ML16342D680

From kanterella
Jump to navigation Jump to search
Insp Repts 50-275/97-01 & 50-323/97-01 on 970414-0502. Violations Noted.Major Areas Inspected:Review of Licensed Operation Requalification Program,Submitted Draft Initial Licensed Operator Exam & Followup to Open Items
ML16342D680
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 05/29/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML16342D679 List:
References
50-275-97-01, 50-275-97-1, 50-323-97-01, 50-323-97-1, NUDOCS 9706040094
Download: ML16342D680 (42)


See also: IR 05000275/1997001

Text

ENCLOSURE 2

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket Nos.:

License Nos.:

Report No.:

Licensee:

Facility:

Location:

Dates:

Inspectors:

Accompanying

Personnel:

Approved By:

50-275

50-323

DPR-80

DPR-82

50-275/97-01

50-323/97-01

Pacific Gas and Electric Company

Diablo Canyon Nuclear Power Plant, Units

1 and 2

7 1/2 miles NW of Avila Beach

Avila Beach, California

April 14 through May 2, 1997

T. O. McKernon, Lead Inspector, Operations

Branch

T. R. Meadows, Reactor Engineer, Operations Branch

H. F. Bundy, Reactor Engineer, Operations

Branch

M. E. Murphy, Reactor Engineer, Operations Branch

M. S. Freeman,

Inspector-in-Training

D. B. Allen, Resident Inspector-in-Training

J. L. Pellet, Chief, Operations

Branch

ATTACHMENTS:

Attachment 1:

Supplemental

Information

Attachment 2:

Simulator Facility Report

97060400'P4

97052'7

PDR

ADOCK 05000275

8

PDR

-2-

EXECUTIVE SUMMARY

Diablo Canyon Nuclear Power Plant, Units

1 and 2

NRC Inspection Report 50-275/97-01; 50-323/97-01

This multi-focused inspection included

a review of the licensed operator requalification

program;

a review of a submitted draft initial licensed operator examination,

a followup to

open items, and sustained

observations

of control room activities, and Unit

1 outage

control activities.

The inspection covered the period from April 14 through May 2, 1997.

~Oerations

Inspectors observed

good control room coordination between the shift foreman and

'he other shift crew members.

Good linkage between the shift foreman and the

senior control operator was observed

during abnormal condition response

(Section 01.4).

Inconsistent linkage between the shift foreman and the senior control operator was

observed

during some requalification examinations,

contrary to the performance

observed

in the control room.

This remains an issue warranting licensee

management

attention.

This issue, also identified by licensee evaluators resulted in

crew and individual failures of the requalification examination and remediation

(Section 04.1).

Although not firmly established,

the control room staff practiced three-way

communications

(Section 01.4).

Inspectors observed

some inconsistent oversight of the shift crews by the shift

supervisors

(Section 01.4);

Overall, the licensed operator requalification program was acceptable

(Section 04.1).

I

Licensed operator requalification examinations

were well constructed,

challenging,

and discriminated at the appropriate knowledge levels (Section 05.2).

Inspectors observed

professional

and consistent performance

on the part of licensed

operator requalification evaluators.

Evaluators conducted

good critiques of the

crews and individual strengths

and weaknesses

were effectively identified.

(Section 05.3).

The remedial t.aining program was adequate

',Section 05.4)

An apparent violation of Technical Specification with two examples related to the

respiratory protection program was identified (Section 05.5).

-3-

A submitted draft initial licensed operator examination was considered

inadequate

for administration,

in that, portions of the operating test were narrower in scope

than the guidance provided in NUREG-1021 (Section 05.1).

Re ort Details

Summar

of Plant Status

Unit 1 entered Refueling Outage

1RS.

Major work activities included valve repairs on the

residual heat removal system,

Diesel Generator

1-3 maintenance,

testing, and replacement

of the station batteries, Charging Pump

1-1 maintenance

and replacement,

and others.

Unit 2 remained at 100 percent power during this inspection period.

No major equipment

problems or transients were experienced.

I. 0 erations

01

Conduct of Operations

01.4

Conduct of 0 erations

- Extended Control Room Observations

Ins ection Sco

e 71715

During the period of April 28 to May 1, 1997, independent

observations

of control

room activities were conducted with a focus on the Unit

1 outage activities.

The

objective of the observations

was to evaluate control room performance

by the

operators, crew command and control, communication practices, work control, and

procedure

usage.

The inspectors

observed

a number of outage management

meetings, control room shift briefings, prejob briefings, shift turnover briefings,

annunciator acknowledgments

and responses,

surveillance tests, and conducted

interviews with selected

key personnel.

b.

