ML16341A621

From kanterella
Jump to navigation Jump to search
Insp Rept 50-323/85-14 on 850325-29.No Violations or Deviations Noted.Major Areas Inspected:Const & Mod Activities,Including Area Insp,Licensee Actions on Previously Identified Items & IE Bulletins
ML16341A621
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 05/03/1985
From: Burdoin J, Dodds R, Thomas Young
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML16341A622 List:
References
50-323-85-14, IEB-79-01, IEB-79-02, IEB-79-1, IEB-79-14, IEB-79-2, IEB-79-23, NUDOCS 8505290120
Download: ML16341A621 (14)


See also: IR 05000323/1985014

Text

U. S.

NUCLEAR REGULATORY COMMISSION

Report No.

Docket No.

License No:

REGION V

50-323/85-14

50-323

Construction Permit CPPR-69

Licensee:

Pacific Gas

and Electric Company

77 Beale Street,

Room 1435

San Francisco, California 94106

Facility Name:

Inspection at:

Diablo Canyon Unit 2

Diablo Canyon Site,

San Luis Obispo County, California

Inspection conducted:

March 25-29,

1985

Inspector:

F.

Bu doin, Reactor Inspector

D te Signed

Approved By:

T. Young, Jr

, Chief, Engine ring Section

D

e

igned

R. T. Dod s, Chief

Reactor ProjectsSection I

D

Signed

Summary:

Ins ection durin

eriod of March 25-29,

1985

(Re ort No. 50-323/85-14

Areas Ins ected:

Unannounced

inspection by one regional inspector of

construction

and modification activities including: an area inspection,

licensee actions

on previously identified items,

enforcement

items, IE

Bulletins,

and 50.55e Items.

The inspection involved 39 inspection hours by

one inspector.

Results:

No violations or deviations

were identified.

8505290120

85050b

PDR

ADOCK 05000323

6

PDR

DETAILS

Individuals Contacted

Pacific

Gas

and Electric

Com an

(PGK)/Pro ect Team General

Construction

PTGC

"-R. R.

-B. R.

'"R. A.

M. N.

J.

B.

R, P.

G. D.

J

~ D.

R. K.

G. R.

G. T.

W. K.

W. E.

V. R.

W. J.

D. S.

S. J.

Lieber, Field Construction

Manager

Tinkle, Technical Assistant to the Project Superintendent

Hobgood,

QC Supervisor

Norm, Lead Startup Engineer

Maysey,

QC Inspection

(Mechanical)

Gilbreath, Instrumentation

and Control Assistant Supervisor

Morrison, Electrical Field Engineer

Lawton, Startup Technician

Rhodes,

Instrumentation

and Control Supervisor

Vincent,

QC Inspector

Glasscock,

Resident Electrical Engineer

Glenn, Startup Engineer

Coley, Assistant

Lead Startup Engineer

Foster,

Senior Power Production Engineer

Kelly, Licensing Representative

Wright, Electrical Performance

Test Supervisor

Foat,

Power Production Engineer

Various other engineering

and

QC personnel.

"-Denotes attendees

at exit management

meeting

on March 29,

1985.

An independent

inspection

was

made in Unit 2 containment at

elevations

91 ft., 117 ft and

140 ft.

The equipment

spaces

inspected

included two reactor coolant

pump (2-1 and 2-2) areas,

the seal table

area,

reactor pit area (elevation

63 ft.), and recirculation

sump area.

Construction

(completion) work was still in process in some areas in the

containment.

No violations of NRC requirements

were identified.

Licensee Action on Previous Enforcement

Items

(Closed)

Noncom liance (50-323/85-06-04) Electrical Racewa

Su

orts

Modification Not Performed In Accordance With Procedures

Three electrical raceway supports:

2H-100-4-63,

2F-117-3-90,

and

2A-119-6-20 were identified in this citation.

The installation drawing for support 2H-100-4-63 required that

a washer

be installed under the bolt which attached

a S-6 brace to the unistrut

support.

No washer

was installed.

Drawing MC-28 for support 2F-117-3-90 called for the installation of a

P-1001/C-41 unistrut with two clamps.

However,

a P-1001 with one

clamp

had been installed.

A six inch weld on a six inch long angle iron added to stiffen support

2A-119-6-20 was undersized for 25 percent (lq") of the length (6") of the

weld.

Ex lanation and Corrective Ste

s Taken

Su

ort 2H-100-4-63

This support

was incorrectly identified in the Notice as support

1178-H-100-4-63.

The correct support

number is 2H-100-4-63 'esign

Change Notice DC2-EC-18480 required

a washer to be installed

on the S-6

brace of this support

and

a torque value of 85 ft/lb applied at that

location.

The brace

was torqued to 85 ft/lb, and no washer

was

installed.

A QC inspector overlooked this condition during inspection.

The licensee's

Discrepancy Report No. E-3148 was written to document the

condition when it was identified by the NRC, and the support

was reworked

to conform to the design drawing.

Corrective action was completed

on

January

28,

1985,

when the discrepancy report was closed.

Su

ort 2F-117-3-90

Design

Change Notice 'OC2-EC-16532 required the removal of three existing

supports

and the installation of three

new ones'wo of the three

new

supports

called for P-1001 unistruts at all three locations.

A QC

inspector overlooked this condition during inspection.

The licensee's

Discrepancy Report No. E-3145

was initiated to document the condition

when it was identified by the

NRC.

The support

was reworked in

accordance

with Design Drawing DC2-EC-16532 requirements.

Corrective

action was completed

on January

28,

1985,

when the discrepancy report was

closed.

Su

ort 2A-119-6-20

Design required

a 1/8-inch fillet weld 6-inches

long to be made

on an

angle used to stiffen the support.

The weld was undersized for

25 percent

(1-1/2 inches) of the length of the weld, which exceeded

the

accepted

tolerance of 10 percent.

A QC inspector

overlooked this

condition during inspection.

The licensee's

Discrepancy Report

No. E-3209

was written to document this condition when it was identified

by the

NRC and was forwarded to Project Engineering in San Francisco for

resolution.

Project Engineering

reviewed the existing condition,

determined it was adequate'or

the structural integrity of the support,

and

recommended

a use-as-is

disposition.

Corrective action was completed

on January

30,

1985,

when the discrepancy

report was closed.

Retraining of QC inspectors

in, order to enhance

job performance is

standard practice at Diablo Canyon.

However,

due to a reduction in

personnel,

one of the

QC inspectors

involved with the items cited in the

Notice is no longer employed at Diablo Canyon

and retraining is not

necessary.

The other individual is employed by a different contractor

L'

E

~

'4

and has been retrained in accordance

with that contractors'rocedures.

In addition,

the Field Observation

Memorandum program,

implemented at

Diablo Canyon subsequent

to the original work on the cited items,

provides

an additional means

through which onsite contractor personnel

can identify possibly deficient conditions to the licensee's

equality

Control for investigation.

This program

h'as increased

the licensee's

ability to identify and correct any deficient conditions at Diablo

Canyon.

Based

on the actions described

above, Project Engineering's

review of the type and severity of each condition found, the adequacy of

existing procedures,

and the licensee's

ongoing surveillance

program; it

is felt that adequate

corrective actions

have been taken to prevent

recurrence.

The inspector verified the completion of the repairs to raceway supports

2H-100-4-63

and 2F-117-3-90 by inspection of these

two supports in the

field and examination of the

gC records for the repair work.

The

documentation

supports

the corrective measures

taken.

The inspector also

examined the licensee's

resolution of the discrepancy for support

2A-119-6-20.

The modifications

and resolution of the identified

discrepancies

for the three identified raceway supports

appear to be

adequate

and complete.

Based

on a review of the corrective measures

taken and inspection of the

modified supports, it is concluded that this item is closed.

1

4.

Licensee Action on IE Bulletins

a.

(Closed)

IE Bulletin 79-01

Environmental

uglification of ASCO

Solenoid Valves

The bulletin required the replacement of certain acetal plastic

material parts

and buna "N" elastome material gaskets in those

ASCO

solenoid valves

exposed

to an accident environment.

The inspector

examined

DCO-EM-378 and other documentation onsite for

replacement

of gaskets

and acetal plastic parts, verification of

solenoid coil materials

and retesting of 37 solenoid valves for

Unit 2 ~

This Bulletin is closed for Unit 2.

b.

(Closed)Bulletin 79-02

Pi e Su

ort Base Plate Desi n Usin

Concrete

Ex ansion Anchor Bolts

IE Bulletin 79-02 summarized

the requirements for pipe support base

plate designs

using concrete

anchors.

The licensee's

internal review program

(IRP) established

in mid-1982

for Unit 2, required that all Class

1 system

be re-analyzed.

This

resulted in the redesign

and modifications to

a large number of

Class

1 pipe supports.

The licensee's final response

to IE Bulletin 79-02 was submitted by

letter dated February 4,

1985.

This letter states

that during the

ly ~

1

Ht

weeks of October

22 and November 26,

1984 and January

14,

1985, the

NRC staff

(NRR) conducted audits of Unit 2 piping design analysis

work; and that these audits verified compliance with the concerns of

IE Bulletin 79-02.

Supplement

No.

30 to the Diablo Canyon plant

safety evaluation .report supports

the licensee's

conclusions.

This Bulletin is closed.

(Closed) Bulletin 79-1.4

Seismic Anal ses of Safet -Related

Pi in

S stems

IE Bulletin 79-14,

summarized

the requirements

for the seismic

analysis of as-built safety-related

piping systems.

The licensee's

final response

to IE Bulletin 79-14 was submitted by

letter dated Fe'bruary 4,, 1985.

The internal review program

(IRP) for Diablo Canyon Unit 2,

as

described in the licensee's

letters

dated October 5, October

19,

and

November 2,

1984,

was initiated by the licensee in mid-1982.

The

program included:

(1)

a walkdown of all seismic, Category

1 piping

systems

which ensured that as-built drawings reflect plant

conditions,

and (2) seismic

reanalyses

which used the verified

piping geometry

and support configurations.

The final phase of the

reanalysis

includes

an as-built reconciliation scheduled for

completion by February 28,,l985.

The licensee's letter dated October

17,

1979, included

Attachments

A-E which provided the response

to Item

1 of the

Bulletin for Units

1 and 2.

The walkdowns

and seismic reanalyses

satisfy the requirements

of Items

2 and 3.

Item 4 of the Bulletin

is not applicable to Unit 2 because

reanalyses

of all seismic

Category

1 piping systems

were based

on as-built piping and

supports.

The licensee's

final response

states

that during the weeks of

October

22 and November 26,

1984 and January

14,

1985,

the

NRC staff

(NRR) conducted audits of Unit 2 piping design analysis work; and

that these

audits verified compliance with the concerns of IE

Bulletin 79-14.

Supplement

No.

30 to the Diablo Canyon plant safety

evaluation report supports

the licensee's

conclusions.

This Bulletin is closed.

(Closed)

IE Bulletin 79-23

Potential Failure of Emer enc

Diesel

Generator Field Exciter Transformer

The bulletin required certain actions,

described

below, to be taken

by the licensee

to determine

the reliability of operation of the

emergency diesel generator(s)

(EDG).

Over heating of the exciter

power transformer

due to circulating current had caused,

an EDG at

the Turkey Point facility to trip during

a 24-hour full load test.

-3

t

II

t

C

ll.

'1

~

N(,

The licensee's

response

to the subject bulletin submitted by letter

dated November 8,

1979 included the following responses

to two

requirements:

1.

Determine whether or not connections

have been

made between

low

KVA rated transformers

and high KVA rated

EDGs without adequate

limitations on the flow of circulating currents.

If

applicable,

provide

a description of the corrective action

being taken to address

this

problem.'.

Provide

a schedule for the completion of a full-load operation

test of EDGs, or provide the results of a sustained full-load

operation tests for the

EDGs at your facility.

The test should

demonstrate full-load carrying capability for an interval of

not less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, of which 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> should be at

a load

equivalent to the continuous rating of the diesel generator

and

2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at

a load equivalent. to the

2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> rating'f the diesel

generator.

The test should also verify that voltage

and

frequency requirements

are maintained

and that the cooling

system functions within design limits.

R~es

ense

1.

Connections

do not exist between low KVA rated transformers

and

high KVA rated

EDG.

The Diablo Canyon low KVA rated

CPTs are

wired in an open delta configuration while the high KVA rated

EDGs are wired in an ungrounded

"Y" configuration.

2.

Pull-load tests of the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> duration were performed

on

Diesel Generators ll and

12 and

13 on March 9,

1979,

February 28,

1979

and October 2,

1979 respectively.

This test

consisted

of a

2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> overload condition at

> 2750KW followed

by a 22 hour2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> full load condition at

> 2484I5l.

Voltage,

frequency,

and jacket cooling water temperature

were recorded

and logged for the duration of the tests

and were all

maintained within design limits.

The full load operation

(24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />) tests

have. not yet been performed

on Unit 2 EDGs

21 and 22.

The,24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> tests

are scheduled

to be

performed

on EDGs

21 and 22 prior to Unit 2 reactor going to Mode 4

operation.

These

two diesel generators

21 and

22 are identical

machines

to EDGs ll, 12 and 13.

The inspector

examined test results of recent

(October 83/January

84) full load operation

(24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />) tests

run on

EDGs 11,

12 and 13.

The inspector 'also examined reliability tests

performed

on EDGs

21 and

24 by the startup

group.

These tests

included four separate

starts

followed by a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> run at

app'roximately

2MW load, which is slightly less than full load.

All

test results

examined

appeared

to be in order and demonstrates

the

operability of the EDGs.

The licensee

has satisfied

the

requirements

of the bulletin.

This item is closed for Unit 2.

v

k.

i

h

V

'I

(Closed)

(50-323/85-02-03)

Pollowu

Item:

Concern

Re ardin

Limitor ue

A contract inspector

expressed

a concern

as to the environmental

qualification of limitorque operators

on valves

LCVs 108,

109;

MPHs 06,

ll; and

MPGs

21 and 48.

The concern for the LCVs 108 and

109 (limitorque

model

SMC) was an impression

from an earlier experience in this area by

the contract inspector,

that the manufacturer

had been unable to

environmentally qualify this model

SMC valve operator.

It was also the

contract inspectors'pinion

that the other four valves

(MPHs 06/ll and

MPGs 21/48) which were equipped with brake

shoes

were not qualified since

the operators

were qualified without brake shoes.

The limitorque valve operators identified in the concern are located

outside the containment.

However, they are subject to a hi-energy line

break environment because

main steam lines and feedwater lines pass

through the area of the location of the above identified valves.

The

NRC inspector

examined the qualification type test report No. B0003,

and documentation for qualification of the above identified limitorque

valve actuators for Class

lE service outside primary containment,

and

found it to be in order.

The inspector also examined the completed

design

change notice

(DCN),

DC2-EM-935 which required the removal of brake

shoes

from valve operators

MPH-6 and MPG-48.

The inspector inspected in the field these

two valve

operators

to be assured

that the brake

shoes

had been

removed.

The

DCN

completed in March 1983 was found to be in order.

The inspector

examined

the licensee's

corrective action review of valve

operators

equipped with brakes with regard to operators

MPH-11 and

MPG-21.

These valve operators

actuate

containment

spray

pumps 2-1 and

2-2 discharge isolation valves.

The justification for exemption of the

removal of brake

shoe from these

two valve operators

concludes:

these

valves are required to open at the initiation of containment

spray

and

close prior to the initiation of spray recirculation from the

RHR system.

Since post-accident

radiation exposure of these valves occurs after

recirculation initiation, loss of functionality does not occur until

after the valves safety function is completed.

Therefore,

the failure

mode of these valves

does not prevent or impair their post-accident

safety function.

It is concluded the initial concern identified has

been properly

considered

and adequately

evaluated

by the licensee.

This item is

closed.

On March 29,

1985, the inspector; met with the licensee's

representatives

identified in paragraph

1.

During this meeting,

the inspector

summarized

the scope of the inspection activities and reviewed the inspection

findings as described in the report.

The licensee

acknowledged

the

concerns identified in the report.