ML16154A702

From kanterella
Jump to navigation Jump to search
Insp Repts 50-269/95-19,50-270/95-19 & 50-287/95-19 on 951009-13.No Violations Noted.Major Areas Inspected: Engineering
ML16154A702
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 10/18/1995
From: Casto C, Moore R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML16154A703 List:
References
50-269-95-19, 50-270-95-19, 50-287-95-19, NUDOCS 9511140285
Download: ML16154A702 (7)


See also: IR 05000269/1995019

Text

REGo

UNITED STATES

o

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W., SUITE 2900

ATLANTA, GEORGIA 30323-0199

Report Nos.:

50-269/95-19, 50-270/95-19 and 50-287/95-19

Licensee: Duke Power Company

422 South Church Street

Charlotte, NC 28242

Docket Nos.:

50-269, 50-270, and 50-287

License Nos.:

DPR-38, DPR-47,

and DPR-55

Facility Name:

Oconee Nuclear Station Units 1, 2 and 3

Inspection Conducted: October 9-13, 1995

Inspector:

R.'\\e~rdD

te Signed

Approved by:

/ 4

1--/0

C. Casto, Chief,

Date Signed

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This routine, unannounced inspection was conducted in the area of engineering

(IP 37550). The inspection reviewed the design base documentation for the

Keowee hydroelectric generators' mechanical support systems to verify that the

design information was consistent with industry standards and that the

systems' safety functions were adequately identified and verified.

Additionally reviewed were the licensee's actions to resolve a system

reliability issue from the 1992 Loss-of-Offsite Power (LOOP) event.

Results:

In the areas inspected, violations or deviations were not identified.

The licensee's design documentation for the Keowee mechanical systems was

consistent with industry standards. The systems' safety functions were

identified and appropriate calculations and testing were developed to verify

these functions.

9511140285 951018

PDR

ADOCK 05000269

Enclosure

GPDR

2

The modification to the Keowee 600 VAC power logic improved the reliability of

the governor oil system and the hydroelectric generators. Overall, the

licensee's actions demonstrated an increased understanding of the Keowee

mechanical systems' operating and design characteristics since the 1992 LOOP

event.

0

Enclosure

REPORT DETAILS

1 .

Persons Contacted

Licensee Employees

  • E. Burchfield, Regulatory Compliance Manager

M. Bailey, Regulatory Compliance

  • D. Coyle, Mechanical Systems Engineering Manager
  • J. Davis, Engineering Manager

B. Foster, Safety Assurance Manager

  • C. Little, Electrical Engineer
  • K. Louvin, Mechanical System Engineer

R. McCoy, Seismic Qualification Utilities Group Senior Engineer

F. Moss, Seismic Qualification Utilities Group Senior Engineer

  • B. Peele, Station Manager
  • R. Severance, Mechanical Systems Engineer
  • J. Smith, Regulatory Compliance

Other licensee employees contacted during this inspection included

craftsmen, engineers, technicians and administrative personnel.

NRC Employees

P. Harmon, Senior Resident Inspector

L. Keller, Resident Inspector

  • N. Salgado, Resident Inspector
  • Attended exit interview

Acronyms and abbreviations are identified in paragraph 8.

2.

Background

The Keowee Hydroelectric Station provides the emergency AC power source

for the Oconee Nuclear Station. There are two hydroelectric generators

with independent support systems. The hydro station was not originally

under the Duke Power Nuclear Generation Department management;

therefore, documentation and programmatic controls to ensure Keowee met

nuclear industry standards were not fully implemented. Audit and

inspection activities over several years indicated that aspects of the

design, operation, and maintenance merited improvement. An October,

1992, Loss of Offsite Power event demonstrated that there was inadequate

understanding of Keowee operation and design.

The Power Upgrade Project was initiated in September, 1994, to bring the

Keowee design, operations and maintenance activities to nuclear

standards. An element of the project was to develop design basis

documentation (DBD) for the Keowee hydroelectric generator mechanical

systems, upgrade and control drawings, and develop calculations and

testing to verify the design function of these systems. The DBDs

provided a basis to improve the licensee's understanding of systems'

Enclosure

2

operating characteristics and design. This inspection reviewed the

licensee's mechanical systems DBDs, drawings, and calculations to

determine if they were consistent with nuclear industry standards.

