ML17053D113

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-410/81-13 on 811130-1211 & 17-18. Noncompliance Noted:Inadequate Review of Design Change & Spec,Inappropriate & Ineffectively Executed QA Program & Failure to Conform W/Procurement Spec
ML17053D113
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 03/01/1982
From: Chaudhary S, Ebneter S, Paolino R, Reynolds S, Schulz R, Lester Tripp
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17053D110 List:
References
50-410-81-13, NUDOCS 8204200492
Download: ML17053D113 (80)


See also: IR 05000410/1981013

Text

I

y

I

U.S.

NUCLEAR REGULATORY COMMISSIlt',"

OFFICE OF INSPECTION AND ENFORCE>'

I

Region I

Report

No.

50-410/81-13

Docket No.

50-410

License

No.

CPPR-112

Priority

Category

A

Licensee:

Nia ara

Mohawk Power Cor oration

300 Erie Blvd.

Nest

S racuse

New York

13202

Facility Name:

Nine Mile Point Station

Unit 2

Inspection at:

Scriba

and Syracuse,

New York

Inspection

conducted:

November

30 - December

11

V

Inspectors:

~

. tl ~,6 cu.< o

S.

K. Chaudhary,

Reacto

Inspector

Pa lino,

eactor Inspector

December

17,

18,

1981

da

e signed

W /9 g~

te

igned

.

D.

Re

olds, Jr.,

Reactor

In pector

da

e signed

~

r'

Chief,

M&PS, EIB

date

signed

Schul

Resident

Inspector

date

signed

Approved by:

S.

D. Ebneter,

Chief, Engineering

Inspection

Branch

a

e signed

Ins ection

Summar

Ins ection

on November

30

December

11

and December

17-18

1981.

Re ort Number 50-410/81-13

Areas Ins ected:

Announced

team inspection

conducted at the Nine Mile Point,

Unit 2 site

and

NMPC Corporate offices by four regional-based

and

one resident

inspector of quality assurance;

design controls; project management;

procurement

control

and construction controls in the electrical,

mechanical

and

NDE areas.

The inspection

involved 394 inspector-hours

onsite

and

128 inspector-hours

in

the office.

Results:

Of the five major areas

inspected,

no items of noncompliance

were

identified in two areas;

three

items of noncompliance

were identified in three

areas

(Severity Level IV - Inappropriate

and ineffectively executed quality

assurance

program,

Sections 2.2.1, 2.2.2, 2.2.4, 2.2.5, 2.2.8,

and 4.1.1; Severity

Level IV Inadequate

review of design

change

and specifica-

tion, Sections 3.1.2.4

and 5.1.7;

and Severity Level

V Nonconformance with

procurement specification,

Section 5.1.4)

8204200492

8203i7

PDR AoaCX QSQQQOio

9

PDR

I

)I )

I f

) V

TABLE OF CONTENTS

Persons

Contacted

1.2

1

~ 3

2.0

Niagara

Mohawk Power Corporation

Stone

and Webster Engineering

Corporation

Other

  • "'"""

2.1

2.2

Site Organization

Areas Inspected

2.2.1

2.2.2

2.2.3

2.2.4

2.2.5

2.2.6

2.2.7)

2.2.8

2.3

3.0

Quality Assurance/Quality

Control Implementation

Training

Document Control

Control of Material

Nonconformances

and Corrective Action

Record Control

Audits

Management

Involvement

Documents

Reviewed

ODiD

C

3.1

3.1.1

3.1.2

3.1.3

3.1.4

3.2

4.0

Areas Inspected

Program

Program Implementation

Management

Involvement

Availability and Traceabi lity of Records

Documents

Reviewed

Project

Mana ement

4.1

Areas Inspected

a

4.1.1

4.1.2

4.2

5.0

Program

Implementation

Documents

Reviewed

Procurement

Control

5,1

5.1.1

5.1

~ 2

5.1.3

5.1.4

5.1

~ 5

5.1.6

Areas Inspected

Procurement

Documents

Document Control

Conformance with Procurement

Documents

Specification

Changes

gualification of Suppliers

Specification

Review

5.1.7

Detection of Reactor Coolant

Leakage

5.1.8

6.0

6.1

6.1.1

6.1.2

6.1.3

7.0

Cable Tray Spacing

Electrical

Areas Inspected

Equipment Storage

In-Place

Receiving

and Storage

Documentation

Storage Facility

Mechanical

and

NDE

7.1

7.1.1

Previous

Open Items

Licensee Actions on Previous

Inspection

Findings

7.2

7.2.1

7.2.2

7.3

8.0

9.0

Areas Inspected

Visual Observation of Welding

Welding Material Control

Documents

Reviewed

Unresolved

Items

Exit Interview

~

y

l

I,I)

f""$

DETAILS

Persons

Contacted

Nia ara

Mohawk Power Cor oration

NMPC

J. Arkerson, .Lead Administrative Engineer-Project

Manual

and Methods

(3)

J. Bartlett, Executive Vice President

(2)

J. Belko, Manager,

Project Quality

R. Bonzagni, Project Control Engineer-Cost

(2)

M. Bryant, Manager,

Corporate Quality Assurance

(2)

R. Clancy, Senior Vice President

(1)

R. Dahlin,

Lead Mechanical

Construction

Engineer

(2)

J. Dillon, Lead Site

QA Engineer

(1)

G. Doyle, Asst.

QA Technician

(Group Leader,

IKC

Bldg. Serv./Programs

Group)

( 1)

M. Dunlop,

QA Technician

(under contract

from

Universal Testing Laboratories)

(2)

L. Fenton,

Assoc.

Sr.

QA Technician

P. Francisco,

Lead Licensing Engineer

Y. Goyal, Assistant

Manager,

Project Control-Cost

C. Jasinski,

Project Control Engineer-Scheduling

C. Kolarz,

Lead Construction

Planning

Engineer

B. Lamers,

Mechanical

Construction

Engineer

L. Lessard,

Manager,

Operations Analysis

(2)

E. Manning,

QA Technician

(Group Leader,

Mechanical

& Concrete

Group)

(3)

S.

Manno, Project Manager

(1)

H. Mastin,

Lead Electrical Construction

Engineer

(1)

D. Maxwell, Records

Management

Supervisor

v

(1)

C. Millian,

Lead Quality Engineer-Construction

(2)

R.

Norman, Supervisor,

Quality Assurance,

NMP ¹2

F. Osypiewski,

QA Engineer

(Group Leader, Electrical 5

Steel

Group)

(1)

D. Palmer,

Supervisor,

Quality Assurance,

NMP ¹1

D. Pracht,

Lead Mechanical

Engineer

(1)

J. Ptak,

Manager of Construction

(2)

G.

Rhode,

Vice President-System

Project

Management

(1)

W. Rumberger,

Assistant Project Manager,

Operations

D. Sandwick,

Lead Quality Engineer-Headquarters

J.

Saurina,

Lead Civil Construction

Engineer

R. Smith, Jr.,

Mechanical

Construction

Engineer

J.

Swenszkowski,

Assoc.

QA Technician

(Group Leader,

Piping/NSSS

Group)

(2)

C. Terry, Manager,

Project Engineering

Stone

and Webster

En ineerin

Cor oration

SEW

L. Alley, Senior Construction Supervisor

L. Barsuck, Office Supervisor

(1)

R. Barnard,

Fi el d Qual ity Control

(FQC),

Boston Office

J.

Burgess,

QA Supervisor

(1)

K. Conkad,

Construction

Completion Control

Program

(CCCP)

Administrator

C. Corso, Electrical

Engineer

S.

Crowe, Assistant Supt.,

FQC

L. Dalhaus,

Lead Electrical

QC Engineer

(1)

C.

Deban,

Senior

Records Supervisor

D, Boe,

Lead pater'ills Engineet,

Cherry Hi'll

I

~

1

I f

i rg

(1)

E. Eichen, Asst. Supt. of Engineering

J. Ellis, Chief Construction Supt.,

Welding

(4)

T. Farrell, Principle Structural

Engineer

D. Friedrich, Chief Construction

Engineer

K. Goodness,

Material Controller

T. Giler,

CCCP Administrator

(4)

A. Grual, Principle Electrical

Engineer

R.; Hardison,

QC Engineer

(4)

M. Hazzan,

Power Engineer

J. Hinton, Calibration Inspector

(4)

E. Hubner,

Lead Controls Engineer

R.

Huggon,

QC Engineer

(1)

J.

Huston, Asst. Project Manager,

Operations

(1)

R. Kelly, Vice President

5 Manager,

Corporate

QA

R. Kebien,

Senior

QC Engineer

H. Kenyon, Senior

FQC Inspector

S.

Lazarek, Structural

Engineer

J.

Logewski, Calibration Inspector

E.

Magi lley, Asst.

Supt. of

FQC

R. Nagel, Training Coordinator

B. Niyogi, Mechanical

Engineer (seismic)

(1)

M. Oleson, Asst.

Supt. of Engineering

P.

Osborn, Office Engineer

(1)

G.

Pace,

Manager,

Project Quality Assurance

N. Palmer,

Senior Welding Supervisor

a'

C. Patrick, Construction Welding Supervisor

G. Philippi, Lead Structural-Mechanical

Engineer

B. Pierce,

Training Specialist

(1)

G. Pierce,

Site

QA Supervisor

h

H. Pierce,

Chief Office Engineer

R. Plant,

Manager,

FQC

(4)

J.

Posusney,

Principle Structural

Engineer

B.. Poythress,

Materials Manager

N. Sedgley,

Asst.

Supt. of Construction

(1)

L. Shea,

Supt. of Engineering,

Site Engineering

Group

(1)

F. Sheldon,

Supt. of Construction

(4)

M. Stocknoff, Radiation Protection

Engineer

C. Sperling,

Senior Material Controller

(4)

L. Theriault, Principle Piping Engineer

(1)

J.

Thompson,

Supt. of 'FQC

(4)

S. Tsombaris,

Electrical Engineer

(1)

R. Wagner,

Resident

Manager

& Senior Site Representative

,R. Wisecarver,

Concrete Construction Supervisor

(1)

C. Zappile, Project Engineer

Other

J.

Conlon, Chief Field Engineer,

Walsh Construction

Company

J.

Flannery, Material Control Coordinator,

L.K. Comstock

& Co.

D. Giguere,

QC Manager,

ITT Grinnell

P.

Lockwood, Senior

Document Control Engineer,

L.K. Comstock

&

Co.

I

~

I

B. Pion, Mechanical

Engineer,

ITT Grinnell

K. Williams, Asst. Field Administrator, Cives Steel

Corporation

(1)

Denotes

those present at the 12/ll/81 site exit meeting

(2)

Denotes

those present at the 12/18/81 exit meeting at Syracuse

(3)

Denotes

those present at the 12/ll/81 and 12/18/81 exit meetings.

(4)

Contacted via telephone

at the

S8W Cherry Hills Office.

In addition to those listed above,

the inspectors

contacted

other representatives

and/or employees

of the above organizations

during the course of this inspection.

2.0

ualit

Assurance

The

QA inspection effort covered licensed activities in selected

functional areas.

In each of the functional areas

the inspector

reviewed written policies,

procedures,

and instructions;

interviewed

selected

personnel;

and reviewed selected

documents

to determine

whether:

The licensee

had written policies,

procedures,

or instructions

to provide management

controls in the subject areas;

The policies,

procedures,

and instructions

as

implemented,

were adequate

to assure

compliance with the regulatory

requirements.

The program provided indoctrination

and training of personnel

performing activities affecting quality as necessary

to

assure that suitable proficiency was achieved

and maintained.

2.1

Site Or anization

Ultimate responsibility for quality assurance

at the Nine Mile

Point, Unit 2 Power Station rests with Niagara

Mohawk Power

Corporation.

Niagara

Mohawk has contracted with Stone

& Webster

Engineering Corporation to maintain

and implement separate

but

subsidiary Quality Assurance

Programs

for Nine Mile Point, Unit

2, responsive

to and designed

to satisfy the intent of the

Quality Assurance Criteria of Appendix B.

Stone

& Webster,

in

carrying out this function,

has

some contractors

complying with

Stone

& Webster'

QA Program, while other s have their own

QA

Programs,

which have

been

approved

by Stone

& Webster.

For

example,

L.K. Comstock

and

Company

(permanent plant electrical

contractor),

Walsh Construction

Company (civil contractor),

and

t

I

I

Cives Steel

Corporation (structural

steel contractor)

operate

under Stone

& Webster's

QA Program.

ITT Grinnell (piping

contractor)

and Chicago Bridge.& Iron (liner and biological

shield wall) operate

under their own

QA Programs.

This

situation is somewhat

unique

and appears

to have contributed to

noncompliance

examples

as discussed

in Sections

2.2.1

and 2.2.2

of this report. Niagara'ohawk regularly conducts

scheduled

audits

and performs'continuous

survei llances of Stone

& Webster

and contractors

at the site.

The quality control inspection

efforts are carried out by Stone

& Webster

and contractor

personnel.

2 '

Areas Ins ected

The inspection

has

been divided into the following areas:

quality assurance/quality

control implementation, training,

document control, control of materials,

nonconformances

and

corrective action,

records,

and audits.

2.2.1

ualit

Assurance/ ualit

Control

Im lementation

In general,

the overall quality assurance

program

and the

QA/QC

organizations

of Niagara

Mohawk and Stone

& Webster

have the

essential

elements

to control construction activities;

however,

specific practices

were observed that appear

to be

a departure

from industry standards

such

as

ANSI QA standards

and/or

practices

designed

to ensure effective quality control.

Stone

and Webster Engineering Corporation

has

been

overdependent

on contractor construction

personnel

to identify

quality related

problems

and monitor quality related

activities, especially

dependent

on those contractors without

their own

QA Programs,

who are required to comply with Stone

&

Webster's

QA Program.

This reliance

was identified in the

structural

steel

inspection

program,

concrete

inspection

program, material

release,

and control of measuring

and test

equipment

as discussed

below.

It is an example of

noncompliance with 10 CFR 50, Appendix B, Criterion I

(410/81-13-01).

2.2.1.1

Stone

& Webster

was relying on Cives contractor construction

personnel

to verify numerous

weld preparations

and joint fit-ups

for structural

steel

welding.

Stone

& Webster's

QA Program

required only random inspections

by quality control personnel

of weld preps

and fit-ups to verify compliance with AWS Dl.l

and ANSI N45 2.5,

1974.

The sampling

(random)

procedure

was

not based

on recognized

standard

practices

per ANSI N45.2.

1

~

I'Jf>

Stone

& Webster

was relying on Walsh contractor construction

personnel

to verify that numerous

concrete

placements

were

cured in accordance

with Stone

& Webster Specification

NMP2-S203C,

Revision 6,

and ANSI N45 2.5,

1974.

Stone

& Webster's

gA

Program only required,

as

a minimum, the following curing

checks:

ADT

. Number of Ins ections

Per Week

Bel ow 40

Above 40

As discussed

in Inspection

Report 410/81-12,

several

of these

inspections

were not performed resulting in a series

of'oncompliances.

In addition,

from July 27,

1981, to October 29,

1981 there

were

thirty nonconformances

written by Stone

& Webster resulting

from missing or mislocated

dowels in concrete

pours.

The

missing dowels were identified by Walsh contractor construction

personnel,

after Stone

& Webster field quality control personnel

had inspected

and failed to identify the missing

dowels.

Stone

& Webster

was relying on Cives contractor construction

personnel

to control

and issue material,

as discussed

in Section

2.2.4 of this report, contrary to Stone

& Webster Construction

Methods Procedures.

Stone

& Webster

was relying on contractor construction

personnel

to properly handle

and store calibrated

measuring

and

test equipment,

without documented

survei llances

or audits of

storage

and handling activities.'n addition, training was not

being given to contractor

personnel

on proper handling

and

storage.

Stone

& Webster's

gA Program addressed

the singular

aspect, of calibration control

on

a time interval basis

such

as

6 months or 12 months,

as applicable,

but failed to address

control

between

required calibration intervals.

Calibrated

measuring

and test equipment

was issued to construction

personnel,

and

need not be returned to Stone

& Webster until the item

needed re-calibration,

in accordance

with the pre-established

calibration interval.

An item was to be returned to Stone

&

Webster, if found damaged,

prior to the elapsed calibration

interval, but controls

had not been

implemented to reduce the

possibility of damage

and maintain calibrated

instruments

during the calibration period.

Niagara

Mohawk auditors identified

this lack of control in Nonconformance

Report ¹314, dated

July 13,

1981, which stated

in part that calibrated

equipment

was

handed

from one construction

personnel

user to another.

~Trainin

Stone

& Webster's training and qualification program for

guality Control personnel

responsible

for inspections

was

evaluated

against

ANSI N45 2.6,

1978 and the alternatives

specified in the September

14,

1981

NMPC letter to the Office

of Nuclear Reactor Regulation.

The inspector also reviewed qualification records for Niagara

Mohawk guality Assurance

personnel

to see that their experience

and training was commensurate

with the scope,

complexity or

special

nature of the activities to be audited.

No items of noncompliance

or significant observations

were

identified.

Stone

& Webster's training program for contractor personnel,

who are required to comply with Stone

& Webster's

gA Program,

was reviewed to ascertain

that the program provided indoctrination

and training of personnel

performing activities affecting

quality as necessary

to assure that suitable proficiency is

achieved

and maintained.

The inspector

found that there

was

a significant lack of training

given to contractor personnel,

especially

in regards

to procedures,

hold points,

and inspection

requirements.

The majority of the

training was in safety programs,

rather than Stone

& Webster'

gA Program,

which contractor

personnel

were required to follow.

The inspector

identified nineteen

nonconformances

which were

written by Stone

& Webster in a period from February

11,

1981

to November

16,

1981, resulting from contractor personnel

not

being aware of the Stone

& Webster

(}A Program in regards

to

procedures,

hold points,

and inspection

requirements.

The

applicable contractor

and nonconformance

and disposition reports

are listed below.

Walsh

Cives

L.K. Comstock

2016

2047

2085

2103

2111

2198

2375

2508

2142

2160

2455

2468

2511

2592

2187

2275

2332

2649

In addition,

Niagara

Mohawk stated

on July 28,

1981 in Nonconformance

Report ¹315,

"Of the

19 contractors

on site,

less

than half

have participated

in any structured

form of training."

As discussed

above in Section 2.2.1,

there is an overdependence

on contractor personnel

to identify quality related

problems.

~

g

0

10

This is further compounded

by a lack of gA training for contractor

personnel.

This is a further

example of noncompliance with 10 CFR 50, Appendix B, Criterion I (410/81-13-01).

Document Control

The document control

program

was reviewed for conformance to

regulatory requirements,

equality Assurance

Program Requirements,

and applicable industry guidance

and standards.

Drawings and

procedures

were reviewed for current revisions, distribution

lists,

and assigned

responsbi lities.

E&DCR'

were checked for

issuance

and affected drawing control.

No items of noncompliance

or significant observations

were

identified.

Control of Material

Receipt

and storage of equipment

and material

was reviewed to

ascertain

whether the licensee

was implementing

a gA program

that was in conformance with regualtory requirements

and commitments

in the guality Assurance

Program,

implementing procedures,

and

in accordance

with ANSI N45 2.2,

1972.

The inspector verified

that responsibilities

were assigned

for receipt,

acceptance,

storage,

and release.

Nonconforming items were reviewed for

identification, segregation,

control,

and release.