Observations

and Findin s

Overall, communications

were effective, but the application of formal three-way

communications was inconsistent.

Three-way formal communications was a recent

management

expectation

and it was apparent that its use was not yet firmly

established

in the control room staff.

Quite often, the receiver of the instructions

had to be prompted to repeat them back and, in other instances,

the communication

lapsed into informal practices.

For example, during initial fuel assembly removal,

the operator in the control room and the communicator on the refueling floor in the

containment

had difficulty communicating the requirement for the fuel upender

machine to be secured

prior to the fuel handlers on the refuel bridge grappling

another fuel assembly.

This confusion appeared,

in part, due to not completing the

third leg of the three-way communications.

At other times, the control room staff

-5-

did utilize three-way communications effectively when giving task instructions to

plant personnel

and reporting critical information.

The inspectors

also heard plant

operators employ proper three-way communications

on the plant radios.

Despite

the lapses

in communication practices, communications

by the licensed operators

was improved over that observed

during the prior year's requalification program

inspection.

Shift management

oversight of activities in the control room was effective.

There

was good linkage between the shift foreman, other members of the shift crew, and

responsible test engineers.

The senior control operator and shift foreman

demonstrated

good linkage during observed

abnormal situations.

For example, at

one point during fuel movement

a containment e'vacuation

alarm annunciated

at the

same time an area high radiation alarm and a smoke detector alarm annunciated.

The operators

responded

promptly to the alarms under the direction of the shift

foreman.

The reasons for the alarms were promptly identified and plant

announcements

made.

Additionally, during a medical emergency

in containment

and a flooding event in the auxiliary saltwater intake structure caused

by leaking

check valves, the situations were properly evaluated

by control room personnel

and

appropriate instructions were provided to field personnel.

Proper public address

announcements

were made to alert plant personnel to the events

in progress.

Appropriate briefings between control room personnel

and technicians were

conducted

prior to commencing plant work activities, which could impact plant

safety.

The inspectors witnessed

a briefing conducted

by the shift foreman, which

related to manipulating relays in energized

13.8 kV breaker enclosures.

The work

activity and potential effects on plant electrical distribution, as it related to the

outage safety plan, were discussed

in detail.

Briefings on other important work

activities, which were not expected to have a direct effect on plant safety, were

appropriately conducted

by the assistant shift foreman.

Routine work activities for plant operators were effectively controlled.

The

inspectors witnessed assignment

of an activity involving cross-tying emergency

diesel generator

air compressors.

The sequence

of the work activities and the

appropriate procedure steps were properly specified.

The performer demonstrated

his understanding

of the task by repeating the instructions.

For the outage unit, shift turnover began

an hour prior to shift change.

The

inspectors observed that logs and turnover checklists were properly reviewed and a

comprehensive

control board walkdown was performed by the oncoming operator

accompanied

by the offgoing operator.

Prior to assuming the watch, the oncoming

crew conducted

an all hands meeting.

Crew members summarized the status of

equipment under their jurisdiction and expected work activities.

The operations

liaison to the outage control center also provided an overview of outage work status

and expected outage work for the upcoming shift. The overall information

exchange

was effective and all crew me~nbers were cognizant of their

responsibilities.

0-

-6-

The inspectors attended

outage control center critical activities and shift turnover

meetings.

The operations

liaison provided appropriate input on plant operational

considerations

as they affected scheduled

work. All participants demonstrated

appropriate concern for plant operational and safety considerations.

Operations personnel exhibited heightened

sensitivity to previous problems with

ground buggy installation on major electrical equipment.

The inspectors observed

restoration of Engineered

Safety Feature

Bus F.

An operator and th

shift technical

advisor performed

a deliberate walkdown prior to energizing the bus where they

checked for proper fuse alignment, ground buggy installation and door bolting.

The

inspectors discussed

the transformer explosion from the previous outage with

several operators

and the shift foreman.

All were well aware of the causes

and

how improper ground buggy installation contributed to the event.

Peer checking was used on control panel manipulations.

The inspectors observed

the unloading portion of the overspeed

test on Emergency Diesel Generator

1-3.

This'was performed in accordance

with Procedure

STP M-9B, "Overspeed Trip Test

of Diesel Generators,"

Revision 17.

During the evolution, control room operators

self-checked

and peer-checked

each step of the procedure

as it was performed.

The peer-checker

read the procedure

and verified the operator was performing the

steps on the proper equipment.

Prejob briefings were conducted

in a thorough and formal manner.

Prior to restoring

Engineered

Safety Feature

Bus F to service the shift foreman specifically warned

operators how ground buggies should be installed.

Prior to performing the

overspeed

test on Emergency

Diesel Generator

1-3 the shift foreman emphasized

to

operations

and test personnel

involved the precautions

and limitations in the

procedure,

specifically the maximum speed

on the diesel.

In some instances,

inconsistent shift supervisor to shift crew interaction and

oversight was observed.

While one shift supervisor involved himself in oversight of

unanticipated

annunciator responses

and prebriefings,

as well as, shift turnover

briefings, another shift supervisor limited his involvement to shift turnover and a

few status briefings by the shift foreman.

The inspectors noted that the licensee's

expectations

for shift supervisor shift crew involvement was not specifically

delineated.

Procedure

OP1.DC10, Revision 3, stated that the shift supervisor

responsibility was for direction of the shift foreman and for providing overall

coordination of all plant activities.

The procedure

did not set forth management's

expectation

as to the amount of shift supervisor to crew involvement. The licensee

management

representative

acknowledged

the observation

and stated that more

consistent involvement in interactions was an area for improvement.

The inspectors observed

one instance

in which there appeared

to be a lapse in

communication between the clearance coordinator and the shift foreman, which

related to the status of control board clearance tags.

During the preparation for

re-energization of the 4 kV Bus F, the 'iftforeman noted

a control board

-7-

information tag on the 480 volt Bus F.

Prior to re-energizing the 4 kV bus the shift

foreman had personnel physically verify no grounding straps were installed on the

480'volt bus and verified all work activities on the 480 volt bus had been reported

'omplete

and ready for testing.

The inspectors noted that Procedure'P2.ID1,

Revision 7, required the clearance coordinator to inform the shift foreman when it

was appropriate to have the operators remove control board information tags.

This

example represented

good oversight by the shift foreman and cautious actions

taken prior to re-energizing the 4 kV bus.

No safety concern or personnel

hazard

existed.

The licensee initiated an event trending record to track the administrative

error.

Because of this example, the inspectors reviewed training provided on the

clearance request process prior to entering the 1RB Refueling Outage.

The

inspectors verified that clearance training had been provided to both licensed and

non-licensed

operators between February 10 and March 14, 1997.

The training, a

2-hour class, included familiarization with the clearance

procedure,

how to

manipulate clearances,

and a practical exercise

in making a master clearance

and

subclearances.

The inspectors considered

the training appropriate

and

comprehensive.

Conclusions

Control room communications,

command,

and control were effective.

Although it

was not a uniformly implemented practice, the control room staff normally practiced

formal three-way communications when providing instructions and reporting critical

information.

Prejob briefings and peer-checking

were used properly.

Shift turnover

was effective and crew members demonstrated

a good understanding

of plant

status and work activities.

Communications

and coordination of work between the

control room and the outage control center was effective.

Some variance in shift

supervisor to shift crew interaction was observed.

There was good linkage between the shift foreman and the operating crew members

during responses

to abnormal conditions.

04

Operator Knowledge and Performance

04.1

0 erator Performance

on Annual Re uglification Examinations

Ins ection Sco

e

71001

The inspectors observed the performance of two shift crew groups and one staff

crew group during their annual requalification evaluations.

Each shift crew group

was composed

of five active licensed operators

and one shift technical advisor.

The staff crew group was a composite group of licensed shift operators,

inactive

licenses,

a certified trainer, and one shift technical advisor.

The 2-year licensed

operator requalification cycle began with Session

95-1 on June 19, 1995, and

-8-

ended for licensed operators with Session 96-7 on April 18, 1997, for a total of

14 sessions.

The cycle included two annual operating examinations during

Sessions

95-8 (May 21 through June 21, 1996) and 96-7 (March 15 through

April 18, 1997). These operating tests included simulator dynamic performance

evaluations

and five job performance

measures

for each licensed operator.

Also

included was a written examination during Session 96-7 for each operator

consisting of an open reference examination.

Observations

and Findin

s

The inspectors observed

a portion of Session 96-7 biennial examination during the

week of April 14, 1997.

All three crew groups observed

passed

all portions of their

evaluations.

However, one individual on the staff (composite) crew group failed the

dynamic simulator evaluation.

Additionally, a shift crew failed the dynamic

simulator evaluation during the first week of requalification examinations

administered

prior to this inspection period.

The cause for the failures was primarily performance deficiencies

in crew oversight,

communication,

and procedure

usage skills. The licensee's practice was that the

senior control operator serve as a procedure

reader during abnormal and emergency

evolutions, allowing the shift foreman to focus attention on plant conditions and

procedure entry conditions and transitions.

The inspectors observed inconsistent

linkage between the senior control operator,

a licensed reactor operator, the shift

foreman, and a licensed senior reactor operator.

