ML16342D301

From kanterella
Jump to navigation Jump to search
Insp Repts 50-275/96-03 & 50-323/96-03 on 960226-0301 & 0408-12.No Violations Noted.Major Areas Inspected:Licensee Self Assessment of Engineering & Corrective Action Program
ML16342D301
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 05/14/1996
From: Vandenburgh C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML16342D302 List:
References
50-275-96-03, 50-275-96-3, 50-323-96-03, 50-323-96-3, NUDOCS 9605280121
Download: ML16342D301 (36)


See also: IR 05000275/1996003

Text

ENCLOSURE

U.S.

NUCLEAR REGULATORY COMMISSION

REGION IV

Inspection Report:

50-275/96-03

50-323/96-03

Licenses:

DPR-80

DPR-82

Licensee:

Pacific Gas

and Electric Company

77 Beale Street.

Room 1451

P.O.

Box 77Uu00

San Francisco,

California

Il

Facility Name:

Diablo Canyon Nuclear

Power Plant.

Units

1 and

2

Inspection At:

San Luis Obispo,

Cali fornia

Inspection

Conducted:

February

26 through March

1 and April 8-12.

1996

Inspectors:

Paul

C.

Gage.

Reactor

Inspector.

Engineering

Branchy

Division of Reactor Safety

William M. McNeill, Reactor

Inspector.

Engineering

Branch.

Division of Reactor Satety

Approved:

rts ..

an

en urg

.

engineering

rane

Division of Reactor Safe

5-lQb

Ins ection

Summar

A~I

t d:

R

tt

.

d

1

1 tt

1 tt

11

11

assessment

of the engineering

and corrective action programs.

Results:

En ineerin

~

The inspectors

concluded that implementation of the plan and management

of the assessors'inding

was very good.

The licensee's

self-assessment

team displayed excellent synergism regarding multiple discipline

interaction in team meetings.

The licensee's

"team work" skills was

considered

a strength

(Section 2.3).

9605280121

960521

PDR

ADOCK 05000275

8

PDR

-2-

The inspectors

determined that

a qualified team had conducted

an

independent

and objective assessment

of engineering activities

(Section 1.1).

The inspectors

found the scope

and depth into assessment

areas

to be

ambitious

and satisfied all the inspection

requirements of NRC

Inspection

Procedure

37550 (Sections

2. 1 and 2.2).

The inspectors

concurred with the problems identified by the licensee's

team and the: disposition of the problems.

No operability concerns

were

identified by the licensee's

team (Section 2.4).

The engineering

self-assessment

team found that engineering

was

generally effective,

and programmatic controls

met regulatory standards.

Engineering

was producing

many effective designs.

analysis

and other

products

(Section 2.4.2).

The engineering

self-assessment

team found strengths

in regard to the

auxiliary feedwater

system in the pro-active trending of pump

performance.

and the timely and te"hnically sound resolution of flow

issues.

Weaknesses

found by the licensee's

team were in the translation

of design basis

requirements

into test requirements

for pump speed.

differential pressure,

and acceptance criteria.

Weaknesses

were also

found in configuration control of changes.

such

as valve stroke time and

the current design not fully reflected in the design basis

documents

(Section 2.4.2).

A noncited violation was identified in that the licensee's

team found

that the minimum flow requirements

had changed

in the surveillance

procedure

and Technical Specifications

(AR QE-AFR 0011838):

however,

the

safety analysis report

and the design basis

document

had not changed.

The licensee's

procedures

required that the design basis

document

be

changed

before the procedure

was changed

(Section 2.4.2).

A none ted violation was identified in that the licensee's

team found

a

calculation

had been

done in support of the steam generator

tube rupture

analysis without the proper review and approval

(Technical Specification

AR QE-AFR 0011839).

An assumption

on the amount of back pressure

changed

and.

as

a result.

the effect on the overfill margin was

calculated.

However. this calculation did not receive the review and

approval

required

by design control procedures

(Section 2.4.2).

The licensee's

team identified

a strength in system engineering

performance

regarding

knowledge.

ownership.

problem identification,

problem documentation.

surveillance test development.

and providing

0

-3-

support of the conduct of surveillance tests.

The self-assessment

team

identified weaknesses

involving untimeliness

in providing responses

to

Technical Specification interpretations

and updates

to design basis

documents

(Section 2.4.2).

A noncited violation was identified in that the licensee's

team

identified several

changes

to emergency diesel

generator

Design

Basis

Document

OCM S-21,

which had not been incorporated into the

design basis

document over the past

3 years,

in spite of the required

annual

update.

The team subsequently

performed

a review of additional

design basis

documents

and found similar problems

as in Design Basis

Document

DCM S-21.

The team concluded that the usability of a number

of design basis

documents

have

been adversely

impacted

as

a result of

several

changes

not being incorporated

as required

by procedure

(Section 2.4.2)

The licensee's

team found system engineering

strong in knowledge/

ownership of their systems.

problem identification. "tai lboards" (prejob

briefings)

~

and communication.

The team also

found that system

engineering

was weak in the issuance of quarterly reports

and use of

checklists

in performance of walkdowns (Section 2.4.2).

The licensee's

team reviewed design

change

packages

not associated

with

the vertical

sample of systems.

It was found that design

change

ackages

were technically adequate

and sound.

Strengths

noted by the

icensee's

team were the analytical capability. trending of marginal

pump performance.

and the desire to recapture

some the

pumps performance

margin.

Meaknesses

noted by the licensee's

team were

a lack of

attention to detail

and errors in transferring of design basis

information into surveillance

tests

(Section 2.4.2).

The licensee's

team found that system engineering

was

a strength in

support of operations

in response

to conditions that challenged

continued plant operation.

In addition. it was noted

by the licensee's

team that engineering

was well prepared

and effective on complex tasks.

The licensee's

team also

found that engineering

was not consistent

in

its high quality effort in support of routine work. such

as procedure

writing. addressing

operator

"work around"s

(or compensatory

measures),

and other items.

The licensee's

team concluded

the use of probabi 1'-+ic

risk assessment

information was good (Section 2.4.2).

The licensee's

team concluded that engineering

support of maintenance

was effective.

The team reflected concerns

by technical

maintenance

related to the amount of the engineering

backlog (Section 2.4.2).

The licensee's

team found the erosion/corrosion

program to be

a strength

(Section 2.4.2).

0

The team concluded that engineering

had effectively communicated,

tracked.

and implemented setpoint changes'nd

that design basis

setpoints

have

been properly transmitted via design

and scaling

calculations.

The team observed

a weakness

regarding

a lack of timely

setpoint

updates

in the plant information management

system

and that

nondesign

basis setpoints

are not comprehensively

incorporated into the

plant information management

system (Section 2.4.2).

The licensee's

team found the independent

safety engineering

group to be

highly effective in conducting performance-based

assessments.

Two

strengths

identified by the licensee's

team were independent

safety

engineering's

performance of comprehensive.

thorough'nd

the in-depth

reviews of industry events.

In addition the independent

safety

engineering's

recommendations

and justification of recommended

actions

in response

to industry events

was viewed as

a strength.

One weakness

was the lack of formal review of licensee

.event reports

(Section 2.4.2).

~

The team concluded that engineering

backlog was not effectively managed

and was considered

a serious

weakness.

The team identified current

indicators which reflect

a reduction or stable workload.

when actual

routine workload was increasing

and manpower

was decreasing.

The self-

assessment

team recognized effective management

of backlog in two

distinct areas:

overdue

nonconformance

reports

and design

change

drawings.

The team noted that both of these

areas

were identified as

needing

improvement

by outside entities to engineering

in the past year

(Section 2.4.2).

~

The licensee's

team found

a strength in the high priority given problem

resolution in that most problems

were resolved

in a technically correct

and comprehensive

manner.

One weakness

the licensee's

team identified

was one problem they discovered that was not fully pursed to resolution

(Section 2.4.2).

~

The licensee's

team found no strengths

or weaknesses

in the areas of

minor modifications

and safety evaluations

(Sec.ion 2.4.2).

~

The inspectors

concluded that the licensee activities were satisfactory

in the areas of post-maintenance

testing

and the safety evaluation

screening

process

(Sections

3. 1 and 3.2).

~

The inspectors

found the inservice testing

program for two types of

components

met the regulatory requirements

(Section 3.3).

Summar

of Ins ection findin s:

~

Three noncited violations were identified (Section 2.4).

Attachment:

~

Attachment

- Persons

Contacted

and Exit Meeting

0

-5-

DETAILS

1

TEAN COHPOSITION

(40501)

1. 1

ua 1 ificati ons

Ob ecti vit

and

Inde endence

1.1.1

Inspection

Scope

The purpose of this inspection

was to determine the qualification.

objectivity. and independence

of the licensee's

self-assessment

team in

accordance

with NRC Inspection

Procedure

40501,

""Licensee Self Assessments

Related to Team Inspections."

0 "egion IV NRC team inspection

was planned to

accomplish the core inspection

program requirements of NRC Inspection

Procedure

37550.

"Engineering"

and 40500 'Effectiveness

of Licensee Controls

in Identifying. Resolving.

and Preventing

Problems."

The option of permitting

licensees

to conduct

a self assessment

in lieu of an

NRC team inspection is an

NRC program aimed at minimizing regulatory

impact, and utilizing NRC resources

more efficiently.

In a letter dated January

24.

1996.

the licensee

proposed

to perform

a self assessment

of engineering activities using the guidance of

NRC Inspection

Procedure

37550

and relevant sections of NRC Inspection

Procedure

40500.

1. 1.2

Observations

and Findings

In a letter dated January

24 '996.

the licensee

provided the

NRC the

engineering

self-assessment

plan that included

an outline of the

qualifications of the team members.

The inspectors

compared

the

submitted inspection

plan against

the requirements

of NRC Inspection

Procedure

37550

and determined that the licensee's

assessment

plan included

all the key elements listed in the inspection

procedure.

The inspectors

reviewed the qualifications of the team members

and found they exhibited

a

wide scope of engineering disciplines: with each

member possessing

significant

engineering

experience.

The inspectors

noted that extensive preparation

was conducted

by the licensee

to enhance

the team members qualification regarding

the self-assessment

effort

with the focus

on the auxiliary feedwater

system

and the emergency diesel

generator

system.

The specific areas

as

documented

during the preparation

phase for the team

members

included reviews of nonconformance

reports. quality

evaluations'esign

change packages'nd

system walkdowns.

The inspectors

noted that presentations

regarding probabilistic risk assessments'essons

learned

from prior self assessments

. and performance-based

training were

provided to the licensee's

team members.

The inspectors

confirmed that the licensee's

team was

composed primarily of

Pacific Gas

and Electric personnel

from the quality and engineering

organizations.

The inspectors

noted that the team members

were assigned to

various

sub

teams

based

on their technical

areas of expertise,

but were

excluded

from participation in specific sub teams

where the possibility of

0

-6-

reviewing their own work might have existed.

The licensee's

team composition

was supplemented

with a peer reviewer from the Grand Gulf Nuclear Generating

Station.

!n a letter dated February

14.

1996.

the

NRC accepted

the proposed timing.

scope of effort. credentials.

and experience of the licensee's

self

assessment.

Two inspectors

reviewed the licensee's

self-assessment

effort

from February

26 through March

1 and April 8-12.

1996. in accordance

with NRC

Inspection

Procedure

40501.

"Licensee Self Assessments

Related to Team

Inspections."

2

LICENSEE SELF-ASSESSMENT

PROCESS

2.1

~Sco

e

2.1.1

Inspection

Scope

The inspectors

observed

the licensee's

engineering

self-assessment

team

activities in implementing the submitted plan.

This included interviews with

the licensee staff and observation of the detailed planing of sub tasks.

2. 1.2

Observations

and Findings

The inspectors

found that the submitted plan was

a combination of vertical

and

horizontal

reviews.

The vertical reviews were of two systems,

auxiliary

feedwater

and emergency diesel

generator systems'hat

were selected

because

of the probabi listic risk analysis significance

and narrow design margins

associated

with these

systems.

Mithin these

systems.

the licensee

reviewed

engineering

products.

such

as design

changes.

minor modifications.

temporary

modifications.

selected

design issues.

surveillance

and post modification

testing.

The licensee's

horizontal review was of selected

topical areas

such

as system

engineering.

erosion/corrosion,

independent

safety engineering,

design

changes.

minor modifications. safety evaluations.

setpoint controls,

engineering

support of operations

and maintenance.

engineering

workload

management,

and problem resolution.

Mithin the topical area of design

changes.

the licensee

addressed

several

subjects that recently emerged

from

plant experience.

The self-assessment

team selected

the safety injection pump

replacement.

white light (Regulatory Guide 1.97).

and low temperature

and over

pressure

protection setpoint modifications

as the emergent activities.

Prior assessments

identified corrective action. training and qualification.

and the accuracy

and consistency of the safety analysis

report

as topics in

need of management

attention.

The licensee did not address

these topics in

this self assessment.

-7-

2.2

~0e th

2.2.1

Inspection

Scope

The inspectors

observed

the licensee's

engineering

self-assessment

team in

performance of system walkdowns.

interviews.

and team meetings.

as well as

reviewed the assessor's

notes.

2.2.Z

Observations

and Findings

The licensee's

team divided each of the topics into sub tasks

and for each

sub

task

a detailed plan was developed of interview questions.

documents.

and

subjects

to be reviewed.

The self-assessment

team conducted interviews with

both closed

and open

ended questions.

The inspectors

found the detailed

planning of the licensee's

team to be

a strength.

The inspectors

based this

finding on the quantity of material,

e.g.

~ the number of minor modifications

reviewed.

and the extent of review, e.g.

~ the number of very minor procedure

errors identified by the licensee's

team in the area of minor modifications.

The details of design that were addressed

by the licensee's

team also

showed

depth into the areas

reviewed.

For example,

the verification by the team that

the auxiliary feedwater

flow changes

did not affect the analysis of a steam

generator

tube rupture.

2.3

Plan

and

Im lementation

2.3. 1

Inspection

Scope

The inspectors

reviewed the final report.

assessor's

notes.

and the licensee's

nonconformance/corrective

action documents

called action'requests.

2.3.2

Observations

and Findings

The licensee's

management of findings followed the process of an assessor

to

first identify a concern

as

an "issue."

Issues

became

in'formation requests

or

open items.

When it became clear that

some evaluation

was necessary.

then

an

action request

was issued.

Action requests

had seven levels of significance.

The AT-EVAI -type of request

was

an issue which was not

a formal quality

problem.

but did require resolution.

