ML16148A728

From kanterella
Jump to navigation Jump to search
Insp Repts 50-269/92-29,50-270/92-29 & 50-287/92-29 on 921214-18.Violations Noted.Major Areas Inspected:Isi, Snubber Insp & Functional Testing & Licensee Actions on Previous Insp Findings
ML16148A728
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 01/06/1993
From: Blake J, Chou R, Kleinsorge W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML16148A725 List:
References
50-269-92-29, 50-270-92-29, 50-287-92-29, NUDOCS 9301200043
Download: ML16148A728 (14)


See also: IR 05000269/1992029

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET,N.W.

ATLANTA, GEORGIA 30323

JA.NI

Report Nos.:

50-269/92-29, 50-270/92-29 and 50-287/92-29

Licensee:

Duke Power Company

P.O. Box 1007

Charlotte, N.C. 28201-1007

Docket Nos.:

50-269, 50-270

License Nos.:

DPR-38, DPR- 47,

and 50-287

and DPR-55

Facility Name:

Oconee Units 1, 2 and 3

Inspection Conduc

-18,

1992

Inspector:

/

.1

insorge P.

gate'Signed

ac or Inspector

Inspector:

Q

R. C. Chou

bate Signed

Reactor Inspector

Approved by:

. Blake, Chief

Date Signed

M erials and Processes Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This routine, announced inspection was conducted onsite in the area of

Inservice Inspection (ISI), snubber inspection and functional testing, and

licensee actions on previous inspection findings.

Results:

In each of the areas examined the inspectors discovered that nondestructive

test (NDE) examiners were conducting conservative examinations in accordance

with the appropriate test procedure, except as noted below. NDE procedures

were also noted to be very detailed, well organized and technically effective

in implementing the applicable code requirements. Supervisors, engineers, and

9301200043 930111

PDR ADOCK 05000269

PDR

REPORT DETAILS

1. Persons Contacted

Licensee Employees

  • H. Barron, Oconee Station Manager
  • G. Bibb, UT Examiner
  • T. Coleman, ISI Coordinator/Compliance Engineer
  • W. Foster, Superintendent Mechanical Maintenance
  • F. Linsley, Component Engineering
  • B. Peele, ONS Engineering
  • S Perry, Regulatory Compliance
  • R. Pettit, ISI Outage Support
  • T. Royal, Component Engineering

Other licensee employees contacted included technicians, operators,

mechanics, security force members, and office personnel.

NRC Resident Inspectors

B. Desai, Resident Inspector

  • P. Harmon, Senior Resident Inspector

K. Poertner, Resident Inspector

  • Attended exit interview.

Acronyms and initialisms used throughout this report are listed in the

last paragraph.

2. Inservice Inspection (ISI)

The inspectors reviewed documents and records, and observed activities,

as indicated below, to determine whether ISI was being conducted in

accordance with applicable procedures, regulatory requirements, and

licensee commitments. The applicable code for ISI, for Unit 1, Unit 2,

and Unit 3, is the ASME B&PV Code,Section XI, 1980 Edition with Addenda

through Winter 1980 (80W80). Unit 1 has completed the fourteenth cycle,

and is in the second outage of the third 40 month period, of the second

ten year ISI interval (02,P3,I2). Unit 1 received its operating license

on February 6, 1973 and commenced commercial operations on July 15, 1973.

Unit 2 is operating, in the thirteenth fuel cycle, of the third 40 month

period, of the second ten year ISI interval (P3,12).

Unit 2 received its

operating license October 6, 1973 and commenced commercial operations on

September 9, 1974. Unit 3 is operating, in the fourteenth fuel cycle, of

the third 40 month period, of the second ten year ISI interval (P3,I2).

Unit 3 received its operating license July 19, 1974 and commenced

commercial operations on December 16, 1974. The licensee's

nondestructive examination personnel are performing the liquid penetrant

(PT), magnetic particle (MT), and ultrasonic (UT) examinations under the

umbrella of the Duke Power Company (DPC) Quality Assurance (QA) program.

2

a. ISI Program Review, Units 1, 2 and 3 (73051)

The inspectors reviewed the following documents, relating to the ISI

program to determine whether the plan had been approved by the

licensee and to assure that procedures and plan's had been

established for the applicable activities. Documents were reviewed

for technical content.

