
was
used to push
cable through flexible conduit.
All personnel
stated it was
necessary
to station
personnel
(h symbol in figure 2) along the
routing of the cable installation to shake
and straighten
the
curved sections
of the flexible conduit to pass
the cable through
the curved sections of the installation.
The licensee
installed safety-related
Neutron Monitoring System
cables without using documented
instructions or procedures
approved
and authorized
by responsible
engineering
personnel
to
control
and provide inspection criteria to ensure acceptability
of the work performed.
g.
The licensee
did not use tension monitoring devices
as required
by Section 3.2.3.3 of Specification
E-061A which states,
in part,
that:
"tension monitoring of manual pulls in conduit/duct is
not required providing that the conduit/duct
does not exceed
the
length specified in Table
1.
Table
1 states that'for horizontal
pulls
up to and including 270 degrees
of bends
and
25 ft 'total
length between pull points tension monitoring is not required.
The installed Neutron Monitoring System cables
exceeded
the total
number of degrees
as well as the length between pull points
as
noted in
EKDCR No.
11960.
The disposition of this nonconformance
was that the cable
was pushed,
not pulled, therefore
the
bend
and length limitations did not apply.
Based
on the above critique the inspector
determined
the coaxial
cable installation to be
a violation of 10 CFR 50, Appendix B,
Criterion V.
(50-410/85-42-03)
The inspector questioned
the licensee
regarding possible
damage
to the cable
from the apparent
push/pull type of action required
and
used to install the coaxial cable in the flexible conduit.
The licensee
setup
a typical worst case installation to demonstrate
that the cable could
be pushed
through the conduit without damaging
the cable.
December
4,
1985 was set aside
as the scheduled
demon-
stration date.
This allowed the licensee
approximately
3 weeks to
prepare
the test configuration.
4.0
Instrumentation
Cables
and Terminations
-
ualit
Record
Review
The inspector
reviewed pertinent, work and quality records for activities
relating to the installation of the safety related
Neutron Monitoring System
to ascertain
whether the records
meet established
procedures
and whether the
records reflect work accomplished
consistent with NRC requirements
and
FSAR commitments.
Areas
examined
include cable pull tickets, terminations,
nonconformances,
testing
and inspection.
Items examined for this determination
include:
Inspection
Report Nos.
E5A43806,
ESA4766,
ESA43970,
ESA43689,
ESA43775
and
E5A43688
)
Cable Pull Tickets for Coaxial
Cable
Nos.
2NMPAYX002 thru 007 and
2NMPBGX001 thru 008.
Nonconformance
Report Nos.
11015,
11960,
13190
& 11893
Quality Assurance
Inspection
Plan
No.
N20E061AFA025 revision
OG change
2
Electrical Installation Specification
No.
E-061A revision
10 dated
May 20,
1985
Quality Standard
QS. 10.52NM revision
A dated
June
10,
1985
Engineering
and Design
Change
Report
Nos.
EKDCR-12187,
C-45477,
F-02258A
and
F-12513
In reviewing the above
documents
the inspector
noted the following:
a.
Specification
E-061A, Appendix B,
on "Cable Test Procedures"
does
not
include test instructions for testing coaxial cable.
This had
been identified by the licensee
in an
EKDCR F02258 of May 15,
1985 five days after completing installation of Neutron Monitoring
System coaxial cables.
The revised
BOCR F02258A was issued
on May 31,
1985 to revise Appendix
B to include test requirements
for coaxial
and
twinaxial cable.
b.
guality Assurance
inspection reports
(IR') indicate Insulation
Resistance
readings
to verify acceptability of the installed Neutron
Monitoring System control cables
was not performed until August 10,
1985.
The megger testing for Insulation Resistance
was done prior to and after
completing cable connector
assembly.
The test data
shows that all
cables
met or exceeded
the minimum insulation resistance
requirements
listed in
EKOCR 02258A.