The inspectors were concerned

because

there were times when the shift foreman was not aware of changing plant

conditions and responses

directed by the senior control operator and was unaware

that errors in procedure

usage occurred, such that the incorrect emergency

operating procedures

were being implemented.

In one instance, the shift foreman failed to conduct tailboards prior to transitioning

between emergency

procedures

and failed to inform the shift supervisor of the

transition.

In another instance, the shift foreman was unaware that the primary

operator had been directed to secure the residual heat removal pumps during cold-

leg recirculation swapover and had performed the actions.

During such instances,

the senior control operator appeared

to direct other reactor operators during

emergency

scenario conditions, while reading the emergency

procedures.

While the

senior control operator's actions were not considered

sufficient to justify a failure,

the importance of the senior control operator informing and getting the concurrence

of the shift foreman of actions was reinforced by the licensee evaluations during the

crew critiques.

-9-

The inspectors were concerned with the shift foreman and senior control operator

linkage issue because

only a senior operator is licensed by.10 CFR 55 to direct

reactor operators.

This issue had been previously identified during NRC inspections

(e.g., 50-275;-323/95-04 performed in June 1995).

The inspectors pointed out to

the licensee staff that the policy to allow the senior control operator to read the

emergency

and abnormal procedures

was vulnerable because

it could, at times,

result in a violation of regulations when a breakdown of the shift foreman to senior

control operator linkage occurred.

The licensee's staff acknowledged

this vulnerability and agreed to reevaluate

the

policy and also strengthen

the linkage between the senior control operator and shift

foreman through their training feedback system.

Except for the examples discussed

above, operator performance

in the simulator

was consistent with that observed

in the control room.

Inspectors

did not observe

a similar shift foreman to senior control operator linkage problem in the control room

during abnormal conditions response.

During stressful simulator scenario

conditions, formal three-leg communications

broke down at times and lapsed into

informal communications.

This weakness

was most obvious in the crew group

discussed

above, but also apparent,

to a lesser degree,

in the other two groups

evaluated during this session.

The inspectors

also observed that the shift technical

advisors demonstrated

more involvement in assisting the crews than in previous

inspections.

This was evidenced

by shift technical advisors making helpful

observations

on required component settings and monitorir" vital components.

The licensee's staff acknowledged that crew communications

weaknesses

had been

identified and improvements incorporated into the training program through the

feedback process.

Conclusions

The inspectors concluded that, with the exception of the one crew failure and an

individual failure in the dynamic simulator portion of the requalification examination,

which were primarily caused

by performance deficiencies in crew oversight,

communication,

and procedure

usage,

the licensed operators exhibited good

knowledge and ability during the requalification examinations.

The inspectors concluded the licensee requalification program was acceptable.

Shift management

issues related to inconsistent linkage between the shift foreman

and the senior control operator remains an issue warranting licensee management

attention.

-10-

05

Operator Training and Qualification

05.1

Initial Licensin

Examination Develo ment

The facility licensee developed

an initial licensing examination in accordance

with

guidance provided in Generic Letter 95-06, "Changes

in the Operator Licensing

Program."

However, prior to administration the licensee decided to withdraw the

application.

As such, the planned licensed operator examination was cancelled.

The following provides observations

as to the licensee developed draft examination.

05.1.1 Examination Outline

a.

~Sco

e

The licensee submitted the initial examination outlines on February 14, 1997.

The

chief examiner reviewed the submittals against the requirements of NUREG-1021,

"Licensed Operator Examiner Standards,"

Revision 7, Supplement

1, and

NUREG/BR-0122, "Examiner's Handbook for Developing Operator Licensing Written

Examinations,"

Revision 5.

b.

Observations

and Findin s

The chief examiner determined that the initial examination outlines satisfied the

above requirements.

However, minor changes to the written examination were

made so that a more evenly weighted distribution would be achieved

in Group III of

plant systems.

The chief examiner also noted that the job performance

measures

outline did not meet the requirements of NUREG-1021/ES-201

in that there was

direct overlap between Job Performance

Measure

7 and Event 5 of Scenario 2.

Other observations

by the examiner were minor. The comments on the outline were

discussed

with the licensee author and revisions were made and submitted along

with the draft examination.

C.

Conclusion

With the exception of the inadequate

job performance

measure

outline, the licensee

submitted generally good examination outlines.

05.1.2 Draft Initial Examination Packa

e

a.

~Sco

e

On March 10, 1997, the licensee submitted

a draft initial reactor operator

examination developed

under the guidance of the pilot examination program.

The

chief examiner reviewed the draft examination and provided comments to the

licensee author and supervisor on April 14, 1997.

-11-

b.

Observations

and Findin

s

The chief examiner reviewed the draft initial examination and determined that with

the exception of the operating portion of the test, the examination was adequate.

