ML16154A683

From kanterella
Jump to navigation Jump to search
Insp Repts 50-269/94-26,50-270/94-26 & 50-287/94-26 on 940829-0902 & 12-16.Violations Noted.Major Areas Inspected: Adequacy of Corrective Actions for Violation,Deviation & Findings Identified During Edsfi
ML16154A683
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 10/12/1994
From: Steven Rudisail, Shymlock M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML16154A681 List:
References
50-269-94-26, 50-270-94-26, 50-287-94-26, NUDOCS 9411010087
Download: ML16154A683 (12)


See also: IR 05000269/1994026

Text

R EGU

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W., SUITE 2900

ATLANTA, GEORGIA 30323-0199

Report Nos.:

50-269/94-26, 50-270/94-26 and 50-287/94-26

Licensee: Duke Power Company

422 South Church Street

Charlotte, NC 28242

Docket Nos.:

50-269, 50-270, and 50-287

License Nos.:

DPR-38, DPR-47, and DPR-55

Facility Name:

Oconee Nuclear Station Units 1, 2 and 3

Inspection Conducted: August 29 - September 2, and

September 12 -

16, 1994

Inspector: 2. -1-7

' 4

S.'Date

Signed

Approved b

1ymoc

,i

/LM.P'Shymlock, W1ief

.t in

Plant Systems Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This special announced inspection was conducted to review and assess the

adequacy of corrective actions for a violation, deviations and findings

identified during the Electrical Distribution System Functional Inspection

(EDSFI) of NRC Inspection Report 50-269/93-02, 50-270/93-02, and 50-287/93-02.

Temporary Instruction 2515/111, Electrical Distribution Follow-up Inspection

was used for guidance during this inspection.

Results:

In the areas inspected a violation was identified. In response to Deviation

93-02-01, the licensee issued a procedure to semiannually verify the

corrective action of locking valves open on Keowee cooler heat exchangers.

The licensee had failed to perform this verification. This was identified as

violation 94-26-01 (paragraph 3.4).

Violation 93-02-01, Failure to Classify

Feeder Circuit Breakers as Safety Related was closed. Corrective actions were

Enclosure

9411010087 941013

PDR ADOCK 05000269

PDR

2

determined to be adequate. Deviation 93-02-02 was not closed. Corrective

actions identified by the licensee had not been completed. Inspection of

cable identified in the corrective action was not scheduled for completion

until October 31, 1995. A modification to separate cables for 2LP-19 and 2LP

20 was scheduled for the Unit 2 refueling outage EOC14. The findings of the

EDSFI were collectively identified as IFI 93-02-03. The response to these.

findings and the applicable corrective action was reviewed. Most calculations

required to be revised in response to the findings were not complete and

therefore not reviewed. Other corrective actions were also incomplete.

Overall, the inspector considered the progress of the corrective actions to be

slow. These items were addressed in a management meeting between Duke Power

and the NRC on September 29, 1994. At that meeting Duke Power identified a

completion date of November 1995 for the outstanding items associated with the

EDSFI. The inspector closed IFI 93-02-03 to document the items completed in

response to EDSFI findings.

IFI 94-26-02 was opened for further review of

incomplete finding responses.

IFI 93-02-04, Items Identified for Further NRC Review was closed.

Additionally, IFI 93-20-04, Alarm Circuit/Control Circuit Interface was

reviewed and closed. Corrective actions for this item were reviewed and

determined to be satisfactory.

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

  • M. Abercrombie,.Keowee Operations
  • M. Bailey, Regulatory Compliance
  • S. Burton, Keowee Operations
  • J. Davis, Engineering Manager
  • B. Dolan, Safety Assurance Manager
  • T. Grant, Electrical Engineering
  • T. Ledford, Supervisor, Electrical Engineering

T. Lee,-Operations Support

  • C. Little, Supervisor, Electrical Engineering

M. Miller, Electrical Engineering

  • G. Rothenberger, Operations Superintendent
  • R. Severance, Mechanical Engineering

BS.

Townsend, Keowee Operations

Other licensee employee contacted during this inspection included

craftsmen, engineers, technicians, and administrative personnel.