The equipment
used
by the licensee
was properly calibrated
and within
the calibration
due date.
The inspector
noted
some imperfection,
blemishes
on outer cable jacket
of the coaxial cable
Mark No. NJP-29.
The licensee
had identified
similar defects
as reported
in nonconformance
NKD 11893.
The report
listed
14 cable reels with surface
imperfections.
Physical
and electrical test of the cable
per specification
E024B
indicate defects
were limited to the outer jacket
and determined
to
be acceptable.
E8DCR 13190 identifies
3 cable failures attributed to moisture that
may have
been present
between
conductor, dielectric and shield.
These
cables
were retested
following a period of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> under
a dry nitrogen
purge to remove the moisture.
Cable test results
met minimum require-
ments.
No violations were ident,ified.
5.0
Demonstration of Methods
Used for Installin
Neutron Monitorin
S stem
Coaxial
Cables
5.1
The test took place in the vendor
shop
on site on'ecember
4,
1985.
Personnel
present
during the demonstration
by craft personnel
are
noted in Details,
paragraph
1 with a *
symbol.
Figure
1 illustrates
the original test configuration setup in the vendor
shop
as being representative
of the actual installation of the Neutron
Monitoring System
under the Reactor Yessel.
Discussions
with. various
craftsmen
indicated that'they
had practice
sessions
(approximately
two
weeks)
on the installed 'configuration
and were successful
in pushing
the 'coaxial
cable through the flexible conduit.
The inspector
examined
the test configuration
and determined it was not representatives
of
C
y 'I
\\
the actual installed configuration.
Discussions with supervisory
personnel
indicated that
no one
had examined
the actual installation
or reviewed routing drawings
necessary
in determining the worst case
test configuration.
The installed test configuration was
a simple
straight line/single plane configuration having minimum bends
and not
representative
of the worst case configuration (Figure 1).
The
inspector determined
the test configuration to be unacceptable
for
determining whether the installed Neutron Monitoring System coaxial
cables
were
pushed
or pulled through the flexible conduit.
Figure 2,
more closely illustrates the changes
requested
by the inspector
based
on photographs
taken of the actual installation under the Reactor
Vessel.
Although the changes
made
were not entirely representative
of the worst case conditions
found under the vessel, it was agreed
that the configuration of figure
2 was representative
of the majority
of the installed cables.
One difference
(and
an important difference)
being the spacing
between
each
succeeding
bend.
The installed flex-
ible conduit bends
under
the Reactor
Vessel
were
spaced
much closer
(by at least
1/2 of the distance)
than the spacing
between
bends in
the test setup.
.The length of the flexible cable
used in the test
setup
was established
at 60 feet for the 3/4 inch flexible conduit
and
65 feet for the 1/2 inch flexible conduit.
Some craftsmen
had
indicated the actual installed lengths to be as
much as
80 feet.
The
simulated
bends
and angles
were formed by attaching
the flexible
conduit with cable ties to the supports installed in the Comstock
Electrical
shop.
The total
number of bends
was conservatively
estimated
to be 800 degrees.
To aid in passing
the cable through the flexible conduit,
a lubricant
was used.
The lubricant was applied through
a 1/4 inch tygon (semi-
rigid) tubing using
80 psig air regulated
to 45 psig
so that the lubri-
cating fluid just oozed out of the
end of the tygon lube tube.
The
tygon lube tube (approximately
80 feet long) had
been pulled through
the 3/4 inch flexible conduit using what is commonly
known as
a fish
line.
The fish line is
a solid 1/8 inch diameter flexible plastic
line pushed
through the flexible conduit.
This line is then attached
to the semi-rigid lube tube
and pulled back through the flexible con-
duit.
Lubrication fluid oozing out of the end of the lube tube
as it
is pulled through the flexible conduit reduces frictional resistances
allowing tube to be pulled through the flexible conduit.
