ML16154A809

From kanterella
Jump to navigation Jump to search
Insp Repts 50-269/95-10,50-270/95-10 & 50-287/95-10 on 950605-16.No Violations Noted.Major Areas Inspected: Electrical Design
ML16154A809
Person / Time
Site: Oconee  
Issue date: 07/12/1995
From: Steven Rudisail, Shymlock M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML16154A810 List:
References
50-269-95-10, 50-270-95-10, 50-287-95-10, NUDOCS 9507240382
Download: ML16154A809 (16)


See also: IR 05000269/1995010

Text

pft REG&

UNITED STATES

o~

NUCLEAR REGULATORY COMMISSION

REGION II

0

101 MARIETTA STREET, N.W., SUITE 2900

ATLANTA, GEORGIA 30323-0199

Report Nos.:

50-269/95-10, 50-270/95-10 and 50-287/95-10

Licensee:

Duke Power Company

422 South Church Street

Charlotte, NC 28242

Docket Nos.:

50-269, 50-270, and 50-287

License Nos.:

DPR-38, DPR-47,

and DPR-55

Facility Name:

Oconee Nuclear Station Units 1, 2 and 3

Inspection Conducted:

June 5 -

16, 1995

Inspector: J

7 7 95

S.' Rudisail

Date Signed

Accompanying Personnel: V. Beaston, NRR

Approved by:

_

_

_ _

_

7-__

_

_

M. Shymlock, C6Aef

Date Signed

Plant System Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This routine, announced inspection was conducted in the areas of electrical

design to review the licensee action in response to Electrical Distribution

System Functional Inspection (EDSFI) findings and other EDSFI issues

identified in NRC Inspection Report 50-269, 270, 287/93-02. These items were

being resolved as part of the licensee's Power Upgrade Project (PUP).

Results:

In the areas inspected, violations or deviations were not identified.

The inspector reviewed the licensee response and corrective actions for

violation 94-26-01, Failure to Perform Procedure as Corrective Action. This

violation was closed.

Deviation 93-02-02 was also closed. The licensee had completed the remaining

corrective actions for the deviation.

Enclosure

9507240382 950714

PDR

ADOCK 05000269

0

PDR

2

The inspectors reviewed various PUP items completed in response to EDSFI

findings. These findings were identified as Inspector Follow-up Item (IFI)

93-02-03.

Overall, the calculations were of good quality with no problems identified

during the calculation reviews. The licensee corrective actions for these

items were technically sound and through.

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

L. Azzarello, Mechanical Systems Engineering

  • K. Burchfield, Regulatory Compliance

P. Colaianni, Nuclear General Office, License Renewal

D. Coyle, Mechanical Systems Engineering

  • J. Davis, Engineering

T. Grant, Electrical Systems Engineering

  • J. Hampton, Site Vice-president

T. Ledford, Electrical Systems Engineering

  • C. Little, Electrical Systems Engineering

D. Patterson, Regulatory Compliance

  • B. Peele, Plant Manager

J. Stevens, Electrical Systems Engineering

Other licensee employee contacted during this inspection included

craftsmen, engineers, technicians, and administrative personnel.

NRC Employees:

P. Harmon, Senior Resident Inspector

  • L. Keller, Resident Inspector

K. Poertner, Resident Inspector

  • Attended exit interview

Acronyms and abbreviations used throughout this report are identified in

the last paragraph.

2.

Background

During January 25 through March 5, 1993, the NRC conducted the

Electrical System Distribution Functional Inspection (EDSFI).

The

purpose of this inspection was to assess the capability of the Oconee

Electrical Distribution System to perform it functions during normal

operations and accident conditions. The conclusion of the EDSFI team

was that the electrical distribution system would perform its intended

function pending further analysis and testing by the licensee. During

the EDSFI inspection a violation and several deviations were identified.

Additionally, findings identified during the EDSFI were collectively

identified as IFI 93-02-03.

3.

Review of Corrective Action for Violation and Deviations (IP 92702)

The inspector reviewed a violation identified during a previous EDSFI

follow-up inspection and three deviations identified at Oconee during

the EDSFI. These items are discussed in the following paragraphs.

2

3.1

(Closed) Violation 50-269, 270, 287/94-26-01, Failure to Perform

Procedure as Corrective Action was closed. This violation was

identified after it was determined that Keowee procedure OP/A/2000/45,

Lock Verification had not been performed. This procedure was issued as

part of the corrective action for deviation 93-02-02. During a review

of the corrective actions for this deviation it was determined that this

procedure had not been performed until the results were requested for

review by the inspector. This procedure was required to be performed

semi-annually. During this inspection the corrective actions for this

violation were reviewed. The inspector verified that this procedure had

been included in the procedure tracking system and reviewed the results

of the most recently completed procedure. The results of this review

were adequate. This violation was closed.

3.2

(Closed) Deviation 93-02-02, Item 1, Deviation from FSAR Color Coding

Requirements for Cables was one of three examples of this deviation

identified during the EDSFI.

The first example was identified as power

cables 1XS2 and 1XS48 not being correctly color coded. These cables run

from the motor control centers 1XS1 and 1XS2 to transformer CT4 cooling

fans. Final Safety Analysis Report (FSAR) section 8.3.1.3 states that

motor control center (MCC) 1XS1 power and control system cable are color

coded gray and that MCC 1XS2 cables are color coded yellow. Contrary to

this requirement, both cables were color coded black.

The licensee responded to this deviation and agreed that it was a

deviation from the requirements of the FSAR and an oversight during

initial installation.

The licensee considered the color coding was

intended to ensure separation during installation. The separation

requirements are for mutually redundant cables to be run in separate

trays. The cables are routed in different cable trays until they reach

the block house of the CT4 transformer. The cable is interlocked armor

type cable. The licensee determined the impact of failure of both

cables and concluded that should they fail the transformer would

continue to operate as designed with only a small impact on transformer

life. Alarms are available to indicate loss of power to the fans and

high oil and winding temperature in the transformer. Operator action

would be required upon receipt of alarms. The licensee concluded that

the impact on safety due to the cable being color coded black was

insignificant. The inspector agreed with this conclusion. The licensee

proposed additional corrective action to perform an inspection of all

plant, switchyard, and Keowee cables fed from safety related busses not

previously identified as having mutually redundant safety related

functions.

The inspector reviewed the results of the cable separation study. This

was identified as item 13 of the licensee's PUP. This study identified

several cables of mutually redundant systems at Keowee which were routed

in the same cable tray. The licensee had determined that these cables

were routed such that the distance between the cables was sufficient to

preclude the need for re-routing the cables for the purpose of cable

tray separation. The inspector performed a walkdown of the affected

cables to determine if the licensee evaluation of their safety

II

3

significance was appropriate. These cables were interlocked armor type

cables and were adequately separated. The inspector agreed that these

cables were sufficiently separated to preclude the mutual failure of

both cables. This deviation item was closed.

3.3

(Closed) Deviation 93-02-02, Item 2, identified mutually redundant

cables for Unit 2 emergency core cooling isolation valves 2LP-19 and

2LP-20 being routed in the same cable tray. This was contrary to the

requirements of FSAR section 8.3.1.4.6.2. The licensee agreed that this

was a deviation.

The corrective action for this deviation was to perform a modification

to separate the cables. Minor modification OE-5990 was prepared to

separate the cables. The inspector reviewed this modification and the

scope of work accomplished during its performance. This modification

accomplished the required corrective action. Inspection of Unit 1 and

Unit 3 cable for valves LP-19 and LP-20 were performed and the

separation problem did not exist. The licensee proposed additional

corrective action to perform an inspection of all plant, switchyard, and

Keowee cables fed from safety related busses not previously identified

as having mutually redundant safety related functions. This study was

discussed in item 1 of the deviation.

Item 2 of the deviation was

closed. This closes deviation 93-02-02.

Item 3 of the deviation was

closed in inspection report 50-269,270,287/94-26.

4.

Review of Inspector Follow-up Items (IP

92903, TI 2515/111)

The inspector reviewed the items identified at Oconee as Findings.

IFI 93-02-03, EDSFI Findings consisted of six findings with several

issues identified in each finding. This finding was closed in NRC

inspection report 50-269, 270, 287/94-26 to document the findings which

were closed in that report.

IFI 94-26-02 was opened to identify the

EDSFI finding items which remain opened.

4.1.

Finding 2 was an identification of analyses, studies and calculations

which were not complete or had not been performed. There were ten

elements identified in this finding. Item 2.j was closed in IR 50-269,

270, 287/94-26. The other nine items identified in finding 2 remained

open. Some of these items were reviewed during this inspection and are

discussed below:

4.1.1 Finding 2.a identified that calculation OSC-2059, Oconee Unit 1 Voltage

and Load Study may not have bound the worst case. During the EDSFI

review of the Oconee short circuit and voltage studies, the team

identified deficiencies in calculation OSC-2059. The Unit 2 and Unit 3

calculation were being revised during the EDSFI and were not available

for review. The team noted during the review of OSC-2059 the following.

(1) The momentary current on the 4.16 kV supply breakers under the

worst case scenario was 83 kiloamperes (kA) exceeding the breaker

rating of 80 kA. The team noted that some of the breakers had

been successfully tested at 83 kA by the manufacturer.

4

(2) There was only one input file for both short circuit and voltage

drop calculations which may not bound the worst case minimum and

maximum voltages.

(3) The calculation did not adequately model the transformer tap

position or the pre-fault bus voltage.

(4) When determining the total loads on transformers the study used 75

degree cable temperature, and constant motor efficiency and power

factor at full load.

(5) Only one 230 kV system impedance was modeled in the study.

However, the,EDSFI team previously concluded that even though the

calculation results may not be bounding that they were acceptable and

no operational problems were identified.

Item 22 was identified to address this EDSFI finding. The inspector

reviewed the following calculations revised to address this finding.

Calculation OSC-2059 Rev. 3, calculation OSC-2060 Rev. 3, Oconee Unit 2

Voltage and Load Study, and OSC-2061 Rev. 2, Oconee Unit 3 Voltage and

Load Study. The calculations were reviewed to ensure that adequate

voltage would be provided to the units auxiliary power system and that

the fault duty of the switchgear and protective devices were adequately

sized.

The concerns identified in the EDSFI were also reviewed to

ensure that they were addressed by the revisions to the calculations.

The methodology used to perform the calculations was reviewed to ensure

each item was addressed. The inspector determined from review of the

calculation that only one input file is needed as this file contains

manufacturers and test data and actual cable lengths. The revision

incorporated the actual transformer impedance for the tap setting and

modeled pre-fault bus voltages. The calculation uses actual motor KVA

and power factors. The worst case 230 kV system impedance was used to

calculate fault currents.

The results of the revised calculation

lowered the magnitude of the calculated faults thus addressing the

circuit breaker rating concern. This item was closed.

4.1.2 Item 2.c identified that a transient voltage study for the 4kV safety

loads when supplied by the Lee or Central substation was not available.

The licensee responded that a calculation to demonstrate dynamic

modeling of the Lee and Central power sources would be completed. In

EDSFI report section 2.6.2 a concern was expressed that during starting

of a unit's LOCA loads and two unit's shutdown loads, the transient

voltage dip could exceed 20 percent. The licensee agreed to prepare a

transient voltage study for the 4 kV safety load groups when they are

supplied by the Lee gas turbine or from Central substation. During this

inspection the revision to calculation OSC-3585, Voltage Study for the

Oconee Auxiliary System When Fed from the 100 kV System via CT5 Rev. 1

was reviewed. This revision computed the transient reactance of the 100

kV system (while being supplied from the central substation) to the

standby bus. The transient reactance when the Oconee auxiliary system

is supplied by the 100 kv system is 1.5 times less than when the Oconee

5

auxiliaries are supplied from Keowee. This results in a smaller

transient dip when supplied by the 100 kV system. The inspector

concluded that the calculation OSC-3585 demonstrated the ability of the

100 kV system (while being supplied from the central substation) to

supply adequate voltage to the Oconee auxiliaries and recover from the

postulated transient. This part of finding 2.c will be closed. The

review of the voltage study for Lee gas turbine supplying the Oconee

auxiliaries remains open.

4.1.3 Item 2.d identified that a study to review control cable length and the

size of fuses that protect them had not been conducted.

This item was

addressed by the licensee as PUP item 22.

The licensee completed three

calculations in response to this finding. The inspector reviewed

calculation OSC-5930 Rev. 0, Unit 1 QA1 Motor Starter Circuit and Fuse

Adequacy Calculation, calculation OSC-6143 Rev. 0, Unit 2 MCC Contactor

Voltage Adequacy and Fuse Adequacy Verification and OSC-6144 Rev. 0,

Unit 3 MCC Contactor Voltage Adequacy and Fuse Adequacy Verification.

The purpose of the calculations was to demonstrate that each units motor

control circuits would have adequate voltage during a LOCA degraded grid

scenario and that during an overvoltage condition the fuses would not

blow. The results of the calculations demonstrate that adequate voltage

is available for each of the motor starting circuits and fuses are

adequately sized for the circuit application. The inspector did not

identify any additional concerns during the calculation reviews. This

item was closed.

