ML16342D295

From kanterella
Jump to navigation Jump to search
Insp Repts 50-275/96-10 & 50-323/96-10 on 960415-25.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support
ML16342D295
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 05/14/1996
From: Powers D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML16342D296 List:
References
50-275-96-10, 50-323-96-10, NUDOCS 9605210490
Download: ML16342D295 (18)


See also: IR 05000275/1996010

Text

ENCLOSURE

U.S.

NUCLEAR REGULATORY COMMISSION

REGION I

II'nspection

Report:

50-275/96-10

50-323/96-10

Licenses:

DPR-80

DPR-82

Licensee:

Pacific Gas

and Electric Company

77 Beale Street.

Room 1451

P.O.

Box 770000

San Francisco.

California

Facility Name:

Diablo Canyon Nuclear

Power Plant.

Units

1 and

2

Inspection At:

San Louis Obispo, California

Inspection

Conducted:

April 15-25.

1996

Inspector:

Claude

E. Johnson.

Reactor

Inspectors

Maintenance

Branch

Division of Reactor

Safety

Approved:

r.

.

owers,

ie

.

ann enance

rane

Division of Reactor Safety

a e

Ins ection

Summar

Areas

Ins ected

Unit 2

Routines

'announced

inspection of the implementation

of maintenance activities.

Areas

Ins ected

Unit 1:

No inspection of Unit

1 was performed.

Results

Unit 2

~0erations

~

The operations

functional area

was not inspected.

Maintenance

~

There was

good supervisory oversight of the work activities observed

(Section 2.1.1).

~

Work orders

and instructions

were clear

and detailed

enough for workers

to accomplish the tasks

(Section

2. 1. 1).

96052i0490 9605i7

PDR

ADOCK 05000275

8

PDR

-2-

~

Planners

were observed

in the field scoping job activities before

developing work instructions

(Section 2. 1. 1).

~

There was good foreign material exclusion control during work activities

(Sections

2.1.1

and 2.1.1.1).

~

A licensee

maintenance

foreman maintained close control over contractor

personnel

work activities (Section

2. 1. 1).

~

Maintenance

personnel

were fully aware of management

expectations

and

procedural

compliance

requirements.

In particular,

maintenance

personnel

planning. coordination.

and execution

performance

was

excellent during the removal of a reactor

coolant

pump seal

package.

One example of poor work practice

was identified when

a maintenance

technician did not have the work package at the work location

(Sections 2.1.1, 2.1.1.1.

2.1.1.2.

and 2.1.1.3).

~

In general,

the material condition of the equipment

inspected

was good

(Section 2.3).

En ineerin

~

The engineering

functional area

was not inspected.

~P1

tS

t

There was continuous quality control

and radiation protection oversight

of the work activities observed

(Section 2.1.1).

~

Site personnel

were identifying an increased

amount of problems'hich

was attributed to their heightened

awareness

of the action request

process

(Section 2.2).

~

In general.

housekeeping

was good (Section 2.3).

R~1U i

1:

N t

ppli

b1

Summar

of Ins ection Findin s:

~

None

Attachments:

~

Attachment

1

- Persons

Contacted

and Exit Meeting

~

Attachment

2

- Documents

Reviewed

-3-

1

PLANT STATUS

DETAILS

During this inspection period. Unit

1 was at power,

and Unit 2 was in

Refueling Outage

7.

2

MAINTENANCE PROGRAM IMPLEMENTATION (62700)

The inspector

used

NRC Inspection

Procedure

62700 for guidance to:

~

Observe

maintenance activities in progress.

!

Determine if maintenance activities were implemented in accordance

with

work instructions

and procedures.

d

~

Observe craft performance of selected

work packages

and evaluate craft

experiences

with recent work packages.

2. 1

Maintenance Activities Ins ected

The inspector

observed all, or portions of, licensee activities related to

implementing approximately

20 maintenance

work orders.

Specific work orders

witnessed

are listed in Attachment

2.

2. 1. 1

Observations

and Findings

The inspector

found that work activities performed in accordance

with the work

orders

were done in a professional

and thorough manner.

All work activities

observed

were performed with the work package

present

except for one instance

discussed

in Section

2. 1. 1.2.

The inspector noted excellent supervisory.

quality controls

and radiation protection oversight of the work activities

observed.

