August 19, 1988 Docket Nos.:
50-275 and 50-323 Mr. J.
D. Shiffer, Vice Pres ident
'uclear Power Generation c/o Nuclear Power Generation, Licensing Pacific Gas and Electric Company 77 Beale Street, Room 1451 San Fr anci sco, California 94106
Dear Mr. Shiffer:
DISTRIBUTION NRC
& Local PDRs'D5 Reading GMHo 1 ahan JLee HRood OGC (for info)
EJordan BGrimes ACRS (10)
SUBJECT:
TRANSMITTAL OF TECHNICAL EVALUATION REPORT (TER)
AND REQUEST FOR ADDITIONAL INFORMATION CONCERNING THE DETAILED CONTROL ROOM DESIGN REVIEW (DCRDR)
FOR DIABLO CANYON (TAC NOS.
56117 AND 68040)
Enclosed is the TER prepared by a staff contractor, SAIC, concerning the Diablo Canyon DCRDR.
The TER is based on your Supplemental Summary Report (SSR) dated November 3, 1987 and the conference call of January 13, 1988.
The staff concurs with the evaluations and conclusions in the TER.
In summary, the TER concludes that the SSR is incomplete with respect to Human Engineering Discrepancy (HED) assessment, and selection of design improvements.
Also enclosed is a request for additional information which resulted from our contractor's review.
We request that you complete the HED assessment process and document the proposed corrective actions for HEDs before providing the requested information.
- Further, we request that you respond to this RAI within 90 days of receipt of this letter.
If you have any questions, please contact us.
Sincer ely, original si gned by Harry Rood, Senior Project Manager Project Directorate V
Division of Reactor Projects - III, IV, V and Special Projects cc:
w/enclosures See next page DRSP/PD5 HRood:dr 8/g /88 DRSP/D:PD5 4 GWKnighton 8/j41 /88
Enclosures:
1.
Technical Evaluation Report (TER) 2.
Request for Additional Information (RAI) 8810110Z 05000275 00 880819 PDR AXIOCK.
P
August 19, 1988 Docket Nos.:
50-275 and 50-323 Mr. J.
D. Shiffer, Vice President Nuclear Power Generation c/o Nuclear Power Generation, Licensing Pacific Gas and Electric Company 77 Beale Street, Room 1451 San Francisco, California 94106 DISTRIBUTION NRC
& Local PDRs PD5 Reading GMHo1ahan JLee HRood OGC (for info)
EJordan BGrimes ACRS (10)
Dear Mr. Shiffer:
SUBJECT:
TRANSMITTAL OF TECHNICAL EVALUATION REPORT (TER)
AND REQUEST FOR ADDITIONAL INFORMATION CONCERNING THE DETAILED CONTROL ROOM DESIGN REVIEW (DCRDR)
FOR DIABLO CANYON (TAC NOS.
56117 AND 68040)
Enclosed is the TER prepared by a staff contractor, SAIC, concerning the Diablo Canyon DCRDR.
The TER is based on your Supplemental Summary Report (SSR) dated November 3, 1987 and the conference call of January 13, 1988.
The staff concurs with'he evaluations and conclusions in the TER.
In summary, the TER concludes that the SSR is incomplete with respect to Human Engineering Discrepancy (HED) assessment, and selection of, design improvements.
Also enclosed is a request for additional information which resulted from our contractor's review.
We request that you complete the HED assessment process
.and document the proposed corrective actions for HEDs before providing the requested information.
- Further, we request that you respond to this RAI within 90 days of receipt of this letter.
If you have any questions, please contact us.
Sincerely, original signed.by Harry Rood," Senior,.Project Manager Project Directorate V
Division of Reactor Projects - III,
'V, V and Special Projects cc:
w/enclosures See next page DRSP/PD5 HRood:dr 8/g /88 DRSP/0:PD5 GWKnighton 8/g/88
Enclosures:
1.
Technical Evaluation Report (TER) 2.
Request for Additional Information (RAI)
t P/
p 4,
1
r
~Q AEVI
~4 I
O IVl gO
++**+
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 August 19, 1988 Docket Nos.:
50-275 and 50-323 Mr. J.