Documents Reviewed

ID

Revision

Title

Unit 1 ISI Plan for Outage 2 Period 3,

Interval 2

(R7)

Second Interval Inservice Plan Oconee

Nuclear Station

The licensee is in the process of replacing a number of check valves

on the Feedwater systems. The style of the replacement valves will

facilitate valve maintenance. The inspectors reviewed the

licensee's program for valve replacement. Documents were reviewed

for technical content.

Documents Reviewed

ID

Revision

Title

MP/O/A/1810/014

(Chl8)

Valves and Piping -Weld Removal and

Replacement- Class A through F

MP/O/A/1800/086

(Ch2)

Pipe Cold Spring

(R91-01)

Oconee Nuclear Station Mechanical

Maintenance Welding Program

OS-0243.00-00-0001

(R16)

Piping Installation Specification

L-100

(R14)

Welding Program

L-200

(R39)

Gas Tungsten Arc Welding

L-300

(R37)

Shield Metal Arc:Welding

L-102'

(R3)

Gas Tungsten Arc.Welding of Carbon

Steel Piping (Large Diameter Pipe Open

Root) Impact Procedure

L103 2

(Rl)

Shielded Metal Arc Welding (SMAW)

Carbon Steel

te

OpenButt

3

Documents Reviewed (Cant.)

ID

Revision

Title

L-185

(R2)

Gas Tungsten Arc Welding

L-154

(R7)

Shielded Metal Arc Welding

L-250

(R17)

Gas Tungsten Arc Welding

L-350

(R16)

Shielded Metal Arc Welding

1

Procedure Qualification Record (PQR) supporting Welding

Procedure Specification (WPS) Field Weld Data Sheet (FWDS)

L-250 and Performance Qualification (PQ) L-185

2

PQR supporting WPS FWDS L-350 and

PQ [-154

PQR Supporting PQ L-185

The licensee's program documents appear adequate for their intended

applications.

b. Review of NDE Procedures, Units 1, 2 and 3 (73052)

The inspectors reviewed the procedures listed below to determine

whether these procedures were consistent with regulatory

requirements and licensee commitments. The procedures were also

reviewed for technical content.

Procedures Reviewed

ID

Revision

Title

NDE-25

(R14)

Magnetic Particle Examination

Procedure and Techniques

NDE-35

(R13)

Liquid Penetrant Examination

All procedures reviewed appeared to contain the necessary elements

for conducting the specific examination.

c. Observation of Work and Work Activities, Unit 1 (73753)

The inspectors observed work activities, reviewed certification

records of NDE equipment and materials, and reviewed NDE personnel

qualifications for personnel who had been utilized in the ISI

4

examinations during this outage. The observations and reviews

conducted by the inspectors are documented below.

Activities Observed

Liquid Penetrant Examination (PT)

The inspectors observed PT examinations of piping welds listed

below. The inspectors performed an independent evaluation of the

indications obtained to confirm the NDE examiner's evaluation.

Liquid Penetrant Examinations Observed

Item No

Weld No.

Size

Component

E010.001.007

1PRZ-WP63-7

1"x1.187"

Pressurizer Nozzle to

Safe End Weld

The inspectors noted the following relative to the PT examinations

observed:

o

With the documentation provided the PT examiner to perform the

examination of weld 1PRZ-WP63-7 (Reactor Coolant Pressure

Boundary (RCPB) pressurizer nozzle to safe end butt weld), the

inspectors could not determine the exact location of the weld.

The PT examiner indicated he would PT examine the entire area

which he perceived to have been prepared by the cleaning crew

(the bright shiny area), to assure coverage of the weld and the

one half inch of adjacent base material on each side of the

weld, as required by procedure NDE-35, "Liquid Penetrant

Testing" Revision 13, Figure 3, for RCPB butt welds.

Subsequently the licensee obtained a drawing from off site,

that indicated the upstream weld fusion line was the boundary

dividing the bright shiny area (inconel weld metal) from the

oxidized area (carbon steel nozzle) on the nozzle-weld-safe end

assembly. Therefore the PT examiner examined the weld and

approximately six inches of adjacent base material downstream

of the weld, but failed to examine any adjacent base material

upstream of the weld.