An A-type was the next higher levels

but

still a low significance quality problem.

An AT-QAAF-type request

was

similar. but the significance

rose to the level of requiring the quality

organization

review and concurrence

in order to close the report.

A QE was

a

higher level of significance that normally required root-cause

analysis,

generic review,

and corrective actions.

A QE-AFR was similar, but of greater

significance

and required root cause.

generic

review.

and corrective actions.

The highest level was

an

ACR, which also required root cause.

generic review,

corrective actions.

and quality review and approval for close out of the

report.

0

-8-

In the licensee's

team meetings.

the inspectors

observed

the team's

good work

skills.

For example.

when one team

member

was working on an issue of the use

of setpoint information in the plant information management

system,

others

on

the team suggested

areas

to be explored

and assisted

in the inspection.

The

team meetings

were of a reasonable

length of time.

even with the large size of

the team.

The team meetings

were policed by the team members,

when

someone

got off the subject

they were reminded

by other

team members.

2.4

Results of the Licensee's

Self Assessment

2.4. 1

Inspection Objectives

The inspectors

performed

a detailed review of the final licensee's

engineering

self-assessment

report.

the assessor's

notes.

and action requests

generated

from the self assessment.

2.4.2

Observations

and Findings

The engineering

self-assessment

team found that engineering

was generally

effective.

and programmatic controls

meet regulatory standards.

Engineering

was producirg

many effective designs.

analysis

and other products.

~

Auxiliary Feedwater

System

The engineering

self-assessment

team found strengths

in the pro-active

trending of pump performance,

and the timely and technically sound

resolution of flow issues.

Weaknesses

found by the licensee's

team were

in the translation of design basis

requirements

into test requirements

for pump speed. differential prcssure'nd

acceptance criteria.

Weaknesses

were also found in configuration control of changes.

such

as

valve stroke time and the current design not fully reflected in the

design basis

documents.

These observations

were based

on the licensee's

team walk down of the system,

review of design changes'esign

basis

issues.

surveillance test acceptance criteria.

and observation of

surveillance testing.

Two more significant findings were in the areas

of minimum flow and calculations.

The licensee's

team found that the engineering staff had changed

the

minimum flow requirements

in a surveillance

procedure after receiving

NRC approval of a Technical Specification

(AR QE-AFR 0011838)

change.

However. the safety analysis

report and the design basis

document

had

not been

changed prior to the change in the surveillance

procedure.

The

licensee's

administrative

procedure

required that the design basis

documents

be changed

before implementing changes

to the surveillance

procedures.

Nine months after the surveillance

procedure

change.

engineering

proposed

a design

change which updated

the design basis

document

and the safety analysis

report.

-9-

Criterion

V of 10 CFR 50. Appendix B. requires that procedures

be

implemented.

Procedure

CF3,

"Design Control

and Plant Technical

Specification Requirements".

Revision

1. requires that acceptance

criteria be based

on the design basis

documents.

The inspectors

noted

that the fai lure to revise the surveillance

procedure

based

on the

design basis

document could result in the loss of design control

information.

Corrective actions

were to change

the design basis

document.

At the time of this inspection.

the root cause

and generic

corrective actions

were to be established

(due December

31.

1996).

This

licensee-identified

and corrected violation is being treated

as

~

noncited violation. :onsistent with Section VII.B.1 of the

NRC

Enforcement Policy.

The licensee's

team also found that

a calculation

had been

done in

support of the steam generator

tube rupture analysis without the proper

review and approval

(Technical Specification

AR (1E-AFR 0011839).

An

assumption

on the amount of back pressure

changed

and,

as

a result.

the

effect on the overfill margin was calculated.

However. this calculation

did not receive the review and approval

required

by design control

procedures.

Criterion

V of 10 CFR 50. Appendix B. requires that procedures

be

implemented.

Procedure

CF3. ID4, "Design Calculations."

Revision 0,

requires that design calculations

be reviewed

and approved.

The

inspectors

noted that the failure to have this calculation

reviewed

and

approved

was

a noncited violation.

Corrective actions

were to have the

proper review done

and obtain the proper approval.

At the time of this

inspection.

the root cause

and generic corrective actions

were to be

established

(due July 1.

1996).

This licensee-identified

and corrected

violation is being treated

as

a noncited violation. consistent with

Section VII.B.l of the

NRC Enforcement Policy.

The inspectors

reviewed design basis

issues

in the areas of

environmental qualification of the auxiliary feedwater

components.

station blackout design.

and remote hot shutdown panel design.

The

inspectors

reviewed the turbine speed

acceptance criteria in detail

and

concurred with the disposition of the problem as documented

in an action

request.

Emergency

Diesel Generator

System

The licensee's

team identified a strength in system engineering

performance

regarding

knowledge,

ownerships

problem identification.

problem documentation.

surveillance

test =development.

and providing

support of the conduct of surveillance tests.

The self-assessment

team

-10-

identified weaknesses

involving untimeliness

in providing responses

to

Technical Specification interpretations

and updates

to design basis

documents.