The inspector considered

the observations

below as positive

elements of the licensee"s

maintenance

program or its implementation.

Work orders

and instructions

were clear

and detailed

enough for workers

to accomplish tasks.

Several

planners

were observed

in the field scoping the job activities

before developing the work instructions.

Good foreign material exclusion controls were noted during work

activities'nd

Continuous controls

by licensee

foreman were visible over contractor

personnel

work activities.

0

2.1.1.1

Reactor Coolant

Pump Seal

Removal.

Inspection,

and Replacement

The inspector

observed

a'thorough prejob briefing before the removal of

Reactor Coolant

Pump 2-1 seal

package.

The task

was performed in'an excellent

and controlled manner.

The removal of Seals l. 2.

and

3 were conducted in a

smooth flowing and efficient manner.

The inspector concluded that the

maintenance

technicians

were well trained

and experienced.

The foreign

material exclusion coordinator performed

an excellent job in controlling

foreign material exclusion in the job area.

The coordinator

controlled every

item that went into and out of the reactor coolant

pump.

There was excell~~t

communication

and visual cont""t between

the coordinator

and the mechanical

maintenance

technician inside the pump.

Radiation protection personnel

rovided excellent support in monitoring the radiation

and contamination

evels

and obtaining

smear

samples

during the removal of all three seals.

The

vendor representative

(Westinghouse)

provided continuous oversight of the work

activity.

Overall. the removal of Reactor Coolant

Pump 2-1 seal

package

was well

planned. coordinated'nd

executed.

2. 1. 1.2

Replacement

of Main Feedwater

Pump Motor

The inspector

observed

a maintenance

technician

remove

an existing coupling

from Main Feedwater

Pump Motor

PP 2-1.

and replace it with a new coupling.

The inspector

asked the maintenance

technician to provide the work package

for

review.

The maintenance

technician

informed the inspector that he had left

the work package in the maintenance

shop.

proceeded

to the shop to acquire the

work package.

and returned.

The maintenance

technician

informed the inspector

that. normally. the work package

would be at the work location;

however.

in

this instance

the shop

was not far away and the work was within the skill of

the craft.

The inspector

informed licensee

management of the incident described

above.

The licensee's

management

informed the inspector that the maintenance

technician

had not met management

expectations

that maintenance

technicians

should have work packages

at the work locations.

The inspector

noted that the replacement of the coupling appeared

to be witl; n

the skill of the craft.

There were no sign off steps

in the instructions that

the maintenance

technicihn

had over looked.

However,

the inspector considered

that working without

a work package

was

an example of poor work practice that

appeared

to be isolated.

Z. l. 1,3

Nondestructive

Examinations

The inspector also witnessed

nondestructive

examinations

performed

by

nondestructive

technicians

on several

maintenance activities observed.

The

inspector

determined that these

examinations

were performed in accordance

with

procedures.

l

J '

la

0

-5-

The inspector

reviewed nondestructive

examination

records listed in

Attachment

2 of this report.

2. 1.2

Personnel

Interviews

The inspector

interviewed maintenance

personnel

during work activities in

progress

about the following subjects:

~

Procedural

compliance,

~

Quality of work packages

and instructions.

~

Action request

process,

Procedural

step signoffs,

~

Management

expectations.

and

~

The recent organizational

combining of instrumentation

and control with

electrical.

The inspector determined that the majority of maintenance

personnel

were fully

aware of management

expectations

and procedural

compliance requi rements.

In

general,

most maintenance

personnel

were pleased with the content

and detail

of procedures

and work packages.

The maintenance

technicians

also indicated that they were familiar with the

action request

process

and the requirement to signoff on completed work steps

in the work packages.

The inspector

also questioned

instrumentation

and controls

and electrical

technicians

about the combining of the two groups into the technical

maintenance

group.

Several

technicians

indicated that most technicians

(instrumentation

and control

and electrical) did not like the merger,

but had

began to accept it.

The inspector

asked

the technicians if there

was any

decline in safety

as

a result of this merger.

The technicians

did not believe

there was

a declining trend in safety

as

a result of the merger.

The

technicians

informed the 'nspector that most technicians

took pride in thei r

work and would not compromise safety of the plant over

a merger.