An inadequate document package caused the PT examiner to fail

to comply with the extent of examination requirements

delineated in Figure 3, of procedure NDE-35, in that he did not

examine one half inch of adjacent base material upstream of

weld 1PRZ-WP63-7. Failure to follow procedure requirements for

activities affecting quality is a violation of Title Ten, Code

of Federal Regulations, Part 50, Appendix B, Criterion V. This

violation will be identified as 50-269,270,287/92-29-01:

"Failure To Follow PT Procedure".

0

5

Inspection by otrvec

12'

ALctual Inrume+oa

711

1 PRZ-HPS3-7

Pressurizer Nozzle to Safe End Assembly

0

The inspectors discussed the above with another PT examiner,

who indicated that when he examined similar pressurizer

nozzles, due to lack of specific knowledge of the exact weld

location, he examined the entire nozzle assembly from the

pressurizer face to the end of the nozzle-weld-safe end

assembly (approximately 12-inches).

The inspectors indicated

that the licensee has a weakness related to ISI weld drawings

which has caused unnecessary PT examination coverage, and

resulted in unnecessarily longer stay times in high radiation

areas.

The inspectors reviewed the certification documentation for

penetrant Batch No.87KO43, developer Batch No. 91C17P and cleaner

Batch No 92K051.

The inspectors reviewed the certification, qualification, and visual

acuity documentation for PT-II examiners EDC and ADG.

With the exception of the issues discussed above the examinations

were satisfactorily performed.

Magnetic Particle (MT) Examination

The inspectors observed the MT examination of the welds listed

below. The inspectors performed an independent evaluation of the

indications obtained to confirm the NDE examiner's evaluation.

6

Magnetic Particle Examinations Observed

Item No

Weld No.

Size

System

C05.021.118A

1-03-10-WG91C 14"XO.750"

Feedwater

C05.021.115A

1-03-10-WG91B 14"XO.750"

Feedwater

The licensee attempted to MT examine several other welds while the

inspectors were present however the licensee determined the surface

preparation was not acceptable for MT examination.

The inspectors reviewed the certification documentation for 8A Red

MT powder Batch No.89DO81, yoke OCQUA-183, and ten Lbs. test weight

S/N SYNT 11016.

The inspectors reviewed the certification, qualification, and visual

acuity documentation for MT-II examiners DLC and JWR.

The examinations were performed satisfactorily.

Ultrasonic Examination (UT)

The inspectors observed the UT examination of the welds listed

below. The inspectors observed examiners perform equipment

calibrations and ultrasonic examinations for the welds listed below.

Ultrasonic Examinations Observed

Weld Number

Item Number

Component

1CFTA-UH-SLH*

C01.020.001

Core Flood Tank Head To

Shell Weld

ICFTB-LH-SLH

C01.020.005

Core Flood Tank Head To

Shell Weld

  • Observed calibration activities only, because the licensee

determined that the surface preparation was not acceptable for

examination at the time the inspectors were present.

The examination and calibrations were performed satisfactorily.

Radiographic Film Storage

On a previous inspection conducted on site, August 10-14, 1991, the

inspectors examined the film storage facilities at the Oconee

Station for compliance with DPC procedure QA-102 and identified some

discrepancies with both the procedure and the implementation of that

procedure. The inspectors conducted a followup inspection in that

area, noting the following:

7

o

The licensee is in the process of reorganizing the film storage

facility. At this writing the majority of the film is storied

consistent with the film manufacturers recommendations. The

licensee has conducted more frequent temperature and humidity

checks, since the last inspection in thisi area.

o

The licensee is in the process of revising the procedure to

correct the short comings noted in the August inspection.

d. Visual Examination of ISI Pipe Supports

The inspectors randomly selected 20 pipe supports for walkdown

reinspection. The 20 pipe supports, in various systems, are located

in the Reactor Building and Turbine Building. The inspection

results were compared with the applicable procedure, QAL-14,

Revision 13, "ISI Visual Examination, VT-3 and VT-4," dated November

2, 1992. The visual inspection included a check on configuration;

defects such as distortion, cracks, bent members, weld failures

induced by operations; condition of connections to supporting

structures; and/or component settings. The inspectors' observations

generally agreed with the information reported by the licensee's ISI

examiners except for the discrepancies as noted below:

Table 1

Pipe Support Walkdown Reinspection

Support No.