These observations

were based

on the licensee's

review of a

modification to improve radiator air flow. which included design

calculations.

design criteria. surveillance testing.

and temporary

modifications for the emergency diesel

generator.

The team evaluated

the implementation of Design

Change

Packages

DCP H-

47760

and

DCP H-50203 related to the emergency

diesel

generator

radiator

air flow modi+'cation project.

The team's activities followed the

evaluation of the problem identification, operability evaluation,

root-

cause

determinations

problem resolution

and corrective action

implementation.

including the design

changes

and their associated

calculations.

The team concluded the design

change

packages

were

properly prepared

and adequately

addressed

the design issues.

The licensee's

team identified several

changes

to emergency diesel

generator

Design Basis

Document

DCM S-21. which had not been

incorporated into the design basis

document over the past

3 years,

in

spite of the required

annual

update.

The team subsequently

performed

a

review of additional

design basis

documents

and found similar problems

as in Design Basis

Document

DCM S-21.

The team concluded that the

usability of a number of design basis

documents

have

been adversely

impacted

as

a result of several

changes

not being incorporated

as

required

by Procedure

CF3.NE2.

"Development

and Maintenance of Design

Criteria Memoranda".

Revision 0, paragraph

5.7.2.A.

The corrective

actions

addressed

the need to verify and update

design basis

documents.

The team stated that the root cause

and subsequent

long-term corrective

actions will be established

and implemented

by

a target date of

August l. 1996.

Criterion V of 10 CFR 50. Appendix B. requires that

activities affecting quality shall

be accomplished

in accordance

with

procedures.

The inspectors

noted that the failure to update the design

basis

documents

constitutes

a licensee identified violation which is

being treated

as

a noncited violation. consistent with Section VII.B.1

of the

NRC Enforcement Policy.

The self-assessment

team evaluated

the emergency diesel

generator

surveillance test procedure for technical

adequacy

by reviewing

a sample

of associated

open action requests.

evaluations'nd

nonconformance

reports.

including surveillance test procedures

against the Technical

Specifications

and the Updated Final Safety Analysis Report.

The

licensee's

team identified. through their review of action

requests'hat

some of the action requests

were not being responded to within the

assigned

due dates.

One example involved

a Technical Specification

interpretation

requested

on May 24 '995.

by Action Request

A0341640

~

which addressed

the ramifications of paralleling

an emergency diesel

generator to startup

power during Modes

1. 2, 3, or 4.

In this

condition. both second

level under voltage relays

were defeated,

which

subsequently

placed the plant in a condition not specifically identified

by Technical Specification 3.3.2.

Table 3.3-3

~

Item 7.B. 1.

The

-11-

inspectors

noted that due to the diligence of the licensee's

self-

assessment

team.

the Technical Specification interpretation,

as well as

other untimely responses

by regulatory services,

documented

in Action

Requests

A0325313.

A0334971.

A0341374.

and A0345025 were discussed

by

the surveillance

engineering

group, regulatory services.

and engineering

management.

The team documented

the untimely response

regarding

Technical Specifications

and changes

in surveillance test procedure

program with Non-Conformance

Report

N0001972.

The inspectors

viewed

these short-term actions

as appropriate.

System Engineering

The licensee's

team found system engineering

strong in

knowledge/ownership of their systems,

problem identification,

"tailboards" (prejob briefings).

and communication.

The team also found

that system engineering

was weak in the issuance of quarterly reports

and use of checklists in performance of walkdowns.

The inspectors

were concerned

about the number of system engineers

(4)

interviewed as being sufficient to support the conclusions

drawn by the

licensee's

team.

The assessor's

notes

were revised to document

interviews with an additional eight system engineers.

Other Design

Change

Packages

The licensee's

team reviewed design

change

packages

not associated

with

the vertical

sample of systems.

It was found that design

change

packages

were technically adequate

and sound.

Strengths

noted

by the

licensee's

team were the analytical capability, trending of marginal

pump performance.

and the desire to recapture

some the

pumps performance

margin.

Meaknesses

noted

by the licensee's

team were

a lack of

attention to detail

and errors in transferring of design basis

information into surveillance tests.

These observations

were based

on

review of three emergent

work areas:

a safety injection pump

replacement.

low temperature

over pressure

protection setpoints.

and

white lights (Regulatory Guide 1.97) modification.

Hinor Hodifications

The licensee's

team did not identify any weaknesses

or strengths

in this

area.

The licensee's

team concluded the minor modification process

was

a good system to make plant changes.

Some minor procedural

adherence

~

~

roblems

on approval.

revision

~

and verification were identified by the

icensee's

team.

Some minor problems

were noted by the licensee's

team

on configuration management of drawings.

databases.

and design

documents.

Some suggestions

were

made for improvement

by the licensee's

-team.

Approximately 30 minor modifications were reviewed by the

licensee's

team.

