MONTHYEARNRC-14-0033, Annual Non-Radiological Environmental Operating Report for 20132014-04-28028 April 2014 Annual Non-Radiological Environmental Operating Report for 2013 Project stage: Request ML14224A3532014-09-0303 September 2014 License Renewal Environmental Site Audit Regarding Fermi, Units 2 Project stage: Other ML14294A7922014-10-28028 October 2014 Project Manager Change for the License Renewal of Fermi, Unit 2, Project stage: Other ML14294A8122014-11-17017 November 2014 Summary of the Severe Accidents Mitigation Alternatives Environmental Site Audit Related to the Review of the License Renewal Application for Fermi 2 Project stage: Approval ML14308A5302014-11-20020 November 2014 Summary of Phone Call Between the NRC and DTE Electric Co, Concerning RAIs Pertaining to the Fermi 2 LRA Environmental Review Project stage: RAI ML14308A5982014-11-20020 November 2014 Summary of Telephone Conference Call Held Between NRC and DTE Electric Co., Concerning Requests for Additional Information Pertaining to Fermi, Unit 2 License Renewal Application Project stage: RAI ML14330A2632014-12-15015 December 2014 Summary of Telephone Conference Call Held on November 17, 2014, Between the U.S. Nuclear Regulatory Commission and DTE Electric Company, Concerning Requests for Additional Information Pertaining to the Fermi 2 License Renewal Application En Project stage: RAI ML15355A4642015-12-21021 December 2015 DTE Response to Beyond Nuclear Hearing Request and Motion to Reopen Project stage: Request ML16190A0842016-06-0808 June 2016 Public Meeting, June 8, 2016 (Pmc Comments1) Project stage: Meeting ML16190A0692016-06-0808 June 2016 Scoping Meeting Transcripts, June 8, 2016 Project stage: Meeting ML16166A0442016-06-22022 June 2016 Schedule Revision for the Environmental Review of the Fermi 2 License Renewal Application Project stage: Approval ML16256A1682016-09-21021 September 2016 Letter to EPA - Notice of Availability of the Final Plant-Specific Supplement 56 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Fermi 2 Nuclear Power Plant Project stage: Other 2014-04-28
[Table View] |
Similar Documents at Fermi |
---|
Category:Letter
MONTHYEARIR 05000341/20240032024-11-0606 November 2024 Integrated Inspection Report 05000341/2024003 IR 05000341/20240122024-11-0101 November 2024 Commercial Grade Dedication Inspection Report 05000341/2024012 IR 05000016/20240012024-11-0101 November 2024 Enrico Fermi Atomic Power Plant, Unit 1, NRC Inspection Report 05000016/2024001 IR 05000341/20245012024-10-0808 October 2024 – Emergency Preparedness Inspection Report 05000341/2024501 ML24276A2032024-10-0303 October 2024 FEMA Level 1 Finding Transmittal Letter ML24268A0992024-10-0101 October 2024 Power Plant – Audit Summary for License Amendment Request and Regulatory Exemptions for a Risk Informed Approach to Address ECCS Strainer Performance IR 05000341/20240132024-09-30030 September 2024 Phase 2 Post Approval License Renewal Report 05000341/2024013 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24257A1652024-09-13013 September 2024 FEMA Region 5 Fermi 2 Nuclear Power Plant Level 1 Finding September 2024 ML24254A3562024-09-0909 September 2024 FEMA Level 1 Finding for Fermi 2024 Biennial Exercise ML24240A3532024-08-27027 August 2024 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20244042024-08-21021 August 2024 Public-Fermi Power Plant, Unit 2 - Material Control and Accounting Program Inspection Report 05000341/2024404 IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000341/LER-2024-002, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024 Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications 05000341/LER-2024-001, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 ML24002B1812024-03-0404 March 2024 Issuance of Amendment No. 228 Regarding Revision of Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) 2024-09-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 17, 2014 Mr. Vito Kaminskas Site Vice President - Nuclear Generation DTE Electric Company Fermi 2 - 280 OBA 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
SUMMARY
OF THE SEVERE ACCIDENTS MITIGATION ALTERNATIVES ENVIRONMENTAL SITE AUDIT RELATED TO THE REVIEW OF THE LICENSE RENEWAL APPLICATION FOR FERMI 2 (TAC NO. MF4064)
Dear Mr. Kaminskas:
On October 6-8, 2014, a review team consisting of staff from the U.S. Nuclear Regulatory Commission (NRC) and contractors from the Center for Nuclear Waste Regulatory Analyses participated in a site audit at Fermi 2 (Fermi) in Newport, Michigan, related to the severe accidents mitigation alternatives (SAMA) environmental review of the Fermi license renewal application. The primary goal of the site visit was to review documentation and gather information to ensure that the environmental requirements for license renewal, as codified in Title 10 of the Code of Federal Regulations Part 51 were met, in accordance with the issued audit plan (ML14252A831). The enclosure is a list of representatives from NRC and personnel from DTE Electric Company (DTE) and its contractors who participated in the site audit.