D. Shiffer, Vice President Nuclear Power Generation c/o Nuclear Power Generation, Licensing Pacific Gas and Electric Company 77 Beale Street, Room 1451 San Francisco, California 94106
Dear Mr. Shiffer:
SUBJECT:
TRANSMITTAL OF TECHNICAL EVALUATION REPORT (TER)
AND REQUEST FOR ADDITIONAL INFORMATION CONCERNING THE DETAILED CONTROL ROOM DESIGN REVIEW (DCRDR)
FOR DIABLO CANYON (TAC NOS.
56117 AND 68040)
Enclosed is the TER prepared by a staff contractor, SAIC, concerning the Diablo Canyon DCRDR.
The TER is based on your Supplemental Summary Report (SSR) dated November 3, 1987 and the conference call of January 13, 1988.
The staff concurs with the evaluations and conclusions in the TER.
In summary, the TER concludes that the SSR is incomplete with respect to Human Engineering Discrepancy (HED) assessment, and selection of design improvements.
Also enclosed is a request for additional information which resulted from our contractor's review.
We request that you complete the HED assessment process and document the proposed corrective actions for HEDs before providing the requested infotmation.
- Further, we request that you respond to this RAI within 90 days of receipt of this letter.
If you have any questions, please contact us.
Sincerely, Harry Roo
, Senior Project Manager Project Directorate V
Division of Reactor Projects - III, IV, V and Special Projects
Enclosures:
1.
Technical Evaluation Report (TER) 2.
Request for Additional Information (RAI) cc:
w/enclosures See next page
P
~
Mr. J.
D. Shiffer Pacific Gas and Electric Company Diablo Canyon CC:
Richard F. Locke, Esq.
Pacific Gas
& Electric Company Post Office Box 7442 San Francisco, California 94120 Janice E. Kerr, Esq.
California Public Utilities Commission 350 McAllister Street San Francisco, California 94102 Ms. Sandra A. Silver 660 Granite Creek Road Santa Cruz, California 95065 Mr.
W. C. Gangloff Westinghouse Electr ic Corporation P. 0.
Box 355 Pittsburgh, Pennsylvania 15230 Managing Editor San Luis Obispo County Telegram Tribune 1321 Johnson Avenue P. 0.
Box 112 San Luis Obispo, California 93406 Mr. Leland M. Gustafson, Manager Federal Relations Pacific Gas and Electric Company 1726 M Street,.
N; W.
Washington, DC "20036-4502 Dian M. Grueneich Marcia Preston Law Office of Dian M. Grueneich 380 Hayes Street, Suite 4
San Francisco, California 94102 NRC Resident Inspector Diablo Canyon Nuclear Power Plant c/o U.S. Nuclear Regulatory Commission P. 0.
Box 369 Avila Beach, California 93424 Mr. Dick Blakenburg Editor
& Co-Publisher South County Publishing Company P. 0.
Box 460 Arroyo Grande, California 93420 Bruce Norton, Esq.
c/o Richard F. Locke, Esq.
Pacific Gas and Electric Company Post Office Box 7442 San Francisco, California 94120 J
Dr. R.
B. Ferguson Sierra Club - Santa Lucia Chapter Rocky Canyon Star Route Creston, California 93432 Chairman San Luis Obispo County Board of Supervisors Room 270 County Government Center San Luis Obispo, California 93408 Director Energy Facilities Siting Division Energy Resources Conservation and Development Commission 1516 9th Street Sacramento, California 95814 Ms. Jacquelyn Wheeler 3033 Barranca Court San Luis Obispo, California 93401
r
Pacific Gas I% Electric Company Diablo Canyon CC:
Ms. Laurie McDermott, Coordinator Consumers Organized for Defense of Environmental Safety 731 Pacific Street, Suite 42 San Luis Obispo, Ca 1 iforni a 93401 Mr. Jack McGurk, Acting Chief Radiological Health Branch State Depar tment of Health Services 714 P Street, Office Building I/8 Sacramento, Califor nia 95814 Regional Administrator, Region V
U.S. Nuclear Regulatory Commission 1450 Maria Lane Suite 210 Walnut Creek, California 94596 Ms. Nancy Culver 192 Luneta Street San Luis Obispo, California 93401 President California Public Util ities Commission California State Building 350 McAllister Street San Francisco, California 94102 Michael M. Strumwasser, Esq.
Special Assistant Attorney General State of California Department of Justice 3580 Wilshire Boulevard, Room 800 Los Angeles, California 90010
ENCLOSURE 1
TECHNICAL EVALUATION REPORT