NRC Employees

P. Harmon, SeniorResident Inspector

  • L. Keller, Resident Inspector
  • K. Poertner, Resident Inspector
  • Attended exit interview

Acronyms and abbreviations used throughout this report areidentified in

the last paragraph.

2.

Background

During January 25 through March 5, 1993, the NRC conducted the

Electrical System Distribution Functional Inspection (EDSFI).

The

purpose of this inspection was to assess the capability of the Oconee

Electrical Distribution System to perform it functions during operating

and accident conditions.

The conclusion of the EDSFI team was that the

electrical distribution system would perform its intended function

pending further analysis and testing bythe licensee.

During the EDSFI

inspection a violation and several deviations were identified.

Additionally, findings identified during the EDSFI were collectively

identified as IFI 93-02-03.

3.

Review of Corrective Action for Violation and Deviations (TI 2515/111)

The inspector reviewed a violation and three deviations identified at

Oconee during the EDSFI.

These items are discussed in the following

paragraph.

2

3.1

(Closed) Violation 93-02-01, Failure to Classify Feeder Circuit Breakers

as Safety Related, was issued for failure to classify feeder circuit

breakers from the startup transformers to the Reactor Coolant Pump

busses or the 4.16 kV load shed circuit breakers feeding non-safety

related loads as safety related. Duke Power responded to this violation

and denied the examples cited were a violation of NRC requirements.

However, Duke Power agreed to enhance the maintenance and testing of the

subject circuit breakers commensurate with the requirements for safety

related circuit breakers. The NRC responded that the enhancement of the

circuit breaker testing and maintenance would place the licensee in

compliance with the NRC requirements.

The inspector reviewed the licensee implementation of the maintenance

and testing of the circuit breakers as safety related. Nuclear Station

Directive NSD B.1 307, QA Condition Structures, Systems and Components

was revised to require 6.9 kV Switchgear TA and TB to be maintained and

tested as QA-1. The NSD was also revised to require 4.16 kV switchgear

TC, TD, and TE as QA-1.

Procedure IP/0/A/2001/003A, Inspection and

Maintenance of 4.16kV and 6.9kV ACB's was also reviewed. This procedure

had been revised to require Quality Control requirements and inspection

of maintenance activities as required for QA-1 components.

Additionally, work orders were reviewed for performance of maintenance

on circuit breakers. Work order 93082223 was issued for maintenance on

circuit breaker 1TE-06. This work order required the replacement of the

puffer tubes on the circuit breaker. The inspector verified that this

work order accomplished the work as required for QA-1 work activities

and the replacement of parts met the requirements for QA-1 work

activities. Violation 93-02-01 was closed.

3.2

(Open) Deviation 93-02-02, Item 1, Deviation from FSAR Color Coding

Requirements for Cables was one of three examples of a deviation

identified during the EDSFI. The first example was identified as power

cables 1XS2 and 1XS48 not being correctly color coded.- These cables run

from the motor control centers 1XS1 and 1XS2 to transformer CT4 cooling

fans.

Final Safety Analysis Report (FSAR) section 8.3.1.3 states that

motor control center (MCC) 1XS1 power and control system cable are color

coded gray and that MCC 1XS2 cables are color coded yellow. Contrary to

this requirement, both cables were color coded black.

The licensee responded to this deviation and agreed that it was a

deviation from the requirements of the FSAR and an oversight during

initial installation. The licensee considered the color coding was

intended to ensure separation during installation. The separation

requirements are for mutually redundant cables to be run in separate

trays. The cables are routed in different cable trays until they reach

the block house of the CT4 transformer. The cable is interlocked armor

type cable. The licensee determined the impact of failure of both

cables and concluded that should they fail the transformer would

continue to operate as designed with only a small impact on transformer

life. Alarms are available to indicate loss of power to the fans and

high oil and winding temperature in the transformer. Operator action

3

would be required upon receipt of alarms. The licensee concluded that

the impact on safety due to the cable being color coded black was

insignificant. The inspector agreed with this conclusion. The licensee

proposed additional corrective action to perform an inspection of all

plant, switchyard, and Keowee cables fed from safety related busses not

previously identified as having mutually redundant safety related

functions. These cables will be inspected to ensure that they are not

routed in the same tray with other cables with redundant functions.