-12-

Engineering

Support of Operations

The licensee's

team found that system engineering

was

a strength in

support of operations

in response

to conditions that challenged

continued plant operation.

In addition. it was noted by the licensee's

team that engineering

was well prepared

and effective on complex tasks.

The licensee's

team also found that engineering

was not consistent

in

its high quality effort in support of routine work. such

as procedure

writing. addressing

operator

"work around"s

(or compensatory

measures).

and other items.

The licensee's

team concluded the use of probabi listic

risk assessment

information was good.

Engineering Support of Maintenance

The licensee's

team observed

maintenance activities. including a

calibration.

a freeze

seals

a heat exchanger

cleaning,

and also

conducted

several

interviews with maintenance

and engineering

personnel

in both field and office locations.

The licensee's

team reported that

the maintenance craft personnel,

planners'oremen'nd

the director of

mechanical

maintenance

stated that engineering

support of maintenance

was good.'he

licensee's

team reported that mechanical

maintenance

personnel

agreed that it required

more effort to locate the responsible

engineer

since the reorganization that reassigned

their maintenance

engineers

to engineering

sections:

however

. they still indicated that

the support received

was good.

The team reflected concerns

by technical

maintenance

related to the amount of the engineering

backlog.

The

licensee's

team concluded that engineering

support of maintenance

was

effective.

Erosion/Corrosion

Program

The licensee's

team found this program to be

a strength.

This was based

on the licensee's

team review of the program

and observation of emergent

repair

work on

a small bore unisolable

leak in the Unit 1 high pressure

turbine exhaust

socket weld.

The inspectors

were concerned that the licensee's

team review had

focused

more on personnel

safety than plant safety.

For example,

the

inspectors

noted that erosion/corrosion

programs typically focused

on

potential

breaks of carbon steel

piping in the secondary

steam

system

and that few of the components

in the program are safety-related

components.

Nevertheless

there are safety- elated

components

in the

program.

The inspectors

noted that the only repair activity observed

by

the team

was limited to a nonsafety-related

component.

The licensee's

team indicated that they would extrapolate their observations

from the

nonsafety-related

components

to safety-related

components.

However.

when the assessors

found the radiography

performed

as part of the repair

was of poor quality. the inspectors

questioned

why the repair work was

not radiographed

again.

The inspectors

were informed that the

radiography

was acceptable

because

the component

was nonsafety-related,

c~~.

-13-

but the

same radiography

on

a safety-related

component

would not be

acceptable.

The licensee's

team concluded

the erosion/corrosion

program

to be

a strength

based

on observation of nonsafety-related

activities

under the assumption that safety-related

and nonsafety-related

were

treated

the

same.

The inspectors

found the assessor's

logic in review

of the erosionicorrosion

program and the associated

conclusions to be

faulted.

The inspectors

considered this to be

a minor weakness of the

engineering self assessment.

Setpoint Control Program

The self-assessment

team examined the implementation of mechanical,

electrical'nd

instrumentation

and control setpoints

in accordance

with

current setpoint control procedures,

The team conducted setpoint

checks

against electrical

drawings. plant information management

system,

and

plant configuration

as appropriate.

The team concluded that engineering

had effectively communicated.

tracked.

and implemented setpoint

changes'nd

that design basis setpoints

have been properly transmitted via

design

and scaling calculations.

The team verified that the design basis setpoints

have

been

updated in

the plant information management

system

and properly utilized in the

field.

The team observed

a weakness

regarding

a lack of timely setpoint

updates

in the plant information management

system

and that nondesign

basis setpoints

are not comprehensively

incorporated into the plant

information management

system,

even though,

Procedure

CF6. IOl "Setpoint

Control Program",

Revision 0. states'n

part

~ that setpoint data

should

be centralized

in the plant, information management

system

as

a common

data

base.

The team verified that mechanical

and instrumentation

and

control setpoints

are in the plant information management

system.

but

electrical

setpoints

were still shown in the electrical

device list

Orawings

050024

and 050011.

The self-assessment

team concluded that the formation of the continuous

improvement

team, consisting of key representatives

of various plant

departments'ill

enhance

the setpoint control program.

The self-

assessment

team observed that the continuous

improvement

team had

initiated

a prioritization of relevant

issues

and generated

a draft

revision to the setpoint control

program procedure.

The self-assessment

team determined.

due to the preliminary stage of the self'-initiated

continuous

improvement

team. that it was premature to assess

the

effectiveness

and impact on the setpoint control program,

but felt that

continued

management

support in allocated

resources

for improvement

was

warranted.

Independent

Safety Engineering

The licensee's

team found the independent

safety engineering

group to be

highly effective in conducting performance-based

assessments.

Two

strengths

identified by the licensee's

team were independent

safety

-14-

engineering's

performance of comprehensive,

thorough'nd

the in-depth

reviews of industry events.

In addition the independent

safety

engineering's

recommendations

and justification of recommended

actions

in response

to industry events

was viewed as

a strength.

One weakness

was the lack of formal review of licensee

event reports.

