Advises That Scheduled 840910-19 Safeguards Regulatory Effectiveness Review Postponed Until Early 1985 to Allow Complete Integration of Safe Shutdown Facility & Full Implementation of Final Physical Security Plan
ML16152A322
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 04/11/1984
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Tucker H
DUKE POWER CO.
References
NUDOCS 8405070122
Download: ML16152A322 (1)


Text

APR 1 1 1984 Duke Power Company ATTN:

Mr. H. B. Tucker, Vice President IEFILE Copy Nuclear Production Department 422 South Church Street Charlotte, NC 28242 Gentlemen:

SUBJECT:

SAFEGUARDS REGULATORY EFFECTIVENESS REVIEW AT OCONEE In my letter of March 14, 1984, I informed you that a Safeguards Regulatory Effectiveness Review (RER) had been tentatively scheduled for September 10-19, 1984, at your Oconee facility.

At the request of plant personnel, the Oconee RER is being postponed until early 1985 to allow complete integration of the Safe Shutdown Facility and full implementation of the site's final Physical Security Plan.

A new date will be arranged in discussions between members of your staff and Regional personnel.

Sincerely Richard C. Lewis, Director Division of Project and Resident Programs cc:

M. S. Tuckman, Station Manager bcc: R. F. Burnett, NMSS J. Suerman, NRR Project Manager J. Bryant, NRC Sr. Resident Inspector Document Control Room State of North Carolina RI H

RII RII Gu ire:pw arr JP I ohr a d VLBrownlee HCDance Lewis 04/q /84 04/( /84 04/4 /84 00 04/4 /84 04/q /84 04/ a84 B405070122 840411 PDR ADOCK1 05000269 F