4.1.4 Item 2.e of the EDSFI identified that the Keowee 600V Auxiliary Power

System Voltage Analysis did not evaluate maximum and minimum expected

voltages. PUP item 4.a was identified to address this EDSFI item. The

licensee completed calculation KC-UNIT-1-2-0095 Rev. 0 to address

voltage adequacy in the auxiliary power system. The calculation

documented and analyzed the adequacy of Keowee electrical distribution

system voltages when supplied by either the 230 kV switchyard or the

Keowee generators. The results of the calculation demonstrate that the

Keowee Station auxiliary electrical system will be within acceptable

limits to allow performance of their design functions under all system

configurations and at minimum and maximum predicted switchyard voltages.

The inspectors reviewed the calculation and found the results

demonstrated the adequacy of the voltage supplied to the Keowee

electrical auxiliaries. This item was closed.

4.1.5 Item 2.f, was a concern that no analysis existed to support that the

Keowee auxiliaries would not be damaged by overvoltage or overfrequency

when supplied by one Keowee unit.

Item 2.h identified that an analysis

to support the assumption that Oconee safety loads could properly

perform during an overfrequency transient lasting 40-50 seconds. The

licensee plans to complete an analysis to support this assumption.

During a previous inspection documented in NRC inspection report 50-269,

270, 287/94-26, the inspector reviewed the actions completed for these

finding. One calculation had been completed. The calculation to

demonstrate the effect of overvoltages and overfrequencies on the Keowee

  • II6

auxiliaries was complete. The calculation OSC-5701 Rev. 0, Oconee

Keowee Overhead Path Analysis identified weaknesses that limit the

percent power the Keowee units can generate to the grid and the

alignment of the Keowee units. Additionally, calculation OSC-5952 Rev.

0, Oconee-Keowee Underground Path Analysis Using Cyme was reviewed

during this inspection and discussed in paragraph 4.2.2 of this report.

Corrective actions identified by these calculations are being addressed

in modification NSM 52966 currently being reviewed by the NRC. This

item will remain open pending the completion of this review and

implementation of the modification by the licensee.

4.1.6 Item 2.i identified that calculations for the Safe Shutdown Facility

were not complete. PUP items 16 and 17 was identified to address this

finding. The inspector reviewed the completed calculations for this

finding. The licensee had completed calculation OSC-5093 Rev. 0, SSF

Electrical Distribution System Load Flow, Voltage Adequacy, and Fault

Study. The inspector reviewed the results of this calculation.

The

results of the calculation for the SSF Diesel Static Analysis which was

attachment 5 of the calculation indicated a potential overload of the

feeder breaker for load center MCC XSF. The feeder breaker had a long

time setting of 660 amperes. The calculation demonstrated that this

breaker could be subjected to 863 amperes. This loading could result in

a breaker trip after 5 minutes. PIP 4-095-0400 was initiated based on

this calculation result. Immediate corrective actions were taken to

ensure SSF operability. Four duct heater breakers (for room heating)

were tagged out which would reduce loading sufficiently to correct the

problem. Long term corrective action included a minor modification to

replace the breaker trip element to a size sufficient to support the

calculated loading.

Other than this problem the results of the

calculation demonstrated the adequacy of the SSF electrical system

ratings. This finding was closed.

4.2

Finding 5 of the EDSFI was the identification that Keowee engineering

analyses were not sufficiently comprehensive and specific values had not

been established which would bound the design criteria. Four items were

identified in this finding. Finding 5.a identified that all credible

failure modes for the governor control system and voltage regulator had

not been considered. This item was not reviewed during this inspection

and remains open. The additional items for finding 5 are addressed in

the following paragraphs.

4.2.1 The inspectors reviewed PUP item 5 which addressed EDSFI finding 5.b.

Finding 5.b of the Oconee EDSFI report stated "The basis for bypassing

Keowee trip functions during emergency start of the unit was not fully

analyzed or documented."

Section 3.2.4.2 of the Oconee EDSFI inspection report, "Protective

Feature Issues," stated that "the control logic bypasses all of the

Keowee normal automatic electrical and mechanical protective trips on an

emergency start. The bypassed trips included generator and turbine

bearing overtemperatures, volts/hertz, overspeed, governor oil pressure,

7

generator field ground, and maximum excitation."

The EDSFI team had

concluded that the basis for bypassing Keowee trip functions during

emergency start of the units was not fully analyzed. As a result of the

concern, the licensee initiated PIP 0-093-0081 to request an analysis of

Keowee lockout relay trip signals.

The inspectors reviewed calculation/analysis KC-0107, Analysis of Keowee

Lockout Relay Trip Signals, dated May 22, 1995. This analysis

documented the bases which would be used to determine lockout trip

signals at Keowee.

