ML16340B199

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-275/80-16 on 800801-31.No Noncompliance Noted.Major Areas Inspected:Preoperational Testing,Plant Tour,Ie Circulars & Operator Training
ML16340B199
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 09/12/1980
From: Bagaglio M, Sternberg D, Thomas Young
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML16340B200 List:
References
50-275-80-16, NUDOCS 8010270138
Download: ML16340B199 (12)


See also: IR 05000275/1980016

Text

U. S.

NUCLEAR REGULATORY CO>~Q1ISSIOV

OFFICE

OF INSPECTION AND ENFORCEIKNT

REGION V

50-275/80-16

Report

No.

50/275

License

No.

Priority

CPPR-39

Category

Licensee:

Facility Name:

Inspection at:

Pacific

Gas

and Electric Company

77 Beale Street

San Francisco,

California 94106

Diablo C:nyon Unit 1

Diablo Canyon Site,

San Luis Obispo County, California

August 1-31,

1980

Incpcccion

condo ccd;

Inspectors:Tolbert Young Jr.,

e

d'or

Hario

B ga

x.o

.,

es

en

i eac or

nspec or

D'e Signed

Da

e Signed

Aoproved

Summary:

D. N. Ster

Reactor

Op

erg,

xe7, Iteac

o

r5 ec

s

rations

and Nuclear Support Branch

Date Signed

qJ(~

o

Date Signed

Ins ection of August 1-31

1980

l,'Re ort No. 50-275/80-16

Areas Inspected:

Routine inspection of preoperational

testing, plant tour,

IE circulars,

operator training and tuitnessing of testing in progress.

This inspection involved 200 inspector-hours

onsite by tvo

NRC resident

inspectors.

Results:

No items of noncompliance

or deviations r'ere identified.

IE:V Form 919(l)

S0102ndo

Jgg

0

(

(

DETAILS

Persons

Contacted

-R. D. Ramsay,

Plant Manager

R.

D. Etzler, Project Superintendent

+R. Patterson,

Plant Superintendent

N. iforem, Resident

Startup Engineer

+J.

S.

Diamonon,

QC Supervisor

+J. H. Gisclon,

Po~'er Plant Engineer

+D. A. Backens,

Supervisor of Maintenance

  • W. B. Kaefer, Technical Assistant

to Plant Superintendent

  • J. A. Sexton,

Supervisor of Operations

+R. T.

T~ iddy,

QA Supervisor

The inspectors

also talked vith and intervieved

a number of other licensee

employees

including members of general construction,

the operations staff

and

QA personnel.

  • Denotes those attending

the exit interviev.

2.

Administration

Effective April 1,

1980,

the plant staff +as reorganixed

as part of the

Company's

commitment to address

lessons

learned

from the Three Mile Island

accident.

Mr. Ramsay,

Plant Superintendent,

~"as promoted to Plant Manager,

a ne~ ly

created position that ha . responsibility for direct supervision of all

administrative functions at the plant level, including personnel

manage-

'ent,

personnel

training, revier. and audit, security

and quality control.

He retains overall responsibility for the safe operation of, the plant.

Reporting to him are the Plant Superintendent,

the Technical Assistant

to the Plant Manager,

the Quality Control Supervisor,

the Security Super-

visor and the Personnel

Representative.

Hr. Patterson,

Supervisor of Operations,

is promoted to the Plant Super-

intendent

and

he

~ ill be in charge of the routine day-to-day operational

maintenance

and technical activities in the plant.

Reporting to Hr.

Patterson're

the Supervisor of Maintenance,

the Supervisor of Operations,

the Pover

Plant Engi<<err the, Supervisor of 'Chemistry

and Radiation Protection

and

the. Office Supervisor.

,i

Hr. Kaefer, Senior Poi.er Production Engineer,

takes over the position vacated

by Hr. J.

D. Shiffer and is no~. the Technical Assistant to the Plant Manager.

Hr. Boots, Senior Chemical

and Radiation Protection Engineer, no~'eads

a

group ~.hich had branched

out from the Technical Department

to become

a

separate

department.

lie is

nov, Supervisor of Chemi. try and Radiation

Protection.

Messrs.

Kaefer and Boots vill become

members of the

PSRC

once the

ne~ Charter is approved.

"~

-2-

3.

IE Bulletin/Circular Pollo~~n

Circular No. 79-17

A licensee field inspection

revealed

that

CE type SB-12 switches

are used

only in the Unit 2 switchgear

and

no auxiliary switch spares

have

been

ordered

to date.

All future SB-12 auxiliary s'tch

spares

are to be reviewed by Quality

Contxol for date of manufacture prior to acceptance

during receipt

inspection.

As a matter of standard

procedure,

operators

and electrical maintenance

personnel

also periodically monitor breakers'ed

light for continuity check

of the trip coil and the auxiliary switch which is another assurance

that the .

contact wipe problem of the auxiliary switch will be detected

should it

occur at the plant.

Circular No.

79>>19

'I

The Diablo Canyon Residual

Heat Removal

Pumps are Ingersoll-Rand

type

8X20h~ (2 each unit).

Loosening of the

pump impeller locking device was

first noted

on

RHR Pump

1>>1 during preventive maintenance

check on 7/8/77.

The impeller locknut and capnut were found loose although toraued to procedure.

The locknut and capnut were found to be smaller in diameter

than the bore

of the impeller and this caused deflection of the washer that when the

pump

is heated

up, it c.ould relieve tension on the locknut causing it to come loose.

I

In consultation

~ ith Ingersoll-Rand,

a design

change

was initiated to correct

the problem.

A larger size capnut

~.as fabricated which assures

a metal to

metal fit between

the shaft

and impeller", the i asher

was modified riith a

positive locking device.

After performance

test

on the

pump proved that flow

characteristics

~.ere not altered, modifications on the other three

pumps

followed.

Circular No. 79-20

Quality Control reported that this type of relay is not used in the Diablo

Canyon Engineered

Safeguards

Syst: em or in any safety-related

applications.

The

AC auxiliary relays in us'e are either the flapper or the rotary-type

relays where,

becau.,e of their construction,

the problem observed is nonexistent.

Circular 79-22

Surveillance Test Procedure

V-3J1, "Exercising Pressurizer

Power Operated

Relief and Isolation Valves," recuires

exercising

and verifying stroke time

of. thc Diablo PORVs at least ruarterly to assure

that they will perform

as intended.

The concern of this Circular has

been addressed

by the plant staff.

Circular No. 79-23

The

DCPP Units

1 and

2 250VDC motor control centers

were supplied

by ITE<<Gould.

As the problem is only confined to

NEHA si

e

3 motor starters

and contactors,

the motor starters

that would apply are the ones for the generator air side

backup seal oil pumps

(one for each Unit). However,

the date

codes for these

starters

are i'ay before the period of concern,

therefore,

the circular does

not apply.

A check by Quality Control on warehouse

stock revealed

that although the

plant staff ordered

and received size

3 starter

replacement

parts during

the period of concern

(Purcha. e Order 595606 dated 7/6/78), there were no

complete units ordered but only additional pole add>>on kits.

Consultation

with the manufacturer

concludes

the add-on kits are not part of the problem

described

in the circular.

Circular No. 79-25

As several mechanical

shock arrestors

'(seismic limiters) manufactured

by

Pacific Scientific are installed in both units, Quality Control investigated

the possibi.lity that the Circular would apply to the plant.

Consultation

with Pacific Scientific, General Construction Hanger Group, andthe hanger

installation contractor

(Pullman Power Products)

confirmed that the

PSA sizes

in question are not installed in any of the plant piping systems

and that no

Bergen-Paterson

hardwares

have been used in either unit.

The Circular,

therefore,

does not apply to the plant.

No items of noncompliance or deviations

were identified.

4.

Follow

on Previousl

Identified Items

Volume Control'Tank

VCT

(79-06-01,

closed)

Because of the problems

revealed during

of the unit 2's VCT.

Unit 1's

VCT was re-inspected

and the

were noted.

Both VCT.'s were repaired

and hydrostatic tests

The test results

were examined with the

same procedures

and

reported in Inspection Report

No. 50-323/79-06.

the inspection

same indications

were performed.

results

as

No items of noncompliance

or deviations

were identified.

5.

PG-PL

L oodvard Governors

TI 2515/22

The Terry Corporation procedures

to assure

turbine restart within 30 minutes

without experiencing

an erroneous

overspeed trip have

been incorporated

into the surveillance test procedures.

The Supervisor of Operations

committed

to making the necessary

changes

in the operating procedure.

No items of noncompliance

or deviations

~ ere identified.

6.

Containment Purging

TI 2515/26

The inspector

reviewed

P & ID's and held discussions

with plant technical

personnel

to ascertain

that there are no manua'1 over-vide features for

containment isolation valves at Diablo Canyon.

Supplement

No.

9 to the

SER,

dated

June

1980,

@tates in part that the applicants

analysis

has

been

reviewed

and a conclusion

made that the 48 inch containment

purge valves

will operate

when reeuired during

a loss-of-coolant accident.

'o

items of noncompliance or deviations

were identified.

-4-

7 ~

tPlant Tour

The inspectors

walked through various areas of the plant on a weekly basis

to observe activities in progres;

to inspect

the genexal state of clean-

liness,

housekeeping

and adherence

to fire protection rules; to check the

proper approval of "man on the line, caution

and clearance"

tags

on e~uip-

ment,

and to review ~-"ith operation personnel

the status of various

systems

in the plant.

The inspectors

noted that the status of the systems

and the housekeeping

appeared

consistent

.;ith ccnstruction activities.

The reactor cavity is

still being maintained

as a clean area

and extra personnel

are still

assigned

to cleanup

crews.

Cleanliness

and housekeeping

of the plant is

still improving.

No items of noncompliance

or deviations

were identified.

8.

0 orator Trainin>>

The operations division is continuing their intensive retraining program

for the operators

and technical advisors to include two weeks at the

Mestinghouse

simulator.

The inspector's

have monitored

some of these

classes

and will monitor more classes

throughout the training program.

No items of'oncompliance

or deviati'ons

were identified.

0 eratin>>,

Administrative

and Surveillance Test Procedures

An inspector reviet ed several

new and revised

licensee operating,

adminis-

trative,

and surveillance test procedures.

Procedures

reviewed included:

EP OP-29

EP OP-31

EP OP-40

EP OP-41

EP OP-22

EP OP-23

EP

OP 74

NPAP A101 Sup

1

NPAP C-3

NPAP C'-9 Sup

1

NPAP C-703

EP"OP-27

EP OP-6

EP OP-ll

EP OP-16

EP OP-18

EP OP-38

STP 1-1584

STP I-20

STP I-64

E:excessive

Load Increase

System Underfre<uency

Accidental Depressuri,".ation of Hain Steam

System

Hydrogen E::plosion Inside Containment

Emergency

Shutdown

Natural Circulation of Reactor Coolant

Loss of Containment Integrity

Relieving the Match

Conduct of Plant

and Enuipment Tests

Sealed Valves

Meldex'dentification Symbol

Irradiated Fuel Damage

Emergency )3oration

Loss of Component Cooling Mater

Nuclear Instrumentation Halfunctions

Charging of Letdown Line Failure

Anticipated Transient Mithout Trip

Respon.

e Time Testing of Containment

Pressure

Transmitters

Calibration of Charging

Plo~; Channel,917

Calibration of Containment Recirculation

Sump Level

Channels

940 6 941

0

-5-

STP P-8B

STP N-84A

EP N"6

STP I<<'30A

STP I-30B

STP I-32A ,

STP I"32B

STP I-61

STP I-63

STP I-12B11

Op Order 0-1

OP-L-4

STP I-12B8

OP-A-4A-V

Op Order 0-2

Op Order 0-3

Routine Surveillance Test of CCfl Pumps

Hotor Operated

Valve Thermal. Overload Bypass Functional Testing

Nonradiological Fire

Functional Test of Accumulator Level Channels

950-957

Calibration of Accumulator Level Channels

950-957

Functional Test of Accumulator Pressure

Channels

960>>967

Calibration of Accumulator Pressure

Channels

960-967

Calibration of Containment Structure

Sump Flow Channels

40 6 41

Calibration of Reactor Cavity Sump Flow Channel

42

Response

Time Testing of Steam Generator

Pressure

Operation of Limitor~ue Valve Actuators

Operation at Power

Response

Time Testing of Steam Generator

Flow Transmitters

Pressurizer

Heaters - Emergency Operations

Operation of Hagan Controllers

Notifying the Shift RHi of Technical Specification Re<'uirements

Based

upon review, the following comments

are pertinent:

A.

Some Surveillance Test Procedures

(STP)

do not have

a provision to ensure

the restoratdon of environmental aualifications for safety related transmitters

after completion of periodic testing.

The licensee

has

committed to incorporate

such

a provision in existing STP's for safety related transmitters

or

generate

an independent

procedure

that would delineate

steps

to be taken

to restore transmitter environmental c~ualifications.

Pending revision of

existing procedures or generation of an independent

procedure this comment

will remain an open item for followup (80-16-01).

B.

Four of the above procedures;

OP L<<4,

EP OP-16,

EP OP-24,

and

EP H-6;

appear

to conflict with reouirements

in the licensee's

proposed Technical

Specifications.

Thc licensee

has

been provided with x"ritten comments

addressing

the potential areas of conflict.

Pending resolution of the

comments

by the

licensee,

this concern

~ ill remain an open item for follo~~p (80-16-02) .

No items of noncompliance or deviations

were identified.

10.

Exit Interview

The inspectors

met

x ith a senior licensee

representative

on a weekly

basis

and wi,th the representatives

denoted

in .Paragraph

1 on August 29,

1980.

The scope

and findings of the inspection were

summari: ed by the

inspectors.