ML16148A709

From kanterella
Jump to navigation Jump to search
Insp Repts 50-269/92-17,50-270/92-17 & 50-287/92-17 on 920803-07,0902-04 & 0908-09.Violations Noted.Major Areas Inspected:Occupational Exposure During Extended Outages & Review of Info Notices
ML16148A709
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 11/17/1992
From: Bryan Parker, Pharr E, Rankin W, Shortridge R, Testa E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML16148A705 List:
References
50-269-92-17, 50-270-92-17, 50-287-92-17, NUDOCS 9212040272
Download: ML16148A709 (23)


See also: IR 05000269/1992017

Text

REG

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

101 MARIETTA STREET, N.W.

ATLANTA, GEORGIA 30323

NOV 2 0 1992

Report Nos; 50-269/92-17, 50-270/92-17

and 50-287/92-17

Licensee: Duke Power Company

422 South Church Street

Charlotte, NC 28242

Docket Nos.: 50-269, 50-270, 50-287

License Nos.: DPR-38, DPR-47, DPR-55

Facility Name: Oconee 1, 2, and 3

Inspection Conducted: August 3-7, 1992*

September 2-4, 1992+

September 8-9, 1992+

Ins pector:_

ze 1.

L71V- (

R. B S

idg

ine

Accompanied By:

11/

o

Ara: ESio

.H

ai

fihie

"7 1

Date igned

E. D. jestaDai

Si ned

t ITned

/1 /7 )

Approvt

i ne

.ate/Signed

roveBaiti

adiation Protection Branch

Radiological Protection and Emergency Preparedness Branch

Division of Radiation Safety and Safeguards

SUMMARY

Scope:

This routine, unannounced inspection was conducted in the area of occupational

exposure during extended outages and included a review of Information Notices.

A second inspection covering two periods was conducted to respond to a

potential exposure in excess of regulatory limits.

This included a review of

the event, how the licensee assessed the event and assigned the exposure, and

a review of the program to determine adequacy in preventing recurrence.

9212040272 921120

PDR ADOCK 05000269

G

PDR

Results:

The inspector found the radiation protection (RP) program at Oconee to be

adequate in protecting the health and safety of the public and plant

employees. However, during both inspections, apparent violations of

regulatory requirements were identified that signify the need for improvements

in the RP program and increased attention by plant management.

The (*) signifies reference to the first inspection of August 3-7, 1992.

The

(+) signifies reference to the second inspection ending on September 9, 1992.

(*) Apparent violation for inadequate posting of radiological control zones

with multiple examples:

(a) The normal sump area in containment where people were working in

respirators in very high levels of contamination was not posted as

an airborne radioactivity area; and

(b) There were work areas in the primary chemistry laboratory that

were not posted or taped to signify a controlled contamination

area. These areas had varied readings of 1,000 to greater than

100,000 corrected counts per minute (ccpm).

(*) Apparent violation with examples for failure to label radioactive

material:

(a) Air sampler reading greater than 10,000 ccpm was observed in

Unit 2 Auxiliary Building without.a radioactive material label;

and

(b) A contaminated screwdriver was located in a tool box in the

primary chemistry laboratory unlabeled, and reading greater than

1,200 ccpm.

(+) An apparent violation was identified when a Primary Chemist and a

Radwaste Operator failed to access a Radiation Work Permit (RWP)

prior

to performing radiological work.

REPORT DETAILS

1..

Persons Contacted

Licensee Employees

  • B. Baron, Plant Manager

+S. Benesole, Plant Safety Review Group

+S, coy, Supervisor, Radiation Protection

+J. Davis,-Manager, Safety Assurance

+J. Hampton Vice President, Oconee Nuclear Station

+M. Hassell, Scientist, Radiation Protection

+B. Jones, Manager, Chemistry

  • +M.

