ML16342C851

From kanterella
Jump to navigation Jump to search
Insp Repts 50-275/95-01 & 50-323/95-01 on 950113-17 & 23-27. No Violations Noted.Major Areas inspected:safety-related MOV Testing & Surveillance & Followup of Engineering Issues
ML16342C851
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 02/22/1995
From: Westerman T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML16342C850 List:
References
50-275-95-01, 50-275-95-1, 50-323-95-01, 50-323-95-1, NUDOCS 9503070084
Download: ML16342C851 (38)


See also: IR 05000275/1995001

Text

ENCLOSURE

U.S.

NUCLEAR REGULATORY COHHISSION

REGION IV

Inspection Report:

50-275/95-01

50-323/95-01

Licenses:

DPR-80

DPR-82

Licensee:

Pacific Gas

and Electric Company

77 Beale Street,

Room 1451

P.O.

Box 770000

San Francisco.

California

Facility Name:

Diablo Canyon Nuclear

Power Plant. Units

1 and

2

Inspection At:

Diablo Canyon site,

San Luis Obispo County, California

Inspection

Conducted:

January

13-17 and 23-27,

1995

Inspectors:

C. Hyers,

Reactor Inspector,

Engineering

Branch

Division of Reactor

Safety

H.

Runyan

~ Reactor

Inspector,

Engineering

Branch

Division of Reactor

Safety

Accompanying

Personnel:

H. Rathbun, Office of Nuclear

Reactor Regulation

Approved:

es

erman,

ie

.

ngineer>ng

nc

Division of Reactor Safety

Ins ection

Summar

Areas

Ins ected

Units

1 and

2

Special,

announced

inspection of'afety-

related motor-operated

valve testing

and surveillance

and followup of

engineering

issues.

Results

Units

1 and

2

~

The inspectors verified completion of the licensee's

commitments to

Generic Letter 89-10, contingent

on submittal within 60 days of the date

of this report,

a letter to the

NRC documenting additional justification

related to periodic verification and the capability of untested

motor-

operated

valves (Section

1. 1).

9503070084

950302

PDR

ADQCK 05000275

8

PDR

-2-

i

~

The inspectors

concluded that the licensee

had adequately

established

the design basis capability of motor-operated

valves that had not been

tested at or

near

design basis conditions.

Some additional effort was

needed to confirm generic

assumptions

used in support of untested

motor-

operated

valves

and to address

certain valves using the Electric Power

Research

Institute valve factor evaluation process

(Section 1.5).

~

The licensee's

motor-operated

valve program included consideration of

valve mispositioning (Section 1.2).

~

The licensee's

analysis

and corrective actions taken for potential

pressure

locking and thermal binding concerns

were thorough

and timely.

Modifications of susceptible

valves

had been completed.

(Section 1.3).

The inspectors

found that the licensee

had incorporated all appropriate

vendor information regarding diagnostic

system

measurement

accuracy.

Additional sources of error

had been identified (Section 1.4).

Grouping of valves for comparison of test results

was utilized to

justify the capability of untested

valves.

Additional information was

requested

regarding implementation of the grouping guidelines of Generic Letter 89-10.

Supplement

6 (Section 1.5).

Limited differential pressure testing

was included

as part of the

licensee's

plans for periodic verification.

The licensee

was requested

to provide additional information regarding several

issues

related to

periodic verification (Section 1.6).

Detailed maintenance fitup of valve internals

and performance trending

had been

implemented

and were considered

strengths

in the licensee's

ongoing program (Section 1.6.2 and 1.7.2).

Continuing strong quality assur ance oversight of the motor-operated

valve program was evident.

The technical

depth of the audits

was

considered

a strength.

Some recent audit findings had not been resolved

at the time of the inspection

(Section 1.8).

Summar

of Ins ection Findin s:

Inspection

Followup Item 275;323/9319-02

remains

open pending issuance

of a planned

NRC generic communication

on the issue of pressure

locking

and thermal binding (Section 1.9. 1).

Inspection

Followup Item 275;323/9139-02

was reviewed but left open

(Section 1.9.2).

Additional information was requested

to clarify ongoing program

commitments

as identified in Attachment 2.

Attachments:

-3-

~

Attachment

1

- Persons

Contacted

and Exit Meeting

~

Attachment

2 - Additional Information Requested

to Clarify Ongoing

Program

Commitments

'

4

DETAILS

1

GENERIC LETTER 89-10,

"SAFETY-RELATED MOTOR-OPERATED VALVE TESTING AND

SURVEILLANCE"

(2515/109)

On June

28 '989,

the

NRC issued

Generic Letter 89-10, which requested

licensees

and construction permit holders to establish

a program to ensure

that switch settings for safety-related

motor-operated

valves were selected.

set.

and maintained properly.

Subsequently,

six supplements

to the generic

letter have

been issued.

NRC inspections of licensee

actions

implementing

commitments to Generic Letter 89-10 and its supplements

have

been conducted

based

on guidance

provided in Temporary Instruction 2515/109

~ "Inspection

Requirements

for Generic Letter 89-10, Safety-Related

Motor-Operated

Valve

Testing

and Surveillance,"

Revision

1.