The written examination and the scenarios

needed only minor enhancements.

However, the administrative and walkthrough portions of the operating test were

not adequate

for examination administration.

Several of the administrative and job

performance

measure followup questions were considered

direct lookups.

Some job

performance

measure followup questions

were constructed

such that multiple

answers were required.

In another instance,

a job performance

measure was

co'nsidered

overly simplistic in that it contained only one active step and was

considered to discriminate poorly.

The walkthrough portion of the operating test

failed to meet the quality assurance

checklist, "Examiner Standard 301-?",

items 3a, b, and d of NUREG 1021, Revision 7, Supplement

1.

Conclusion

The chief examiner concluded that the draft initial examination was not adequate

for

administration in that portions of the operating test were narrower in scope than the

guidance provided in the examination standard,

NUREG-1021.

05.2

Review of Re uglification Examinations

a.

Ins ection Sco

e

71001

The inspectors performed

a review of the annual requalification examinations,

including operating tests and biennial written examination, to evaluate general

quality, construction,

and difficulty level.

The inspectors

also reviewed the

methodology for developing the requalification examinations.

b.

Observations

and Findin s

The operating examinations consisted of job performance

measures

and dynamic

simulator scenarios.

The scenarios followed the guidelines of NUREG 1021,

"Operator Licensing Examiner Standards,"

Revision 7, Supplement

1, in complexity

and quantitative event requirements.

The scenarios

were written with clear

objectives, expected operator actions, and critical task identification and evaluation

criteria.

The job performance

measures

were adequate

in scope and depth, and

covered

a broad range of topics as required by the training program and the

regulations.

Critical steps in the job tasks were appropriately identified.

The inspectors determined

.hat the written examinations were of the appropriate

breadth of coverage

and depth of knowledge,

and of particularly effective

discriminating value.

-12-

c.

Conclusions

The inspectors

concluded that the requalification examinations were well

constructed,

challenging,

and discriminated at the appropriate knowledge level.

05.3

Re uglification Examination Administration

a.

Ins ection Sco

e

71001

The inspectors observed

the administration of all aspects of the requalification

examinations

to determine the evaluators'bilities to administer an examination

and

assess

adequate

performance through measurable

criteria.

The inspectors

also

observed

the plant simulator to support training and examination administration.

Five licensed operator requalification training evaluators

and one operations

management

evaluator were observed participating in one or more aspects of

administering the examinations,

including pre-examination

briefings, observations

of

operator performance,

individual and group evaluations of observations,

techniques

for job performance

measure

cuing, and final evaluation documentation.

Additionally, the feedback system for entering training information and modifying

the requalification training was reviewed.

Observations

and Findin s

The evaluators conducted the examinations

professionally,

and thoroughly

documented

observations

for later evaluation.

Job performance

measure

cues were

provided appropriately as needed,

with no inadve'rtent cuing observed.

A formal evaluation method was used that reviewed crew and individual critical

tasks following the scenario observations,

and then competencies

for the crew and

for individuals when appropriate.

During the simulator evaluations,

the inspectors

noted that the evaluator staff was particularly effective in identifying and properly

categorizing operator performance deficiencies and weaknesses.

The inspectors

also observed strong operations staff participation.

A representative

from the

operations department performed the crew evaluation in the simulator and was

involved with making the pass/fail decision for the crew.

The post-scenario

examination evaluation caucuses

were well organized

and efficient with the

evaluation team reaching

an accurate consensus

on performance results.

This

evaluation method minimized overall crew stress.

The inspectors observed that the

crews held independent

self-critical caucuses,

led by their shift supervisors,

who

were also involved with developing remediation plans, when necessary.

The

inspectors

also observed that shift supervisor ownership for crew and individual

performance was a management

expectation

and was apparent

in most cases.

The inspectors observed that the performance of the simulator in supporting the

examination process was good.

Simulator issues were not observed during the

examination

(see Attachment 2).

-13-

The inspectors

also reviewed operator classroom

and simulator critiques for the

month of January 1997.

Also reviewed were training steering committee meeting

minutes and event trend report information input into operator training.

Overall, the

training department

appeared

responsive

to operator feedback and had recently

started providing a direct response

to comments using the licensee's

e-mail system.

The training department

also presented

the disposition of operator training feedback

comments to the training steering committee.

This appeared

to be a proactive

initiative and provided

a mechanism for establishing direct accountability of the

training department to operations.

Event trend records which are utilized to

document lower threshold problems that do not require specific corrective actions

were also tracked and trended.

The summaries of the records were also presented

to the training steering committee to determine whether specific training was

required for any specific area of operator performance.