The Keowee hydro units are equipped with two lockout relays (LOR),

designated as the Emergency LOR (86E) and the Normal LOR (86N). In

addition each unit has a shutdown relay (99SX) which causes the wicket

gates to close when deenergized and an Alarm LOR (30X) which will

prevent non-emergency automatic starts of the Keowee units. The 86E LOR

is designed to immediately separate a Keowee unit by tripping the

generator output breakers without unloading the unit. The 86E LOR is

not bypassed during an emergency start of the Keowee units. The 86N LOR

is designed to unload the generator by activating the 99SX relay first

and allowing the wicket gates to reach their speed-no-load positions

prior to tripping the generator output breakers. The 86N LOR is bypassed

during an emergency start of the Keowee units.

The Keowee lockout relay analysis concluded that the existing design was

adequate to ensure proper unit response to an emergency, however, it

also recognized that system enhancements could be achieved. One of the

recommendations made in the analysis was to move the volts/hertz and

generator overexcitation trips from the 86N LOR to the 86E LOR. This

recommendation will be addressed by Keowee Voltage Regulator

modification NSM ON-52965. The overspeed trip will be removed when NSM

ON-52966 is implemented and replaced by a time-delay trip input to the

86E LOR. The analysis also recommended that the mechanical systems

group review the bearing overtemperature trips setpoints to see if they

could be set just below the bearings' material melting points, thereby

allowing operators more time to take action.

The inspectors found the licensee's basis for bypassing Keowee trip

functions during emergency starts acceptable, and concluded that the

basis had been adequately analyzed and documented. The licensee was

tracking the recommendations of the analysis with PIP 4-095-0577. This

item was closed.

4.2.2 The inspectors reviewed PUP item 4.h which addressed EDSFI items 5.c and

5.d.

Findings 5.c of the Oconee EDSFI report stated "The effect of frequency

of the electrical power supplied by Keowee to the ECCS pump motors had

not been fully evaluated."

8

Finding 5.d of the Oconee EDSFI report stated "Acceptable voltage and

frequency limitations for the Keowee electrical auxiliaries and the

emergency power system should be defined. Additionally, acceptable

recovery times from voltage and frequency excursions should also be

identified."

Section 3.4.1 of the Oconee EDSFI inspection report, "Review of Voltage

and Frequency Analyses and Tests," identified concerns with the

licensee's analysis of the Keowee hydro units ability to supply adequate

power to Oconee auxiliaries during voltage and frequency transients.

The inspectors reviewed calculation OSC-5952, Oconee-Keowee Underground

Path Analysis Using Cyme, dated May 25, 1995. The purpose of this

calculation was to determine the adequacy of the Keowee units when used

to provide emergency power to the Oconee auxiliaries via the underground

path. The calculation contained voltage and frequency plots for five

different scenarios. Also provided in the calculation were the

transient start data for the ECCS pump motors. The five scenarios

modeled were:

(1) A Keowee unit running at steady state, no load, accepts Oconee

Unit 1 LOCA loads and Oconee Units 2 & 3 LOOP loads

simultaneously;

(2) A Keowee unit running at steady state, no load, accepts Oconee

Unit 1 LOCA loads followed 20 seconds later by Oconee Units 2 & 3

LOOP loads;

(3) A Keowee unit running at steady state, no load, accepts Oconee

Unit 1 LOCA loads along with one condensate booster pump;

(4) A Keowee unit supplying 75 MW to the grid receives an emergency

start demand, the Keowee unit accepts Oconee Unit 1 LOCA loads

plus a condensate booster pump once the governor reduces system

frequency to 110% of its rated value, Oconee Units 2 & 3 LOOP

loads are accepted by the Keowee unit 9 seconds later;

(5) A Keowee unit supplying 75 MW to the grid receives an emergency

start demand, the Keowee unit accepts Oconee Unit 1 LOCA loads,

Oconee Unit 2 LOOP loads, plus a condensate booster pump once the

governor reduces system frequency to 110% of its rated value,

Oconee Units 3 LOOP loads are accepted by the Keowee unit 9

seconds later.

The licensee compared the results of the transient analysis using the

following criteria to determine the operability of the Oconee auxiliary

system:

(1) At the 4 kV level, voltages on switchgear ITD (Bus 115) were

compared against the settings of the 27S relays to determine the

effects of transient voltages on the relays operation;

  • I

9

(2) At the 600 V and lower level, voltages at MCC XS1, XS2, and XS3

were compared with pick-up and drop-out voltages of contactors to

determine the effects of transient voltages on contactor

operations. The licensee based the pick-up and drop-out voltages

for contactors on test values provided by GTE Sylvania;

(3) Motor starting currents were compared against the settings of

their associated overcurrent relays to determine the effects of

transient voltage on motor operation.