Manager, Regulatory Compliance

+B. Peele, Manager, Engineering

  • +S. Perry, Technical Assistant, Regulatory Compliance
  • +R. Sweigart, Acting Plant Manager, Operations Superintendent

+M. Thorne, Supervisor, Radiation -Protection

+R. Vassey, Plant Safety Review Group

  • L. Wilkie, Manager, Chemistry
  • +C. Yongue, manager, Radiation Protection

Other licensee employees contacted during the inspection included

craftsmen, technicians, and administrative personnel.

Nuclear Regulatory Commission

  • +B. Desai, Resident Inspector

+P. Harmon, Senior.Resident Inspector

  • Attended 1st Exit Interview August 7, 1992

+Attended 2nd Exit Interview September, 9, 1992

2.

Occupational Exposure During Extended Outages (83729)

a.

Organization and Management Controls

The licensee is required by Technical Specification (TS)

6.1.1.1

to establish clear lines of authority, responsibility, and

communication from the highest management levels through

intermediate levels including the operating organization.

The

inspector reviewed staffing levels and lines of authority as they

related to the Radiation Protection (RP)

program and discussed the

organization with the RP Manager. The inspector verifiedthat the

licensee had not made changes that would adversely affect their

ability to implement -critical elements of the RP program.

42

b.

Audits and Appraisals (83729)

TS 6.1.3.4 requires that audits of plant activities be performed

under the cognizance of the Nuclear Safety'Review Board (NSRB) and

that the audits.shall encompass, in part, the conformance of plant

operation to provisions contained within the TSs and applicable

license conditions at least once per 12 months.

The inspector reviewed a Quality Assurance (QA) audit of RP

program activities, NG-92-03 (ON), performed since the previous

NRC inspection of program activities conducted January 27-31,

1992, and documented in Inspection Report (IR)

92-06. The

inspector noted that the audit was well-planned and documented

and, most importantly, appeared to adequately assess the program.

The audit contained items of substance relating.to the program and

valid nonconformances were identified. The inspector noted

thorough investigations and responsive commitments by-management

to implement corrective actions for the deficiencies identified.

The inspector also noted a high level of management visibility for

audit findings and subsequent responses.

The inspector also reviewed Radiological Deficiency Reports (RDRs)

and Problem Identification Reports (PIRs) initiated from

January 1 to July 31, 1992.

During discussions with licensee

representatives, the inspector was informed that whereas the RDR

was only an internal RP self-assessment program, the PIR program

was to be used by all work groups to identify and investigate any

plant-related problems.

The inspector noted that the 19 RDRs which were written during the

1st quarter of 1992 usually documented poor work practices

resulting in contamination, both personnel and area. As well, 17

incident reports involving improper use of dosimetry and drifting

or offscale self reading dosimeters (SRDs) were made during the

first quarter of 1992. Since the PIR program was initiated in

April 1992, 15 RP-related PIRs had been written. The inspector

noted that these reports included procedural violations, non-ALARA

components/areas which posed potential procedural violations, and

lost, drifting, and offscale dosimetry. During review of the

identified RORs and PIRs, the inspector noted that the

investigations were thorough and that corrective actions were

appropriate and comprehensive. The inspector noted that

corrective actions did not always appear to be timely in that nine

of the 15 PIRs, had not been resolved at the time of the

inspection. However, the inspector noted that the licensee did

track PIRs as to their open or closed status and that identified

problems were trended quarterly. The inspector informed licensee

representatives that the method for trending deficiencies and for

tracking open items to final and approved resolution appeared

effective.

No violations or deviations were identified.

3

3.

Training and Qualifications (83729)

10 CFR 19.12 requires, in part, that the licensee instruct all

individuals working in or frequenting any portions of a restricted area

in the health protection aspects associated with exposure to radioactive

material or radiation; in precautions or procedures to minimize

exposure; in the purpose and function of protection devices employed; in

the applicable provisions of the Commission regulations; in the

individual's responsibilities; and in the availability of radiation

exposure data.