This action is scheduled to be completed by October 31, 1995. This

deviation remains open.

3.3

(Open) Deviation 93-02-02, Item 2, identified mutually redundant cables

for Unit 2 emergency core cooling isolation valves 2LP-19 and 2LP-20 as

being routed in the same cable tray. This was contrary to the

requirements of FSAR section 8.3.1.4.6.2. The licensee agreed that this

was a deviation.

The corrective action for this deviation was to perform a modification

to separate the cables.. Minor modification OE-5990 was prepared to

separate the cables. This modification was scheduled to be performed

during Unit 2 refueling outage (RFO) (EOC14) scheduled for the fall of

1994. The inspector reviewed this modification and the scope of work to

be accomplished during its performance. This modification will

accomplish the required corrective action. Inspection of Unit 1 and

Unit 3 cable for valves LP-19 and LP-20 were performed and the

separation problem did not exist. The licensee proposed additional

corrective action to perform an inspection of all plant, switchyard, and

Keowee cables fed from safety related busses not previously identified

as having mutually redundant safety related functions. These cables

will be inspected to ensure that they are not routed in the same tray

with other cables with redundant functions. This action was scheduled

to be completed by October 31, 1995. This deviation will remain open

pending completion of the modification and inspection.

3.4

(Closed) Deviation, 93-02-02, Item 3, identified examples of heat

exchanger cooler piping that did not have a provision for relief of

overpressure. United States of America Standards (USAS) 831.1, section

101.4.2 requires either design of the piping to withstand overpressure

conditions or a means of pressure relief be provided. FSAR section

3.2.2.2 established the design criteria for Keowee system cooler piping

as USAS B 31.1.0 section 101.4.2. The Keowee turbine guide bearing oil

cooler, generator thrust bearing cooler, and generator air coolers were

not designed with the ability.to withstand increased pressure in an

isolated mode. The licensee agreed that this was a deviation.

The proposed corrective action was to lock open the outlet valves in

accordance with Operation Management Procedure (OMP) 1-17.

This

requires semi-annual verification that the valves are locked. To

accomplish this verification, a new procedure was prepared and issued to

provide for semiannual verification of the locked valves. Keowee

procedure OP/A/2000/45, Lock Verification was issued to accomplish this

action. During this inspection the inspector reviewed the results of

4

the semi-annual verification of lock position. The licensee had not

performed the procedure since issuance on June 29, 1993, and had no

record of its performance at the time of issuance. The procedure was

performed September 1, 1994, following this determination. The

inspector reviewed the results of the procedure and confirmed that the

valves required to be locked open were in the appropriate locked

position. This was identified as Violation 94-26-01, Failure to

Accomplish Procedure for Corrective Action. This example of the

deviation was closed.

4.

Review of Inspector Follow-up Items (IP 37550)

The inspector reviewed the items identified at Oconee as Findings.

These items are discussed in the following paragraphs.

4.1

(Closed) IFI 93-02-03, EDSFI findings consisted of six findings with

several issues identified in each finding. Finding 1 of the IFI

identified a lack of integrated testing for the Oconee emergency power

system and a lack of testing to demonstrate the design capability of the

power source. Several features of the.emergency power source had not

been tested. The overhead path from Keowee and the switchyard isolation

relays of the Emergency Grid Protection system had not been tested. The

Keowee Hydro Emergency Start test procedure PT/0/A/0620/16 was

identified as not performing tests in accordance with FSAR section

8.3.1.1.1. Also, the composite of all Keowee testing was identified as

not bounding the design requirements.

The licensee response to Finding 1 was reviewed by the inspector.

Testing of the switchyard isolation relays has been accomplished.

During the subsequent RFO for Unit 2, test procedure PT/0/A/0610/022 was

performed on May 22, 1993.

The NRC witnessed this testing as documented

in NRC Inspection report 50-369, 270, 287/93-19. This was an integrated

test of the overhead power path which included the isolation relays.

The second channel of the switchyard isolation relays was tested during

the RFO for Unit 1 on May 24, 1994. These test results were reviewed

with no discrepancies identified.