2.2

Review of Action Re uests

The inspector

selected

action requests

generated

by technical

and mechanical

maintenance

from February to April 1996 (approximately

2 months) for review.

The inspector

reviewed those action requests

listed in Attachment

2 of this

report.

The purpose of this review was to determine the types of maintenance-

related

problems that had been identified and if appropriate corrective

0

-6-

actions

were taken.

Most'esolutions of the action requests

were considered

by the licensee

as incomplete at the time of the inspection.

Howevers

in

reviewing these action requests'he

inspector identified several

potential

programmatic

problem areas'uch

as:

~

Components

incorrectly installed/poor configuration control.

~

Lack of procedural

adherence,

and

~

Vendor drawings/procedures

not revised or included in work packages.

The inspector

informed licensee

management

that attention

was

needed

in these

areas that had potential

programmatic

problems,

especially safety-related

systems

and structures,

to ensure

themselves

that these

components,

structures.

and systems

were built in accordance

with design drawings.

Licensee

management

informed the inspector that action requests

were being

initiated more than in the past

because of heightened

awareness.

The

inspector considered

the licensee's

actions to heighten site personnel

awareness

of the action requests

program

as

a positive performance indicator.

The inspector discussed

the above potential

programmatic

problem areas with

NRC management,

which concluded that this concern would be reviewed during

a

near-term inspection that was previously planned.

2.3

Material Condition

The inspector toured the Unit 2 auxiliary building and diesel generator

building. observing

housekeeping

and material conditions of the following

components

and their

rooms:

Containment

Spray

Pumps

PP-2-2

and PP-2-1;

. Charging

Pump (Positive Displacement

Pump) 2-3;

Diesel Generators

2-1. 2-2,

and 2-3;

Unit 2 Battery

Room 332-2 (Battery 22):

and

~

Component Cooling Water

Pumps

PP-2-2,

2-3.

and 2-1.

The inspector

noted that there were no excessive oil or water leaks visible

on, or near'he

equipment.

and housekeeping

was good in the rooms.

3

REVIEW OF UPDATED FINAL SAFETY ANALYSIS REPORT

(UFSAR)

COMMITMENTS

A recent discovery of a licensee

operating their facility in a manner contrary

to the

UFSAR description highlighted the need for a special

focused, review

that compares

plant practices.

procedures

and/or

parameters

to the

UFSAR

descriptions.

While performing the inspections

discussed

in this report, the

inspector

reviewed the applicable portions of the

UFSAR that related to the

containment

fan cooler units.

The inspector verified that the

UFSAR wording

was consistent with the obs..rved plant practices,

technical specifications,

procedures,

and/or parameters.

The licensee

had

made proposed

changes

on

marked

up pages of the

UFSAR.

However.

these

marked

up page

changes

had not

been incorporated into the latest revision as of this inspection.

F

~

R%,1

V

~

EI

ATTACHMENT 1

PERSONS

CONTACTED AND EXIT MEETING

1

PERSONS

CONTACTED

1. 1

Licensee

Personnel

"J. Alviso. Engineering Assistant.

Regulatory Services

  • M. Brewer. Supervisor,

Procurement

Services

  • D. Brosnan.

Director. Regulatory Services

  • C. Harbor.

NRC Interface.

Regulatory Services

R. Harris. Director, Materials.

Haintenance

Services

"J. Minds. Director, Quality Control

  • T. McKnight, Supervisor.

Quality Assurance

  • D. Hiklush. Manager.

Engineering Services

~J.

Holden,

Hanager.

Maintenance

Services

  • 0. Oatley, Director, Mechanical

Maintenance

  • H. Phillips. Director, Technical

Maintenance

  • R. Powers.

Acting Plant Manager

~J.

Sopp. Supervisor.

Quality Control

  • B. Waltos. Director. Balance of Plant,

Engineering Services

1.2

NRC Personnel

  • S. Boynton. Resident

Inspector

In addition to the personnel

listed above,

the inspector contacted other

personnel

during this inspection period.

  • Denotes

personnel

that attended

the exit meeting

on April 25,

1996.

2

EXIT HEETING

An exit meeting

was conducted

on April 25.

1996.

During this meeting,

the

inspector

reviewed the scope

and findings of the report.