The inspector reviewed training provided to contract technicians in

preparation for the Unit 3 refueling outage. During discussions with

licensee personnel, the inspector was informed that prior to performing

RP tasks, vendor technicians must first successfully complete General

Employee Training (GET)

and respiratory protection training; a written

Health Physics (HP) knowledge test; site specific training, to include

applicable industry events; and qualification in tasks which the vendor

will be assigned. The inspector noted that successful completion of the

required training sessions required passing each associated written test

with at least 70 percent correct for seniors. The inspector reviewed

the HP knowledge test and noted that the test adequately addressed basic

HP concepts. However, the inspector considered passing standards of

70 percent for senior technicians and 50 percent for junior technicians,

respectively, to be relatively low for the material content.

The

inspector was informed that in response to a concern regarding vendor

passing standards raised during IR 92-06, the licensee was evaluating

increasing the passing score for senior technicians to 80 percent.

Additionally, licensee representatives stated that each vendor's

qualifications were assessed by the RPM and evaluations of the

technician's performance to certain tasks were performed as necessary.

The inspector also discussed with licensee representatives training

provided to the core vendor technician staff. The inspector was

informed that this core group consisted of 45 technicians which provided

RP support to the three Duke Power nuclear stations during outages.

However, during non-outage operations, a group of 15 technicians were

assigned to a base plant. .The 15 technicians assigned'to Oconee Nuclear

Station during operating periods participated in both continuing

training and special training sessions.

The inspector was informed that

special training was recently implemented for RP technicians And the 15

core vendors. This special training consisted of 34 computer-based

training modules and associated tests which focused primarily on

refresher HP theory and practices.

The modules were introduced in 1991

and by December 31, 1992, all technicians, both in-house and vendors,

were required to successfully complete 12 of the 34 training modules.

The inspector reviewed training files for selected RP te .hnicians signed

in on RWP associated with removal and decontamination of component drain

header piping. For those records reviewed, training was current and

included GET, site-specific training, the HP knowledge test, and various

task qualifications. Based on the above, the inspector found the

licensee's vendor RP training program to be satisfactory.

No violations or deviations were identified.

4.

External Exposure Controls (83729)

10 CFR 20.101 requires that no licensee possess, use, or transfer

licensed material in such a manner as to cause any individual in a

restricted area to receive in any period of one calendar quarter a total

occupational dose in excess of 1.25 rems to the whole body, head and

trunk, active blood forming organs, lens of the eyes, or gonads;

18.75 rems to the hands, forearms, feet and ankles; and 7.5 rems to the

skin of the whole body.

The inspector reviewed 1992 external exposure records for workers

involved with RWP activities associated with the Unit 3 component drain

header and valve replacement. The inspector noted that the maximum

whole body dose during any one quarter was 450 millirem (mrem).

However, during discussions with licensee representatives, the inspector

was informed of an exposure in excess of administrative limits which

occurred in January 1992. The inspector reviewed the accompanying RDR

which reported the circumstances of the incident and determined that,

based on TLD results, the individual received an exposure of 564 mrem,

exceeding his administrative limit of 500 mrem.

Investigation of the incident revealed that the individual received the

exposure while installing level indicating equipment on both the hot and

cold legs of "B" steam generator. On January,12 and 13, 1992, the

individual made three separate entries into the reactor building to

perform the specified work and received exposures of 250 mrem, 60 mrem,

and 195 mrem, respectively, based on electronic dosimeter readings.

When the individual attempted to enter the Radiation Controlled Area

(RCA) the following day, the Electronic Dose Capture (EDC) system would

not allow entry since the individual had exceeded his 500 mrem

administrative limit. Further investigations revealed that a different

RP technician provided job coverage for the individual on January 13,

1992. This RP technician did not attend the pre-job ALARA briefing on

January 12, 1992, and was not aware of complete dose rates in the work

area, nor the workers' complete dose information. As well, longer than

estimated stay times were encountered and no dose extensions were

requested by the workers' supervisor. Additionally, the licensee

determined that the individual did not understand basic radiological

terms and the ALARA impact of body positioning and low dose waiting

areas during high radiation work, nor did the individual fully

understand the EDC system. Corrective actions in response to the

incident included GET retraining for the involved individual, and

counseling for the RP technician on the importance of complete job scope

5

review, detailed pre-job surveys, and knowledge of workers' remaining

exposure -imits. As well, a case study of the incident was prepared for

presentation to RP technicians and supervisors to ensure continued

awareness to prevent recurrence.