Temporary Instruction 2515/109

was

divided into two parts:

Part

1,

"Program Review;" and,

Part 2, "Verification

of Program Implementation."

The Temporary Instruction 2515/109,

Part

1,

program review inspection

was conducted at Diablo Canyon during October

1991

and was documented

in NRC Inspection Report 50-275/91-39;

50-323/91-39.

The

Temporary Instruction 2515/109,

Part 2. implementation

review inspection

was

conducted at Diablo Canyon during July 1993 and was documented

in NRC

Inspection Report 50-275/93-19;

50-323/93-19.

A followup Part

2 inspection

was conducted during June

1994 and was documented in NRC Inspection

Report 50-275/94-17;

50-323/94-17.

The licensee notified the

NRC in a letter

dated

November 28,

1994. that Diablo Canyon's

commitments to Generic Letter 89-10 had been completed.

The principal focus of this inspection

was to evaluate the licensee's

process

for qualifying the design basis capability of each of the motor-operated

valves in the Generic Letter 89-10 program.

Though most valves were tested

under conditions applying

a high percentage of the design basis differential

pressure,

some were tested only under static or low differential pressure

conditions.

As discussed

in Generic Letter 89-10, these

were considered to be

valves for which

a two-stage

approach

should

be utilized.

The first stage

was

.

to set

up the valve using the best available

information.

The second

stage

required

a more precise

methodology.

which could include comparison to a

similar valve, prototype testing,

use of the Electric Power Research

Institute (EPRI) testing results,

or other methods.

1. 1

Summar

Status of Generic Letter 89-10 Motor-0 crated

Valves

At the time of the inspection,

155 motor-operated

valves were included in the

Generic Letter 89-10 program.

Approximately 68 percent of the motor-operated

valves

had been tested

under differential pressure

conditions.

The remainder

of the motor-operated

valves were tested only under static conditions.

-5-

Based

on the documents

reviewed during this inspection

and discussions

with

cognizant licensee

personnel,

the inspectors verified completion of the

licensee's

commitments to Generic Letter 89-10. contingent

on submittal of

additional justification and information related to several

areas of ongoing

program activities

as described

in this report.

and subsequent

NRC review.

1. 1. 1

Generic Implications Report

The inspectors

reviewed Procedure

ICE-12,

"18C Engineering

Procedure for

Preparation of Rotor Operated

Valve Sizing and Switch Setpoint Calculations,"

Revision 10.

This procedure

was developed

and implemented to ensure that

motor-operated

valves were properly sized

and setup prior to differential

pressure testing.

In addition,

Procedure

ICE-12 provides guidance

on

evaluating the results of differential pressure testing.

As required

by Procedure

ICE-12. the licensee

developed

a "Report on Generic

Implications of 89-10 Testing" following completion of the differential

'ressure

testing

recommendations

of Generic Letter 89-10.

The inspectors

reviewed the licensee's

report dated

December

9,

1994.

This document

summarized the methods

and assumptions

used to qualify each valve in the

program as being capable of performing its safety function under

design basis

conditions.

The report discussed

the results of differential pressure testing

for each valve type and included

an evaluation of assumed

valve factors.

rate

of loading.

and stem friction coefficient.

Test valve factors

and rates of

loading were compared to design assumptions.

In cases

where test results

indicated marginal motor-operated

valve capacity,

the licensee

provided an

engineering evaluation to support design basis capability.

The. inspectors

reviewed the available margin identified by the licensee

for

each of the motor-operated

valves at the conclusion of their program.

Generally,

the inspectors

found that the licensee

had adequately

demonstrated

the existing design basis capability for each of the valves consistent with

their

program plan commitments.

1. 1.2

Actions Taken for Valve Factor Exceeding Assumptions

Valve factor is

a measure of the condition of the valve internals affecting

valve operation.

Valve factor is defined

as the ratio of the actuator thrust

to the differential pressure

force.

The actuator

thrust setpoint

range

was

established

using the design valve factor.

The existing margin based

on as-left switch settings

was termed the "ICE-12

margin," after Procedure

ICE-12, which defines the motor-operated

valve

testing program.

A positive

ICE-12 margin was required for motor-operated

valve operability.

The licensee did not routinely revise the design valve factor for

a motor-

oper ated valve group to account for measured

valve factors that exceeded

the

original assumption.

This feedback of test information was

a

common method to

validate design basis capability of the entire allowable range of thrust

-6-

settings.

Rather,

long-term maintenance of acceptable

valve settings

was

controlled by using what was termed the "effective margin."

The effective

margin was based

on the lowest permissible thrust setting within the setpoint

window.

The fact that

some motor -operated

valves

had positive effective

margins

even though the measured

valve factor exceeded

the design valve factor

was attributable to conservatisms

in estimating

pa'cking

and ejection loads

and

rates of loading.

Some motor -operated

valves,

however,

had negative effective

margins

(meaning that. if the valve were set at the low end of the setpoint

window, it may not have adequate capability).