Receipt

inspection reports

were examined for applicable

signatures,

justification for use,

damage

recorded,

and stipulated inspection

criteria.

Procedures

were reviewed for levels of storage

and

appropriate

environmental

conditions.

Cives Steel

Corporation

was not in compliance with the procedures

Stone

& Webster

had written to control the issuance

of material

to the field.

Cives was neither placing received material

in a

hold area

as required

by

CMP No. 1.2-11.81

Receiving Material

and Equipment,

Section 2.7.1,

nor writing stores requisitions

to withdraw items from storage

as required

by

CMP No.

1.3-2.79 - Material/Equipment Storage,

Section 5.10.5.

This is

contrary to

10 CFR 50, Appendix B, Criteria I and VIII.

Stone

& Webster personnel

were not involved in the issuance

of

material

as required

by their program, but were relying on

Cives construction

personnel

to control issuance.

The inspector

noted that two Noncompliance

and Di'sposition Reports

had resulted

from Cives bypassing

the material

release

control

system,

installing rejected material delineated

on

N&DR ¹2592,

dated

October

15,

1981

and installing uninspected

material delineated

on

N&DR ¹2160,

dated

November ll, 1980.

If an item was

on hold

or in reject status,

construction

personnel

were relied upon"

not to take

an item for erection,

rather

than depending

on the

material requisition process

and field .quality control interfacing.

l

I

11

This is another

example of'oncompliance with 10 CFR 50,

Appendix B, Criterion I (410/81-13-01).

Nonconformances

and Corrective Action

The inspector

reviewed this area to verify that measures

have

been established

to identify and correct conditions adverse

to

quality such

as failures, malfunctions, deficiencies,

deviations,

defective material

and equipment.

Corrective action taken to

preclude repetition

was also examined.

The area of nonconformances

was reviewed for prompt identification and correction.

Nonconformances

were not analyzed

on

an individual basis at the

time they were written,

as to why the nonconformance

occurred

or what corrective action

needed to be taken.

Rather

they

were solely resolved

on the technical acceptability,

rework,

repair, or scrap disposition, without regard to the root cause

of the nonconformance.

Trend analysis

was done by Stone

&

Webster

on

a six month and one month basis.

The lack of prompt

identification and correction of the root cause of the nonconformance

has led to numerous

nonconformances

being written in a short

period of time involving the

same functional area,

as in the

case of concrete

curing nonconformances

referenced

in Inspection

Report 410/81-12.

In addition,

one significant nonconformance

may require prompt corrective action

as stated

in

10 CFR 50,

Appendix B,

Criterion XVI.

The 'analyzing of nonconformances

on

a individual basis

can also pinpoint program weaknesses.

This is another

example of noncompliance with 10 CFR 50,

Appendix B, Criterion I.

(410/81-13-01)

The inspector

observed that there

was

a significant

problem in the timeliness of corrective action in regards to

Niagara

Mohawk audit findings.

This problem was largely due to

the delay in getting Stone

& Webster to answer

Niagara

Mohawk

audit findings concerning

the Stone

& Webster Quality Assurance

Program

and the

inadequacy of Stone

& Webster

responses

on

numerous

occasions.

There appeared

to be

a light regard for

Niagara

Mohawk audit findings.

Stone

& Webster not only didn'

comply with requested

response

dates,

but even missed extension

dates

granted

by Niagara

Mohawk.

For example,

Niagara

Mohawk

identified in July of 1981,

Nonconformance

¹315,

a significant

training problem at the site

and requested

a reply by August

28,

1981.

As of December

8,

1981,

no response

had been given.

Examples of other audit findings and response

delays

were

seen

on Nonconformance

Report No's.

311 thru 314,

308,

309,

300,

298,

and 297.

Nonconformance

¹297,

dated 1/5/81,

was still

open.

Nonconformance

Reports

297 and

298 required additional-

responses

due to the nature of the first response.

Another

example of an inadequate

response

was verified concerning

a

Niagara

Mohawk storage finding, delineated

on Nonconformance

e'

J

I

12

Report //309, dated July 17,

1981.

The finding stated that

a

24" control valve for reactor recirculation

was not being

stored in a controlled atmosphere

as required

by the manufacturer

and that the present

containment building storage

area

was

a

high humidity area

and therefore,

preventive

maintenance

was

needed.

Stone

& Webster's

response

dated August 14,

1981

stated that the containment

was not a high humidity area

and

no

preventive

maintenance

was, being performed

because

none

was

required.

The inspector,

through inspections,

has verified that

the containment is frequently subject to high humidity conditions.

Various guality Assurance

Management

personnel

stated during

interviews that they were not at all satisfied with the type of

responses

from Stone

& Webster,

nor the time delays in obtaining

the responses.

Corrective action

on Niagara

Mohawk audit findings

is far from timely and requires

added attention.

The inspector

questioned

why top management

had not taken

steps

to correct

this situation.

This is another

example of noncompliance with

10 CFR 50, Appendix B, Criterion I.

(410/81-13-01)

Record Control

The records

program was reviewed to"ascertain

that the licensee

was implementing

a program relating to the control of records

that was in conformance with regulatory requirements,

guality

Assurance

Program,

and

ANSI N45 2.9-1974.

Record storage

controls were reviewed along with means of transferring

records

to the vault.

Various records

were reviewed for implementation

of the program

and personnel

were interviewed concerning

storage,

access,

and retrievability.

The record index was examined

and

the Stone

& Webster vault was checked against

the criteria of

'NSI N45 2.9-1974.

No items of noncompliance

or significant observations

were

identified.

Audits

The licensee's

audit program

was reviewed to ascertain

whether

the licensee

has developed

and implemented

a program that is in

conformance with regulatory requirements

and applicable industry

guides

and standards.

The inspection

included verification of

the following:

scope of the program is consistent with PSAR

requirements,

responsibilities

for overall

management

of the

program

has

been

assigned,

and auditors were qualified in

accordance

with the nature of the activities to be audited.

No items of noncompliance

or significant observations

were

identified.

I

~

'A

C

13

2.2.8

Mana ement

Involvement

2.2.8.1

Pro osed

Reor anization of ualit

Function

The requirements

of NRC dictate that the licensee

establish

a quality

assurance

program

such that the program's

appropriate

and effectively

executed.

To assess

the extent of the appropriateness

and effectiveness

of the

licensee's

present

and proposed quality assurance

program'he-.-

inspector

reviewed the organizational

struct,ure of the present

gA

organization

and the proposed organization of Project guality, the

staffing plan for the

new organization,

and the qualification of the

designated

staff members of the

new organization.

The inspector

also held discussions

with the cognizant

personnel

of both the

existing

and proposed .organization

to determine their perception of

the responsibility of each organization,

the understanding

of their

functions

and any potential interface

problems.

Based

on the review of documents

and discussions

with cognizant

personnel,

the inspector determined that there

appeared

to be

an

excessive

turnover in the present

gA organization

inasmuch

as there

were only three

members

who have

been in gA for over

a period of

three years,

and they were all stationed off-site in the

NMPC corporate

headquarters

in Syracuse,

New York. The inherent instability of gA

staff due to excessive

turnover did raise

a question

as to the

effectiveness

and capability of the gA organization

to identify and

resolve quality

issues'urthermore,

by review of the staffing structure,

and the

scope of

the responsibility

as perceived

by the management

of the newly

proposed

Project guality Organization,

the qualification of assigned

personnel,

and extensive discussion with the management,

the inspector

observed that the personnel

assigned

to the

new

PgO did not have

adequate

training and experience

to carry-out the functions of a gA

organization.

Moreover, the responsibility

as perceived

by the

management

of PgA was not consistent with the department's

functions

as described

in the submittal to NRC.

2.2.8.2

Mana ement

Su

ort

The

number

and nature of the findings in the

gA area

as described

previously in this report led to further examination of the degree

of NMPC Management

support received

by gA.

The inspector

found

through interviews that

some onsite

NMPC gA personnel

working on the

NMP-2 project were not treated

the

same

as other onsite

employees.

That is, in their efforts to increase

staffing levels

on the

NMP-2

project,

NMPC management

initiated

a policy in the Spring of 1981

wherein

NMPC employees with permanent

residences

more than

20 miles

from the site

who were transferred

to the

NMP-2 site received

a

10%

pay bonus

and

a commuting mileage allowance.

This had been

I

\\

retroactively applied to all

NMPC employees

commuting more than'0

th

NNP-N tt

pt

T

IIA

pt y

.

Th

~th

A

employees

onsite

who commute~ore

than 20 miles from their permanent

residences

and did not receive

such allowances.

In another situation,

a former QA engineer

applied for, and

received

a September,

1981 transfer

from QA to

a position as

a

discipline engineer

in the

NMPC project organization.

With his

transfer

from QA,

he

became eligible for, and

now receives

the

special

bonus

and commuting allowance.

Thus, onsite

QA personnel

are treated

in an inequitable

manner,

thereby leading to financial disincentives

to remain in QA.

This demonstrates

a lack of NMPC management

support for QA

and/or

an insensitiveness

on the part of management

to the

inequities that they have permitted.

It is perceived

by

NMPC

personnel

to be

an indication of lack of corporate

management

support and/or lack of QA management

influence.

~Alla ation

On Oecember

11,

1981,

NRC received

anonymous allegations via

the

NMP-2 Resident Inspector's

phone relating to the Niagara

Mohawk Quality Assurance

Program.

These allegations

reinforced

most of the

NRC findings and concerns

in this area

up to that

point.

The alleger's

basic

concern

appeared

to be with the

attitude of the utility management

toward quality assurance.

Examples

given were; barring of certain

QA people

from the

site,

poor responses

to Quality Assurance

Audits and Quality

Control Inspection

Report findings,

and unfair treatment of QA

personnel,

alledgedly

because

they had generated

the findings.

He further stated that because

of this poor attitude,

there

had

been

a large turnover of QA personnel.

