SEP 17 >9M
Docket No. 50-275
Pacific Gas and Electric Company
P. 0.
Box 7442
San Francisco,
California 94106
Attention:
Mr. Philip A. Crane, Jr.
Assistant
General
Counsel
Gentlemen:
No items of noncompliance with NRC requirements
were identified within
the scope of this inspection.
Xn accordance
with 10 CFR 2.790 of the Commission's regulations,
a
copy of this letter
and the enclosed inspection report will be placed
in the NRC's Public Document
Room.
Xf this report contains
any infor-
mation that you believe to be exempt from disclosure
under
(a)(4), it is necessary
that you (a) notify this office by telephone
within ten (10) days from the date of this letter of your intention
to file a request for withholding; and (b) submit within 25 days from
the date of this letter a written application to this office to with-
hold such information. If your receipt of this leter has
been delayed
such that less than seven
(7) days are available for your review,
please notify this office promptly so that a new due date
may be
established.
Consistent
with section 2.790(b)(1),
any such applica-
tion must be accompanied
by an affidavit executed
by the owner of the
information'hich identifies the document
or part sought to be with-
held,
and which contains
a full statement of the reasons
on the basis
which it is claimed that the information should be withheld from public
disclosure.
This section further requires the statement to address
with specificity the considerations
listed in 10 CFR 2.790(b)(4).
10930&97 8169T7~)
R ADOCK 05000275I
d
P~DR
'
~ ~ ~ ~ ~ ~ ~ ~ ~
D
gtsznh
9'81
RV.:.e
OFFICE/
SURNAME/
DATE0
ung..
9l~iS1
J.....C..
s
..M.... en
ac
0/.!~j.Sg...... 9!&!81,
g
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~
~
~
~
~
~
~
V.
This refers to the routine monthly inspection conducted
by Mr. J.
Carlson and Mr. M. Mendonca of this office fxom July 31 to August 28,
1981, of activities authorized
by NRC Construction,-Permit
Nos.
CPPR-39
and CPPR-69,
and to the discussion of our findings held by Mr. Carlson--."-
and Mr, Mendonca with Mr. Thornberry and other members of your "staff
at the conclusion of the inspection.
Areas
examined during this inspection are Qescribed in the enclosed
~
~
~
~
~
~
~
~
~
~
~
~
inspection report.
Within these
areas,
the inspection consisted of
selective
examinations of procedures
and representative
records,
interviews with personnel,
and observations
by the inspector.
NRC FORM 3I8 110/80) NRCM 0240
" OFFICIAL RECORD COPY
o USGFO: 198~294I24,
Pacific Gas
and Electric Company
-2-
SEP 1'f 1981
The information sought to be withheld shall be incorporated
as far
as possible into a separate
part of the affidavit. If we do not
hear from you in this regard within the specified periods
noted
above,
~ the report will be placed in the Public Document
Room.
I
Should you have any questions
concerning this inspection,
we will
be glad to discuss
them with you.
Sincerely',
Enclosure:
IE Inspection Report
No. 50-275/Sl-22
D. M. Sternberg,
Chief
Reactor Operations
Projects
Branch
cc/wo enclosure:
J.
O. Schuyler,
PGE
J.
D. Shiffer,
PGE
S.
Raymond,
PGE
R.
C. Thornberry (Diablo Canyon)
bcc:
DHB/Document-Control
Desk
(RIDS)
Distributed by RV:
RV
State of CA (Hahn/Johnson)
Resident Inspector
Engelken
(1 tr)
Sandra Silver (Report only)