The licensee

had implemented

administrative controls to prevent changing the switch setting for these

motor-operated

valves until the setpoint window has

been appropriately

adjusted.

The inspectors

found the licensee's

actions to be adequate.

1. 1.3

Rate-of-Loading Assumption Validated

The generic implications report summarized

an evaluation of the assumptions

made for rates-of-loading.

The rate-of-loading

assumption

was important for

the evaluation of static-only motor -operated

valves

and for other valves for

which

a accurate

rate-of-loading

was not obtained.

Rate-of-loading is the

percentage

change in the thrust at control switch trip from the static to the

dynamic test,

expressed

as

a positive number when the static control switch

trip thrust is greater than the dynamic thrust.

The licensee

had established

a margin of 15 percent to account for rate-of-loading.

Six gate valves

and

four globe valves

had rates-of-loading calculated to be greater

than

15

percent,

with the highest gate valve being 24.65 percent

and the highest globe

valve being 30.30 percent.

The average rate-of-loading for gate valves

was

a

ositive 2.39 percent.

For globe valves, the average

was

a positive

.27 percent.

The licensee

evaluated

each instance

where the measured

rate-

of-loading exceeded

the design value.

Two patterns

were noted:

one in which

high rates of loading were associated

with low test differential pressures.

and one in which high rates of loading were associated

with low measured

valve

factors.

The inspectors

reviewed this information and concluded that the use

of a design value of 15 percent rate-of-loading

was justified.

1. 1.4

Limited Validation of Stem Lubrication Assumption

The generic implications report also addressed

the consistency

between the

measured

and

assumed

values for stem friction coefficient.

The design

assumption for stem friction coefficient was 0.2.

Since the licensee's

diagnostic system did not regularly measure

torque,

only five tests

performed

with a Teledyne

stem mounted thrust and torque strain gage gave results

from

which a stem frictIon coefficient could be calculated.

The highest

measured

values for stem friction coefficient were 0. 12 in the closing direction and

0. 18 in the opening direction.

Based

on these tests

and industry experience,

the inspectors

considered

the design

assumption of 0.2 to be acceptable.

0

-7-

The licensee identified that for one motor-operated

valve.

1-9001B,

a stem

friction coefficient assumption of 0. 15 was used in lieu of 0.2 because

the

use of 0.2 would have yielded

a negative capability margin in the opening

evaluation.

This motor-operated

valve was

on

a special

3-month inspection

and

lubrication schedule.

The inspectors

noted that the licensee

also included

a

7 percent margin for

stem lubrication degradation

in thei r determination of motor-operated

valve

capability.

The inspector

found the licensee's

actions to be adequate.

1. 1.5

Inadvertent

Use of Neolube

on Valve Internals

The licensee

observed

unexpectedly

low pullout thrust requirements

during

initial static testing of several

motor-operated

valves immediately following

valve internal maintenance.

The licensee

discovered that maintenance

personnel

had applied the graphite

base lubricant "Neolube" to the internal

guides.

disks

and seats of 14 Generic Letter 89-10 motor -operated

valves

during valve reassembly prior to differential pressure testing.

The

maintenance

practice

had been

implemented

by procedure to assist in fitup

reassembly of the valve.

Engineering

was unaware of this practice at the time

of the differential pressure testing

and

became

concerned that this practice

may have affected the validity of differential pressure test results.

The

licensee

conducted

various static tests to determine the effects of neolube

on

valve performance.

The licensee's

testing

found that motor-operated

valve

performance

was not affected

by the use of neolube.

In addition. the licensee

concluded that neolube

was rapidly removed

by water

from the valve internals

after

a few valve strokes.

The licensee

considered that all valves

had been

stroked at least ten times prior to differential pressure testing.

The

licensee

concluded that valve performance

during differential pressure testing

was not affected

by the use of neolube.

~

The inspectors

found that the licensee's

static testing

and evaluation

focused

on disk pullout performance

and did not address

valve factor performance

under

differential pressure

conditions.

The inspectors

found no test-basis

for the

licensee's

conclusion regarding the effect of neolube

on valve factor

performance.

The inspectors

were concerned that lubrication of the valve

internals

may have resulted in nonconservative

determinations

of actual

valve

factors

from testing

soon after

reassembly.

The inspectors

noted that the

licensee

had generically

assumed that actual

valve factor did not change.

and

no margin had been specifically identified to accommodate

valve factor

degradation.

The inspectors

reviewed the test results for the

14 affected motor-operated

valves

and found that all valve factors were consistent with the results of

other

valves in thei r group.

None of the valves exhibited

a low valve factor.

0

-8-

In response

to the inspectors'oncern,

the licensee identified that one of

the neolubed valves

had been selected for differential pressure testing during

periodic verification.

According to the licensee,

changes

in valve factor

performance attributable to the previous

use of neolube will be evaluated at

that time to confi rm their opinion.

The licensee is being requested

to

provide additional detai

1 of thei r use of periodic testing to validate thei r

assumptions

regarding the use of neolube in response to this inspection

report.