FSAR section 8.3.1.1.1 states that each Keowee hydro unit generator is

equipped with a volt-per-cycle limiting feature which permits it to

accept full emergency power load as it accelerates from zero to full

speed. The licensee addressed the NRC concern that this FSAR

requirement was not being met by the present mode of testing. Procedure

PT/0/A/0620/016 verifies that the Keowee unit will reach rated speed and

voltage within the required 23 seconds as required by the FSAR. This

test was performed annually. The ability to reject load and separate

from the grid was demonstrated every RFO since January 1992, by

PT/0/A/0610/O1J. This test also demonstrates the ability to reconnect

to the overhead power path and properly align the underground path. The

results of PT/0/A/0610/01J prior to 1987 were provided to demonstrate

the ability to accept loading and accelerate to full speed and voltage

as required.

PT/0/A/0610/022 was performed to demonstrate the ability

to place loads on the generators which exceed the emergency loads. This

5

II

procedure loaded a Reactor Coolant Pump onto the Keowee unit. This load

was measured as 9 MVA steady state and 47 MVA inrush.

The inspector concluded the testing described above satisfactorily

demonstrated the ability of the Keowee units to meet their design

requirements. Finding 1 of IFI 93-02-03 was closed.

4.1.1

Finding 2 was an identification of analyses, studies and

calculations which were not complete or had not been performed.

There were ten elements identified in this finding. Only one

element will be closed.

Item 1 of this finding identified that calculation OSC-2059, 4160

Voltage Study, may not have bound the worst case. The revision to

this calculation was not complete. This item will remain open.

Item 2 identified that no analysis or test was available to verify

the rapid transfer timing was correct. An analysis was scheduled

to document transfer adequacy. This analysis was not complete.

Item 2 of this finding will remain open.

Item 3 identified that a transient voltage study for the 4kV

safety loads when supplied by the Lee or Central substation was

not available. The licensee responded that a calculation to

demonstrate dynamic modeling of the Lee and Central power sources

would be completed. During this inspection this item was not

complete. This item will remain open.

Item 4 identified that a study to review control cable length and

the size of fuses that protect them had not been conducted. The

licensee responded that the load study calculation of OSC-2059

would address fuse adequacy. This item was not complete during

the follow-up and this item will remain open.

Item 5 identified that the Kewoee 600V Auxiliary Power System

Voltage Analysis did not evaluate maximum and minimum expected

voltages. The licensee planned calculation KC-UNIT-1-2-0095 to

address voltage adequacy in the auxiliary power system. This item

was not complete and will remain open.

Item 6, concerned the lack of an analysis to support that the

Keowee auxiliaries would not be damaged by overvoltage or

overfrequency when supplied by one Keowee unit. The inspector

reviewed the actions completed for this finding. One calculation

had been completed. The calculation to demonstrate the effect of

overvoltages and overfrequencies on the Keowee auxiliaries was

complete. The calculation OSC-5701, Oconee Keowee Overhead Path

Analysis identified weaknesses that limit the percent power the

Keowee units can generate to .the grid and the alignment of the

Keowee units. These concerns are being addressed in modification

NSM 52966 currently being reviewed by NRC. This item will remain

open.

6

Item 7 identified the need for the full scope and completion of

component calculations for Keowee. Calculations to resolve this

item were not complete. This item will remain open.

Item 8 identified the lack of an analysis to support the

assumption that Oconee safety loads could properly perform during

an overfrequency transient lasting 40-50 seconds. The licensee

plans to complete an analysis to support this assumption. This

item is not complete and will remain open.

Item 9 of this finding identified that calculations for the Safe

Shutdown Facility are not complete. These calculations are

scheduled for completion by December 1994. This item will remain

open.

Item 10 identified the need for more rigorous testing of the

minimum required pickup voltage for components of the Switchyard

125 VDC system to support calculations.

Calculations had

demonstrated acceptable voltage levels at each component with the

exception of one case. This case was the pickup voltage to the

Cutler Hammer Type M relay. The licensee now purchases the type M

relays from a third party supplier. Test results are provided

which document ability of the relays to operate within the range

of voltage determined from the Oconee calculation.

The inspector

reviewed this documentation. This item was closed.

