NRR E-mail Capture - Acceptance Review Results for Comanche Peak, Unit 2 Request for Alternative 2B3-1
ML17054C926
Person / Time
Site: Comanche Peak Luminant icon.png
Issue date: 02/23/2017
From: Watford M
Plant Licensing Branch IV
To: Hicks J
Luminant Generation Co
References
MF9282
Download: ML17054C926 (2)


Text

NRR-PMDAPEm Resource From: Watford, Margaret Sent: Thursday, February 23, 2017 11:55 AM To: Hicks, Jack Cc: Hope, Timothy

Subject:

Acceptance Review Results for Comanche Peak Relief Request 2B3-1 (CAC No.

MF9282)

Dear Mr. Hicks,

By letter dated February 14, 2017, TEX Operations Company LLC submitted a relief request for Comanche Peak Nuclear Power Plant. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take up to approximately 100 hours4.167 days <br />0.595 weeks <br />0.137 months <br /> to complete. The NRC staff expects to complete this review in approximately 2 months, which is April 2017. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, and unanticipated addition of scope to the review. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

Thank you, Maggie Watford Project Manager, Plant Licensing Branch IV Division of Operating Reactor Licensing U.S. Nuclear Regulatory Commission Phone: 301-415-1233 Email: Margaret.Watford@nrc.gov 1

Hearing Identifier: NRR_PMDA Email Number: 3363 Mail Envelope Properties (Margaret.Watford@nrc.gov20170223115500)

Subject:

Acceptance Review Results for Comanche Peak Relief Request 2B3-1 (CAC No.

MF9282)

Sent Date: 2/23/2017 11:55:25 AM Received Date: 2/23/2017 11:55:00 AM From: Watford, Margaret Created By: Margaret.Watford@nrc.gov Recipients:

"Hope, Timothy" <Timothy.Hope@luminant.com>

Tracking Status: None "Hicks, Jack" <Jack.Hicks@luminant.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 2708 2/23/2017 11:55:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: