ML16340A682

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-275/79-21 & 50-323/79-11 on 790821-24 & 0924-26.No Noncompliance Noted.Major Areas Inspected: Preoperational Testing Evaluation,Verification of Test Results & IE Circular Followup
ML16340A682
Person / Time
Site: Diablo Canyon  
Issue date: 10/19/1979
From: Horn A, Morrill P, Sternberg D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML16340A683 List:
References
50-275-79-21, 50-323-79-11, NUDOCS 7912060104
Download: ML16340A682 (10)


See also: IR 05000275/1979021

Text

50-275/79-21

epor t go

50-323/79-1

1

U ~ S.

NUCLEAR REGULATORX COMMISSION

OFFICE

OF INSPECTION AND ENFORCEMENT

REGION V

Docket

No.

50-275

5 50-323

License

No.

CPPR-'39

5 CPPR-69

/

Licensee:

PaCifiC

GaS

and EleCtriC

COmPany

77 Beale Street

Safeguards

Group

San Francisco,

California

94106

Faci1ity game:

Diablo Canyon Units

1

5 2

Inspection at:

Diablo Canyon Site,

San Luis Obispo County, California

Inspection

condu

ed:

Inspectors:

Au ust 21-24 and

Se tember 24-26,

1979

/- 7

Approved By:

P. J. le rill, React r Inspector

A. J

orp,

React r Ins ectorn.HJ 8.

Bag

o, Jr.'

ctor Inspector

D.

M. Sternberg,

Chief,

eactor Project Section Pl,

Reactor Operations

and Nuclear Support Branch

ate Signed

o I'I Wc

Date Signed

Date

igned

Date Signed

Summary:

Ins ection

on Au ust 21-24 and

Se tember 24-26,

1979

Re ort Nos. 50-275/79-21

and

50-323/79-11

A~Id:

R d,

dd*p

d

I'p

p'

p<<dg,

evaluation

and verification of test results,

independent

inspection,

IE Circular

follow-up, and

a tour of the facility.

This inspection

involved'120 inspector-

hours onsite

by three

NRC inspectors.

'esults:

No items of honcompliance

or deviations were identified.

g

RV Form 219 (2)

1

DETAILS

1.

Persons

Contacted

1R.

Ramsay,

Plant Superintendent

2

1

2R. Patterson,

Supervisor of Operations

. 1'2J.

Diamonon, guality Control-Supervisor

1'2J. Shiffer, Technical Assistant to Plant Superintendent

'<tl. Norem, Resident

Startup Engineer

1

2D. Rockwell, Resident

Engineer, Electrical

'. Gisclon,

Power Plant Engineer

The inspector

also talked with and interviewed several

other licensee

employees,

including members of the construction,

engineering

and

operations staff and

gA organization personnel.

2Denotes

those attending

the exit interview on August 24, 1979.

1

Denotes

those attending

the exit interview on September

26,

1979.

2.

Prep erational

Test Pro

ram

The inspectors

examined eleven Unit 1 preoperational

test procedure

packages

that have

been turned over from the construction organization to the opera-

ting organization.

The packages

were found to contain the proper

documenta-

tion of test results

review and approval,

and resolution of test deficiencies

and problems which occurred during the testing

phase.

The test results re-

viewed were as follows:

4.3

10. 3.1

10. 3.1

10.3.1

23.10

23.10

23.10

34. 2

35.1

Main Safety Valve Setpoints

RHR System Valve Interlocks

Addendum

No. 1, Verify Separate

Power Source for SIS Valve

Position Indication and Verify Power Interlock Contactors

Addendum No. 2, Retest

Valve Interlocks

Containment

Hydrogen

Put ge

(CHP) System

Addendum

No. 1, Air Blow Containment

Hydrogen

Purge Lines

Following l<eld Repair

Addendum

No. 2, Check Pressure

Drop Across

CHP Filters

Fuel

Handling Tools and Fixtures

Reactor Protection

Time Response

tleasurement

35.1

35. 2

35.2

35.2

35.3

35. 3

35. 3

Addendum

No. 1,-Retest

Reactor

Protection

Time Response

After System t<odification

Reactor Protection Ope'rational

Check

Addendum

No. 1, Test Safe Failure of Reactor'rotection

System

on Loss of Power to Process

Instrumentation

Addendum

No. 2, Retest

General

Warning Reactor Trip, Trip

Status Lights and

SSPS

Slave Relays

Safeguards

Systems

Operational

Check

Addendum

No. 1, Retest Trip Status Lights P-ll

Nod and

SSPS

Slave

Relays

Addendum

No. 2, Test Containment Vent Isolation from Nevi

Rms.