Three

recommendations

were also

made

by the licensee's

team as items of

improvement.

These observations

were based

on interviews of independent

safety engineers

and review of their activities by the licensee's

team.

The inspectors

reviewed in detail the problem on the lack of review c~

licensee

event reports

and concurred with the disposition of the issue

in an action request.

Engineering

Backlog

The team documented

the definition of the term "backlog" as work not

actively performed this month and excludes

the upcoming outage work.

which was scheduled.

The team concluded that engineering

backlog was

not effectively managed

and was considered

a serious

weakness.

The team

identified current indicators which reflect

a reduction or stable

workload.

when actual routine workload was increasing

and manpower

was

decreasing.

The self-assessment

team observed that routine workload was not being

measured

in an integrated

manner within the two engineering

departments'ngineering

services

and regulatory

and design services.

The self-

assessment

team recognized effective management

of backlog in two

distinct areas.

overdue

nonconformance

reports

backlog

and design

change

package

drawing backlog. noting.

however. that both of these

areas

were

identified by outside entities to engineering

in the past year.

The

team observed that engineering

had been responsive

to the external

findings and

as

a results

had substantially

reduced

the backlog in these

areas.

The licensee's

team noted

a concern of a possible outstanding safety-

related

issue within the engineering workload.

The team examined

a

sample of backlog of engineering

work and found no safety significant

issues.

The self-assessment

team encouraged

engineering to perform

a

review of the open workload to prioritize the outstanding

work by safety

significance.

The licensee's

team observed that engineering did not

have effective methods for cancelling unnecessary

work.

The team noted

that cancellation criteria. in draft form. had

been developed

as

a tool.

which incorporated

key elements of safety

and management

checks

and

balances.

Problem Resolution

The licensee's

team found

a strength

in the emphasis

placed

on problem

resolution.

in that most problems were resolved in a technically correct

and comprehensive

manner.

One weakness, the licensee's

team identified

-15-

was one problem they discovered that was not fully pursed to resolution.

The licensee's

team observations

were based

on th ir detailed

review of

five areas.

There were three problem areas

on the. auxiliary feedwater

system:

flow issues.

operational problems'nd

steam trap problems.

The

remaining problem areas

were:

diesel

priming pump timer and

a

nonconservative

low temperature

over pressure

setpoint.

The inspectors

reviewed the licensee's

team efforts and concurred with

the licensee's

team conclusions

and disposition of problems in action

requests.

Safety Evaluations

The licensee's

team found no strengths

or weaknesses

in this area.

This

was based

on the team's

in-depth review of five safety evaluations.

The inspectors

reviewed the licensee's

team efforts and concurred with

the licensee's

team conclusions

and disposition.

3

INDEPENDENT NRC INSPECTION

3. 1

Post-Hodification Testin

3. 1. 1

Inspection Objectives

The inspectors

reviewed

a sample of three design

change

packages

and one minor

modification which had been performed

on motor operated

valves

and limited to

stroke time changes.

The packages

reviewed were:

~

DCP J-47193.

Change

gear ratio in valve HS-1-FCV-95.

~

DCP J-47277.

Change

stems

and gears

on 20 valves.

DCP J-48193.

Change

stems

and <ears

on

11 valves.

and

~

AT HH A0366534.

Valve actuator modification on 4 valves.

3. 1.2

Observations

and Findings

The inspectors

found that

~ in the past.

the licensee

had not performed post-

modification testing with the acceptance criteria based

on

a new calculated

'troke

time.

Presently.

the licensee

did have

a programmatic'equirement

to

perform diagnostic testing of valves

when the operator

was overhauled

or

replaced.

This testing would cause

an evaluation of the

new stroke time as

part of post-modification testing.

0

-16-

3.2

Safet

Evaluations

Screenin

s

3.2. 1

Inspection Objectives

The inspectors

reviewed the

10 CFR 50.59 screenings

associated

with five minor

modifications.

The screenings

were performed

by the licensee to determine if

a safety evaluation

was necessary.

The minor modifications were those

identified in the engineering

self-assessment

report

as having "split scope."

The minor modifications were:

A0368806.

fuse replacement.

A0372961

~ spent fuel bridge crane modification,

A0373444.

spent fuel bridge crane modification,

A0390686.

replacement of pressure

indicator isolation valves'nd

A0392219.

replacement

of centrifugal charging

pump bypass

valve.

3.2.2

Observations

and Findings

Minor modifications by proce"ure definition should not have

a safety

evaluation.

but should

have only a screening.

The screening

information was

documented within the minor modification packages.

The licensee

had

a

procedure

which allowed changes

to safety analysis

report figures without a

safety evaluation. if the safety analysis

report text was not changed.

A

drawing change

was initiated. but neither

a safety analysis

report change

nor

a safety evaluation

was initiated.

The licensee

also

had

a procedure in place

that caused

an annual

review of all drawings

used

as figures in the safety

analysis report

and

an update of the safety analysis

report figures

on an

annual

basis

when the drawings were revised.