The inspector reviewed the individual's exposure history for first and

second quarter 1992 and determined that the maximum dose received during

either quarter was 564 mrem. The inspector concluded that for those

selected individuals reviewed, all external exposures were within 10 CFR

Part 20 limits.

During tours of the Unit 3 Containment Building, the inspector noted

that the incore instrument wires retracted into the incore instrument

tank, and the tank was flooded with water for shielding.

However, the

method of restraint appeared to be a continuous restraint wire running

through all the lifting bail/support clamp type arrangement.

It

appeared to the inspector that the restraint wire running though the

lifting bail/support clamp could be inadvertently lifted which would

lift some of the incore wires from their storage location.

The

inspector discussed this at the exit interview with licensee personnel

and the licensee agreed to review further to see if the incore wires

were properly restrained to prevent inadvertent movement.

10-CFR 20.203(c)(1) requires that each high radiation area shall be

conspicuously posted with a sign or signs bearing the radiation symbol

and the words "Caution High. Radiation Area."

TS 6.4.1, in part, requires that the station be operated and maintained

in accordance with approved procedures.

Paragraph 6.4.1.g specifies

personnel radiation protection procedures.

Health Physics Manual

Section 4.2, Posting of Radiologically Controlled Areas and Materials,

dated March 13,

1986, in Step 3.1.8, defines a high radiation area as

any area-which is readily accessible to personnel and there exists a

potential to expose a major portion of the whole body to greater than

100 millirem per hour (mrem/hr).

During tours of the Unit 3 containment building, the inspector noted in

several areas that there were no barricades to prevent entry or warn

personnel of high radiation levels in the specific area.

There was a

rope and a sign posting the area to the "B" lower steam generator (S/G)

entrance; however, it was not placed across the entryway after the last

person exited the area. The manway was removed from the "B" lower S/G

manway for eddy current testing and a yellow flashing light was in the

area. However, there was no barricade or sign at the entry point of the

area, and thus no barrier existed that led to the 8.9 rem/hour radiation

field at 18 inches from the S/G tube sheet.

The inspector immediately

reported the condition to a health physics technician (HPT)

who posted

the area as required.

The same problem was observed at the entry point (ladder) leading to the

reactor cavity. The area had a flashing warning light; however, the

rope barrier and sign leading to the reactor cavity entrance, with dose

6

rates greater than 500 mrem/hr, were not in place. The HPT in the area

took immediate actions to post the area as required by procedure.

5.

Internal Exposure Controls (83729)

a.

Internal Exposure Assessments

10 CFR 20.103(a)(1) states that no: licensee shall possess, use, or

transfer licensed material in such a manner as to permit any

individual in a restricted area to inhale a quantity of

radioactive material in any period of one calendar quarter greater

than the quantity which would result from inhalation for

40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> per week for 13 weeks at uniform concentrations of

radioactive material in air specified in Appendix B, Table 1,

Column 1.

10 CFR 20.103(a)(3) requires, in part, that the licensee, as

appropriate, use measurements of radioactivity in the body,

measurements of radioactivity excreted from the body, or any

combination of such measurements as may be necessary for timely

detection and assessment of individual intakes of radioactivity by

exposed individuals.