Rev. Discrepancies/Remedies

01A-0-481B-H7A

D3

None

01A-0-481A-H3A

01

None

01A-0-481A-H4A

D1

None

O1A-0-481A-H1A

Dl

None

01A-0-481A-H2A

D1

None

01A-0-481A-H6A

D1

None

O1A-0-481A-H5A

D1

None

1-01A-0-550-HlO

1

The load indicator plate for the

spring can was painted over. The

licensee will reinstruct the painters

again not to paint over load plates

and support tags.

1-01A-1-1-0-401A-H7 2

None

1-01A-0-550-H5

1

None

1-01A-0-550-R3

11

None

0

8

Table 1(Cont.)

Pipe Support Walkdown Reinspection

Support No.

Rev. Discrepancies/Remedies

1-01A-0-550-R4

2

A rod support around column lines L-16

near this support was loose.

A trapeze support located 5' north of

column 16 and 6' west of column L at

EL. 806' the west rod had hit the

insulation on an adjacent pipe and the

east rod was bent and had hit

insulation on another pipe.

The licensee will review and correct

these problems.

1-O1A-1-1-O-401A-H43 3 A 1/4" gap was found between the

washer and the spherical bearing on

the eye rod at the end attachment,

even with spacers installed. The

licensee will review and resolve this

problem

1-53B-4-0-435B-H30 3

None

1-53B-0-435B-R35

8

None

1-53B-4-0-435B-H13

10

None

1-53B-0-435B-DE066 4

The snubber was in contact

with other pipe insulation. The

licensee issued Work Request No.

92054547 to correct it.

1-53B-0-435B-DE067 3

The sway strut was skewed

excessively. The licensee issued Work

Request No. 92054351 to correct it.

1-53B-435B-DE079

2

None

1-03A-1-0-400B-SR56 0

One bent anchor bolt and one anchor

bolt with grout chipped off were found

and recorded by the licensee ISI

examiners. The licensee's actions

regarding this finding are discussed

below.

During this refueling outage, the licensee's QC inspectors

identified that Support No. 1-03A-1-0-400B-SR56 had a bent anchor

bolt with a loose nut and another anchor bolt with grout chipped

off. The licensee's engineers reviewed the base plate calculations

and found that if they considered the bent bolt as an abandoned

anchor, the factor of safety would be approximately 3;

which fails

9

to meet the requirement of greater than 5 for long term design of

self drilled expansion anchor bolts, per paragraph 1-8.2.1.10 of

Design Specification No. OS-0027.00-00-0001. A factor of safety of

3 will meet the temporary operability requirement of greater than 2,

per IE Bulletin 79-02.

The inspectors reviewed the support calculation, rev. 0, dated

November 21, 1981.

Page 6 of this calculation, initiated and

checked on August 9, 1979, used the allowable loads for four 1/2

inch diameter, self-drilling anchor bolts got a factor of safety of

2.51.

Page 7 of this calculation was initiated on October 19, 1979,

used a combination of the 1/2-inch diameter anchor bolt allowable

loads and increased concrete strength due to aging to get a factor

of safety of 3.63. Page 8 of this calcuation was initiated and

checked on December 15, 1979, to record the ISI deficiencies of

chipped grout and a bent anchor bolt. This part of the calculation

clearly indicated the following conditions: a bent anchor bolt and

an anchor bolt with the grout chipped off;

the factor of safety of

3.63 was calculated assuming no deficiencies;

and a recommendation

to modify the support using four 7/8-inch diameter wedge anchor

bolts to replace the bent and other self drilling anchor bolts to

achieve a factor of safety of 5.1 to meet the requirement of factor

of safety of greater than 5.0. The calculation concluded that a

repair was required.

Subsequently, on May 20, 1980, page 8 of the calculation was

revised, and rechecked, using allowable loads for 3/4-inch diameter

anchor bolts to get a factor of safety of 6.38, without considering

the effect of the bent anchor bolt.

Page 5 was added to the

calculation and contained reviews of a final factor of safety 6.38

for IE Bulletins 79-02 and 79-14 dated September 3, 1980 and

September 30, 1981 by two different checkers respectively. From the

above review processes, it appears that at least four persons missed

the bent anchor bolt deficiency during their reviews. Pending the

licensee's investigation of the root cause and correction, this

matter is identified as Unresolved Item 50-269,270,287/92-29-02,

Failure to Identify Pipe Support Design Deficiencies.