Conclusions

The facility evaluators administered

the examinations

professionally and

consistently.

The facility evaluators effectively identified strengths

and

weaknesses

in crew and individual performance

and conducted

good critiques.

Training needs were being fed back into the training program.

05.4

Remedial Trainin

Pro ram Review

a.

Ins ection Sco

e

71001

The inspectors

assessed

the adequacy of the effectiveness of the remedial training

conducted

during this requalification cycle and the training planned for the next

cycle to ensure that it addressed

operator or crew performance weaknesses.

The

inspectors

also reviewed simulator documentation

records for requalification

examinations

administered

during 1995 and 1996 to ascertain whether evaluations

were consistent between crews, and individuals.

Records associated

with

remediation were additionally reviewed to determine if the planned remediation was

appropriate

and timely.

b.

Observations

and Findin s

The inspectors reviewed the observed

failed crew groups'hort-term

remedial

training documentation

process

and the documentation

for other crew and individual

failures that had occurred throughout the requalification cycle.

The inspectors

determined that the short-term remedial training was effective.

The inspectors

determined that of the 12 previous requalification training sessions

and two

evaluation sessions,

each session consisted of approximately

15 crew groups of

5 licensed operators

and

1 shift technical advisor.

During this requalification cycle

-14-

examination,

1 of the crew groups and 5 individuals failed in the simulator, no

individuals failed the written, and two individuals failed the job performance

measures

portion of the operating test.

The inspectors

assessed

that these failure

rates were not excessive

and were consistent with other industry licensed operator

requalification training programs.

In addition to the above,

a review of past requalification results documentation

indicated that the bases

used by evaluators for determining pass)fail grades were

consistently applied.

For those individuals, which required remediation, the

remediation plans were well documented

and the remediation was timely.

For

example, during the 1996 licensed operator requalification examination simulator

scenarios

utilizing Functional Recovery Procedure

FR-S.1, "Response

to Nuclear

Power Generation/ATWS," was used in scenarios for 5 of 17 total groups.

Of the

5 groups, 3 individuals failed the simulator scenarios.

In all three of these cases,

evaluations were consistently applied as related to six performance competency

areas, individual remediation plans were well documented,

and implementation of

'the remediation was timely.

c.

Conclusions

The remedial training program was adequate.

Short-term remedial training was

effective.

Evaluations by the training department staff and representatives

of the

operations department were consistently applied.

Remediation was well

documented

and quickly implemented.

05.5

Review of Conformance with 0 erator License Conditions:

a.

Ins ection Sco

e

71001

The inspectors evaluated the adequacy of the requalification program's compliance

with Subpart C, Medical Requirements'and

10 CFR 55.53, "License Conditions."

The inspectors interviewed operators

and training management,

and examined the

licensee's records to determine compliance for conditions to maintain an active

operator license, reactivation of licenses, and medical fitness.

b.

Observations

and Findin s

Operator license conditions were being accurately identified and tracked.

However,

it was determined that a number of licensed operators (approximately 26) with

corrective lenses

as a condition of license did not have special frames and lens for

their self-contained

breathing apparatuses

used in the control room.

The inspectors

observed that the licensee's

Final Safety Analysis Report, Sections 9.58-24,

9.58-36 and 6.4-3, indicated that self-contained

breathing apparatuses

are provided

for fire brigade and control room personnel

use, which requires that control room

personnel

be self-contained breathing'apparatus

qualified.

As such, the inspectors

considered

the use of self-contained

breathing apparatuses

as design bases

-15-

contingency measure.

It was also noted that Procedure

RP1.ID3, "Respiratory

Protection Program," requires that only special spectacle

kits specified by the

manufacturer of the respirator be used.

Further, Procedure

OM14.ID2, "Medical

Examinations" required individuals with prescription eyeglasses

who are required to

wear a full-face respirator shall use special frames for their glasses that do not

interfere with the face-piece seal.

The inspectors

also noted that operators would

be required to wear self-contained

breathing apparatus

for performance of

procedures

under abnormal environmental conditions, (e.g., Procedure

AP-8B,

"Control Room Inaccessibility - Hot Shutdown to Cold Shutdown."

This was

an'xample

of an apparent violation of Technical Specification 6.8.1a for a failure to

follow procedures,

(50-275;-323/9701-01).

Further, as a result of the inspector's questions with regard to licensed operator

, usage of self-contained

breathing apparatuses,

the licensee performed data base

searches

of the plant information management

system and licensed operator

qualifications.

The licensee determined that approximately 75 percent of the

licensed watchstanders

had not completed the annual refresher training for

self-contained

breathing apparatus.

Procedure

OD1.DC37, Attachment 6.4,

specifies that, "... operators fulfilling a minimum shift crew position must be a

qualified respirator user."

Since the only available respirators

in the control room for

operator use are self-contained

breathing apparatuses,

licensed operators onshift in

the control room are required to be self-contained

breathing apparatuses

qualified.

The Respirator Training Procedure,

TQ1.DC20, steps 2.1-2.3, describes the

respirator training program as a two-part training program consisting of initial

training and an annual followup refresher training course.

The folfowup annual

refresher training course

is designed to provide training on new equipment or

procedures

and work practices,

as well as, check proficiency in the initial cognitive

objectives which include proper actions for abnormal or emergency situations.

However, it was this annual refresher with which many of the licensed operators

standing watch were not current.

This was a second

example of a failure to follow

procedures

and an apparent violation of Technical Specification 6.8.1a

(50-275;-323/9701-01

) .

As corrective actions, the licensee conducted

"Just in Time" training for individuals.

coming onto the watch bill to assure watchstanders

were current in annual

self-contained

breathing apparatuses

training.

The licensee also initiated Action

Request A0429503 to ensure licensed operators

are provided with the required

frames.

-1 6-

c.

Conclusions

The inspectors concluded that the licensee accurately tracked, maintained,

and

controlled the conditions of operator licenses and reactivation of inactive licenses in

accordance

with Subpart

C, "Medical Requirements,"

and 10 CFR 55.53, "License

Conditions."

However, the issues related to licensed operators with conditioned

licenses not having the special frames for self-contained

breathing apparatus

and

not satisfying the required annual self-contained

breathing apparatus

refresher

training were considered

examples of a procedural violation.

08

Miscellaneous Operations Issues (92900)

08.1

Closed

Licensee Event Re ort 50-323/95004:

Technical S ecification 3.0.4 Not

Met Due to Personnel

Error

This licensee event report involved the failure to have hydrogen analyzer cell 82

operable during entry into Mode

1 and 2 while in Action A of Technical Specification 3.6.4.1.

The hydrogen analyzer was determined to be inoperable due

to its isolation valves being closed.

During this inspection, the inspectors verified that long-term corrective actions were

taken by reviewing the event with the appropriate

personnel during technical

maintenance

continuing training.

The training was incorporated

into configuration

control continuing training.

Lessons

plans and attendance

records were reviewed to

verify subject matter coverage

and personnel attendance.

This licensee-identified

and corrected violation is being treated as a noncited

violation, consistent with Section VII.B.1 of the NRC Enforcement Policy

(50-275;-323/9701-02).

08.2

Closed

Licensee Event Re ort 50-323 96005:

Manual Reactor Tri

U on

Discover

of Di ital Rod Position Indicator S stem Ino erabilit

Due to Personnel

Error

This licensee event report was submitted to report the inoperability of the digital rod

position indicator system due to a switch being left in the test position after

completion of periodic testing.

During the inspection, the inspectors verified that the applicable

Procedures

MP l-1.6-1, Revision 2, and MP l-1.10-1 were revised to add

verification steps to ensure the S7 test switches on the data input/output

cards are left in the correct position following testing.

This licensee-identified

and corrected violation is being treated as a noncited

violation, consistent with Section VII.B.1 of the NRC Enforcement Policy

(50-275;-323/9701-03).

-1 7-

08.3

Closed

Violation 50-275 9602-03 50-323/9602-03:

Failure to Com lete

Proficienc

Trainin

Re uired b

Procedure TQ1.DC]2 and the U dated Final Safet

Anal sis Re ort for Individuals Assi ned to the Fire Bri ade

This violation involved the failure to adequately

train fire brigade members

in that

onshift watchstanders

did not complete biennial training requirements.

During this inspection, the inspector verified that long-term corrective actions were

implemented to resolve the cited violation.

The licensee had revised controlling

procedures

to provide the additional guidance necessary

for the individual making

up the fire brigade list for the applicable shift have the fire brigade leader and

members status and qualifications listing available to him in the plant information

management

system.

A watch'bill listing along with a fire brigade member report

were verified for April 22, 1997.

No discrepancies

were identified.

IV. Plant Su

ort

F8

Miscellaneous Fire Protection Issues

F8.1

General Comments

The inspectors observed

general plant housekeeping

incident to administration of

the in-plant job performance section of the operating test.

The facility was

reasonably

clean, well lighted, and the floors were clear a"9 free from debris.

The

operators were conscientious

to note discrepancies

and inform the main control

room.

V. Mana ement Meetin

s

X1

Exit Meeting Summary

The inspectors presented

the inspection results to members of the licensee

management

at the conclusion of the inspection on May 2, 1997.

The licensee

acknowledged

the findings presented.

