ML17055A868
| ML17055A868 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 11/29/1985 |
| From: | Miller W NRC OFFICE OF ADMINISTRATION (ADM) |
| To: | Hooten B NIAGARA MOHAWK POWER CORP. |
| References | |
| NUDOCS 8512090273 | |
| Download: ML17055A868 (4) | |
Text
Docket No. 50-410 goy 29 Sss DISTRIBUTION
'DR LPDR LFMS Actual Manpower File RMDiggs CJHolloway>
~~Reg Docket Fi'1e DWeiss LFMS Reactor File LSolander, PRAB
- MKaltman, PRAB cd~P ~~
E./gi///A~ivy%.
Q, /gAuON~s/+12/Z Niagara Mohawk Power Corporation ATTN:
Mr. B. G. Hooten Executive Director Nuclear Operations 300 Erie Boulevard Hest
- Syracuse, New York 13202 Gentlemen:
As you are aware, 10 CFR 170 of the Comrission's regulations for license and inspection fees was revised effective June 20, 1984.
Section 170.12(b) of the revised rule provides that for applications for permits, licenses, facility reference design approvals, and special projects which have been on file with the Coimission for review for six months or longer, billings would be made at six-month intervals or when the review is completed, whichever is earlier.
Consistent with the requirements of'0 CFR 170.12(b),
we have completed the cost analysis for the Nine Mile Point 2 OL application review for the period June 24, 1984 through December 22, 1984.
The cost through that period is $594,854 (Enclosure 1).
The Office of Resource Management has been notified to bill your Corporation for this amount.
Hhen making
- payment, please make reference to the bill number.
Sincerely,
~nnl Signed bg Pjn joe.~
Hilliam 0. Miller, Director License Fee Management Staff Office of Administration
Enclosure:
As stated Bgf20+027~..0~000410 ssfl~+
pDR ADOCK'DR A
Oeee iCE~
SURNAME~
DATE1e LFMS:
M CJ way:
11 85 LFMS:ADM p
HO~ )er 11/Z,f85 NRC FORM 318 (10.80) NRCM 0240 OFFlCIAL RECORD COPY
'y 1l
~
~
~
tagara Mohawk Power Corporatt<
Operating License Review Costs From 6/24/84 through 12/22/84 FACILITY:
NINE NILE POINT 2 DOCKET NO.:
50-410 Program Office Review Costs Per Professional Staff-hour Professional Staff-hours
~Ed d
Staff-hour Costs Contractual Total Costs Costs NRR
$62 6,360
$394,320
$41,805
$436,125 2.
IE-HQ 3.
REGI ONS 53 548 2,179 29,044 115,487 6,900 35,944 115,487 4.
ACRS 62 12 744 744 5.
NNS5 113 6,554 6>554 Total Cost:
$594,854
iM>>