The licensee did not

express

a position on the inspection findings documented

in this report.

The

licensee did not identify as proprietary any information p"ovided to,

or

reviewed by, the inspector.

0

~

~

ATTACHMENT 2

ACTIVITIES WITNESSED AND DOCUMENTS REVIEWED

Work Order Activities Witnessed

WO R0144840

- "Removal/Internal

Inspection.

Governor Valve MS-2-FCV-15"

WO R0079596

- "Disassembly

and Inspection of Main Feedwater

Pump Turbine 2-2,"

Tasks

2. 3. '4. 5.

and

6

WO R0118350

WO R0119246

- "Internal Inspection

Feedwater

Valve FW-2-494." Task

1

- "Disassemble

and Inspect

RCP 2-1 Seals."

Tasks

1 and 2

WO R0119394

- "MS-Z-FCV-134, Internal Inspection,"

Task

1

WO R0095420

- "Breaker Testing,

480V Vital Bus

H ~ " Task

1

WO R0093939

- "Surveillance Testing of 480V Vital Bus H." Task

1

WO R0093699

- "Station Battery Performance

Test. Battery 22," Task 1.2

WO C0141477

- "Install New Relays

and Terminate

Relay Wiring to 4.16kV

Cubicle 14.

Bus

H"

WO C0141475

WO C0141612

WO C0140125

WO R0138543

WO C0142533

WO C0139986

WO C0141244

WO C0142529

WO C0143868

WO R0106386

WO C0142543

"Install

New Relay Boxes, Cubicle 12. 4. 16kV Bus H." Task

3

"Install Relays

(White Light). Cubicle 8.

Bus 8." Task

3

"Weld Reducer to Feed Ring.

SG 2-4."

Task

3

"Charging

Pump P-2

~ Coupling/Strainer /Inspection."

Task

1

"Main Feedwater

Pump 2-2,

Speed

Probe Installation." Task

1

"Main Feedwater

Pump 2-1.

Replacement

of Motor," Task

2

1

"Replace Cylinder Heads.

Diesel Generator

2-2"

"Replace

Main Feedwater

Pump (2-1) Thrust Bearing Probes"

"Preheat

and Weld Repair of FWP2 Steam

Chest

~ " Task 1.2

"AssemblyKTorquing of Bolts,

AVW FW PP 2-1."

Task

1

"DG 2-3 EGA/EGB Governor Adjustments."

Task

1.

~ ~

0

I'

-2-

Procedures

AD7. ID1

"Use Of Plant Information Management

System

(PIMS) Work Order

Module." Revision

1

AD7

"Work Planning

and Management,"

Revision

OB

TP TD-9610

"Installation Testing Of Yaskawa/PDS

SF6 4. 16kV Gas Rotary Arc

Circuit Breakers

on Energized

Bus or Line." Revision

0

AD2. IDl

"Procedure

Use and A"herence." Revision

4

MA1

"Maintenance,"

Revision

1A

AD7. ID2

"Standard

Plant Priority Assignment

Scheme."

Revision

1B

MA1. IDB

"Control Of Temporary Rigging From Plant Equipment,

Piping and

Structural

Members'

" Revision

OA

MT-4

"General

Magnetic Particle Examination Procedure."

Revision

2

NonDestructive

Examination

Records

Auxiliary Feedwater

Pump (Z-l) rotor - Fluorescent

magnetic particle

Feedpump Turbine (2-2). lower feedpump

case

nozzle block - Fluorescent

magnetic particle

~

Feedpump Turbine (2-2), blade rings

- Fluorescent

magnetic particle

ACT~6~ REtCUf'STS

A0399129

A0399339

A0399498

A0399501

A0397567

A0398350

A0395193

A0396149

A0399152

A0398986

A0348328

A0396617

A0394183

A0348328

A0397247

A0398039

A0398535

A0394540

A0394540

A0395434

A0396181

A0397028

A0393497

A0396658

A0398638

A0398642

A0394185

A0395585

A0398508

A0399444

A0396983

A0397178

A0397403

A0398508

A0399386

A0393945

A0395284

A0395081

A0395084

A0394191

A0395085

A0395087

A0399384

A0398772

A0397917

A0397920

A0396821

A0396822

A0398221

A0398548

A0398552

A0394181

A0325009