The inspector reviewed internal exposure records for selected

individuals associated with RWP work on the Unit 3 component drain

header and valve replacement. For those records reviewed, the

inspector noted a maximum quarterly exposure of 6.32 Maximum

Permissible Concentration-hours (MPC-hrs) for third quarter 1992,

to date. During discussions with licensee representatives, the

inspector was informed that following reactor shutdown for the

Unit 3 outage and prior to operation of the containment purge

system, the licensee experienced airborne iodine levels in the

reactor building up to approximately 16 percent MPC. Licensee

representatives also stated that body burden analyses (BBAs) were

performed for an approximate 100 percent representative sampling

of workers in the reactor building during the increased airborne

levels. The inspector noted that based on BBAs, no iodine uptakes

were detected. The inspector also noted that for the individual

assigned 6.32 MPC-hrs during the first week of the Unit 3 outage,

full-face air-purifying respiratory protection was worn as

necessary and that the individual's internal exposure was based on

air sample results in the work area. The inspector verified that

no exposures in excess of the 40 MPC-hr control measure had

occurred since January 1, 1992.

No violations or deviations were identified.

7

b.

Respiratory Protection Program

10 CFR 20, Appendix A, footnote(d), requires adequate responsible

air of the quality and quantity in accordance with NIOSH/MSHA

certification described in 30 CFR Part 11 to be provided for the

atmosphere-supplying respirators.

30 CFR 11.121 requires that compressed, gaseous breathing air

meets the applicable minimum grade requirements for Type 1 gaseous

air set forth in the Compressed Gas Association (CGA) Commodity

Specification for Air, G-7.1 (Grade D or higher quality).

The inspector discussed with licensee representatives recent

upgrades in the station's breathing air systems.

Licensee

representatives informed the inspector that during previous years,

existing compressors were not adequate to supply the needed

breathing air capacity,' especially during outages.

Therefore, the

licensee recently upgraded their breathing air systems for each of

the three units, to include the turbine buildings.

Licensee

representatives informed the inspector that each unit's breathing

air would be supplied by two oil-cooled/lubricated compressors,

with approximately 15 manifolds in each reactor building. At the

time of the onsite inspection, the licensee had implemented the

Unit 3 system and was supplying breathing air -during the outage.

Additionally, the inspector was informed that the other units'

systems would be implemented in the near future with further

evaluations and operational design changes ongoing with the Unit 3

system.

HP/0/B/1010/02, Radiological Respiratory Quality Assurance, dated

July 28, 1992, requires any compressor or system used for

breathing air purposes be sampled quarterly to ensure Grade D air

quality.

The inspector reviewed breathing air sampling records

for 1992, to date, and noted that sampling was performed to ensure

Grade D quality air at least quarterly.

The inspector further

noted that with the exception of June 1992, all sample results for

carbon monoxide (CO) were less than 10 parts per million (ppm).

For the June sampling of the seven compressor systems, the

inspector noted that CO results ranged from 10.1 ppm to 13.6 ppm.

During discussions with licensee representatives, the inspector

was informed that the licensee's analysis laboratory had explained

that analyses of the seven samples had to be performed twice.

An

adequate testing quantity was not available-for the second

analyses, which produced erroneous results. During the period

from July 23, to August 3, 1992, the breathing air systems were

resampled and results of less than 10 ppm CO were achieved.

Licensee representatives also stated that CO alarms were located

on each breathing air system and that workers were successfully

removed from utilizing breathing air whenever CO alarms were

noted.

8

The inspector also reviewed and disrussed with licensee

representatives maintenance procedures for breathing air

compressors. The inspector noted that with the exception of one,

the procedures included a step for maintenance personnel to notify

RP after system maintenance in order to determine. if resampling to

verify Grade D compliance was necessary. :For the one procedure

without the step, the licensee initiated actions to change the

procedure and to develop a method for adding the notice

requirement to any future procedures or revisions associated with

breathing air compressor maintenance.

No violations or deviations were identified.

C.

Radioactive Source Control (83729)

During review of 1992 PIRs, the inspector noted an incident

investigation involving two sources which could not be located

during the 1991 annual source inventory. Sources ONSI-109

(nominal 100 microcuries (uCi) of strontium-90) and ONSI-134

(nominal 0.06 uCi of radium-226) were used to perform detector

source checks for two skid-mounted radiation detectors.