1,2

~Ill

ltl

The inspectors

reviewed the licensee's

motor-operated

valve program to

determine the licensee's

current treatment of valves subject to

mispositioning.

As recommended

in Generic Letter 89-10. the scope of licensee

motor-operated

valve programs

was to include motor-operated

valves which were

not prevented

from inadvertent mispositioning from the control

room.

The inspectors

found that the licensee's

program continued to include motor-

operated

valves which were not prevented

from inadvertent mispositioning.

The

licensee

had not change'd their consideration of mispositioning in establishing

the scope of their

program.

The inspectors

found the licensee's

position regarding the consideration of

mispositioning within their Generic Letter 89-10 program to be adequate.

1.3

Pressure

Lockin

and Thermal Bindin

During the first Part

2 inspection,

the inspectors

reviewed the licensee's

program to address

pressure

locking and thermal binding, which was documented

in Nuclear Engineering

and Construction Ser'vices

memorandum to Nuclear

Operations

Supports

"Pressure

Locking of Gate Valves," dated October 6,

1992.

As of the date of this inspection,

no additional

program documentation

had

been

issued

on this subject.

The licensee

had identified 26 motor-operated

valves in each unit which met

their review screening criteria for ya1ves susceptible to pressure

locking and

thermal binding.

As

a result of their evaluation.

the licensee identified six

valves considered

susceptible for pressure

locking:

1/2-8703,

2-8801A/B,

and

2-8803A/B.

No valves were considered

susceptible to thermal binding.

The licensee

review recommended

three options

as corrective actions for each

of the valves:

(1) Drill a hole in the high pressure

side of the disk.

(2) Install

a bonnet leakoff line and block valve,

or

(3) Install

a bonnet relief line and discharge line.

During this inspection,

the inspectors

reviewed closed Action

Request

A0316042,

which identified that modifications to the six identified

valves

had been completed in Refueling Outages

1R6 and 2R6.

In addition to

-9-

these modifications, the licensee

stated that,

based

on information obtained

from industry sources.

modifications (drilled upstream valve disks) were

performed

on the six power-operated relief valve block valves,

1-8000A/B/C and

2-8000A/B/C.

The inspectors

concluded that the licensee

had taken sufficient steps to have

met its commitments associated

with pressure

locking and thermal binding for

Generic Letter 89-10 closure.

The inspection followup item (275;323/9319-02)

tracking this issue will remain open pending issuance

and subsequent

reviews

of a planned

NRC generic communication.

1.4

Actions in Res

onse to Generic Letter 89-10

Su

lement

5

The inspectors

reviewed the licensee's

actions in response

to Supplement

5 of

Generic Letter 89-10.

Supplement

5 had requested

information regarding the

diagnostic

systems

being used

by the licensee

during their Generic Letter 89-10 program.

The inspectors

found that the licensee

had responded to Supplement

5 and

identified that the

VOTES diagnostic test system

was used for diagnostic

testing during thei r Generic Letter 89-10 program.

The licensee

uses either

the

VOTES thrust transducer

(yoke-mounted)

or the Teledyne quick stem sensor

transducer

(stem mounted).

Several

unexpected

sources of error were

identified by the licensee during their testing,

as described

below.

The inspectors

found that the licensee

had incorporated all appropriate

vendor

information regarding

measurement

accuracy using the

VOTES system.

The inspectors

found the licensee's

actions to be adequate.

1.4. 1

Transition Zone with Split Stem Design

The licensee identified two incidents of gross calibration errors using the

yoke-mounted,

VOTES thrust sensor

on valves with split-stem designs.

The

discrepant

measurements

were observed

on Auxiliary Feedwater

Globe

Valves 1-LCV-107 and 2-LCV-106.

The stem design for Valves

LCV-106 and

-107

consisted of a coupled

assembly of a threaded portion and

an unthreaded,

portion.

The coupling also served

as the torque restraint.

For purposes of

calibrating the

VOTES thrust sensor

mounted

on the valve yoke. the licensee

had treated this configuration

as

a solid stem geometry change

and applied

vendor recommendations

to avoid locating the "mini-c" calibrator in the

transition zone.

Later confirmatory thrust measurements

used

a strain gage

transducer

(quick stem sensor)

mounted directly on the unthreaded

portion of

the valve stem and analytically calibrated,

indicated only half of the

previously measured thrust.

After extensive investigation of the cause of the observed

discrepancy

including communications with the vendor (Liberty), the licensee

concluded

that transition

zone effects for split-stem valve designs

extended

much

farther beyond the range identified by the vendor,

introducing an error in the

e

0

'

i

-10-

output of the mini-c calibrator.

Due to space limitations in the area

between

the valve yoke and the stem,

the mini-c clamp was required to be placed in an

orientation that caused

a three-point contact with the stem.

The licensee

concluded that having the mini-c clamp in three-point contact with the stem

contributed to the observed diagnostic testing errors.

The licensee

concluded that

VOTES mini-c calibrator could not be used to

calibrate the

VOTES thrust transducer

or the quick stem sensor.