The inspectors were concerned about how the initial voltage level of the

Keowee unit would affect the ability of the ECCS pump motors to start.

At the request of the inspectors, the licensee performed an analysis of

scenario one above for a case were the initial generator output voltage

of the Keowee unit was only 13.2 kV, instead of the 13.8 kV used in the

calculation. This analysis was requested to determine how sensitive the

computer simulations might be to small inaccuracies in the input data,

and to determine how much margin might exist between the nominal

operating voltage of the Keowee units and the minimum values needed to

ensure proper operation of the Oconee safety loads.

To address the inspectors concern about low generator output voltage,

the licensee plotted the starting currents for the low pressure service

water pump and the reactor building spray pump motors at Keowee output

voltages of 13.8 kV, 13.5 kV, and 13.2 kV along with the associated

overcurrent protection relay curves. These motors had been previously

identified by the licensee as the most limiting ECCS motors at Oconee

when started under degraded voltage or frequency conditions. From these

plots the inspectors were able to see how the motor start currents and

start times where changing with Keowee generator output voltage and

frequency, and gain some insight into what the computer simulation was

predicting and the actual trip settings of the overcurrent protection

relays. Based on these plots and the conservatism of the assumptions

used by the licensee in the analysis, the inspectors had no concerns

that the ECCS motors would not start.

The transient simulations conducted by the licensee for calculation OSC

5952 showed that underfrequency effects were not a problem when the

Keowee generator output voltage was within its currently specified

operating band of 13.5 kV to 14.1 kV prior to loading. The transient

analysis also showed that overfrequency effects were not a problem once

the licensee completes a modification of the Keowee units which will

ensure that the Oconee electrical distribution systems are not connected

to a Keowee generator output until after the system frequency has

returned to 110% of its rated value following a Keowee unit load

rejection. The.adequacy of this proposed modification of the Keowee

units is currently under review by the NRC's Office of Nuclear Reactor

Regulation.

Based on a review of calculation OSC-5952, which documents the adequacy

of the Keowee units to supply power to Oconee auxiliaries via the

underground path, prior NRC review of the adequacy of the Keowee units

  • I

10

to supply the Oconee auxiliaries via the overhead path as analyzed in

calculation OSC-5701, Oconee Keowee Overhead Path Analysis and discussed

in NRC IR 50-269, 270, 287/94-26, and the licensee's proposed

modification to eliminate the Keowee overspeed/overfrequency concerns

currently under review by the Office of Nuclear Reactor Regulation, the

inspectors concluded that the issues identified as findings 5.c and 5.d

of Oconee Inspection Report 93-02 have been adequately addressed. These

items will remain open pending completion of a safety evaluation by the

Office of Nuclear Reactor Regulation documenting the adequacy of the

licensee's corrective actions for the Keowee hydro units

overspeed/overfrequency concerns.

5.

Review of Power Upgrade Project Items not Identified as EDSFI Findings

(IP 92903)

5.1

The inspectors reviewed PUP item 4.f, Keowee Voltage Regulator

Setpoints.

While performing an emergency start test of Keowee Unit 1 on

September 20, 1993, it was noted that the generator output voltage

leveled-off at 13.3 kV instead of its rated output voltage of 13.8 kV.

The low generator output voltage was later determined by the licensee to

have been due to the improper setting of the voltage regulator control

signal (See Problem Investigation Process (PIP) 4-093-0793). The root

cause of the problem was determined to be the lack of a documented

voltage setpoint. As a result, the licensee decided to formally

document the voltage regulator setpoints and incorporate the acceptable

generator output voltage operating band into the Keowee emergency start

test procedure.

The inspectors reviewed calculation/analysis KC-Unit 1 & 2-2023 dated

June 4, 1995. This calculation/analysis analyzed the operation of the

Keowee voltage regulator, and documented the bases for the Keowee

voltage regulator settings. The voltage regulator settings should

maintain the Keowee generator output voltage between 13.5 kV and 14.1

kV. This voltage range was based on dynamic computer simulations

performed by the licensee which showed the band to be adequate to ensure

operation of Oconee safety loads.

The licensee's analysis identified that the order in which certain

modules of the voltage regulator were calibrated was critical in

ensuring proper generator voltage during emergency operations. A new

calibration procedure for the voltage regulator was being written which

would specify the order. The analysis also recommended that the current

Keowee main step-up transformer tap setting be changed to tap three.

This change would allow the Keowee generators to operate in a voltage

band of 13.8 kV +/- 5 percent. Changing the transformer tap setting would

also increase the safety margin that currently exists between the Keowee

generator operating voltage and the minimum voltage needed to ensure

operation of Oconee safety loads.