These

monitors were recently replaced and the sources were removed so

that the monitors could be disposed. The sources were

encapsulated with epoxy inside a hollow machine screw,

approximately 3/8 inches long. Following removal from the

monitors, the sources were to be maintained and stored by the

Instrumentation and Equipment (I&E) source custodian.

The inspector reviewed the 1991 source inventory and determined

that withthe exception of ONSI-109 and ONSI-134, all sources were

accounted for and leak tested as required. The inspector also

noted that the responsible source custodian had initiated a letter

to the RPM on June 4, 1992, which identified the lost sources by

isotope and activity. Although the custodian could not

conclusively determine the circumstances surrounding the loss,

corrective actions to prevent recurrence were discussed. These

corrective actions included coordination of I&E and RP to

establish a designated, centralized storage area for I&E sources,

storing the sources in lockable cabinets with sign-out logs to

ensure proper control, as well as returning sources to RP for

disposal when no longer needed. RP representatives stated that

the corrective actions should be adequate in preventing other

source losses. During discussions with licensee representatives

the inspector was informed that.the licensee was confident that

although the sources could not specifically be located, they were

maintained within the plant restricted area and probably within

the RCA. This was evidenced by tests with sources of similar

activity and isotopic content to ensure that the lost sources

could not bypass the plant's exit portal monitors. Additionally,

the licensee stated that efforts would continue to locate the

missing sources.

kII

9

Based on the minor safety significance of the issue due to efforts

taken by the licensee to ensure the sources were within the

restricted area and continuing efforts to locate the sources, the

inspector determined the licensee's actions, to date, were

appropriate but informed licensee representatives that their

followup actions would be reviewed during future inspections.

No violations or deviations were identified.

6.

Control of Radioactive Materials and Contamination, Surveys,

and

Monitoring

a.

Cavity Drain and Letdown Pipe Decontamination

10 CFR 20.203(d)(2) requires that each airborne radioactivity area

be conspicuously posted with a sign or signs bearing the radiation

caution symbol and the words "Caution Airborne Radioactivity

Area." TS 6.4.1, in part, requires that the station be operated

and maintained in accordance with approved procedures and

Paragraph g specifies personnel radiation protection procedures.

Health Physics Section Manual 4.2, Step 3.4.1, requires that areas

with airborne concentrations of radioactive materials greater than

25 percent MPC or areas with this potential (normally due to work

being performed in the area) shall be posted as Airborne

Radioactivity Areas.

During a tour of Unit 3 Reactor Building, the inspector noted that

personnel wearing full-face respirators were working in an area

without the posting for airborne radioactivity area in the sign.

The caution sign was posted as a high radiation area with 4000

5000 mr/hr in the alleyway on oilcloth,.50-5000 mr/hr general

area, and up to 450 mrad smearable. The inspector notified the

nearest HPT who posted the area as required. This was reported to

the licensee as an example of failure to post an area as required

by procedure (50-269, 270, 287/92-17-01).

