UNITEDSTATES NUCLEAR REGULATORYCOMMISSION WASHINGTON, D. C. 20555 SAFETY 'VAL'VATION'Y THE OFFICE 'OF 'NUCLEAR 'REACTOR 'REGUL'ATION SUPPORTING AMENDMENT NO. 26 TO LICENSE NO.
DPR-63 NIAGARA MOHAWK POWER CORPORATION NINE MILE POINT NUCLEAR STATION UNIT NO.
1
'DOCKET NO: 50-'220 INTRODUCTION In conjunction with the Short Term Program (STP) evaluation of Boiling Water Reactor facilities with the Mark I containment
- system, Niagra Mohawk Power Corporation (the licensee) submitted a Plant Unique Analysis (PUA) for the Nine Mile Point Nuclear Station Unit No. l.
This analysis was performed to confirm the structural and functional capability of the containment suppression chamber and attached
- piping, to withstand newly-identified suppression pool hydrodynamic loading conditions which had not been explicitly considered in the original design analysis for the plant.
As part of the STP evaluation, specific loading conditions were developed for each Mark I facility, to account for the change in the magnitude of the loads due to plant-specific variations from the reference plant design for which the basic loading conditions were developed.
I The results, of the NRC staff's review of the hydrodynamic load defini-tion techniques and the Mark I containment plant unique analyses are described in the "Mark I Containment Short Term Program Safety Evalua-tion Report,"
NUREG-0408, December 1977.
As discussed in this report, the NRC staff has concluded that each Mark I containment system would maintain its integrity and functional capability in the unlikely event of a design basis loss-of-coolant accident (LOCA) and, therefore, that licensed Mark I BWR facilities can continue to operate safely, without undue risk to the health and safety of the public, during an interim period of approximately two years, while a methodical, comprehensive Long Term Program is conducted.
As discussed in Section III.C of NUREG-0408, of all of the plant para-meters that were considered in the development of the hydrodynamic loads for the STP, only two parameters are expected to vary during normal plant operation; these are (1) the drywell-wetwell differential pres-sure; and (2) the suppression chamber (torus) water level.
Subsequent to the submittal of the PUA, the licensee was requested to submit proposed Technical Specifications which assure that the allowable range F90 2260 15'
1
'e
of these two parameters during facility operation would be in accordance with the yalues utilized in the'PUA.
The licensee has been operating this facility with differential pressure control to enhance the safety'margins of the containment structure since early 1976.
This evaluation provides'a more
'etailed basis for establishing the allowable range of drywell-wetwell differential pressure and torus water level, in order to quantify containment safety margins.
This amendment incorporates these parameters into the Technical Specifications with the associated limiting conditions for operation and surveillance requirements.
By letters dated May 19 and May 25, 1977, the licensee proposed changes to the facility Technical Specifications to incorporate limiting conditions for operation and surveillance requirements for differential pressure control and torus water level.
Our evaluation of these proposed changes follows.
II.
'EVAL'UATION The licensee has proposed certain Technical Specification requirements for the purpose of assuring that the normal plant operating conditions are within the envelope of conditions considered in their PUA.
These Technical Specification changes establish (1) limiting condition for operation (LCOs) for drywell to torus differential pressure and torus water level, and (2) associated surveillance requirements.
All other initial conditions utilized in the PUA are either presently included in the Technical Specifications or are configurational conditions which have been confirmed by the licensee and will not change during normal operation.
Differential pressure between the dryweil and the suppression chamber will result in leakage of the drywell atmosphere to the lower pressure regions of the reactor building and to the torus air space.
This leakage from the drywell will cause a slow decay in the differential pressure.
Therefore, surveillance requirements for the differential pressure have been included in the Technical Specifications.
Surveillance frequency of once per operating shift for the differential pressure was selected on the basis of previous operating experience.
The torus water level is not expected to vary significantly during normal operation, unless certain systems connected to the suppression pools are activated.
The torus water level would normally be monitored.
whenever such systems are in use.
Therefore, we find that inclusion of periodic torus water level surveillance requirements in the Technical'pecifications is not required.
Me have reviewed the differential pressure and torus water level monitoring 'instrumentation systems proposed by the licensee with regard to the number of available channels and the instrumentation accuracy.
'This type of instrumentation is typically calibrated at six-month intervals.
To assure proper operation during such intervals, two monitoring channels for both differential pressure -and torus water level have been provided, such that a comparison of the readings will indicate when one of the channels is inoperative or drifting. The errors in the instrumentation are sufficiently small relative to the magnitude of the measurement (i.e.,
a maximum differential pressure measurement error of 0.1 psid in a measurement of 1.0 to 2.0 psid and a maximum torus water level measurement error of 10%, of the difference between the maximum and minimum torus water level) that they may be neglected, based on the expected load variation with differential pressure and torus water level.
There are certain periods during normal plant operations when the differential pressure control cannot be maintained.
Therefore, pro-,
visions have been included in the Technical Specifications to relax the differential pressure/control requirements during specified periods.
The justification.for relaxing the differential pressure control during these specific periods and the basis for shlecting the duration of the periods are discussed in detail below.
A.
Startu and Shutdown During plant startup and shutdown, the drywell atmosphere undergoes significant barometric changes due to the variation in heat loads from the primary and auxiliary systems.