Implementing this recommendation

however would require further analysis and coordination of the

electrical system as a whole.

11

The inspectors concluded that the licensee's analysis adequately

documented the bases for the Keowee voltage regulator settings. This

item was closed.

5.2

The inspectors reviewed PUP item 19 which was the Penetration

Overcurrent Protection Calculation.

Section 6.1.2 of the Oconee EDSFI inspection report; "Protection,

Coordination and Containment Electrical Penetration Protection;" stated

"the licensee is not committed to and does not comply with IEEE-317

requirements for penetration back-up protection. In addition, formal

calculations were not available to demonstrate the adequacy of primary

protection."

The inspectors review calculation OSC-4151, Revision 1; "A Review of

Penetration Overcurrent Protection;" dated May 16, 1995. The purpose of

the calculation was to demonstrate the adequacy of primary protection

devices for containment electrical penetrations. The calculation

analyzed the maximum fault currents available at each type of

penetration installed except for penetrations associated with low energy

thermocouple and instrumentation circuits. The fault current levels

were then compared to the field cable insulation thermal limits,

conductor fusing limits, and cable and penetration time-current

protection device settings associated with each type of penetration.

The results of the licensee's calculation showed that electrical

penetrations and their associated cables currently installed at Oconee

are adequately protected by primary overload and fault protection

devices. This protection should be adequate to ensure electrical

circuits passing through the reactor building will not degrade

containment integrity before, during or after a design basis event.

Section "J" of the analysis made recommendations to enhance penetration

overcurrent protection. These recommendations included: (1) adding a

note to design documents which clearly identify type D-12 penetration

load limits; (2) replacing 100 amp circuit breakers associated with type

C2 penetrations with 50 or 60 amp circuit breakers; and (3)

providing

operators with explicit response guidelines to manually shutdown a

reactor coolant pump upon detection of a sustained overcurrent. These

recommendations were being tracked by the licensee with PIP 0-095-0606.

Based on a review of calculation OSC-4151, Revision 1; A Review of

Penetration Overcurrent Protection; the inspectors concluded that the

license's primary protection was adequate. The licensee does not comply

with IEEE-317 requirements for penetration back-up protection, however

they are not committed to this requirement. This item was closed.

5.3

The inspectors reviewed PUP item 20 which identified a revision to the

degraded grid voltage relay setpoints and a change to the degraded grid

voltage detection configuration.

12

In Section 2.3.2 of the Oconee EDSFI inspection report, "Degraded Grid

Protection System," team members noted the following concerns with the

system design:

(1) All three single voltage measurements were monitoring the same "Z"

phase of the 230 kV bus;

(2) The three-relay scheme which only monitored the "Z" phase of the

bus was insensitive to phase voltage unbalance;

(3) The licensee did not have any operating procedure or surveillance

test to monitor the phase voltage unbalance.

The inspectors reviewed calculation OSC-5579, "Design Inputs and 10 CFR

50.49 Evaluation for NSM-ON-52950." Modification NSM-ON-52950 installs

three new QA-1 Capacitor Coupled Voltage Transformers (CCVTs) in the

Oconee 230 kV switchyard, and provides a voltage input to the degraded

grid voltage protection logic. Additionally, the modification adds

three new QA-1 undervoltage relays to the protection logic, and replaces

three Yellow Bus and three Red Bus CCVTs (a total of six CCVTs).

The new CCVTs and undervoltage relays will add a second set of 2-out-of

3 protection logic to the Oconee degraded grid protection system. The

three new CCVTs will monitor different phases of the Yellow Bus and add

diversity to the Oconee degraded grid protection system. Because the

new CCVTs will be connected to three different phases of the Yellow Bus,

modification NSM-ON-5579 addresses the phase voltage unbalance concerns

noted during the EDSFI inspection.

The inspectors had no concerns as a result of their review of

calculation OSC-52950. This item was closed.

5.4

The inspectors reviewed PUP item 92 which analyzed the voltage adequacy

of 208/120 VAC Power Panel Voltage.

The inspectors reviewed calculation OSC-6135, "208/120 VAC Power Panel

Voltage Accuracy," dated June 1, 1995. This calculation performed a

evaluation of each 208/120 VAC station auxiliary panel circuit to

determine if each end device required to operate during a LOCA would

operate at the steady state LOCA reduced voltage conditions.