3.3

Inservice Testin

of Valves

3.3. 1

Inspection Objectives

The inspectors

reviewed the inservice testing of two types of components,

namely the auxiliary feedwater turbine driven

pump steam traps

and the

emergency diesel

generator starting air receiver

check valves.

3.3.2

Observations

and Findings

The inspectors

found that the licensee

had never

placed

these

components

in

the inservice testing program.

although operability of both components

were

necessary

for the auxiliary feedwater

and emergency

diesel

generator

systems

to be operable.

These

components

were not identified in the safety analysis

report

as

ASME Code components.

These

components

had been designed

and built

to United States

of America Standard

831 series of codes.

As

a results

the

only parts of the diesel

system that was considered

to be within the

ASME Code

boundaries

and subjected to inservice testing

was the water jacket.

-17-

In 1993. the

NRC issued

NUREG 1482.

"Guidelines for Inservice Testing at

Nuclear Power Plants,"

recommending

the air check valves should

be in a

inservice testing

program.

The inspectors

were aware that

some licensees

have

put these

valves in their inservice testing

program.

Although there

was not

a

clear requirement

when the check valves are not within the

ASHE Code

boundaries.

the inspectors

judged it prudent to have these

check valves in an

'nservice

testing program.

Having the valves in an inservice testing program

would give the

maximum assurance

of their operability and.

thereby.

the

operability of the diesel

generators.

The inspectors

noted that

~he licensee

tested

the check valves every

18 months in accordance with Surveillance

Procedure

STP V-302,

"Exercising Valves

DEG-214.

225.

236.

247.

258,

and 269, Diesel Starting Air

Compressor

Discharge

Check." Revision 6.

The auxiliary feedwater

steam traps

were tested

every year in accordance

with the preventive maintenance

program

by Maintenance

Procedure

HP E-102.A. "Acoustic Leak Detection Program."

Revision l.

After discussions

with personnel

representing

the

NRC Office of

Nuclear Reactor

Regulations

Mechanical

Engineering

Branch,

the inspectors

confirmed that

non-ASME Code components

that are adequately

tested

on

a

periodic basis

(such

as surveillance or preventive maintenance).

need not be

included in the inservice testing program.

The inspectors

had no further

concerns

in this area.

4

REVIEW OF UPDATED FINAL SAFETY ANALYSIS REPORT

COHHITHENTS

A recent discovery of a licensee

operating their facility in a manner contrary

to the Updated Final Safety Analysis Report description highlighted the need

for

a special

focused review that compares

plant practices,

procedures

andior

parameters

to the Updated Final Safety Analysis Report descriptions.

While

performing the inspections

discussed

in this reports

the inspectors

reviewed

the applicable portions of the Updated Final Safety. Analysis Report that

related to the areas

inspected.

The inspectors verified that the Updated

Final Safety Analysis Report wording was consistent with the observed plant

practices.

procedures

and/or

parameters.

The licensee

had previously found

problems with the accuracy

and consistency of the safety analysis report and

had taken corrective actions in regard to this problem.

0

ATTACHMENT

1

PERSONS'CONTACTED

1. 1

Licensee

Personnel

J. Alviso Engineering Assistant.

Regulatory Services

M. Angus.

Manager.

Regulatory

and Design Services

D. Brosnan.

Supervisor.

Licensing and Design Basis

Management

K. Bych. Supervisor.

Independent

Safety Engineering

Group

W. Crockett'anager.

Nuclear Quality Services

T. Fetterman.

Director. Electrical

and Instrumentation

8 Control. System

Engineering

T. Grebel, Director, Regulatory Services

C. Groff, Director, Secondary

Systems

Engineering

C.

Harbors

NRC Interface,

Regulatory Services

R.

Hess.

Senior Project Engineer.

Support Engineering

S. Ketelsen.

Senior Engineer.

Nuclear Quality Services

D. Miklush. Manager.

Engineering Services

G.

Rueger.

Senior

Vice President.

Nuclear

Power Generation

J.

Shoulders.

Director. Support Engineering

D. Taggart.

Director. Nuclear Safety Engineering

J.

Tomkins. Director. Licensing and Design Basis

Management

R. Waltos. Director, Balance of Plant Systems

Engineering

R.

Webb. Director. Special

Projects

and Technical

Support

D. Vosburg

~ Director. Nuclear

Steam Supply System

J.

Young. Director, Quality Assurance

1.2

NRC Personnel

S.

Boynton. Resident

Inspector

The personnel

listed above attended

the exit meeting.

In addition to the

personnel

listed above.

the inspectors

contacted

other

personnel

during this

inspection period.

2

EXIT MEETING

An exit meeting

was conducted

on April 12.

1996.

During this meeting,

the

inspectors

reviewed the scope

and findings of the report.

The licensee did

not express

a positior. on the inspection findings documented

in this report.

The licensee did not identify as proprietary

any information provided to. or

reviewed by. the inspectors.