In addition, it is during these periods that the drywell is being either inerted with nitrogen gas or deinerted.
In order to keep the periods during which the differential pressure control is not fully effective as short as reasonable, we have limited the relaxation of the differential pressure control requirements
.for the startup and shutdown periods to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> following startup and 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> prior to a shutdown.
This time period was selected on a basis similar to that for the inerting requirements, already existing in the Technical Specifications.
The postulated design basis accident for the contairment assumes that the primary system is at operating pressure and temperature.
During the startup and shutdown transients, the primary
system is at operating pressure and temperature for only a part of the transient, during which the differential pressure is being'stablished.-
'These time periods have been'shown'by previous operating experience to be adequate with respect to the'startup and shutdown transients, and at the same time sufficiently small in comparison to the duration of the average power r'un.
'Since the principal accident event to which differential"pressure control is important to assure containment integrity (i.e., with a factor of safety of two) is a large break LOCA, we have considered whether there is a significantly greater probability of a large break LOCA during the startup and shutdown transients.
We have concluded that there is not.
- Further, the operation of the plant:systems is monitored more closely than normal during these periods and a finite magnitude of differential pressure will be available during the majority of these periods to mitigate the potential consequences of an accident.
B.
Testin and'Maintenance During normal operation, there are a number of tests which are required to be conducted to demonstrate the continued functional performance of engineered safety features.
The testing of certain systems will require, or result in, a reduction in the drywell-torus differential pressure.
The operability testing of the drywell-torus vacuum@ breakers requires the removal of the differential pressure to permit the vacuum breakers to open.
For the testing of high-energy systems (e.g.
high pressure coolant injection pumps) during normal operation, the discharge flow is routed to the suppression pool.
This energy deposition will raise the temperature of the suppression pool, resulting in an increase in torus pressure and a reduction in the differential pressure.
Functional performance testing of engineered safety features is necessary to assure proper maintenance of these systems throughout the life of the plant.
Some of these tests (i.e.,
pump operability and drywell-wetwell vacuum breakers) may require or result in a reduction in the differential pressure.
We estimate that not more than four tests will be required each month which will result in a reduction in differential pressure.
In order to keep the periods during which the differential 'pressure control is not fully effective as short as is reasonable, we have permitted a
relaxation of differential pressure control in order to conduct these
- tests, limited to a period of up to four hours.
- Again, we have carefully considered whether the probability of a large LOCA is significantly greater during these testing periods than that during normal operation.
We conclude that it is not.
Moreover, only the test of the drywell-wetwell vacuum breakers requires complete removal of the differential pressure.
Provisions have also been included in the Technical Specifications for performing maintenance activities'on the differential pressure control. system and for resolving operational difficulties'which may result in an inadvertent reduction in the differential pressure for a short period of time.
'In certain circumstances, corrective action can be taken without having to attaina cold shutdown condition.
To avoid repeated and unnecessary partial cooldown cycles, a restoration period has been incorporated into the action requirements of the LCO for differential pressure control; i.e
,.in the-event that the differ-ential pressure cannot be restored in six hours, an orderly shut-down shall be initiated and the reactor shall be in a cold shutdown condition within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
The six hour restoration period was selected on the basis that it represents an adequate minimum period of time dur ing which any short-term malfunctions could be corrected, coupled with the minimum period of time required to conduct a controlled shutdown.
The allowable time to conduct a controlled shutdown has been minimized, because the containment transients response is more a function of the primary system pressure than the reactor power level.
On this
- basis, we find the proposed restoration period and action requirement acceptable.
We conclude that the limits imposed on the periods of time during which operation is permitted without the differential pressure control fully effective provides adequate assurance of overall containment integrity, and the periods of time differential pressure control is completely removed are acceptably small.
ENVIRONMENTAL CONSIDERATION We have determined that the amendment does not authorize a change in effluent types or total amounts nor an increase in power level and will not result in any significant environmental impact.
Having made this determination, we have further concluded that the amendment involves an action which is insigni-ficant from the standpoint of environmental impact and, pursuant to 10 CFR Section 51.5(d)(4), that an environmental impact statement or negative declaration and environmental impact appraisal need not be prepared in connection with the issuance of this amendment.
CONCLUSIONS The proposed Technical Specifications will provide the necessary assurance that the plant's operating conditions remain within the envelope of the conditions assumed in the Plant Unique Analysis (PUA) performed in conjunction with the Mark I Containment Short Term Program.
The PUA supplements the
facility's Final Safety Analysis Report (FSAR) in that it demonstrates the plant's capability to-withstand the. suppression pool hydrodynamic loads which were not explicitly considered in the'FSAR.
'We therefore conclude that the proposed changes to the'Technical Specifications are acceptable.
We further conclude, based on the considerations discussed above,'that (1) because the amendment does not involve a significant increase in the probability or consequences of accidents previously considered and does not involve a significant decrease in a safety margin, the amendment does not involve a significant hazards consideration, (2) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed
- manner, and (3) such'activities will be conducted in compliance with the Coomission's regulations and the issuance of this amendment will not be inimical to-.the common defense and security or to the health and safety of the public.
pate:
January 29, 1979