Support No. 1-O1A-1-1-0-401A-H43 was found to have a 1/4" gap

between the washer and spherical bearing on the eye rod at the end

attachment for the snubber. The licensee agreed to review and

establish inspection and acceptance criteria for the gap between the

washer and spherical bearing for snubbers and sway struts.

During the support walkdown reinspection, the inspectors noticed

that insulation on some of the supports was not removed for the ISI

inspections. The licensee's understanding of the conditions which

exempt the requirement for removal of insulation, (Paragraph IWF

1300.e of ASME Section XI,) were different between the ISI QC

examiners and engineers. The licensee agreed to review the ASME

code exemptions, and their explanation, with the ISI QC examiners

and engineers.

The inspectors initially reviewed personnel qualification

documentation for eight of the ISI QC examiner's who performed the

inspections of the pipe supports listed in Table 1 above. These

qualifications were reviewed for conformance to requirements in the

areas of activity qualified to perform, expiration date, annual

visual acuity, and color vision examination.

The certification records were found to be generally acceptable,

however, the inspectors found a gap of five months for the visual

accuity examination for one examiner. The Form QA-140B for vision

examination was not in the qualication package for a period of five

months. The examiner had eye examinations for near vision, far

vision, and color perception on July 17, 1991 and December 16, 1992;

this indicated a lapse of five months on the eye examination.

When the inspectors questioned the QC supervisor about the problem,

the supervisor stated that they had found this problem two days

before, and had issued Problem Identification Serial No. 0-092-0693.

The QC supervisor also stated that the examiner in question had a

complete eye examination during a physical examination performed on

February 26, 1992, for respirator qualification and a company

drivers license. He passed the eye examination again on December

16, 1992, two days before this review. Therefore, the QC supervisor

stated that DLC was a qualified QC examiner.

However, thru review of the medical record, the inspectors found

that the examiner was not a qualified QC examiner during the lapse

of five months on the eye examination because he did not have a near

vision or Jaeger examination performed on February 26 1992, since

the Department of Transportation.does not require a near vision

examination to Duke trucks.

The inspectors expanded the review to include all 14 ISI QC

examiners and found another QC examiner, to have an eye examination

lapse of one month between January 4, 1990 and February 4, 1991.

Per Paragraph 7.1.4 of Procedure NDE-B, Training, Qualication, and

Certification of Nondestructive Examination Personnel, the near

vision, distance acuity, and color perception examination shall be

conducted at least once annually and shall be documented on Form QA

140B or an equivalent form. Both of the examiners failed to meet

the above requirements, but in both cases, when the examiners were

tested after the lapse their vision was acceptable. Pending the

licensee investigation of the root cause(s) and corrective actions

on the problem, this matter is identified as Unresolved Item

50-269,270,287/92-29-03, Failure to Conduct Annual Vision Acuity

Examination.

In the areas inspected, no violations or deviations were identified,

except as noted in paragraph 2.c. above.

3. Snubber Inspection and Functional Testing, Unit 1 (70370)

All snubbers in safety-related systems, and non-safety related systems

required to protect safety-related systems, are required to be operable,

and 100 percent visual inspected and ten percent functionally tested

during each refueling outage, per Technical Specification (TS) 3.14 and

4.18. TS 4.18.1 states that snubbers located in the accessible areas can

be inspected during normal operation, while those located in the

inaccessible areas, are to be inspected during refueling outages.

Procedure Nos. MP/1/A/3018/010 for hydraulic snubbers and MP/1/A/3018/019

for mechanical snubbers are used in the inaccessible areas.

Procedure

Nos. MP/1/A/3018/011 for hydraulic snubbers and MP/1/A/3018/020 for

mechanical snubbers are used in the accessible areas. Procedure No.

MP/0/A/3018/009A is used for hydraulic and mechanical snubber functional

testing.

The licensee performed functional tests on more than the 10 percent

required by TS and simultaneously, included all snubber supports, which

were required by ISI inspections, in the functional test during each

refueling outage. The licensee had completed visual inspection on all

the snubbers during or before this refueling outage. The licensee found

all snubbers inspected to be acceptable.

The NRC inspectors conducted independent visual examination verification

on 18 snubbers selected at random. Three hydraulic and three mechanical

snubbers were located in inaccessible areas. Six hydraulic and six

mechanical snubbers were located in accessible areas. These examinations

were conducted in order to evaluate the adequacy of the examination

procedures being used by the licensee and to assess the validity of the

information reported by the examiners. These verification examinations

generally agreed with the findings of the visual examiners except as

noted below:

Table 2

Snubber Inspection

Snubber

Discrepancies/

Support No.