To further assist
in installing the coaxial cable
and demonstrate
that
the coaxial
cable
was
pushed
through the flexible conduit, craftsmen
(indicated in Figure
2 by h) were placed along the routing of the
flexible conduit to straighten
and
shake
the flexible conduit as the
cable
passed
through these
areas.
5.2
To start the test,
the craftsmen
stopped
the flow of lubricant .through
the lube tube
and disconnected
the fish line.
The lube tube
was then
attached
to the larger coaxial
cable
(RSS-6-116/LE)
per figure 3A.
The lubrication fluid was set in motion again
and the cable
was inserted
into the 3/4 inch flexible conduit at the junction box.
Craftsmen at
the other
end proceeded
to guide the lube tube out of the flexible
conduit.
No visible force was observed
as the coaxial 'cable
was pushed
through the straight section of flexible conduit from the junction
~ )
box to the first bend (Figure 2).
After entering the first bend the
two finger'old
on the lube tube
became
one
hand hold then
two hands
with visible exertion of force
on both ends.
The inspector attempted
to push the cable at the junction box end, exerting approximately
20-25 lbs.
Going to the opposite
end, it was determined that
a force
of 5 or more lbs was needed
to pull on the lube tube.
During this
same
time the craftsmen
stationed at various points (6 Figure 2)
along the cable route
had to continually shake
and straighten
various
sections of the flexible conduit to assist
in getting the cable through.
The force required to pull on the lube tube increased,
requiring both
hands
as the cable
passed
through the multiple bend areas
(Figure 2).
At no time was it possible to push without pulling the coaxial cable
through the flexible conduit once the cable
had gone through the first
bend following the junction box.
The time required to pull the coaxial
cable
(RSS-6-116/LE,
NJP-32)
through the 3/4 inch flexible conduit was
6 minutes.
5.3
The demonstration
for installing the coaxial cable
RSS-6-104,
NJP-29
was delayed
pending the installation of the
65 feet 1/2 inch flexible
conduit.
While waiting for the replacement
of the installed shorter
conduit test length (35 ft., Fig. 1),
a dynamometer
was
made available
and
used to measure
the force required to withdraw the previously
installed coaxial
cable
RSS-6-116/LE,
NJP-32.
The lubricant flow had
been
stopped
and the lube tube disconnected
from the cable.
The dyna-
mometer (weighing 7.5 lbs) was fastened
(Fig. 2) to the coaxial
cable
and the cable withdrawn by pulling uniformly on the dynamometer.
The
forces registered
on the dynamometer
were in the 30-35 lb. range to
start,
tapering off to 10-20 lbs. in passing
through the last two bends
prior to the junction box.
Allowing for the weight of the dynamometer
and the
use of lubricant during the push/pull installation of the cable,
the inspector
concluded that the
maximum allowable (calculated)
pull
tension
(69 lbs.) was not exceeded
for the installation of the
RSS-6-116/LE(NJP-32)
coaxial cable.
Having replaced
the short length (35 feet) of 1/2 inch flexible conduit
with the
65 foot length,
the craftsmen
were ready to proceed with the
installation of coaxial
cable
Mark No. NJP-29.
The
same
procedure
was followed for inserting the fish line and drawing
the lubrication tube through the 1/2 inch flexible conduit.
The attach-
ment to the lube tube
was identical (Figure 3-A).
The lubrication medium
was set in motion using the
same criteria
so that the flow just oozed
out of the lube tube.
The craftsmen
inserted
the cable
(Mark No. NJP-29)
into the 1/2 inch flexible conduit at the junction box end.
pushing
the cable to the first bend.
During this process
the lube tube
was
eased
out, of the conduit applying just enough tension to keep the cable
from backing
up.
The cable/lube
tube
movement
was
smooth
up to the
first bend.
At this point force
had to be applied to push the cable
while exerting 3-5 lb pull tension at the lube tube
end.