The licensee did not identify as proprietary any information or materials examined

during the inspection.

0

ATTACHMENT 1

SUPPLEMENTAL INFORMATION

PARTIAL LIST OF PERSONS CONTACTED

Licensee

D. Adams, Nuclear Quality Services

J. Becker, Operations Director

C. Belmont, Nuclear Quality Services, Director

W. Crockett, Nuclear Quality Services

S. David, Operations

Foreman

S. Fridley Operations Services Manager

S. Ketelsen, Regulatory Services

S. LaForce, Regulatory Services

R. Martin, Regulatory Services

J. Molden, Operations Manager

D. OafIcy, Maintenance

Manager

G. Rueger, Senior Vice President

B. Vatter, Learning Services

71001

71715

92900

INSPECTION PROCEDURES USED

Licensed Operator Requal Evaluation

Extended Control Room Observations

Followup

~oened

50-275;-323/

9701-01

50-275;-323/

9602-03

50-275;-

323/9701-02

50-275;-

323/9701-03

Closed

50-275;-323/

2-95-004

50-275;-323/

2-96-005

ITEMS OPENED, CLOSED, AND DISCUSSED

VIO

Failure to Follow Procedures

Related to Respiratory

Protection

VIO

Failure to Complete Proficiency Training Related to Fire

Brigade Personnel

NCV

Technical Specification 3.0.4 Not Met Due to Personnel

Error

NCV

Manual Reactor Trip Upon Discovery of Digital rod Position

Indicator System Inoperability Due to Personnel

Error

LER

Technical Specification 3.0.4 Not Met Due to Personnel

Error

LER

Manual Reactor Trip Due to Digital Rod Position Indicator

System Inoperability Due to Personnel

Error

-2-

50-275;-

323/9701-02

50-275;-

323/9701-03

NCV

Technical Specification 3.0.4 Not Met Due to'Personnel

Error

NCV

Manual Reactor Trip Upon Discovery of Digital rod Position

Indicator System Inoperability Due to Personnel

Error

DOCUMENTS REVIEWED

Procedures

Reviewed

TQ2.ID4, Training Program Implementation

TQ2.DC3, Licensed Operator, Non-Licensed Operator, and Shift Technical Advisor,

Continuing

Training Program.

OP L-6, "Refueling," Revision 26

STP-V-18A, "Full-Flow Accumulator Discharge Check Valve Test," Revision 7

STP-I-1A, "Routine Shifts Checks Required by Licenses," Revision 60

OP1.DC37, "Plant Logs," Revision 5B

OM14.ID2, "Medical Examinations,"

Revision 1A

Operations Policy Guidelines D-3, "Handling of Control Board Caution Tags and Instrument

Stickers," Revision 2

OP2.ID1, "Clearances

and Administrative Tag Outs," Revision 7,

Record of Reactor Operator Medical 5 License Summary, dated April 15, 1997

Operations Section Performance Trends for January

and March 1997

1R8 Plan of the Day, April 30, 1997

STP M-9A, "DG Surveillance"

OPE 5:IV, "Auxiliary Saltwater- Changing over Pump R HX Trains," Revision 5

Equipment Control Guidelines,

ECG 7.4, Revision 0, Table 7.4-1

TQ1.DC20, "Respirator Training Program," Revision

1

AP-BB, "Control Room Inaccessibility - Hot Standby to Cold Shutdown," Revision 8

-3-

Other Documents:

Session 96-7 Group

1 Master Exams (Written, Scenarios,

and JPMs)

Session 96-7 Group 253 Master Exams (Written, Scenarios,

and JPMs)

Sessions

95-8 and 96-7 Biennial examination remedial training records.

Operator Shift Watch List

Active License List

Operator Continuing Training, Session 96-6 Lesson Plans R966C3 5 R966C4, "Clearance

Training"

Simulator Documentation

Records for LR 948SE1, 948SE2, R95-8, and other related

documentation

(e.g., remediation plans, remediation records,

and others) for Licensed

Requalification Examinations during 1995 and 1996.

ATTACHMENT2

SIMULATIONFACILITYREPORT

Facility Licensee:

Pacific Gas and Electric Company

Facility Docket:

50-275, 50-323

Operating Examinations Administered at: Diablo Canyon Nuclear Plant,

San Luis Obispo, Ca.

Operating Examinations Administered on:

April 15-17, 1997

These observations

do not constitute audit or inspection findings and are not, without

further verification and review, indicative of noncompliance

with 10 CFR 55.45(b).

These

observations

do not affect NRC certification or approval of the simulation facility, other

than to provide information which may be used in future evaluations.

No licensee action is

required in response

to these observations.

None.