He also stated that

he

was concerned

about the

new Proposed

Quality Organization

in

that it might circumvent the existing

QA program.

Each of

these

items is discussed

below.

Barrin

of

A Peo le from the Site

In interviews subsequent

to the allegation,

the inspector

identified

a

NMPC QA staff member

who had effectively been

barred

from the site.

In discussing this situation with the

NMPC Manager of QA, it was disclosed that

he

had received

a

written directive from the Executive Vice President directing

him to not use that individual

on the

NMP-2 project.

He no

longer

had

a copy of that directive,

nor did the Executive Vice

President.

The inspector questioned

whether or not this individual

was actually being used

on

NMP-2 since the organization charts

indicated

such

an assignment.

By reviewing this individual's

time sheets for October

and November,

1981, it was finally

0

I

Nl

15

established

that

he

had

been

spending

most of his time on

NMP-2.

The Corporate

Manager of QA indicated that this individual's

involvement

on

NMP-2 had been limited to in-office activities.

Furthermore,

he expressed

concern that even that usage

on the

project was counter to the Executive Vice President's

wishes.

Pursuit of this matter with the

QA Manager's

immediate supervisor

(Vice President)

and the Executive Vice President

disclosed

that their understanding

and memory of this matter

was that the

Executive Vice President

had directed that the individual in

question

not be employed

as

a

QA supervisor,

but did not bar

him from working on the

NMP-2 project.

The individual in

question

was absent

and not available for interview.

The circumstances

surrounding

the above including the apparent

miscommunication

could be construed

as barring the

QA individual

in question

from the

NMP-2 site.

Poor

Res

onses

to

A Audits and

C Ins ection

Findincis

The inspectors

had already

made

a similar finding as discussed

in Section

2 '.5.2.

In further discussions

with NMPC QA personnel,

it was acknowledged that responsiveness

to

QA audit findings

was

somewhat

less

than desired.

It was indicated that this

lack of responsiveness

could be partially attributed to

preoccupation

by QA Department

Management with the proposed

reorganization

of the quality responsibilities for NMP-2 which

decreased

their efforts in pursuit of resolution of audit

findings.

Also, it was noted that there

appeared

to be

a

reluctance

on the part of QA Department

Management

personnel

to

utilize NMP-2 Project

Management

in exerting influence/pressure

in resolving audit findings.

Unfair Treatment of

A Personnel

As discussed

in Section 2.2.8.2,

the inspector

had previously

found that

NMP-2 QA personnel

with onsite assignments

were not

receiving the

same

pay and benefits

as other onsite

NMPC personnel.

No other instances

of unfair treatment of QA personnel

were

identified in subsequent

followup of this part of the allegation.

Lar

e Turnover of

A Personnel

The inspectors

had previously established

that high turnover

rates

had occurred

in QA (Section 2.2.8.1).

It was noted that

difficulties (delays)

had

been

encountered

in obtaining upper

management

authorizations

to replace

QA personnel

who had

previously been working on NMP-2, but had transferred

or quit.

The Executive Vice President attributed this delay to his

desire to wait and

see what

new staffing levels would be required

in

QA with the proposed

reorganization

of the

QA effort.

f

I

I

16

2.2.8.3.5

Possible

P 0 Circumvention of Existin

A Pro

ram

The inspectors

had previously voiced the

same

concern to

NMPC

'anagement;

at the

end of this inspection, it remained

an item

to be resolved

between

NMPC and

NRC.

2 '.8.4

2.3

Conclusion

4

In summary, it was found that there

was

a lack of strong positive

management

support to

QA and attention to

QA personnel

matters.

Findings in this area

include

a high rate of turnover of QA

personnel,

inadequate

prior QA/QC experience

of several staff

members

assigned

to the Project Quality Organization

(PQO),

significant differences

in the perceived charter for the proposed

PQO as expressed

by the Quality Assurance

Department,

Project

Management

and the Manager of PQO, inequitable

pay and fringe

benefits for some onsite personnel

and management

actions which

have in effect barred

a

QA person

from the site.

These findings

taken together with other findings of this inspection

show

a

lack of management

effectiveness

in executing

the quality

assurance

program.

This lack of effectiveness

can

be partially

attributed to lack of management

support to the

QA Department

as evidenced

by .inadequate

attention

and/or actions

on personnel

matters.

This~has

had!an

adverse

impact

on the capability and

effectiveness

of the quality assurance

effort.

This is

a

further example of noncompliance with Criterion I of 10 CFR 50,

Appendix

B which requires that quality assurance

functions

be

effectively executed

(410/81-13-01).

Documents

Reviewed

The inspector

reviewed the documents

of Niagara

Mohawk and

Stone

& Webster

as detailed below:

k

Quality Assurance

Manual

Stone

5 Webster

Quality Assurance

Program

Manuals

Quality Assurance

Procedures

Degree of Compliance With

Regulatory Guides

Quality Standards

Quality Assurance

Directives

MNP 2, Project Manual,

Volume II

Quality Control Instructions

Construction

Methods

Procedures

1.2-11.81,

1.3-2.79,

and 11.1-4.81

Project Specification ¹16

I

'I

17

3.0

Desi

n Controls

The purpose of this part of the inspection

was to determine if

the site design interfaces

were effective, the design controls

applied to on-site design activities were commensurate

with

those applied at the corporate offices,

and that on-site design

documents

were. current.

3.1

Areas Ins ected

3.1.1

~Pro

ram

The responsibility for design

and design control

has

been

~

delegated

by

NMPC to the principal contractor,

Stone

& Webster

Engineering Corporation

(S&W).

The Licensee's direct participation

in design

and its control

was found to primarily consist of

review and approval of selected

design

packages,

and audit of

design activities.

Stone

& Webster Engineering Corporation,

however,

had

a comprehensive

system of design controls applied

at all facets of design effort in its Cherry Hill Operations

Center.

These controls were adequately

proceduralized

in S&W's

Engineering

Assurance

Procedures

Mannual

(EAPs).

3.1.1.1

On-Site

Desi

n b

Site

En ineerin

Office

SEO

3.1.1.2

The inspector held discussions

with S&W engineers

assigned

to

SEO to determine

the extent of SEO involvement in on-site

design

and approval of design

changes

originated in the field.

The inspector also reviewed documents

maintained

in

SEO for

controlling design

and design

changes.

The inspector determined

that there

was

no significant design activity performed at site

by SEO; therefore,

there

were

no site specific procedures

required and/or available

at site to control original design.

The design

change activities were controlled by the

E&DCR

system,

which was

a company wide procedure 'followed by most

S&W

nuclear projects.

Desi

n Interfaces

The inspector determined that all design interfaces

were controlled

by EAPs,

however,

since there

was

no significant design activity

on-site,

no significant design interfaces

existed and/or were

required on-site. All the required interfaces

were controlled

and executed

at

CHOC of S&W.

3.1.2.1

Desi

n Chan

e Control

E&DCRs

The inspector

reviewed. S&W procedure

EAP.6.5, which controlled

the initiation, problem resolution,

and distribution of Engineering

I

18

and Design Coordination

Reports.

The

E&DCRs were found to be

the primary vehicle to initiate, resolve and/or

implement

changes

to an approved

design

document

such

as specifications,

drawings, etc.

The inspector

noted that the procedure,

EAP 6.5

also allowed the

use of E&DCRs system for documenting interpretations

and/or clarifications of design

requirements,

and site-project

technical

communications.

The inspector considered

the procedure

adequate

to control design

changes.

Pro

ram

Im lementation

Desi

n Document Control

The inspector

reviewed the status of several

drawings,

specifications,

and design

changes

to assure

the effectiveness

of measures

established

for their adequacy,

approvali

currenCy,'f

revisions,

and/or posting of changes.

The major portions of

this audit were carried out in conjunction with the documents

reviewed for the design control audit.

No items of noncompliance

were identified.

S ecification/Drawin

Station Control

The inspector

reviewed the drawings

and

E&DCRs located at the

drawing station at S&W's engineering

area

in the construction

offices,

and specifications

and specification

changes

to purchase

specifications

in the warehouse offices to assure

the currency

of drawings

and specifications,

completeness

of information,

posting of changes,

and conformance

to procedural

controls.

The inspector determined that the drawings

and specifications

were current.

The changes

had

been

posted

and procedural

control

was adequately

applied to assure

completeness

and

currency of design information.

No items of noncompliance

were identified in this area.

Im lementation of E&DCR S stem

The inspector

reviewed

a random selection of Engineering

and

Design Coordination

Reports for conformance

to the requirements

of project procedures,

completeness,

and validity and basis of

the changes

approved

through the

E&DCR 'system.

The inspector

also held discussions

with licensee

and A/E personnel

regarding

control, distribution and implementation of such changes.

The inspector determined that the

E&DCRs generally complied

with the procedural

requirements with respect to format,

adequate

problem description

and resolution,

and proper approvals.

The

inspector

did note that due to the

E&DCR systems'pplicability

to other areas,

i.e. interpretations/clarifications

and technical

communications,

there is an over use of the

E&DCR form.

0

1

l

~

~~'

19

Rebar

Desi

n Chan

e

In addition to the above general

observations,

the inspector

specifically noticed that in the month of November,

1979,

E&DCR

¹P00692

was initiated by Project engineering

to modify the

rebar purchase

specification,

S203E.

The structural

reinforced

concrete

design of NMP2 was based

on grade

40 rebars,

and the

rebar purchase. specification specified the correct grade of

rebar

(ASTH 615,

grade

40) to be supplied to site to fulfill

the design basis.

By modifying the purchase

specification to

allow a different grade of rebar to be supplied for use in the

construction,

the reinforced concrete

structures,

however, did

not meet the basic design

assumptions,

and the rebar detailing

based

on

such design.

The inspector pointed out to the licensee

his commitment to Uniform Building Code, ACI-318-71, which

limits the amount of rebar to 75% of the amount required for

balanced ratios of concrete

and steel

(ACI-318, Section

10.3)

in certain structural

members.

The inspector

stated that in

view of substituting

grade

60 rebar for grade

40 rebars

on

a

one to one basis,

the inspector

expected

to see objective

evidence of evaluation

and/or

an analysis

documenting

the

justification for this change.

The licensee

indicated that the

substitution of rebar

was based

on engineering

judgment,

and

there

was

no documented

evaluation or analysis

to support the

change.

The licensee,

therefore,

could not provide any objective

evidence

to the inspector to justify the design

change of

substitution of rebars.

The regulations of 10 CFR 50, Appendix

B, require that the changes

to the original design

be subjected

to the

same controls,

such

as verifying and checking the adequacy

of design,

as applied to the original design.

And, because

the

original structural

reinforced concrete

design

using grade

40

rebar

was not based

on engineering

judgement alone,

the change

in design permitting

a different grade of rebar to be used

one

for one without a documented

analysis

and/or evaluation

was

improper.

Based

on the

above observations,

the inspector

determined that:

There

was

no objective evidence to support that the appropriate

design input, i.e., ACI-318-71, was correctly translated

into the design

change,

nor that the impact of the change

on overall design

had been analysed.

There were

no engineering calculations to confirm the

adequacy of the design

change

nor was there

any objective

evidence of an independent

design verification.

This is an item of noncompliance

(410/81-13-02)

~

0

l

I

20

Desi

n and Installation of Cable Tra

Su

orts

threaded

welded studs

The inspector

reviewed the design

and analysis of cable tray

support ¹RC-240,

performed

a visual inspection of the installed

support;

held discussions

with cognizant licensee

and A/E

personnel

to determine

the technical

adequacy

of design

and

procedural

controls over the design/analysis

activities;

examined

evidence of independent

review of the design

as well as correctness

and completeness

of the design

requirements/data

transfer

to

construction/erection

documents;

and compared

the conformance

of the erected

support to the design

requirements.

No items of noncompliance

or deviations

were identified.

Mana ement Involvement

The inspector

held discussions

and reviewed documentation

to

assess

the extent of management

involvement in the evolution

and control of the design process.

Based

on the discussions,

and procedures

and records

furnished

by the licensee,

the inspector determined that the licensee

management

regularly reviewed the adequacy

of control procedures;

the licensees'ngineering

staff regularly reviewed

and

commented

on conceptual

design

packages

of selected

systems

in the plant;

and the Design Control Issue

(DCI) system

has

been recently

revised through

a

new contract negotiation with SKW to redefine

and establish

the extent of licensee

management

involvement in

the design

process.

No items of noncompliance

were identified.

Avai labilit

and Traceabi lit of Records

The inspector

reviewed the status

of design

and design

change

records

to assess

the availability of records,

and the

traceabi lity of information, data and/or the record itself for

retrieval, and review purposes.

This inspection

was performed

in conjunction with other parts of this inspection

and records

review.

The inspector determined that the records

and the data

contained

in those

records

were generally traceable

to source,

the documentation

was reasonably

retrievable,

and the records

management

program

as applied to design,

appeared

adequate

to

fulfill the project need.

No items of noncompliance

were identified.

)

t

e

3.2

Documents

Reviewed

21

The following is

a list of primary document

reviewed during the

course of this part of inspection.

3.2.1

Nia ara

Mohawk Power

Cor oration

~

.

Nine Mile. Point Unit 2 Project Manual,

Volumes I-V.

~

Niagara

Mohawk QA Manual.

~

Niagara

Mohawk QA Procedures

Manual.

~

Degree of Compliance with Regulatory Guide for Nine

Mile-2 Project.-

~

Project Guidelines

32 '

Project Guidelines

33.

~

Project Organization

Charts.

~

Various letters

and

memoranda

regarding

DCI package

reviews.

3 2.2

Stone

and Webster

En ineerin

Cor oration

Engineering

Assurance

Procedures

Manual.

Quality Standards

Manual.

SKW Specification

203E.

SLW Drawings EC-41A-2 and

EC-42C-S.

S5W, Catagory I, Cable Tray Support Analysis for Support

¹RC-240; Calculation

item ¹E340-TAB6,

pp.

112-118.

On-site

Rebar

Fabrication

Requests.

Material Receiving Reports for Rebar.

A random selection of E&DCRs.

A random selection of NKDs.

Various project Memoranda

regarding design

and interpretation

of requirements.

I

C

22

Project

Mana ement

The objective of this part of the inspection

was to determine

the effectiveness

of project management

by examining

management

support of project requirements

and commitments,

responsiveness

to project needs

and management

involvement in all aspects

of

the project.

Primary emphasis

was

on the

NMPC and

S8W organizations

and their support of the construction effort.

This portion of

the inspection

was directed towards verification that Project

Management

was exercising control in a manner that will assure

a quality product (plant).

Areas Ins ected

~Pro

ram

The inspector

examined organization charts,

lines of authority

and communication,

interface controls,

systems for management

reporting

and mechanisms

for change control.

Program procedures

applicable to these activities are primarily contained within

the joint NMPC-S&W Project Manual.

A project manual

was developed

early in the life of the

NMP-2 project.

In 1980,

a management

audit was performed which identified the

need to expand the

scope of the original manual to clarify and document the overall

management

philosophy

on the project.

This was accomplished

by

restructuring

the existing two-volume Project

Manual into five

volumes,

each serving

a specific project purpose.

The Project Manual

was found to contain project policy, objectives,

division of responsibilities,

and procedures/

guidelines that

expand

upon,

and implement the intent of the overall project

management

plans,

the

NMPC/SEW contract,

corporate policies

and

procedures

(both

NMPC and

SEW),

and licensing/regulatory

requirements

and commitments.

Most of the procedures

in the Project

Manual

have

been

issued within the past year with several

other project

procedures

currently being developed.

The Project

Manual

was

estimated

(by the inspector) to be more than

75% complete.

Most project, activities were found to be adequately

addressed,

with the following exception.

Sections

2.1

and 2.2 of Volume

2

of the Project

Manual

are to provide functional roles

and

position descriptions for the organizations

assigned

to the

NMP-2 Project

by

NMPC and

SAW respectively.

These

two sections

are to define the functional structures for each corporation's

Project organization,

describe

the Project functional

responsibilities

of each

group within the respective

organizations,

and identify the duties

and responsibilities of

key positions within each group.

These

sections of the project

Manual

had not yet been

issued.

Examination of draft copies of

these

sections

and discussion with personnel

responsible

for

coordination of Project

Manual development

indicated that these

23

sections of the manual

are intended to be quite specific

(definitive). This is expected

to include detailed position

descriptions for key personnel

and detailed definition of

duties

and responsibilities.

The difficulties in developing

these

sections of the Project

Manual

appear to be partially due

to differences

in opinion between

NMPC and -S&W with respect

to

how much detail

should

go into these

procedures.

Issuance

of

these

manual

sections

is currently projected for early 1982.

In the interim, the inspector

was unable to find any comparable

formal (written) descriptions

of organizational

and position

roles, duties

and responsibilities.

Furthermore,

interviews

with numerous

S&W personnel

disclosed that they had not seen

and were

not, aware of written position descriptions for their

jobs.

Their understanding

of their job duties, responsibilities,

interfaces,

etc.

were

based

almost entirely on verbal directions

and understandings

with their management.

NMPC personnel

were

found to have individual job descriptions,

but orgnizational

duties

and responsibilities

lacked written definition similar

to

S&W.

This lack of written definition of organizational

and

position duties

and responsibilities is identified as

a further

example of noncompliance with 10 CFR 50, Appendix B, Criterion

I.

(410/81-13-01).

4.1.2

Im lementation

4.1.2.1

~Plannin

Additional management

involvement,

reviews

and controls were

observed to be initiated when trouble spots

were identified.

Interfaces

between

NMPC/S&W and various contractors

are handled

in various ways with considerable

reliance

on regularly scheduled

meetings with each contractor

which are attended

by representatives

of all interfacing organizations.

Staffing/personnel

within the

NMPC and

S&W organizations

appeared

to be adequate

in terms of

numbers,

education

and experience

based

on inspector interviews

with personnel

at all levels within these organizations.

It

was noted that there

had been

more than

a doubling of the

NMPC

staff assigned

to the

NMP-2 project within the past year.

This

appeared

to be primarily in response

to the recommendations

contained within a

NMPC requested

external

management

audit by

Black and Veatch

and

a

New York Public Service

Commission

directed

management

audit by Theodore Barry & Associates.

No noncompliances

or weaknesses

were identified in this area.

4.1.2.2

4.1.2.2.1

Construction Deficienc

Re orts

(CDR's)

The inspector

reviewed documentation

and held discussions

with

licensee's

cognizant

personnel

to determine

the policies and

l.

procedures

for identifying, evaluating,

and reporting of

construction deficiencies

to the

NRC as required

by section

55(e) of 10 CFR 50.

The inspector

determined that the existing

QA/QC program was

relied upon for the identification of any deficiency.

The

licensee,

however,

had established

a specific procedure

for

prompt evaluation

and reporting of such deficiencies

to

NRC.

The current project procedure controlling

CDRs required that

any identified deficiency must

be evaluated within five days to

determine its reportabi lity. If the evaluation

could not be

completed in the five working days,

then the deficiency must be

reported to

NRC as

a potential

problem and the final report

submitted to

NRC as

soon

as possible.

The inspector

reviewed

a

random selection of reports

submitted to NRC,

and found that

they conformed to the project requirements

regarding

the

identification, evaluation,

and prompt reporting to NRC.

No items of noncompliance

were identified.

Performance

Reviews

S&W was found to have

a comprehensive

system for verifying and

reviewing completion of construction

work by contractors

in

conformance with engineering

and contractual

requirements. It

is called the "Construction Control

& Completion Program"

(CCCP)

as covered

by Construction

Methods Procedure

(CMP) No.

1.11-8.79.

In this system,

a Construction

Completion Checklist

(CCC) form is completed

by

S&W construction

personnel

(Construction Supervisor)

monitoring contractor

performance

to

attest that work has

been

accomplished

in accordance

with

approved

drawings

and specifications.

These

CCC forms contain

various entries (attributes) that are to be evaluated,

witnessed

and/or verified as work is completed.

S&W Construction

Supervisors

are to record the results of such inspections

as "satisfactory"

or "unsatisfactory"

in the appropriate

blocks of the

CCC form.

For contractors for which

S&W has total quality responsibility

and

FQC performs all quality control inspections,

the system

functions in the following manner.

Completed units of work are

presented

by contractor

personnel

as ready for FQC inspection.

S&W Construction

Supervisors

inspect the work, and if satisfied,

actually request

the

FQC inspection.

S&W Construction Supervisors

can initiate "unsats"

on the

CCC forms for various situations

as defined in the

CMP including when the completed unit of work

has

been

presented

for S&W Construction

Supervisor

inspection

by the Contractor,

and the Supervisor finds an unsatisfactory

condition.

The

S&W CCCP Administrator also maintains

or compiles logs of

"unsats"

as indicated in

FQC Inspection

Reports (IR's) and

I

25

N&D's.

On

a monthly basis,

the

CCCP Administrator performs

an

analysis of the "unsats"

from all

CCC forms, IR's and N&D's for

each type of onsi te work in progress.

This analysis is further

subdivided to report

on the performance of each discipline and

contractor,

management

areas

and responsible

supervisors.

The

CCCP Administrator convenes

and chairs

a monthly quality

accountability meeting in which the analysis reports

are reviewed

wi,th the contractors

and corrective action requirements

for

recurring problems,

or of isolated

instances

of sufficient

magnitude to warrant special attention,

are discussed.

This

CCCP system

was found to be applied to major contractors

such

as Walsh,

L.K. Comstock

and ITT Grinnell

(embedments

only). It was first implemented

in late

1978 and continued

through

1979,

The anlysis of data

was di scontinued

throughout

1980

and for approximately the first half of 1981 dur'ing the

construction

slowdown.

Recent

CCCP analysis reports

and

accountability

meeting activities were 'inspected for L.K.

Comstock (for primarily September

1981 activities)

and September

and October,

1981 activities for Walsh. This inspection disclosed

areas

of weakness

with this program

as discussed

in the following

two paragraphs.

(410/81-13-03)

Contractors

develop

proposed

preventative

actions/commitments

which are discussed

and finalized as

a part of this process.

At

the time of this inspection,

however,

there

was

no formal

mechanism

or closure

loop for items identified,

as requiring

additional action.

The

CCCP Administrator had relied

on verbal

communication together with a lack of recurrence

as the method

of satisfying that preventative

action

had taken place.

In

response

to the inspector's

concern,

however,

a mechanism

was

implemented

before the

end of this inspection wherein objective

evidence of corrective/preventive

actions

must

be furnished the

CCCP Administrator before that item is closed.

Thus, this part

of the weakness

has

been satisfactorily

addressed.

In the

CCC analyses

examined

by the inspector,

more than

90% of

the "unsats"

had been

implemented

by FgC.

Further analysis

by

the

CCCP Administrator supported this approximate ratio (in one

case,

only 3 of 32 had been

implemented

by construction).

Since construction

performs final inspection before calling

FgC, these

numbers

suggest

several possibilities, i.e., inspection

by construction

to less stringent criteria than

FgC, construction

is not implementating

the

CMP in the intended

manner,

FgC

"unsats"

are subjective

in nature wherein construction

had

judged the

same condition to be "sat", etc.

Time did not

permit the inspector to examine this area

in enough detail to

determine

the source of these

apparent

discrepancies.

Regardless

of the cause,

the discrepancies/

inconsistancies

between

FgC

and construction indicate that the

CCCP system

used for

reviewing/monitoring contractor

performance is not working as

l

A

~

26

well as it should in that very few Construction

Supervisor

problems with contractors

are being

used in the evaluation of

contractor quality performance.

This part of the weakness

within the

CCCP system

had not yet been satisfactorily addressed

by the end of this inspection.

In addition to the weakness

discussed

above,

review of the data

for the accountability meeting for Walsh covering the period

August 31,

1981 to October 4,

1981 further supports

the finding

in Section 2.2.2.2 that contractor quality training is an

example of noncompliance

(410/81-13-01).

The proposed

preventative

action. for twenty-five "unsats" called for more

training with actual

numbers

as follows:

three called for

additional training of placement

personnel,

two applied to

concrete

curing crews,

four applied to carpenter

crews,

and

sixteen applied to ironworker foremen.

4.1.2.3

4.1.2.3.1

Mana ement Involvement

Mana ement

Re ortin

NMPC and

S&W jointly utilize an extensive

meeting

and reporting

system to keep project management

appraised

of the nature of

issues,

status

and progress,

assignment

of responsibilities for

followup, etc.

These

include monthly Project Progress

Reports,'anagement

Action Reports,

Executive

Summaries,

and Project

Meetings with subsequent

"Notes of Conference".

Monthly Management

Review Meetings are held with onsite contractors

to discuss

performance

data,

manpower utilization and any problem areas.

NMPC personnel

assigned

to NMP-2 project

have

a system of

weekly progress

reports which are

used to describe their weekly

activities, progress

and problems in their assigned

areas,

status of work, etc.

These

are

combined at each higher level

of management

resulting in at least monthly progress

reports

for each organizational

entity.

Review by the inspector of samples of reports

from each of the

above categories

indicated active

management

involvement at all

levels in these

management

meeting/reporting

systems.

No

noncompliances

or weaknesses

were observed

in this part of the

inspection.

4.1.2.3.2

~St.a ffi a

In addition to the inspector's

review of staffing levels discussed

in Section 4.1.2.1 staffing levels were discussed

with numerous

personnel

contacted at all levels within the

NMPC and

S&W

project organizations.

In no case did any staff member identify

any significant problem with any aspect of staffing including

approval of requested

staffing levels,

views of staff adequacy,

or maintaining adequate

staffing levels.

I

s

~

No noncompliances

or weaknesses

were identified,

Problems

As

a result of problems

encountered

at NMP-2 with the Biological

Shield Wall, a mechanism

was set

up for systematic

evaluation

of current

QA problem events

and to act as

a vehicle for providing

improved communications.

N&D's, E&DCR's, Problem Reports,

Inspection

Reports,

and

NRC,

NMPC, and

S&W audit findings are

reviewed to identify potential generic

problem areas

per procedure

PRS of the Project Manual.

In addition,

Event Analysis Reports

can

be initiated by anyone

who believes that

a subject

needs

further investigation or action to prevent the development of a

serious

problem.

Any of the above that represent

real

or

potential significant problems

are reviewed in monthly Potential

Problem

Review Meetings

(PPRM) attended

by key

S&W and

NMPC

QA/QC and project personnel.

Assignments of action parties

and

completion dates

are

made

as required.

Interoffice memos,

an agenda,

a monthly summary report of

findings examined for quality trends or potential

problems,

and

the notes of a

PPRM meeting were inspected.

Functioning of this

group was discussed

with S&W QA and

NMPC project management

personnel.

No noncompliances

or weaknesses

were identified.

Mana ement

Reviews ...

Most management

reviews of performance

of individual departments

or sections

was found to be accomplished

informally (verbally).

NMPC does periodically (every six months)

and formally .review

S&W performance

in major areas

such

as quality assurance,

engineering

and construction with certain incentive

awards

based

on the results of these

reviews.

Similarly,

NMPG and

S&W

jointly review contractor

performance

on

a periodic basis with

any incentive

awards (for those with incentive clauses)

based

on the results of these

management

reviews.

At the time of

this inspection,

one of the major contracts

was in the process

of renogiation with significant additions

expected

in the area

of performance/incentive

clauses.

The inspector

found that

significant changes

in

S&W and contractor

management

personnel

assigned

to the

NMP-2 project

had been

made

as the result of

management

performance

reviews.

The most significant overall

mangement

reviews of the project

were

made

as

a part of a

NMPC directed

1980 Black & Veatch/Arthur

Anderson audit and

a

New York Public Service

Commission directed

audit, by Theodore Barry & Associates/Conaton,

Inc.

(TB&A)

completed in 1981.

Review of the

TH&A audit disclosed that the

objectives

and

scope

included control of the project (project

management),

engineering

and construction activities.

It'

charter

included to "provide an overall assessment

of the

k

-Cg

t

i

I

I

28

quality assurance/quality

control efforts of'tone

and Webster

and Niagara

Mohawk."

Review of the

TB&A recommendations

showed

that they were primarily in the area of project management

and

did not directly pertain to gA.

Most of them involved

recommendations

of increased

involvement by

NMPC in project

control

and monitoring in the areas

of cost

and schedule.

Much

of the increased

NMPC project staffing within the past year

has

been in response

to these

recommendations.

Review of the mechanisms

for assigning

action responsibilities,

tracking status of commitments

and handling overall

NMPC

responsiveness

to the recommendations

from both of these audits

showed

them to be effective in controlling follow-up activities.

4.1.2.3.5

No noncompliances

or unresolved

items were identified.

Other Information Channels

Neither

S&W or

NMPC has

a formal system for handling allegations,

suggestions

or worker complaints.

In numerous

interviews at

all levels,

however,

personnel

expressed

no reluctance

to go to

management

with any concerns

about workmanship or quality.

No

concerns

were expressed

about job protection in the event they

were to express

such concerns.

None of the interviewed manager'

could recall

having received

any information that they would

characterize

as

a formal allegation.

4.1.2.3.6

No noncompliances

or weaknesses

were identified.