These standards were established by Regulatory Guide (RG) 1.64, Quality

Assurance Requirements for the Design of Nuclear Power Plants, and

American National Standards Institute (ANSI) N45.2.11 - 1974, Quality

Assurance Requirements for the Design of Nuclear Power Plants.

3.

Keowee Design Base Document

The inspector reviewed the Keowee mechanical DBD to verify that the

systems' design functions and parameters were identified and that

appropriate calculations and testing were referenced to verify the

design functions. The following design basis specifications encompassed

the Keowee mechanical DBD:

OSS-0254.00-00-1043, Design Basis Specification for the Keowee

Turbine Guide Bearing Oil (GBO) System, dated May 24, 1995

OSS-0254.00-00-1044, Design Basis Specification for the Keowee

Governor Air (AG) System, May 24, 1995

OSS-0254.00-00-1044, Design Basis Specification for the Keowee

Governor Oil (OG) System, May 24, 1995

OSS-0254.00-00-1044, Design Basis Specification for the Keowee

Turbine Generator Cooling Water (WL),System, May 24, 1995

OSS-0254.00-00-1044, Design Basis Specification for the Keowee

Turbine Sump Pump (TS) System, May 24, 1995

OSS-0254.00-00-1044, Design Basis Specification for the Keowee Air

Circuit Breaker (ACB) Air System, in draft.

Section 20, System Design Bases, of the specifications stated the safety

function of the systems. The safety related design function of the GBO

system was to maintain a level in the turbine guide bearing upper oil

reservoir to assure lubrication for the turbine shaft guide bearings.

The AG system pressurized the governor oil pressure tank for positioning

the water inlet gates to the water turbine for blackstart of the hydro

electric generator. The OG system controlled the generator output by

positioning of the inlet gates during operation. The WL system removed

heat from the generator air coolers and oil coolers. The TS system .

prevented flooding in the turbine wheel pit sump due to gland leak-off.

The ACB air system provided compressed air for operation of the

generator breaker. The inspector concluded that the safety function of

the Keowee mechanical systems was adequately specified in the DBD.

Enclosure

3

Section 40 or Appendix A, Testing/Calculation Matrix, of the

specifications individually listed the design requirements and

supporting calculation, procedure, or justification. Unsupported design

requirements were identified by a Problem Investigation Program (PIP)

report to track resolution of the design requirement justification. An

example of an undefined design requirement parameter was the minimum

pressure of the governor oil pressure tank at the initiation of a design

base event. This was tracked by PIP 4-095-0673. Additionally, the

test/calculation matrix referenced the test procedure which would

provide routine verification of system equipment performance. The

implementation of the Inservice Testing and Inspection Program (IST/ISI)

for the Keowee mechanical systems was scheduled for November 1, 1995.

The licensee was implementing instrumentation modifications to

facilitate IST/ISI testing. The inspector concluded that the DBD

provided adequate verification of the systems' design requirements.

Design parameters were adequately identified and addressed.

4.

Calculations and Drawings

The inspector reviewed the calculations and drawings which supported the

DBD to verify that all assumptions had been verified, the design

documents were consistent with industry standards, and the drawings were

consistent with the installed configuration. Calculations were

developed in accordance with Engineering Directive Manual procedure EDM

101, Engineering Calculations/Analysis, revision 4. The following

calculations were reviewed:

KC 1-2-2014, High Pressure Oil (HPO) System Analysis, dated

May 25, 1995

KC 1-2-2003, Turbine Sump Pump Flow, May 24, 1995

KC 1-2-2005, Turbine Generator Cooling Water Analysis,

May 17, 1995

1-2-2015, Turbine Guide Bearing Oil System Analysis, May 26, 1995

1-2-2009, WL System Water Hammer Evaluation, May 31, 1995

KC 1-2-2012, Governor Safety System Safety Relief Valve Sizing,

May 31, 1995

KC 1-2-2013, Governor Air System Recovery Time, May 30, 1995

KC 1-2-2018, ACB Air System Recovery Time, May 31, 1995

KC 1-2-2019, Keowee Mechanical Systems Single Failure Analysis,

June 1, 1995.

