7 to Updated Final Safety Analysis Report, Chapter 14, Table 14.3.2-2, Time Sequence of Events for Small Break Loss-of-Coolant Accident
ML16343A142
Person / Time
Site: Cook  
Issue date: 10/24/2016
From:
Indiana Michigan Power Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML16336A263 List: ... further results
References
AEP-NRC-2016-42
Download: ML16343A142 (1)


Text

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revision: 25.0 Table: 14.3.2-2 Page:

1 of 1 Unit 1 Last Revised: Revision 25.0 Time Sequence of Events for Small Break Loss-of-Coolant Accident Event Time (sec) 1.5-inch 2-inch 2.5-inch 2.75-inch 3.0-inch 3.25-inch 3.5-inch 3.75-inch 4.0-inch 6.0-inch 8.75-inch Break Initiation 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Reactor Trip Signal 89.8 45.9 27.9 22.7 19.0 16.2 14.0 12.3 10.9 6.0 4.5 S-Signal 112.8 60.9 38.2 31.6 26.8 23.2 20.3 17.9 15.7 8.4 6.7 SI Flow Delivered(1) 166.8 114.9 92.2 85.6 80.8 77.2 74.3 71.9 69.7 62.4 60.7 Loop Seal Clearing(2) 2492 1341 857 628 516 445 386 390 302 146 30 Core Uncovery(4)

N/A 1897 1027 1017 963 780 664 630 602 342 N/A Accumulator Injection N/A N/A 3065 2129 1707 1264 1031 940 823 345 168 (3)

RWST Volume Delivered(5) 2165.6 2157.6 2145.4 2137.8 2130.0 2120.9 2114.4 2110.2 2106.4 2042.8 1590.7 PCT Time (BOL)

N/A 968.4 1433.4 1452.5 1584.0 1725.0 1705.3 1517.9 1411.2 670.6 N/A Core Recovery (4)

N/A 6663 4032 4081 3977 3840 3973 4110 3404 423 N/A Notes:

(1) SI is assumed to begin 54.0 seconds (SI delay time) after the S-Signal.

(2) Loop seal clearing is assumed to occur when the steam flow through the broken loop, loop seal is sustained above 1 lbm/s.

(3) For 8.75-inch break, accumulator injection begins for Loops 2-4 only; Loop 1 (broken loop) accumulator line is the location of the break and assumed to spill to containment.

(4) The latest point of sustained core uncovery/recovery is reported.

(5) The analysis assumes minimum usable RWST volume (280,000 gal) delivered via ECCS injection and containment spray before the low level RWST water level signal for switchover to cold leg recirculation is reached.