Bldg.

Type

Remedies

1-53A-0-481A-H41C

Reactor

Hydrau.

None

1-53A-0-481A-H40C

Reactor

Hydrau.

The extension piece of this

snubber contacts the nearby pipe

insulation. The licensee will

issue Work Request to correct

it.

1-50-0-66A-RCPM-S5 Reactor

Hydrau.

None

12

Table 2 (continued)

Snubber Inspection

Snubber

Discrepancies/

Support No.

Bldg.

Type

Remedies

1-51-478A-H6142

Reactor

Mechan.

None

1-51-478A-H6140

Reactor

Mechan.

None

1-03-480A-H6071

Reactor

Mechan.

None

1-03A-1-0-400B-SR56 Turbine

Hydrau.

See discrepancy found in Table 1

for this support.

1-03A-1-0-400B-SR54 Turbine

Hydrau.

None

1-03A-1-0-400A-SR53 Turbine

Hydrau.

None

1-03A-1-0-400A-SR52 Turbine

Hydrau.

None

1-O1A-3-0-401A-R9

Turbine

Hydrau.

None

1-01A-3-0-401A-R8

Turbine

Hydrau.

None

1-03A-0-551-R13

Turbine

Mechan.

None

1-01A-1-1-401A-H43 Turbine

Mechan.

See discrepancy found in Table 1

for this support.

1-01A-403C-DE072

Turbine

Mechan.

A portion of the tag was painted

over and it was dfficult to read

the support I.D.

The licensee

will reinstruct painters not to

paint over them.

1-O1A-0-401A-DE071 Turbine

Mechan.

None

1-O1A-0-550-R15

Turbine

Mechan.

None

1-01A-0-550-R16

Turbine

Mechan.

None

The licensee is still in the process of establishing inspection and

acceptance criteria for inspection of the gap between the washers and

spherical bearings at the rod end near the rear bracket or the piston rod

eye near the pipe clamps. This problem was already identified as

Unresolved Item 50-269,270,287/91-05-01 which remains open.

Within the areas inspected, no violations or deviations were identified.

4. Action on Previous Inspection Findings (92701)

(Closed) Bulletin 50-270,287/88-BU-10, Nonconforming Molded Case Circuit

Breakers. The licensee responded to Bulletin 88-10 by letters dated

April 4, 1989, and April 24, 1989. The licensee's evaluation determined

that none of the nonconforming molded case circuit breakers discussed in

Bulletin 88-10 were installed or used in Unit 2 and Unit 3.

In the areas inspected, no violations or deviations were identified.

5.

Exit Interview

13

The inspection scope and results were summarized on December 18, 1992,

with those persons indicated in paragraph 1. The inspectors described

the areas inspected and discussed in detail the findings listed below.

Although reviewed during this inspection, proprietary information is not

contained in this report. Dissenting comments were not received from the

licensee. The licensee was informed by telephone on December 22, 1992,

of the unresolved item related to pipe support design deficiencies.

Violation 50-269,270,287/92-29-01:

"Failure To Follow PT

Procedure".

Unresolved Item 50-269,270,287/92-29-02:

"Failure To Identify Pipe

Support Design Deficiencies"

Unresolved Item 50-269,270,287/92-29-03:

"Failure To Conduct Annual

Vision Acuity Examination"

6. Acronyms and Initialisms

ASME

-

American Society of Mechanical Engineers

B&PV

-

Boiler and Pressure Vessel

Ch

-

Change

DPC

-

Duke Power Company

DPR

-

Dimension Power Reactor

FWDS

-

Field Weld Data Sheet

ID

-

Identification

ISI

-

Inservice Inspection

MT

-

Magnetic Particle

NDE

-

Nondestructive Examination

No.

-

Number

NRC

-

Nuclear Regulatory Commission

P.E.

-

Professional Engineer .

PQ

-

Performance Qualification

PQR

-

Procedure Qualification Record

PT

-

Liquid Penetrant

QA

-

Quality Assurance

R

-

Revision

RCPB

-

Reactor Coolant Pressure Boundary

UT

-

Ultrasonic

WPS

-

Welding Procedure Specification