The licensee

had changed their practice to use

an analytic calibration of the quick stem

sensor

supplied

by the manufacturer for LCV-106 and -107.

No other valves

incorporated the split-stem design.

The inspectors

reviewed the licensee's

root cause evaluation

and found the

licensee's

actions to be adequate.

The licensee

determined that the observed

problem was not reportable

under

Part 21.

The licensee

planned to formally notify the

VOTES diagnostic

equipment

vendor (Liberty) of their observations

and conclusions.

1.4.2

Translating

Torque Restraint Effect

The inspectors

reviewed Action Request

A0354065 which documented that during

the recent

2R6 refueling outage,

the licensee

had performed

a hydrostatic test

of Residual

Heat

Removal Suction Isolation Valve 2-8702 to demonstrate

design

basis capability.

The diagnostic trace indicated

a unexpectedly

large thrust

required for disk pullout during opening of the valve.

The other three

identical valves in this valve group did not display this anomaly.

The

licensee's initial root cause investigation determined the cause of the

anomaly to be

a pressure

locking condition existing during the test.

Motor-Operated

Valve '2-8702 was one of two pressure

isolation valves off the

reactor coolant system to the suction of the residual

heat

removal

pumps.

These pressure

isolation valves were normally locked closed with electric

power

removed during operation.

The licensee identified a closing safety

function to isolate residual

heat

removal pipe break during cooldown operation

and opening safety function to initiate cooldown for Appendix

R shutdown.

The inspectors

observed that the test data for Motor-Operated

Valve 2-8702

indicated that only marginal capability existed.

The inspectors

reviewed the

thrust signature

analysis for this valve and found that the licensee

had

discounted the excessive

opening thrust requirement

as

a test

anomaly in their

analysis of the capability of the motor -operated

valve.

According to the

licensee,

the valve had experienced

pressure

locking due to a valve alignment

unique to the testing which was not possible during normal valve alignment.

The bonnet vent valve to prevent pressure

locking had been closed during

testing.

The inspectors

were concerned that the capability of the motor -operated

valve

could not be demonstrated

based

on the measured

data without discrediting the

anomalous portion of the opening thrust.

While the licensee's

hypothesis of

i

the occurrence of pressure

locking appeared

reasonable

to explain the observed

excessive

opening thrust requirement,

the inspectors

found that the licensee

had

no confirmatory evidence

(such

as measured

bonnet pressure)

to validate

the pressure

locking occurrence.

Furthermore,

the valve had not been

disassembled

for internal inspection.

The inspectors

did not consider the

quality of the test to be an adequate

demonstration of design basis capability

and requested

additional justification.

On further review, in response to the inspectors'oncern,

the licensee

identified

a calibration error affecting the accuracy of the opening thrust

measured

during the test of these valves.

The licensee

determined that the

error was due to a yoke-torque effect during initial valve opening which was

not present

during calibration of the yoke-mounted

VOTES thrust sensor.

The

licensee

had calibrated the yoke-mounted

VOTES thrust sensor

by backseating

the valve to produce

stem tension.

The design of the valve incorporated

a

stem-mounted

torque restraint which translated

along the stationary yoke

during valve stroking.

This design feature subjected

varying portions of the

yoke to.torque

depending

on the location of the torque restraint.

During

. valve stroking the torque restraint translated

past the fixed location of the

VOTES sensor=

on the yoke.

As

a result, the yoke in the location of the

VOTES

sensor

was not subjected to torque during backseating.

However during initial

disk pullout, the yoke in the location of the

VOTES sensor

was subject to

torque.

The l,icensee

concluded that

a backseating

technique could not be used

for open calibration purposes

for valves with the translating torque restraint

design.

The licensee

reanalyzed

the test data for Motor-Operated

Valve 2-8702 using

the close calibration data obtained

from the

same test

and determined that

additional margin was available to justify design basis capability based

on

the actual test data irrespective of the potential pressure

locking

occurrence.

The licensee

reviewed all other uses of the backseating

calibration technique

and found no other

valves which would be similarly

affected.

The licensee

committed to formally notify the

VOTES diagnostic

equipment

vendor (Liberty) of their observations

and conclusions.

The inspectors

found that the licensee

had appropriately selected

the

VOTES

sensor

location based

on vendor

recommended

practice.

The inspectors

found

that the vendor

information did not address

the use of backseat calibration

techniques.

The inspectors

reviewed the licensee's

evaluation

and found the

licensee's

actions to be adequate.

1.5

~Grou in

The inspectors

reviewed the licensee's justification for the design basis

capability of motor-operated

valves which were not tested

under dynamic

conditions.

'

-12-

Approximately 68 percent of the motor -operated

valves in the licensee's

program were tested

under differential pressure

conditions.

and valve factors

were determined

based

on results of the individual valve tests'or

motor-

operated

valves which were not considered

practicable

or meaningful to test

under differential pressure

conditions,

the licensee

determined

design basis

capability

by analysis with an assumed

valve factor for each motor-operated

valve.

The inspectors

noted that the assumed

valve factors in the licensee's

capability analysis

were not validated

by comparison with the test results of

similar valves,

nor were they validated

by industry testing of identical

valves.

Rather,

the licensee

selected

valve factors which were considered to

be adequately

conservative

based

on engineering

judgement

and the best generic

test data available at the time.

Although not defined within their program

as grouping, the licensee

used

a

grouping methodology to validate assumptions

made for valve factors.

Nineteen

valve groups were established,

generally defined by

a specific manufacturer

.

size.

and pressure

class.

Some groups contained

valves with more than one

size or pressure

class.

The inspectors

considered

the groups to represent

an

acceptable

division of valves for the purpose of evaluating valve factors.

The licensee utilized groups of motor -operated

valves for the purpose of

establishing

the best available data for evaluating similar performance.

The inspectors

were specifically concerned with eight untested

feedwater

isolation valves,

1/2-FCV-438,-439,-440.-441.

The licensee identified zero

,existing margin for these

Anchor Darling 16-inch flex wedge gate valves with

an assumed

0.6 valve factor.

The inspectors

considered that the use of 0.6

for valve factor was adequate

as the best available data for Stage

I

qualification of the valve.

But the inspectors

were concerned that the

generic valve factor of 0.6 may not be sufficiently conservative to bound or

have

a high statistical

confidence in representing

expected

valve performance.

Industry test results of'ome similar valves

have

shown valve factors

as high

as 0.8.

Although

a 0.6 valve factor has recently been considered

generally

conservative,

several of the licensee's

tests of flex-wedge gate valves

have

indicated valve factors greater than 0.6.

The inspectors

considered that

additional valve specific justification was requi red for the use of generic

valve factors to demonstrate

the design basis capability of untested

valves.

The inspectors

noted that the licensee

had changed their approach to

justifying Stage II motor-operated

valves

and

had decided not to utilize the

EPRI performance prediction methodology to more precisely estimate the valve

factors for the feedwater

isolation valves

and other valves lacking specific

test validation of valve factor assumptions.

During previous

NRC inspections,

the licensee's

program had intended to use the

EPRI performance prediction

methodology for justification of untested

motor-operated

valves.

-13-

In response to the inspectors'oncern,

the licensee

reviewed their approach

to justifying untested

valves

and stated that they planned to utilize the

EPRI

performance prediction methodology for the eight main feedwater isolation

valves

and the six power operated relief block valves.

Further, the licensee-

stated

they would consider the

EPRI performance prediction methodology or

other justifiable sources of data

as part of the justification for the

remainder of the untested

valves in their program.

The licensee stated they would review their grouping method in view of the

guidelines

presented

in Supplement

6 of Generic Letter 89-10.

In general.. the

inspectors

found the licensee's

method. consistent with the guidance of

Supplement

6.

Exceptions

were noted regarding the use of the highest

individual valve factor as the group valve factor.

The licensee is being requested

to submit additional detai

1 of their program

enhancements

in a written response

to this inspection report.

The inspectors

concluded that the licensee

had adequately

established

the

design basis capability of motor -operated

valves that had not been tested at

or near design basis conditions.

Some additional effort was expected

on the

licensee's

part to obtain applicable data to confi rm generic assumptions

used

in support of untested

motor-operated

valves'.6

Periodic Verification and Post-Maintenance

Testin

1.6. 1

Periodic Verification

The inspectors

reviewed the method utilized by the licensee for periodic

verification of design basis capability.

The licensee

had previously

committed to conduct periodic static testing only for each motor-operated

valve every 2 to 6 refueling outages

depending upon,probablistic risk analysis

risk significance,

performance history, margin,

and control logic utilized.

The licensee

considered that static testing provided adequate

periodic

performance monitoring assuming that observed

valve factors

remain constant.

Prior to this inspection,

the licensee

also committed to conduct additional

testing under differential pressure

conditions to validate their calculation

assumptions

relating to valve factors.

The licensee

planned to test nine

motor -operated

valves

(seven gates.

one butterfly, and one globe) over the

next three refueling outages.

Two differential pressure tests

would be

conducted during the

1R7 outage,

three during 1R8.

one at power

between

1R8

and

2R7,

and three during 2R7.

After that time, the need for further

differential pressure testing would be evaluated.

The licensee

issued Action

Request

A0362274 to track their commitment.

The licensee is being requested to provide additional details following the

inspection regarding their programmatic

enhancements

regarding the use of

differential pressure testing in their periodic verification program or other

justifiable sources of data.

i

-14-

The inspectors

found that the licensee

had not included any specific margin

for valve factor degradation

in their determination of motor-operated

valve

capability.

However.

based

on

a review of the available

margin for all motor-

operated

valves,

the i'nspector considered that of the licensee's

motor-

operated

valves

had adequate

margin to accommodate

some degree of valve factor

degradation until confirmatory differential pressure testing could be

performed during periodic testing.

Some valves.

however,

had very small

margins that

my not be sufficient to account for short-term degradation.

Accordingly. the licensee is being requested

to identify the existing margin

for valve factor degradation

in all motor-operated

valves in their program

as

part of their written response

to this inspection report.

The previous

Inspection Followup Item 9139-02 concerning periodic verification remains

open.

1.6.2

Post-Maintenance

Testing

The inspectors

reviewed licensee

Procedure

AD13. ID4, "Post-Maintenance

Testing," Revision 1.

The inspectors

reviewed the licensee's

post-maintenance

test matrix which identified maintenance activities requi ring subsequent

diagnostic testing to assure that design basis capability is maintained.

The

inspectors

found that the matrix requi red appropriate diagnostic testing

following motor-operated

valve maintenance;

dynamic testing

was identified

generally for valve modifications which could negatively affect efficiency or

valve factor.

However,

no specific maintenance activities were identified.

The inspectors

considered

the lack of prescribed differential pressure testing

following valve maintenance

(e.g.,

valve disc replacement

or reversal,

dimensional

rework. of valve internals. etc.) to be

a weakness.

In response

to

the inspectors'oncern,

the licensee identified detailed maintenance

and

modification activities which would require differential pressure testing.

The licensee stated that the detailed

post-maintenance

testing requirements

would be added to the post-maintenance

test procedure.

The inspectors

reviewed selected

maintenance

records

and found that appropriate testing

had

been performed.

The inspectors

considered

the licensee

actions to be

adequate.

The inspectors

reviewed Maintenance

Procedure

HP M-51.38, "Inspection

and

Haintenance of Wedge Gate Valve Internal

Components."

Revision 0.

The

inspectors

found that the licensee

procedure

required

a detailed inspection

and fitup procedure for all wedge

and parallel disk valves.

The procedure

incorporated the lessons

learned

from industry experience

for good maintenance

pr actices

and critical areas of emphasis

for long-term control of valve

erformance.

The licensee

considered

the detailed inspection information to

e critical in their determination of required differential pressure testing

for post-maintenance

testing.

The inspectors

found the implementation of the

detailed

mai'ntenance

procedure to be

a noteworthy strength in the licensee's

program.

-15-

1.7

Failure Anal sis

and Trendin

1.7. 1

Failure Analysis

The inspectors

reviewed the licensee's

actions in response to recent

operational

problems

encountered

during testing of motor-operated

valves.

According to the licensee,

one operational

fai lure to perform on demand

had

been experienced

subsequent

to differential pressure testing.

The fai lure

occurred

on LCV-109.

The fai lure was considered

an isolated incident.

and the

root cause

involved auxiliary contacts

in the motor contacter in the motor

control center.

The licensee's

failure analysis

was addressed

during

a

previous

NRC inspection.

Based

on

a review of all action requests

for the past two years

regarding

motor -operated

valve problems,

the inspectors

found that the licensee

documented

problems in detail. thoroughly analyzed motor-operated

valve

failures'nd evaluated

design basis capability as

a condition of return to

service of the motor-operated

valve.

Several

noteworthy examples of licensee

failure analysis

are described

below.

1.7.1.1

Valve 1-8923A

The inspectors

reviewed the licensee

documented

results of,differential

pressure testing for Valve 1-8923A.

This Aloyco 6"-1501. split-wedge.

gate

valve displayed

a high closing force requirement

as compared to other

identical valves in its group.

The licensee

disassembled

and inspected

the

valve and found wear

and damage in the valve internals.

The licensee

attributed the high closing force to an inability of the valve disks to rotate

when wedging due to

a wear ridge on the ball of the ball-and-socket joint

which coupled the disks.

The licensee

concluded that the sharp corner of the

socket did not allow the valve disks to rotate to achieve its intended wedging

action.

The licensee's

corrective action involved chamfering the shoulder

on

the socket

and blending out the wear ridge on the ball.

In addition, the

~

licensee

has included two similar valves in the periodic verification program

to monitor for this wear mechanism.

1.7. 1.2

Directional Valve Factors

The inspectors

found that the licensee

had identified a significant flow

di rection effect on the valve factor performance of Aloyco, spit-wedge.

gate

valves with a ball-and-socket joint design.

Although considered to be

bi-directional valves,

the valve factor for flow in one direction was

consistently

observed to be twice the valve factor observed in the opposite

flow direction.

The licensee

analyzed the capability of the motor-operated

valve based

on the worst valve factor displayed.

Furthermore.

specific

procedural

requirements

were established

in Maintenance

Procedure

MP M-51.38

to assure

the orientation of the disk was controlled to prevent reversal of

the disk assembly.

-16-

The licensee stated they will notify the industry of the observed directional

effects

on Aloyco valves via the nuclear

news network.

Furthermore.

the

licensee

plans to notify the valve vendor of their observation

and

conclusions.

The inspectors

found the licensee

actions to be adequate.

1.7.2

Trending-

The inspectors

reviewed the licensee's

motor-operated

valve tracking and

trending program.

The licensee

had established

and was implementing

a

computer

based

program for trending motor-operated

valve data.

The inspectors

found the licensee's

program to be effectively implemented

and capable of

roviding meaningful

performance indicators.

The inspectors

considered

the

icensee's

trending activities to be

a strength in their ongoing program to

maintain design basis capability.