Inputs

37.6

Reactor Coolant

Pump Vibration Measurement

37. 7

37.7

t1ain Steam Isolation Val ves

Adendum

No. 1, Retest

NSIVs Following tlodification

37.15

Pressurizer

Level Control

37.23

Rod Control

System Functional

Test

(No Rods)

The inspectors

observed that for preoperational

test

35.1

and 37.23, the

calabration of test instrumentation verification was documented

in 1976

several

days to several

months after test completion which was contrary

to

iXemo to Startup

Engineers

834.

Licensee representatives

stated that

current plant procedures

provided for documenting

the verification of

instrument calibration at the time of the test and that additional guid-

ance to clarify the use of the "Instrument Calibration Verified" stamp

would be provided to the startup engineers.

The inspectors verified

that the instruments

used for the subject tests

were in calibration

when

used for tests

35.1

and 37.23

and that current plant procedures

provided

adequate

guidance.

No items of noncompliance

or deviations

were identified.

3. 'E Circular Follow-u

The inspector verified by discussions

with licensee

personnel

and review

of Plant Safety

Review Committee Meeting minutes that the following

circulars were r'eceived

by the licensee,

reviewed for applicability by

appropriate

personnel,

and appropriate

actions

were taken or planned.

Circular 78-19 - Manual Overrides

(Bypass) of Safety System Actuation

Signals:

Licensee

personnel

had determined that this issue

had been

considered

during the design stage of Diablo Canyon.

(Closed)

Circular 79-02

Failure of 120 Volt Vital AC Power Supplies:

Licensee

. personnel

concluded that the Diablo Canyon vital AC power supplies

.

differ in principle of operation

from those described

in the circular.

(Closed)

Circular 79-04 - Loose Locking faut on Limitorque Val've Operators:

The inspector verified the licensee's

personnel

have torqued

and staked

all locking nuts

on Unit

1 limitorque valve operators

and that

a similar

program is underway for Unit 2.

(Closed)

Circular 79-10 - Pipefitting Manufactured

from Unacceptable

Material:

The licensee's

review of receiving documents

from March 1978 through

January

1978 indicated

no defective material

(as described

in the

circular)

had

been received.

(Closed)

Circular 79-11 - Design/Construction

Interface

Problem:

The licensee's

Organization

includes operations,

design/engineering,

and construction/

startup for Diablo Canyon.

Departmental

and interface

procedures

exist

which should preclude the concerns of the circular.

(Closed)

Circular 79-12 - Potential

Diesel

Generator Turbocharger

Problem:

A

review of the Diablo Canyon

GM Diesel Turbocharger

Lube Oil System

showed

'that is is significantly different from the

ALCO turbocharger

lube oil

system.

(Closed)

Circular 79-13 - Replacement of Diesel

Fire

Pump Starting Contactor's:

No Cunmins

Engines

Company diesel fire pumps are planned or used

by the

licensee at Diablo Canyon.

(Closed)

No items of noncompliance or deviations

were identified.

Plant Tour

The inspectors

toured the facility and

made the following observations:

a

~

b.

Unit

1 systems

and components

were in a layup status consistent with

'heir

construction

and testing status.

Housekeeping

and cleanliness

in Unit

1 appeared

consistent with

construction activities and applicable fire and safety requirements.

No items of noncompliance or deviations

were identified.

Exit Interview

'he

inspector

met with licensee

representatives

(denoted in Paragraph

1)

on August 24, 1979,

and on September

26, 1979.

The scope

and findings

of the inspection

were summarized

by the inspectors.