Other calculations and studies required for completion of the

actions addressing this finding were in various stages of

development. The inspector did not review draft calculations.

Theses items are all scheduled for completion by November 1995 and

will be reviewed after that date.

These incomplete actions

addressing this finding are identified as Inspector Follow-up

Item, IFI 94-26-02,

EDSFI Finding Items Not Closed During Follow

up Inspection.

4.1.2

Finding 3 identified examples of inadequate control of drawings

and setpoint documents. Inaccuracies were identified in Keowee

mechanical support system flow diagrams and drawings of Keowee air

systems were not available.

The inspector reviewed the corrective actions for the drawing

deficiencies. The following drawings were reviewed: KFD-105A

1.1, Unit 1 Flow Diagram of Governor Oil System, KFD-105A-2.1,

Unit 2 Flow Diagram of Governor Oil System, KFD-101A-1.1, Unit 1

Flow Diagram of the Turbine Guide Bearing Oil System, KFD-101A

2.1, Unit 2 Flow Diagram of the Turbine Guide Bearing Oil System,

KFD-103A-1.1, Unit 1 Flow Diagram of High Pressure Oil System,

KFD-103A-2.1, Unit 2 Flow Diagram of High Pressure Oil System,

KFD-100A1.1, Unit 1 Flow Diagram of Turbine Generator Cooling

System, and KFD-100A1.1, Unit 1 Flow Diagram of Turbine Generator

7

Cooling System. All drawings had been revised to correct the

deficiencies identified during the EDSFI inspection. Finding 3,

item 1 was closed.

Item 2 of this finding noted that bulletins, information notices.

and generic letters had not been reviewed for applicability to

Keowee: The licensee initiated a comprehensive review of

operating experience documents for applicability to Keowee. This

review was completed and actions items have been identified for

any missed items discovered during the review. This item was

scheduled for completion by November 1995 and will remain open.

Item 3 identified that there was not a controlled setpoint

document available at Keowee except for electrical relay settings.

Corrective actions for this item are not complete.

This portion

of the finding will remain open.

4.1.3

Finding 4 identified areas where additional licensee actions were

warranted to complete corrective actions.

Item 1 of this finding

was that the response to the Keowee governor system to postulated

failures was not fully analyzed.

Item 2 of this finding

identified that implementation of a setpoint revision to the Loss

of Field relay at Keowee had not been completed.

The inspector reviewed minor modification OE-6215 which

implemented a setpoint change for the Loss of Field relay in

accordance with the results of design calculation, OSC 4300.

Item

2 of Finding 4 was closed.

The licensee responded to the concern that postulated failures of

the Keowee governor had not been analyzed. The Keowee governor

system single failure analysis had been completed. An enhancement

to the governor's availability was still under review. A

modification to add a DC powered governor oil pump was being

planned.

Item 1 of Finding 4 will remain open.

4.1.4

Finding 5 identified Keowee engineering analyses which were not

sufficiently comprehensive and specific values had not been

established that would bound design criteria. All credible

failure modes for the Keowee governor control system and the

voltage regulator had not been considered. The basis for

bypassing trip functions during emergency start of the Keowee unit

was not fully analyzed or documented. The effect of frequency of

the electric power supplied by Keowee to ECCS pump motors had not

been fully evaluated and acceptable voltage and frequency

limitations for Keowee electrical auxiliaries and the emergency

power system should be defined.

The inspector reviewed calculation KC-Unit 1-2-0098, Keowee

Governor Mechanical Single Failure Analysis. The analysis

methodology did not differ from the original memorandum to file

reviewed during the EDSFI that documented the results of the

8

single failure review of the governor. The licensee initiated a

design study to further examine the bypassing of trip functions

during an emergency start. This study was not complete at the

conclusion of thi.s inspection. Finding 5 will remain open.

4.1.5

Finding 6 identified design features and mechanical components at

Keowee that were not being tested. Weaknesses were identified in

the testing of lubricating oil systems at Keowee. Pressure

switches in the carbon dioxide fire protection system were not

being tested or calibrated. Valves which were required to change

position for Keowee to provide emergency power were not included

on the Keowee active valve list. These valves were 1 and 2 OG-7

which were the float valves for the governor oil tank and the

check valves of the ACB air accumulators. Weaknesses were

identified in the testing procedures associated with ACBs 1, 2, 3,

and 4.

