NRR E-mail Capture - Callaway, Unit 1, Acceptance of Requested Licensing Action Relief Request CAC No. MF8524 Depth Size Inservice Inspection Impracticality
ML16335A016
Person / Time
Site: Callaway Ameren icon.png
Issue date: 11/29/2016
From: John Klos
Plant Licensing Branch IV
To: Elwood T
AmerenUE
References
MF8524
Download: ML16335A016 (3)


Text

NRR-PMDAPEm Resource From: Klos, John Sent: Tuesday, November 29, 2016 5:16 PM To: 'Telwood@ameren.com' Cc: Klos, John

Subject:

Callaway, Unit 1, Acceptance of Requested Licensing Action Relief request CAC No.

MF8524 Depth size Inservice Inspection Impracticality Mr. Elwood, By letter dated October 25, 2016, Agency-wide Documents and Access Management System (ADAMS)

Accession No. ML16299A451, Union Electric Company, Ameren Missouri submitted a relief request for the Callaway Plant, Unit 1. The proposed relief request would address an impractical Inservice Inspection regarding depth size inspections of large-bore dissimilar and austenitic welds. The purpose of this email is to provide the results of the U.S. Nuclear Regulatory (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to all the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 120 hours5 days <br />0.714 weeks <br />0.164 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months, which is October 25, 2017. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me.

John Klos DORL Callaway, Columbia Project Manager U.S. NRC, Office of Nuclear Reactor Regulation, Division of Operating Reactor Licensing, O8E7 NRC/NRR/DORL/LPL4-1, MS O8H4A Washington, DC 20555-0001 1

301.415.5136, 301.415.2102 (fax)

John.Klos@NRC.gov 2

Hearing Identifier: NRR_PMDA Email Number: 3188 Mail Envelope Properties (46600fc3ded148bd9be4f3e766f7a5b7)

Subject:

Callaway, Unit 1, Acceptance of Requested Licensing Action Relief request CAC No. MF8524 Depth size Inservice Inspection Impracticality Sent Date: 11/29/2016 5:15:43 PM Received Date: 11/29/2016 5:15:43 PM From: Klos, John Created By: John.Klos@nrc.gov Recipients:

"Klos, John" <John.Klos@nrc.gov>

Tracking Status: None

"'Telwood@ameren.com'" <Telwood@ameren.com>

Tracking Status: None Post Office: HQPWMSMRS05.nrc.gov Files Size Date & Time MESSAGE 3048 11/29/2016 5:15:43 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: