Acceptance for Review of Application to Revise Technical Specifications Related to Adoption of Technical Specifications Task Force Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control.
ML16335A304
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 12/02/2016
From: Kimberly Green
Plant Licensing Branch III
To: Hamilton D
FirstEnergy Nuclear Operating Co
Green K
References
CAC MF8693, L-16-236
Download: ML16335A304 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 2, 2016 Mr. David B. Hamilton Site Vice President FirstEnergy Nuclear Operating Company P.O. Box 97 10 Center Road Perry, OH 44081-0097

SUBJECT:

PERRY NUCLEAR POWER PLANT, UNIT 1, ACCEPTANCE FOR REVIEW OF APPLICATION TO REVISE TECHNICAL SPECIFICATIONS RELATED TO ADOPTION OF TECHNICAL SPECIFICATIONS TASK FORCE TRAVELER TSTF-501, REVISION 1, "RELOCATE STORED FUEL OIL AND LUBE OIL VOLUME VALUES TO LICENSEE CONTROL" (CAC NO. MF8693) (L-16-236)

Dear Mr. Hamilton:

By letter dated October 27, 2016, First Energy Nuclear Operating Company (FENOC) submitted an amendment request for the Perry Nuclear Power Plant (PNPP). The proposed amendment would revise Technical Specification (TS) 3.8.3, "Diesel Fuel Oil, Lube Oil, and Starting Air," by relocating the current stored diesel fuel oil and lube oil numerical volume requirements from the TS to the TS Bases, consistent with Technical Specifications Task Force Traveler TSTF-501, Revision 1, "Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control." The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of the proposed license amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required.

This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

D. Hamilton Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 210 hours8.75 days <br />1.25 weeks <br />0.288 months <br /> to complete. The NRC staff expects to complete this review by the requested date of October 31, 2017. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates will be communicated, during the routine interactions with the assigned project manager.

These estimates are based on the staff's initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.

Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me at (301) 415-1627.

Sincerely, Kimberly Green, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-440 cc: Distribution via Listserv

D. Hamilton Based on the information provided in your submittal. the NRC staff has estimated that this licensing request will take approximately 210 hours8.75 days <br />1.25 weeks <br />0.288 months <br /> to complete. The NRC staff expects to complete this review by the requested date of October 31, 2017. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates will be communicated, during the routine interactions with the assigned project manager.

These estimates are based on the staff's initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.

Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me at (301) 415-1627.

Sincerely,

/RA/

Kimberly Green, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-440 cc: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsRgn3MailCenter Resource Branch Reading File RidsNrrLASRohrer Resource RidsACRS_MailCTR Resource PSnyder, NRR RidsNrrPMPerry Resource GCurran, NRR RidsNrrDorl Resource RWolfgang, NRR RidsNrrDorllpl3-1 Resource ADAMS Accession No.: ML16335A304 OFFICE DORL/LPL3-1 /PM DORL/LPL3-2/LA DORL/LPL3-1 /BC DORL/LPL3-1 /PM NAME KGreen SRohrer DWrona KGreen DATE 12/01/16 11/30/16 12/02/16 12/02/16 OFFICIAL RECORD COPY