The inspector reviewed the corrective action for this finding.

Procedure IP/1/A/0400/023, Unit No. 1 C02 Fire Protection Pressure

Switch Calibration and IP/2/A/0400/023, Unit No. 2 C02 Fire

Protection Pressure Switch Calibration were developed for the

calibration of the pressure switches in the Kewoee fire protection

system. Procedure MP/O/A/2000/059, Periodic Test of the C02

System Generator No. 1 and Procedure MP/O/A/2000/060, Periodic

Test of the C02 System Generator No. 1 were developed for testing

of the Kewoee fire protection system. These procedures are

implemented and were reviewed and the inspector did not identify

any concerns. Minor modifications OE-5586 and OE-5597 had been

completed to install the necessary valves and test tee for testing

of the fire protection system. These modifications were reviewed

and no problems were identified.

The inspector also reviewed completed work orders for the testing

of oil level switches in the Keowee system. These work orders had

been completed to ensure that all oil level switches in oil

systems effecting operability at Keowee were calibrated. The

inspector found the calibrations satisfactory.

Procedure revisions to remove weaknesses from the procedure for

testing the Keowee Air Circuit Breakers was not complete. The

actions to determine which Keowee equipment will be added to the

Inservice Testing (IST) program was still incomplete. These

incomplete actions will be identified under IFI 94-26-02.

4.2

(Closed) IFI 50-269/93-20-04, Alarm Circuit/Control Circuit Interface

(IP 92701)

The inspector reviewed IFI 93-20-04 which was opened after Unit 1

experienced a turbine driven emergency feedwater pump (TDEFWP) auxiliary

oil status alarm in the control room. Investigation of the problem by

Work Order 40704C revealed blown fuses in the TDEFWP auxiliary oil pump

start circuit. The TDEFWP was declared inoperable because the automatic

9

start feature of the pump was defeated if the auxiliary oil pump is out

of service. The cause of the blown fuses was identified as a shorted

alarm relay AR-15. Problem Investigation Process (PIP) No. 1-093-0545

was opened to determine corrective action for this problem and track its

resolution.

The inspector reviewed the corrective actions associated with the PIP.

A modification to add parallel fuses across the existing fuses was

completed on Unit 1 and 3 by minor modification OE-6080 and minor

modification OE-6082 respectively. Minor modification OE-6081 was

outstanding for Unit 2. The modification prevented a blown fuse in the

indication portion of the circuit from disabling the pump start circuit.

IFI 93-20-04 was closed.

7.

Exit Meeting (IP 30703)

The inspection scope and results were summarized on

September 16, 1994, with those individuals indicated in paragraph 1.

The inspector described the areas inspected and discussed in detail the

inspection findings. There was no dissenting comments received from the

licensee. Proprietary information is not contained in this report.

(Opened)

Violation 50-269/94-26-01, Failure to Perform Procedure as

Corrective Action

(Opened)

Inspector Follow-up Item,-IFI 94-26-02, EDSFI Finding Items

Not Closed During Follow-up Inspection

(Closed)

Inspector Follow-up Item, IFI 93-02-03, EDSFI Findings

(Closed)

Inspector Follow-up Item, IFI 93-02-04, EDSFI Items

Identified for NRC Review

(Closed)

Inspector Follow-up Item, IFI 93-20-04, Alarm

Circuit/Control Circuit Interface

0I

10

8.

Acronyms and Abbreviations

C02

Carbon Dioxide

ECCS

Emergency Core Cooling System

EDSFI

Electrical Distribution System Functional Inspection

IST

Inservice Testing

IP

Inspection Procedure

KFD

Keowee Flow Diagram

kV

Kilovolts

MCC

Motor Control Center

MVA

Mega Volt Amperes

NRC

Nuclear Regulatory Commission

NRR

Nuclear Reactor Regulation

NSD

Nuclear Station Directive

QA

Quality Assurance

RFO

Refueling Outage

TDEFWP

Turbine Driven Emergency Feedwater Pump

VDC

Volts Direct Current