ML17054B921
| ML17054B921 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 10/01/1985 |
| From: | Starostecki R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Mangan C NIAGARA MOHAWK POWER CORP. |
| References | |
| NUDOCS 8510080193 | |
| Download: ML17054B921 (10) | |
Text
Docket No. 50-410 Niagara Mohawk Power Corporation ATTN:
Mr. C.
V. Mangan Senior Vice President c/o Miss Catherine R. Seibert 300 Erie Boulevard West
- Syracuse, New York 13202 Gentlemen:
Subject:
NRC Region I Inspections The purpose of this letter is to solicit more detailed schedular information that will assist us in further developing our inspection program for Nine Mile Point Unit 2.
Based upon your estimated facility readiness for fuel
- load, we intend to conduct inspections in a
number of areas before this milestone in order to ascertain operational readiness.
The specific areas are listed in the enclosure to this letter.
Me request that a
schedule be provided that indicates when each area will be complete and ready to undergo a detailed NRC inspection.
The schedule should be sufficiently detailed to di stingui sh among the various subelements of the areas listed.
Such information will assist us in effectively managing our ef-forts and resources.
Based upon our prior experience with other recent NTOL facilities, it is not advantageous from a
resource expenditure standpoint to conduct multiple inspections in a given area.
Accordingly, it would be appro-priate to update your response, preferably on a monthly basis, to keep the pro-jected schedule current.
The information in your response will be one of the factors considered by us in scheduling the nature and number of inspections.
These inspections wi 11 form the basis for Region I in making a determination as to the state of opera-tional readiness of the facility for fuel load.
A written response is requested as soon as possible.
Thank you for your co-operation in this matter.
Sincerely, PDR ADOCK 05000>4R10 G.
Richard M. Starostecki, Director Division of Reactor Projects
Enclosure:
As Stated OFFICIAL RECORD COPY COLLINS9/18/85 - 0001.0.0 09/18/85
C' I
,A l
V I
cc w/encl:
Connor
& Wetterhahn John W. Keib, Esquire D.
- Quamme, NMP-2 Project Director C.
Local Public Document Room (LPDR)
Nuclear Safety Information Center (NSIC)
NRC Resident Inspector State of New York bcc w/encl:
Region I Docket Room (with concurrences)
DRP Section Chief J. Grant, DRP M.(Haughey,
- LPM, NRR
,>J. Butler, ORB;
RI:DRP RI:DRP RI:DRS RI:DRS RI:DRSS RI:DRSS RI:DRP 28-Linville/sm Collins Durr Bettenhausen Bellamy Joyner Starostecki 27-9/
/85 28-9/
/85 9/
/85 9/
/85 9/
/85 9/
/85 9/
/85 27-,end OFFICIAL RECORD COPY COLLINS9/18/85 - 0002.0.0 09/18/85
I ill, 1 E'U.
bJ' l
R DRP Linville/sm 9/p'85 I.
RP Coll ins 9/yo /85 Durr Bettenhausen 9A/85 'CC85 RI:DRSS Bel] amy 9/w>/85 SS RI:
Joyner Starostecki 9~/85 9/g j/85 OFFICIAL RECORD COPY COLLINS9/18/85 09/18/85
t ll
4
~t 1
P ENCLOSURE 1.
0 erations Maintenance and Surveillance 1.1 Staff Training a.
Licensed Operator b.
Licensed Operator Requalification c.
Non-Licensed Training 1.2 Procedures a.
Surveillance Test Procedures b.
Maintenance procedures c.
Administrative procedures d.
System operating procedures e.
Emergency and abnormal operation procedures 1.3 Implementation of Surveillance Testing 2.
Fire Protection 2.1 Procedures 2.2 Training 2.3 Equipment 3.
Radiolo ical Controls/Chemistr
- 3. 1 Procedures 3.2 Exposure Control Program 3.3 Radioactive Waste Program 3.4 ALARA Program 4.
Securit and Safe uards
- 4. 1 New Fuel Security Plan 4.2 Program and Procedures for Site Security 4.3 Establishment and Implementation of the Site Security Program 5.
ualit Assurance 5.1 QA Plan and Procedures 5.2
. Implementation of the Operational QA Program 5.3 QA Training and Staffing
\\I
6.
Preo erational Testin 6.1 Procedures 6.2 Category I system tests 6.3 Milestones a.
CILRT b.
Loss of Offsite Power Test c.
Fuel Receipt
~
~
~