Enclosure

4

The inspector concluded that the calculations were generally well

documented. There were no unverified assumptions and the conclusions

adequately supported the design base function capabilities which were

addressed. Configuration sketches supporting system flow analysis were

accurate. Industry standards related to design inputs, design

verification, and design document control were appropriately

implemented.

The following drawings were reviewed and field verified:

KFD-1O1A-1.1, Flow Diagram of Turbine Generator Guide Bearing Oil

System, revision 2

KFD-106A-3.0, Flow Diagram of Lube Oil System, revision 0

KFD 100A-1.1, Flow Diagram of turbine Generator cooling Water

System, revision 3

KFD 104A-1.1, Flow Diagram of Governor Air System, revision 5

KFD 105A-1.1, Flow Diagram of Governor Oil System, revision 3

KFD 102A-1.1, Flow Diagram of Turbine Sump Pump System,

revision 2.

The drawings were consistent with the installed equipment configuration

and clearly designated the portion of the systems which were safety

related. This was defined on the drawings as Duke Piping Class F.

Additionally, the drawings were designated as QA Condition 1 documents.

The inspector concluded that the drawings were accurate and drawing

control was consistent with industry standards regarding design

documentation.

5.

Equipment Seismic Qualification

The inspector-reviewed the seismic qualification basis for the

mechanical systems. Qualification of this equipment was provided by the

licensee's implementation of the Seismic Qualification Utility Group

(SQUG) methodology. This methodology incorporated the Generic

Implementation Procedure (GIP)-2, Seismic Verification of Nuclear Plant

Equipment, dated February, 1992. The seismic capability of most of the

equipment was established by the SQUG reviews. The inspector reviewed

the screening evaluation work sheets for critical switches and relays in

the mechanical systems which would impact the emergency start or

operation of the hydroelectric generators. These included the oil level

switches for the HPO and GBO systems and the Generator Carbon Dioxide

(CO2) Release Pressure Switches. These switches and associated relays

could not be qualified by the criteria of GIP-2 and were identified as

outliers as required by the licensee's NRC approved SQUG program. A

minor modification (OE 7258) and PIP 5-094-1755 were initiated to

Enclosure

5

replace the C02 switches. The resolution of the SQUG outliers will be

submitted to the NRC at the completion of the licensee's implementation

of this program in 1996. The inspector concluded that the licensee had

appropriately addressed the Keowee mechanical equipment seismic.

qualification with the SQUG program.

6.

Governor Oil System Reliability

The inspector reviewed the licensee's actions to resolve a reliability

issue identified during the 1992 LOOP event. During the event the power

supply to the governor oil pumps became a critical issue in the

operation of the hydroelectric generators. At that time operator action

was required to align a power source to the pumps as a result of a

transient experienced by the Keowee Station 600 VAC auxiliaries which

powered the pumps. A modification, NSM ON-52930, was installed in

September, 1993, to address this issue. The modification provided power

seeking relays in the auxiliaries' 600 VAC power logic'to permit

automatic auxiliary power swap over for the pump load centers. An

additional proposal under review was the installation of a DC powered

pump. This required further review of the impact on the Keowee

batteries. The inspector concluded that the power logic modification

improved the reliability of the Keowee hydroelectric generators

7.

Exit Meeting

The inspection scope and results were summarized on October 12, 1995,

with those individuals indicated in paragraph 1. The inspector

described the areas inspected and discussed in detail the inspection

findings. There were no dissenting comments received from the licensee.

Proprietary information is not contained in this report.

8.

Acronyms and Abbreviations

AC

Alternating Current

ACB

Air Circuit Breaker

AG

Governor Air

ANSI

American Nuclear Standards Institute

DBD

Design Bases Documentation

DC

Direct Current

GBO

Turbine Guide Bearing Oil

HPO

High Pressure Oil

IST/ISI

Inservice Testing/Inservice Inspection

LOOP

Loss-of-Offsite-Power

OG

Governor Oil

PIP

Problem Investigation Program

SQUG

Seismic Qualification Utilities Group

TS

Turbine Sump

WL

Turbine Generator Cooling Water

EnDCosure