The audit began on October 6, 2014, with an entrance meeting to introduce participants and discuss logistics of the audit. Following the entrance meeting, the NRC environmental review team and DTE discussed the following topics relative to the SAMA analysis: (1) Level 1 Probabilistic Risk Assessment (PRA), (2) Level 2 model PRA, (3) external events, (4) Level 3 consequence analysis, (5) selection and screening of Phase 1 SAMAs, (6) cost-benefit analysis and site-specific cost estimates, and (7) consideration of potentially lower or more effective alternative SAMAs.
During the exit meeting at the conclusion of the site audit, the NRC environmental review team summarized the status of the review with DTE. Most of the team's questions identified in the audit plan or during the audit were answered through the conduct of the audit.
NRC staff is preparing requests for additional information (RAIs), which will be issued in a subsequent letter. While the NRC review team did not identify any significant environmental issues during its site audit, the environmental review of the Fermi license renewal application is ongoing, and thus, any additional information necessary to support the review would be formally requested via the RAI process.
Sincerely,
/RA/
Michael Wentzel, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosure:
List of Participants cc w/encl: Listserv
ML14294A812
- concurred via email OFFICE LA:RPB2:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME IKing MWentzel BWittick MWentzel DATE 11/5/2014 11/12/2014 11/15/2014 11/17/2014
Letter to V. Kaminskas from M. Wentzel dated November 17, 2014
SUBJECT:
SUMMARY
OF THE SITE AUDIT RELATED TO THE REVIEW OF THE LICENSE RENEWAL APPLICATION FOR FERMI 2 (TAC NO. MF4064)
DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRsrg Resource RidsNrrPMFermi Resource M. Wentzel B. Wittick D. Melendez-Colon Y. Diaz-Sanabria M. Kunowski, RIII B. Kemker, RIII P. Smagacz, RII V. Mitlyng, RIII P. Chandrathil, RIII H. Logaras, RIII A. Barker, RIII C. Kanatas, OGC D. Roth, OGC
ENCLOSURE LIST OF PARTICIPANTS FERMI 2 LICENSE RENEWAL APPLICATION REVIEW SEVERE ACCIDENTS MITIGATION ALTERNATIVES SITE AUDIT October 6-8, 2014 PARTICIPANTS ORGANIZATION Leslie Perkins U.S. Nuclear Regulatory Commission (NRC)
Jerry Dozier NRC Bob Schmidt Center for Nuclear Waste Regulatory Analyses (CNWRA)
Roland Benke CNWRA Vito Kaminskas DTE Electric Company (DTE)
Lynne Goodman DTE Randy Westmoreland DTE James Thorson DTE Michael Koenemann DTE John Tibai DTE/URS Angela Rudolph DTE/URS Joe Lavelline DTE/Enercon Nathan Dekett DTE Kevin Lynn DTE/Tetra Tech Lisa Chambers DTE Marvin Morris DTE/Enercon Brian Norman DTE/Enercon Mike Lake DTE