| Site: | Nine Mile Point |
| Issue date: | 05/26/1981 |
| From: | Martin T NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Lempges T NIAGARA MOHAWK POWER CORP. |
| Shared Package | |
| ML17053C676 | List: |
| References | |
| NUDOCS 8106160620 | |
| Download: ML17053C675 (4) | |
See also: IR 05000220/1981009
Text
~ ~q Rangy,
o
~y
0O
I
I
3a
I
lq
0
Docket No. 50-220
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION I
631 PARK AVENUE
KING OF PRUSSIA, PENNSYLVANIA19406
Niagara
Mohawk Power Corporation
ATTN:
Mr. T.
E.
Lempges
Vice President
Nuclear Generation
300 Erie Boulevard West
Syracuse,
13202
Gentlemen:
MAY 8 6
1981
IeFILCCap>V
'
.~~<~llQ "
CD~ R
4(/gg4~
8
~%
q~s
Subject:
Inspection
50-220/81-09
P
This refers to the routine safety inspection
conducted
by Mr.
R. A. McBrearty of
this office on April 20 - 23,
1980 at Nine Mile Point Unit
1 Nuclear Generating
Station, Scriba,
New York of activities authorized
by
NRC License
No.
and
to the discussions
of our findings held by Mr. McBrearty with Mr. T. J.
Perkins
of your staff at the conclusion of the inspection,
and to a subsequent
telephone
discussion
between
Mr. F. Hawksley of your staff and Mr. McBrearty on April 29,
1981
and between
Mr. T. J.
Perkins of your staff and Mr. McBrearty on May 4,
1981.
Areas
examined during this inspection
are described
in the Office of Inspection
and Enforcement
Inspection
Report which i s enclosed with thi s letter.
Within
these
areas,
the inspection consisted
of selective
examinations of procedures
and representative
records,
interviews with personnel,
and observations
by the
inspector.
Within the
scope of this inspection,
no items of noncompliance
were observed.
In accordance
with 10 CFR 2.790 of the Commission's
regulations,
a copy of this
letter and the enclosed
inspection .report will be placed in the NRC's Public
Document
Room.
If this report contains
any information that you (or your con-
tractors) believe to exempt from disclosure
under
10 CFR 9.5(a)(4), it is necessary
that you (a) notify this office by telephone within ten (10) days
from the date
of this letter of your intention to file a request for withholding; and (b)
submit within 25 days from the date of this letter
a written application tb this
office to withhold such information.
Consistent with section 2.790(b)(1),
any
such application must be accompanied
by an affidavit executed
by the owner of
the information which identifies the document or part sought to be withheld,
and
which contains
a full statement
of the reasons
on the basis which it is claimed
that the information should
be withheld from public disclosure.
This section
further requires
the statement
to address
with specificity the considerations
listed in 10 CFR 2.790(b)(4).
The information sought to be withheld shall
be
incorporated
as far as possible into
a separate
part of the affidavit. If we do
not hear from you in this regard within the specified periods
noted above,
the
report will be placed in the Public Document
Room.
The telephone notification
"~
Niagara
Mohawk Power Corporation
~
~
of your intent to request withholding, or any request for an extension
of the
10 day period which you believe necessary,
should
be
made to the Supervisor,
Files Mail and Records,
USNRC Region I, at (215) 337-5223.
No reply to this letter is required;
however,
should you have
any questions
concerning this inspection,
we will be pleased
to discuss
them with you.
Sincerely,
Thomas
T ~ Martin, Chief, Engineering
Inspection
Branch, Oivision of
Engineering
and Technical
Inspection
Enclosure:
Office of Inspection
and Enforcement
Inspection
Report
Number 50-220/81-09
cc w/encl:
M. Silliman, Acting General
Superintendent,
Nuclear Generation
T.
Roman, Station Superintendent
R. Abbott, Operations
Supervisor
E.
B. Thomas, Jr.,
Esquire
1