Mana ement/Em lo ee Interface

Management's availability to employees,

interest

and dedication

to quality and support to employees

was explored in contacts

with all levels of personnel

in

NMPC and

S&W as well as onsite

contractor personnel.

All personnel

indicated that their

managers

were readily available

most of the time in the various

work areas.

All contacted

personnel

indicated

a perceived

emphasis

on quality at all organizational

levels with the

exception of some perceived

lack of support fo the

NMPC guality

Assurance

Department

as discussed

in Section 2.2.8.2.

4.2

No items of noncompliance

or weaknesses

were. identified.

Documents

Reviewed

The following is a list of the primary documents

reviewed

during the course of this part of the inspection.

l

p

~

29

4.2.1

NMPC

Nine Mile Point Unit 2 Project Manual,

Volumes I-V

Weekly and Monthly Progress

Reports (at various organizational

levels).

Meeting Minutes for Weekly Area and Task Force

Meetings

Project Status

Summary Report ("Executive

Summary" ).

Organization

Charts.

Various Internal

Correspondences

Status

Report (Draft) .for

NMPC Project Procedures

(PPNM)/Project

Memoranda

(PMNM).

4.2.2

SKW

CMP 1.11-8.79,

Construction Controls

and Completion

Program

CCCP Analysis and guality Accountability Meeting

Reports

Monthly Project Reports

Management Action Reports

Agenda for Management

Review Meetings

(and Minutes)

PPRM memos,

Agenda,

Monthly Summary Report

and

Meeting Minutes

4.2.3

Organization

Charts

Interoffice Memos

Other

Theodore Barry & Associates/Conatom,

Inc. Audit of

NM2 Project

5.0

Procurement

Control

The objective .of this part of the inspection

was to determine

whether the purchase

of components

and materials for systems

important to safety

was in conformance with the licensee's

approved quality assurance

program

and implementing procedures.

l

)

1

$

~

30

Areas Ins ected

Procurement

Documents

The inspector

examined

procurement

and specification

documents for the following materials

and components:

C041-D

, Resistance

Temperature

Detectors

C071-M

Electronic Transmitters

E021-P

Electrical Penetration

E023-C

600 Volt Power Cable

E024-A

1000 Volt Fire Resistant

Cable

E024-P

300 Volt Instrument

Cable

E024-T

Co-Axial Cable

E026-A

Cable Trays

P281-F

Category I & II Radiation Monitoring

Equipment

The inspector verified that the documents

used in the purchase

of components,

equipment or types of materials in systems

important to safety include proper approval, quality inspection

requirements,

and quality record requirements.

No items of noncompliance

were identified.

Document Control

In reviewing the above

documents,

the inspector

noted

a possible

problem area

in that the individuals receiving the control

level

1 documents

were making penciled notations

in the control

document.

The inspector specifically cited the

C071-M document

in the guality Assurance

and Engineering

group.

The document

assigned

to each

group was extensively

marked

and the information

transferred

from the accompanying

addendums

was in error.

The inspector

determined this to be

a problem in document

control that could res'ult in misinformation.

The licensee

took immediate action by issuing

a project

memorandum

requiring all such notations in control documents

be notarized

and dated

by authorized

personnel.

In addition, the licensee

has

agreed

to review this area

and determine

adequacy of the

control measures.

This item is considered

resolved.

l

1

<~

~

31

Conformance with Procurement

Documents

The inspector verified that documentary

evidence is available

onsite to support

conformance

to procurement

documents.

The

inspector

reviewed cable qualification data

from two suppliers

and found the data to be in conformance with the procurement

document.

C

No items of noncompliance

were identified.

S ecification

Chan

es

The inspector

examined the cable tray specification

document

E026-A to determine

whether

changes

made in the procurement

document

as

a result of the bid evaluations

or precontract

negotiations

were subjected

to review and that

such reviews

. include the determination of any additional or modified design

criteria imposed after preparation

of the initial procurement

document

as the result of subsequent

analysis of exceptions

made or requested

by the supplier.

The inspector determined that'the qualification tests

(Vendor

Report

No. 24781)

does not conform to the specification

requirements

of E026-A.

Examples of differences

between

the procurement

specification

and the vendor

supplied qualification results

were as follows:

line 291-294 of specification

E026A, states,

in part,

that:

"Except as specifically stated or otherwise inferred,

the cable tray shall

conform to the requirements

of NEMA

standard

VE-1 for cable trays."

Section

VE1-3.01 of the

NEMA document states,

in part,

that:

"The working (allowable)

load capacity represents

the ability of a cable tray to support the static weight

of cables.

It is equivalent to the destruction .load

capacity,

as determined

by testing in accordance

with

paragraph

VE1-4.01."

VE1-3.02 specifies

three working load categories

for cable

trays

as 50,

75 and

100 lbs. per linear foot.

The cable tray supplier

used

35 lbs. per foot as allowed

by an engineering

change

in the specification.

Engineering

justification, however, for deviating from the

NEMA document

was not

available'E1-4.01,

paragraph

B, states,

in part, that:

"test

spans

shall

be simple

beam

spans with free unrestrained ends....."

I

~

p

4

32

VE1-4.01, paragraph

0, states,

in part, that:

$"Each end

of the

specimen

shall

be supported

by a

1 1/8 inch wide by

3/4 inch high steel

bar(s) with a

120 degree

"Vee" notch

cut in its bottom to a depth of 3/16 inch.

The "Vee" notch

shall rest

on

a I inch solid round steel

bar which is

welded

~ ~ ..."

Sketch

No. 86, of the Test Report

No.

24781 illustrates

a

different test mounting configuration

used for the static

load test of the cable tray specimen.

The sketch

shows

two

illustrations of cable tray specimens,

one bolted and the

other clamped,

both in the horizontal position

on

an "H"

type unistrut frame.

Pg 2-2a of specification

E026-A, states

in part, that:

"...base

natural

frequency of cable tray shall

be determined.

Vertical fundamental

frequency shall

be above

20 cps,

verified by calculations

using the stiffness data obtained

during the performance

of vertical loading and horizontal

tests

specified.

~ ."

Since the tray specimen static load data

was obtained

from

tray specimens

that were bolted/clamped

in position,

the

stiffness data obtained is much higher than would have

been obtained if the test were performed

as specified,

thus affecting the calculation

used in verifying the >20

cps frequency requirements.

On page

C-10,

item (3) of the qualification test Report

No.'24781,

the supplier states,

in part, that:

"...we

will use only unspliced straight sections

for frequency

tests

since splice plate fittings give erroneous results."

Item (f), same

page of test Report

No. 24781.

The supplier

indicated that since past experience

has

shown that fittings

were weakest in the vertical direction, they intended only

to conduct the seismic tests

on the horizontal

elbow.

Item (h),

same

page of test Report

No.

24781 the supplier

states:

"...frequency tests

conducted without hold clamps

on trays."

The review document

(BK7801270015) of the suppliers technical

document

shows engineering

approval

as defined by the

specification.

It appears

that the supplier was unable to meet the original

requirements

and is performing tests

which do not meet

minimum

commercial

standards

as specified in

NEMA VE-l. In addition,

engineering justification for the less restrictive tests

was

not available.

~

f

4

33

The licensee

was informed that this is an item of noncompliance

and

an infraction of 10CFR50 Appendix B, Criterion VII, which

states,

in part, that:

"Measures

shall

be established

to

assure

that purchased

material,

equipment

and

services'

..

conform to the procurement

documents."

(410/81-13-04)

>

ualification of Su

liers

The inspector verified that the licensee

has established

procedures

for the selection of qualified suppliers of services,

materials

and components

and that the established

procedures

are being implemented.

S ecification Review

The inspector

reviewed specification

No.

P281F for Category I

and II Radiation Monitoring Equipment to determine whether the

procurement

document contains applicable technical

and

QA

requirements

necessary

in meeting

NRC licensing requirements

and

SAR commitments.

The inspector questioned

the adequacy of

the Category

1 Radiation Monitoring Equipment in meeting the

sensitivity detection

requirements

of 10 CFR 20, Appendix B,

and Regulatory

Guide 1.45.

It appears

that the Radiation

monitors containing

two or more channels

are of the series

type.

This implies that the

sample flow rate through the

systems

would be the

same.

Published data,

however,

indicates

that particulate

and gaseous

radiation monitors require

a high

flow rate (8-10 cfm) to meet sensitivity detection

requirements

and

a low flow rate (1-2 cfm), for iodine detection

due to

absorption charactistics

of the charcoal cartridge.

In addition,

criteria for installation of the Radiation Monitoring Equipment

were not defined.

Since the Radiation Monitoring function is

dependent

upon obtaining

a representative

sample, installation

of the

sample line should

be compatible with the equipment

being installed.

Discussions with the licensee

indicates

the

P281F specification

has

been withdrawn and that

a

new specification

is being drafted which addresses

the inspectors

concerns.

-The

inspector

had

no further questions

at this time.

Detection of Reactor Coolant

Leaka

e

The inspector

reviewed section 5.2.3.12 of the

PSAR on Primary

Containment

Leakage Monitor System

and section H.3.13 of Appendix

H on Containment

Atmosphere Monitoring.

10 CFR 50, Appendix A,

Criterion 30 requires that means

be provided for detecting

reactor coolant leakage.

Regulatory Guide 1.45 provides the

minimum acceptable

method for detecting reactor coolant leakage.

The guide states

that one of two required

methods

shall

be by

Radiation Monitor of a sample.

No such provisions

have

been

made in the

NMP 2 design.

The licensee

has not taken

a position

on implementation of Regulatory Guide 1.45 or its equivalent.

4

h

~

+

4

34

This is an unresolved

item in that

an acceptable

method of

meeting

10 CFR 50 Appendix

A requirements

has not been

implemented

to date.

(410/81-13-05)

5.1.8

Cable Tra

S acin

The inspector

noted that the licensee's

response

to

NRC question

R8.9, listed in section

8 of the

PSAR supplement

6 requires

some clarification.

Section 6.2.3,

paragraph

3 of the response

states,

in part:

"As a minimum, where vertical stacking of trays...at

least

12

inches will be maintained

between

top of tray below and the

bottom of tray above.

~ .."

Section 6.2.3 paragraph

6 of the

response

states,

in part:

"... In tray crossovers

at least

an

18 inch clear

space

shall

be maintained...."

Section 8.1.1 of the response

states,

in part:

"... In general,"

the minimum vertical

spacing for cable trays wi 11

be

17 inches,

measured

between

cable tray bottoms for trays with an inside

depth of 4 inches

and

16 inches for trays with an inside depth

of 3 inches."

Electrical Specification

E061A specifies

a

12 inch clearance

space

between trays.

6.0

The response

contains conflicting space

separation

requirements

for vertical stacking of trays.

The licensee

response

indicates that design control measures

have not been

implemented for verifying or checking the adequacy

and consistency

of design criteria.

Specified criteria were

not included in the erection specification.

This is an additional

example of noncompliance

with the

requirements

of 10 CFR 50, Appendix B, Criterion III

(410/81-13-02).

Electrical

The objective of this part of the inspection

was to observe

work performance, partially complete work and/or completed work

as appropriate,

associated

with the emergency

(standby) diesel

generator

and the motor control centers

to determine

whether

the requirements

of applicable specifications,

work procedures

and inspection

procedures

are being accomplished

in accordance

with NRC requirements

and licensee

commitments.

6.1

Areas Ins ected

4

EV

35

6.1.1

E ui ment Stora

e In-Place

The inspector

examined

the control of equipment stored-in-place

foi post-installation protective requirements,

physical protective

barriers,

protection

against

condensation

and surveillance

activity.

6.1

~ 2

No. items of noncompliance

were identified.

Receivin

and Stora

e Documentation

The inspector

reviewed receiving documentation,

certificate of

compliance,

documentary

evidence of tests

performed

and

surveillance

records of equipment identified above.

The inspector

found the documents

to be legible, easily retrievable

and

current.

6.1.-3.

No items of noncompliance

were identified.

Stora

e Faci lit

7.0

The inspector

examined

the level

A and level

B storage facility.

The records confirm that the equipment is stored

in the proper

area,

the inspection activity is performed

as required

and the

required protection

has

been provided.

No items of noncompliance

were identified.

Mechanical

and

NDE

7.1

Previous

0 en Items

7.1.1.1

Cl osed

Unreso 1 ved Items

80-04-01

and

80-04-02

These

unresolved

items concern clarification of the criteria to

be used for the disposition of ultrasonic indicat'ions reported

in tests

conducted

on inner wall, cover plate

and stiffener

welded junctions in the biological shield.

The metallurgical

studies

which were incomplete at the time of issuance

of 80-04-01

were reviewed by the

NRC inspector

and are

summarized

in

S8W

Report "Final Report

on Biological Shield Mall Nine Mile Point

Nuclear Station Unit 2" forwarded to

NMPC on 8/1/80 (9M2-8844).

Detailed finite element

( FE) analyses

and linear elastic fracture

mechanics

(LEFM) analyses

were conducted

on each type of suspect

welded joint in the biological shield with results indicated in

the aforementioned

document.

The engineering disposition of

the ultrasonic indications

was based

on the calculated

FE and

LEFM acceptable

defect sizes.

Engineering evaluation of defect

sizes for acceptance

purposes

is an acceptable

practice for AMS

Dl.l structures.

These

items are considered

resolved.

J

<) ~

36

7.1.1.2

Closed

Unresol ved Item

81-09-01

This item concerned

the demonstration

of the adequacy

of a

complete

composite joint for safety related

attachment

welds

made to the bioshield which includes

a weld overlay on the

bioshield wall.

The licensee

has committed

S&W to conduct

an

engineering

evaluation

weld mockup test assembly

as specified

in

E&DCR F10525.

S&W and

NMPC has committed to answer

concerns

raised in inspection report 50-410/81-09,

paragraph

8(b) concerning

inadequacies

in the

CB&I MPS E70T-1

(B-U3-GF)/13640 by revision

to the

MPS.

The subject inspection report erroneously

reported that the

filler metal certification for the

E70T-1 utilized 100% Argon

where iq .fact. the test. was conducted with 100% C02.

This item

'is- considered

resolve~

b-sed- on the licensee's-

commitments.>>

7.1.1.3

Closed

50.55

e

Item

79-00-01

This item was previously discussed

in inspection reports

79-09,

81-09

and 81-12.

Inspection report 81-09 indicated resolution

of 7 of the

8 items (weld joint configurations).

The instrument

penetration-adaptor

to sleeve

welds could not be resolved

due

to the lack of availability of UT examination

records for the

sampling

UT tests

conducted.

Discussions with the licensee

and

review of documents

indicated that

no

UT records of the examination

were available

due to the generation

of spurious reflector

signals

caused

by the special

geometry including

a combination

of small diameter,

thin wall and dissimilar metal welds.

The

reflectors

negated

proper evaluation of the data

and full

compliance with ASME Code

UT inspection

requirements.

Engineering

review of the

ASME Code requirements

indicated that

UT was not

a code acceptance

requirement for the'configurations

welded.

The

NRC inspector

reviewed calculations

and the design requirements

for the joints.

This data indicated that,

in addition to the

code required safety factors,

the actual

weld size resulted

in

a multiplier factor of 2 or more for all but two joints (3.5"

diameter).

For the 3.5 inch weld joints, the additional

safety

factor multiplier is approximately 1.3.

These

two joints were

given

a verification

PT examination

as witnessed

by the

NRC

inspector

and reported in

S&M PIT00068 which showed

no indications.

No further response

is required.

This item is considered

to be

closed.

7.2

7.2.1

d~ld

Visual Observation

of Weldin

The following welds were visually inspected

by the

NRC inspector

including review of ISO drawings

and the welding documentation:

4'

) IP

~

P

(

,~~~.~P.k.CI 4-)V[()P V1 1379lil';,fl~)'~ "f

37

~Drawin

Material

Code

a.

ISO 25-13,

FW007

P8-P8

B31.1

CSH

10" x 0.365

b.

ISO 66-7,

FW003

Pl-Pl

III-2

RHS

12" x 0.375

c.

ISO 66-42,

FW014

Pl-Pl

III-2

RHS

6" x 0.280

The preparation for purge, joint fitup and the

SMAW portion of

weld a were observed.

During the

SMAW welding, the

NRC inspector

observed

a tong meter check of welding amperage.

This weld was

on the B31.1 side of the B31.1/ASME Class

2 breakline of

25-13-2-CSH-7-4-8.

7.2.2

Welds

b and

c were visually inspected

in the final

ground-for-RT condition.

Both of these

welds were rejected

on

RT.

The repair cycle has not been

implemented at the time of

the inspection.

The weld da'ta

sheets

for the original welds

were reviewed along with the filler metal requisition

forms.

The finished ground weld 'configuration 'for ISI inspection

was

a flush geometry rather

than

a flat top geometry.

No items of noncompliance

were identified.

Weldin

Material Control

The

NRC inspector

reviewed the

S&W filler metal control

specifically at the issue station.

The procedures

for purchasing,

receiving, storing

and distribution to the issue station

were

previously reviewed

and re-reviewed at this time.

The

identification, storage

and control in accordance

with procedures

was reviewed.

The procedures

for controlling moisture in

hydroscopic filler metals

were reviewed.

It was Inot~ed that,

with the exception of one can of filler metal held for turbine

pipe welding, the only carbon

on low alloy steel

SHAM filler

metal in the issue station

was

E7018.

7.3

No items of noncompliance

were identified.

Documents

Reviewed

Interoffice correspondence

G.

Phi lippi to C. Eri ksson

and

reply by Eriksson dated

December

4,

1981 regarding

clarification of "numerous indications"

as quoted in C.

Eriksson letter to P.

M. Mcguaid dated

September

10,

1981

on

UT evaluation

examination of penetrations.

S&W Project

Memo

(NMP 2)

PM70

Rev

1 dated

February

17,

1981.

D.

P.

Pope

Report to

S&W, "Horizontal Stiffener to Inner

Shell Wall," dated

February,

1980.

<<s

g A

38

D.

P.

Pope

Report to

SKW, "Horizontal Stiffener to Inner

Shell Wall," dated April, 1980.

Dr.

C.

Mel Adams letters to K. Ward dated

March 23,

1980 and

April 28,

1980.

SEW Metallurgical Report,

NMP2, Unit 2, "Biological Shield

Wall Base

Ring to Outer Shell Weld," dated January,

1980.

Teledyne

Engineering

Services

(Waltham, Mass.) Technical

Report TR-4250-1

dated

May 15,

1980,

"Cause,

Repair

and

Engineering

Assessment,

of Weld Failures in the Biological

Shield Wall for NMP 2."

C.

C. Zappi le to C.

D. Terry letter 9M2-1,453, dated

December

10,

1981,

"Primary Containment

Instrument Penetrations

NRC

IE Inspection

81-12

NMP Nuclear Station

Unit 2."

8.0

Unresolved

Items

Unresolved

items are matters

about which more information is required to

ascertain

whether they are acceptable

items,

items of noncompliance,

or

deviations.

An unresolved

item disclosed during the inspection is discussed

in Section 5.1.7.

9.0

Exit Interview

The inspectors

met with the licensee

representatives

(denoted

in Section

1)

at the conclusion of the inspection

on December

11,

1981

and December

18,

1981 at the Nine Mile Point Unit 2 construction site 'and Syrocuse

corporate

offices respectively.

The inspectors

summarized

the

scope of the inspection

and discussed

the inspection findings.

/

'I I