1.1 ~lit

1

The inspectors

reviewed "Site Quality Assurance

2R6 Technical

Support Outage

Assessment."

The licensee

performed this follow-up assessment

of items

identified in thei r Generic Letter 89-10 Management

Prerogative Audit

(Audit 94016I), the 89-10 High Impact Team's activities during the

2R6 outage.

and the Stage

2 qualification of the main feedwater

isolation valves.

The inspectors

found that the licensee's

self-assessment

efforts were

comprehensive

and indicated

a strong commitment to ensuring the design basis

capability of motor-operated

valves.

The inspectors

reviewed reports

summarizing the activities discussed

above

and noted that the findings and

observations

were substantive.

As

a result of the licensee's

self-

assessments,

several

action requests

were initiated.

Action Request

A0354168, "Qualification of Stage

2 Motor-Operated

Valves

(Generic Letter 89-10 Program),"

was

among the action requests

generated

by

the quality assurance

self assessment.

This recent action request identified

a need to prepare

adequate justification for the change in commitments to the

NRC regarding the basis for the Stage

2 qualifications of the main feedwater

isolation valves.

This action had not been completed prior to the

NRC closure

inspection.

The'icensee

was requested

to address

closure of all outstanding

quality assurance

findings in a written response to this inspection report.

The inspectors

found the strong quality assurance

involvement in the

licensee's

closure activities to be

a performance strength.

0

'

1. 9

~0en

Items

-17-

1.9. 1

0 en

Ins ection Followu

Item 93-19-02:

Pressure

Lockin

and Thermal

~Bindin

This issue is discussed

in Section

1.3 of this report

~

This item will remain

open pending issuance of a planned

NRC generic communication addressing

pressure

locking and thermal binding.

1.9.2

0 en

Ins ection Followu

Item 91-39-02:

Periodic

Ver ification

This item is discussed

in Section 1.6 of this report.

This item will remain

open pending the licensees

submittal of additional information and

NRC review.

0

ATTACHMENT 1

1

PERSONS

CONTACTED

1. 1

Licensee

Personnel

  • H. Angus,

Manager,

Regulatory

and Design Services

  • H. Baker,

Engineer,

Electrical Maintenance

  • W. Crockett,

Manager,

Engineering Services

  • H. Frauenheim,

Engineer,

Electrical Maintenance

W. Fujimoto. Vice President,

Nuclear

Power Generation

  • R. Goel,

Engineer,

Nuclear

Engineering Services

  • T. Grebel. Director, Regulatory Compliance
  • K. Hubbard,

Engineer,

Regulatory Compliance

  • C. Lewis, Engineer,

Nuclear Quality Services

~J.

Holden.

Manager,

Maintenance

Services

  • H. Phi lips. Director, Technical

Maintenance

L. Pulley.

Engineers

Nuclear Engineering Services

K. Riches.

Engineer.

Regulatory Compliance

  • A. Toy, Engineer,

Predictive Maintenance

  • L. Womack. Vice President.

Nuclear Technical

Services

  • M. Williamson, Engineer,

Onsite Nuclear Engineering Services

  • J. Young.

Directors'uclear

Quality Services

1.2

NRC Personnel

  • T. Westerman,

Engineering

Branch Chief, Division of Reactor Safety,

RIV

The personnel

listed above attended

the exit meeting.

In addition to the

personnel

listed above,

the inspectors

contacted

other

personnel

during this

inspection period.

  • Denotes personnel

that attended

the exit meeting.

2

EXIT HEETING

An exit meeting

was conducted

on January

27.

1994.

During this meeting,

the

inspectors

reviewed the scope

and findings of the report.

The licensee

acknowledged

the inspection findings documented

in this report.

The licensee

did not identify as proprietary any information provided to.

or reviewed by,

the inspectors.

ATTACHHENT 2

Information Requested to Clarify Certain

Program Commitments

Regarding Generic Letter 89-10

Clarify intended

use of the Electric Power Research

Institute

Performance

Prediction Hethodology or other justified sources for

confi rming the design basis capability of motor -operated

valves which

have not been tested

under differential pressure

conditions in the

Diablo Canyon Generic Letter 89-10 program.

Specifically address

the

main feedwater isolation valves

and the block valves for power

operated

relief valves

(Section 1.5).

'.

Provide the results of the Pacific Gas

5 Electric's review of the

grouping of untested

motor- operated

valves consistent with the guidance

of Supplement

6 to Generic Letter 89-10.

In particular justify any

exceptions to the use of the highest individual valve factor as the

group valve factor (Section 1.5).

3.

Provide additional detail of the intended

use of periodic verification

testing to validate assumptions

regarding the effect of neolube

on valve

factors

(Section

1. 1.5).

4.

Provide additional detail of the use of differential pressure testing

as

periodic verification (Section 1.6.1).

s.

Identify the margin for valve factor degradation existing in all motor-

operated

valves in your Generic Letter 89-10 program (Section 1.6. 1).

Identify the status of any outstanding quality assurance

audit findings

related to motor-operated

valve program closure

(Section 1.8).

0'