ML16161B194

From kanterella
Jump to navigation Jump to search
Forwards IE Bulletin 80-20, Failures of Westinghouse Type W-2 Spring Return to Neutral Control Switches. Requests Info Re Estimate of Manpower Associated W/Corrective Actions Needed After Identifying Problem
ML16161B194
Person / Time
Site: Oconee, Mcguire, Catawba, McGuire  Duke Energy icon.png
Issue date: 07/31/1980
From: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parker W
DUKE POWER CO.
References
NUDOCS 8008140587
Download: ML16161B194 (1)


Text

t pfl REOj w 0 UNITED STATES 0

aNUCLEAR REGULATORY COMMISSION Z,

REGION II1 101 MARIETTA ST., N.W., SUITE 3100 I

ATLANTA, GEORGIA 30303 JUL 3 1 1980 In Reply Refer To:

RII:JPO 50-369, 50-370 0-287,> 50-413 50-414 Duke Power Company ATTN:

W. 0. Parker, Jr.

Vice President, Steam Production P. 0. Box 2178 Charlotte, NC 28242 Gentlemen:

Enclosed is IE Bulletin No. 80-20 which requires action by you with regard to your nuclear power facility(ies).

In order to assist the-NRC in evaluating the value/impact of each Bulletin on licensees, it would be helpful if you would provide an estimate of the manpower expended in conduct of the review and preparation of the report(s) required by the Bulletin.

Please estimate separately the manpower associated with corrective actions necessary following identification of problems through the Bulletin.

Should you have any questions regarding this Bulletin or the actions required by you, please contact this office.

Sincerely, James P. O'Reilly Director

Enclosures:

1.

IE Bulletin No. 80-20

2.

List of Recently Issued IE Bulletins' cc w/encl:

M. D. McIntosh, Plant Manager J. C. Rogers, Project Manager J. E. Smith, Station Manager D. G. Beam, Project Manager J. W. Hampton, Station Manager 80081405'W4