Craftsmen
tried to push the NJP-29 cable through after passing
the first bend
but were unsuccessful.
It was evident that the lube tube
had to be
pulled out and that the coaxial cable
Mark No.- NJP-29 could not be used
to push the lube tube through the conduit.
Here again,
craftsmen
had
to be positioned
(6 Figure 2) along
the. conduit routing to vigorously
shake
and straighten
the curve section of the flexible conduit to
complete
the installation.
to push the
6.0
Unresolved
Items
The conclusion following both tests is that the coaxial cable could
not have
been
pushed
through the installed configuration.
Tension
had to be applied to pull the cable through.
The amount of tension
(Approximately 3-5 lbs) is much less
than the calculated
allowable
pull tension for cable
Mark No.
NJP-29
(35 lb) and therefore it may
be concluded that there
was
no damage
to the cable.
This has
been
verified through insulation resistance
tests
per
E8DCR 02258A.
One
additional test
was performed to determine if the cable without the
lubrication tube could
be pushed
through the flexible conduit.
The
coaxial
cable
Mark No.
NFP-29
was released
from the lube tube
and
withdrawn from the flexible conduit.
Starting from the
same point at
'the junction box the cable
was
pushed
through the flexible conduit in
approximately
6 minutes.
Craftsmen did vigorously shake
and
straighten
the curved sections
in the conduit but they were able to
push the cable through indicating
much of the problem in trying to
push the cable
was in trying to push the
much more rigid lube tube
ahead of the softer,
more flexible coaxial cable.
The force required
coaxial
cable
mark no.
29 was estimated
to be 15-20 lbs.
Unresolved
items are matters
about which more information is needed
to
determine
whether it is acceptable
or
a violation.
Unresolved
items are
discussed
in paragraph
2.0.
7.
~Ei
The inspector
met with the licensee
and construction
representatives
(denoted
in Detail, paragraph
1.0) at the conclusion of the inspection
on November
15,
1985 and at the demonstration
of December
4,
1985, at the construction
site.
The inspector
summarized
the findings of the inspection
and the
licensee
acknowledged
the inspectors
comments.
At no time during the inspection
was written material
pro'vided to the
licensee
by the inspector.
COMSTOCK SHOP
Unistrut/Pipe Supports
Suspended
from Ceiling
4" Rigid Conduit
Representing
7ft
thru
Reactor
Vessel
Pedestal
Cable Ties
Used
To Attach Flex-Conduit
o Supports
I/2" American
BOA
Flex-Conduit
(35 ft',
3/4" American
BOA
Flex-Conduit
(60 ft)
Junction
Box
Original Test Configuration
FIGURE
1
~
~
COMSTOCK SHOP
Bends - A
roximate
Degrees
Unistrut/Pipe Supports
Suspended
From Ceiling
90
7 ft Penetration
.Representing
'throu
h Reactor
Yessel
9
Pedestal
to
\\
80
18
45
5 ~
3/4" American
BOA Flex-Conduit
60 ft
In
1/2 American
BOA
lex-Conduit
(65 ft)
~ 1/4" Tyson Lube Tube
Lubricant Flow Adjusted
> To Ooze Out of End of
~Tubing
Junction
Box On
Outer Shield
Mal 1
.Cable Entry Point
Pressure
Regulated
to 45 PSI
80 PSI Air
Coiled Cable
Cut
To Length
Dynamometer
Revised Test Configuration
Legend:
X - Cable ties securing flex-conduit to unistrut
- Personnel
pulling/pushing cable
and lube tube thru flex-conduit
~ - Personnel
assisting
movement of cable through flex-conduit by
shaking twisting flex-conduit
C3 - Personnel
coiling cable
FIGURE 2
e
'Several
Layers of Electricians
Stranded
Conductor with Insulation
Tape
Wrapped Around Connection
I/4" Tygon Tubing
A
Coaxial
Cable
FIGURE 3
E(