The calculation used the panel board voltages calculated in OSC-2059,

OSC-2060, and OSC-2061; the voltage and load studies for Oconee Units 1,

2 & 3 respectively. From these steady state panel board voltages, end

device terminal voltages were calculated based on cable impedances and

the expected end devices' load currents. Results of the calculation

showed that in general the calculated end device voltage levels were

greater than or equal to the minimum operating voltages published by the

manufacturers. Several end device voltages however were slightly less

than the manufactures' published minimum operating voltages. In these

instances, the licensee relied upon other vendor documentation or test

data to conclude that the reduced voltages were acceptable.

II13

Due to the volume and details of the calculation, the inspectors only

reviewed a portion of the OSC-6135, to verify that all loads fed from

the 208/120 VAC station auxiliary panels would have adequate voltage

available to perform under a worst case voltage condition. This

included instances were an end device would be supplied with a terminal

voltage less than the published manufacturer's minimum operating

voltage. The inspectors noted during their review that there was

conservatism included in both calculation OSC-6135 and the voltage and

load study calculations used to determine the steady state panel board

voltages.

Based on a review of calculations OSC-6135 and the review of

calculations discussed in paragraph 4.1.1, the inspectors concluded

there was adequate assurance that loads fed from the 208/120 VAC panel

boards would be supplied with the minimum voltage needed to perform

during a design basis accident. The inspectors did not however review

or consider transient voltage conditions which might occur during a

design basis accident. This item was closed.

5.5

The inspectors reviewed PUP item 113. This item documented an

evaluation of the 230 kV Switchyard 125 VDC Power System for float

charging the switchyard batteries at a higher voltage. The Oconee 230

kV switchyard batteries were recently replaced with larger capacity

cells with a 60 cell battery bank. The previous batteries were 59 cell

batteries and were floated at 2.17 to 2.25 volts per cell (VPC)

resulting in a maximum system voltage of 132.75 Volts Direct Current

(VDC). With a 60 cell configuration and a maximum floating voltage of

2.25 VPC the maximum system voltage would be increased to 135 VDC. An

evaluation of the 125 VDC system components was needed to determine if

the increased voltage would exceed the allowable voltages of the devices

powered from the batteries and charger.

Calculation OSC-5976 Rev. 0, 230 kV Switchyard 125 VDC Power System

Overvoltage Evaluation was reviewed by the inspector. The inspector

reviewed each component identified within the calculation that would be

affected by the increased voltage. Documentation was included within

the calculation to document the acceptability of the increased voltage

for these components. All components identified within the calculation

were found to be adequate for application in a system operating at the

higher voltage with the following exceptions:

(1) Cooper Bussman type REN fuses are recommended for replacement by

Cooper Bussman with type KNW-R, KTN-R, and FRN-R type fuses.

(2) Cooper Bussman type NON-0.5 and NON-3 fuses should be replaced

with NON-15 type fuses.

(3) Gould Shawmut type OT-6 fuses rated 10 amperes or less should be

evaluated and replaced as necessary.

14

PIP No. 4-095-0522 was initiated to document the fuse replacements.

This PIP is still open. The 125 VDC System is being operated at the

original float voltage of 132.75 VDC pending completion of the

corrective actions required by this PIP.

No additional concerns were identified by the inspector during this

review. PUP item 113 was closed.

6.

Exit Meeting

The inspection scope and results were summarized on June 16, 1995, with

those individuals indicated in paragraph 1. The inspector described the

areas inspected and discussed in detail the inspection findings. There

was no dissenting comments received from the licensee. Proprietary

information is not contained in this report.

(Closed)

Violation 50-269, 270, 287/94-26-01, Failure to Perform

Procedure as Corrective Action

(Closed)

Deviation 50-269, 270, 287/93-02-02, Deviation from

Separation and Color Coding Requirements for Cable and

Overpressure Protection for Piping

7. Acronyms and Abbreviations

CFR

Code of Federal Regulations

ECCS

Emergency Core Cooling System

EDSFI

Electrical Distribution System Functional Inspection

FSAR

Final Safety Analysis Report

IEEE

Institute of Electrical and Electronics Engineers

IFI

Inspector Follow-up Item

IP

Inspection Procedure

IR

Inspection Report

kA

Kiloamperes

kV

Kilovolts

KVA

Kilo- Volt- Amperes

LOCA

Loss of Coolant Accident

MCC

Motor Control Center

MVA

Mega Volt Amperes

NRC

Nuclear Regulatory Commission

NRR

Nuclear Reactor Regulation

MW

Mega-Watts

PIP

Problem Investigation Process

PUP

Power Upgrade Project

SSF

Safe Shutdown Facility

TI

Temporary Instruction

V

Volts

VAC

Volts Alternating Current

VDC

Volts Direct Current

VPC

Volts Per Cell