The inspector observed the personnel in the area performing

decontamination of the letdown and cavity drain lines to support

shipment of the-same. The inspector noted that the deconners were

spraying water via a high pressure lance into the piping in the

general location of the normal sump, but the water exiting the

piping was not going into the sump. On occasion, the worker would

decon a piece of pipe with multiple pipes coming off in different

directions. When this pipe was deconned using the high pressure

lance, water would go in the direction of the pipe openings,

sometimes in all directions. The inspector exited containment to

review the RWP that controlled the work. RWP 3389, Revision 0,

dated June 24, 1992, required a pre-job briefing and protective

clothing for working in wet conditions. Radiation surveys of the

piping being deconned ranged as high as 30 R/hr before flushing,

cutting, and removal from the system. Immediately after the

10

Piping was cut out, radiation/contamination surveys ranged as high

as 10,000 mrem/hr gamma and 27,000 mrad beta. The inspector

reviewed the pre-job briefing as documented as Enclosure 5.1 of

HP/O/B/1000/ 73, ALARA Work Packages, dated August 1, 1992. All

personnel on the job were verified as having attended the pre-job

briefing; however, the ALARA considerations during the job stated

that a tent may be required to control the spray but did not

contain any special instructions other than that. The procedure

stated in a note to Step 5, in part, that all sections of the

piping reading greater than 100 mrem/hr should be taken to the

normal sump and deconned with a high pressure sprayer. Surveys of

deconned piping revealed that radiation levels had dropped

significantly, indicating that the extremely high levels of

radiation and contamination prior to decon were caused by loose

crud. The inspector noted that, although the methods to remove

the loose crud from the piping may have been appropriate, the

licensee's failure to adequately contain the crud and/or failure

to employ more restrictive radiological conditions led to poor

radiological work practices. The inspector informed the licensee

that the failure to use a containment as -suggested with ALARA work

packages and the lack of specific instructions on either the RWP

or ALARA Work Package to contain or control the crud was a poor

practice. Upon exiting the RCA, the inspector discussed the

operation and lack of controls with the RP Manager. The RP

Manager stated that this decon method had been used on Unit 1 and

not resulted in any problems.

He also stated that he thought all

piping had been deconned, but if not,,a method to contain the crud

would be utilized.

b.

Hot Particle Contaminations

The inspector noted by review of data and interviews with HPTs

that hot particle contaminations had been a problem during early

parts of the outage and were attributed to known failed fuel. A

total of 122 personnel contamination events (PCEs) occurred from

January 1, 1992, to August 1, 1992. Of these, 29 PCEs involving

hot particles had occurred since the start of the outage on

July 21, 1992, with two being particles on the skin and nine being

particles on clothing. Between August 1 and August 5, 1992,

sixteen PCEs occurred, five of which involved particles on the

skin.

Between August 5, 1992 and September 2, 1992, 88 additional

PCEs occurred. Eighteen of the last 37 were hot particles on the

skin. The inspector expressed concerns to the licensee and the

licensee noted the concerns and attributed the hot particles to

failed fuel.

The licensee stated that all fuel had been inspected

and as part of their new zero fuel defects program, there were no

known leakers in the core. At least eight leaking fuel assemblies

were replaced.

11

The licensee implemented a hot particle surveillance program after

August 6, 1992. The program contained the following guidance:

1.

Once-Through Steam Generator (OTSG) Work

a.

Worker should be surveyed with an open window R02-A

after breaking the plane of the manway with any part

of the body.

b.

Worker should be surveyed with an open window R02-A

after handling highly contaminated equipment inside

playpen (i.e., Probe driver, Roger equipment, hoses,

cables, etc.).

c.

Playpens should be surveyed with an open window R02-A

routinely or after significant work evolutions.

d.

Outside of playpens should be surveyed routinely with

an open window R02-A.

e.

Care should be taken handling plastic bags and plastic

anti-cs because of the static charge which attracts

the.hot particles. Don't forget to survey yourself

routinely.

2.

Breaching Primary Systems/Working with Open Primary Systems

a.

Routinely every hour, survey workers for hot particles

with an R02-A who are physically in contact with open

primary systems and/or laying on floor where systems

have been opened (i.e. CDH, valve work).

b.

Survey open systems, valves, piping, etc., for hot

particles prior to beginning work.

c.

Survey work areas where you know systems have been

opened prior to allowing workers to work there.

The inspector reviewed substantive evidence that the licensee was

taking a number of measures to both detect hot particles and

reduce exposure times. However, the inspector noted that the

problem was more significant than ever with some days having five

or six hot particle skin contaminations.

C.

Control of Radioactive Material

TS. 6.4.1 requires that the station be operated and maintained in

accordance with approved procedures.

0II

12

Oconee Radiation Protcction Manual Procedure (ORPMP) 5.1, Movement

of Radioactive Materials Within the Owner Controlled Area, dated

August 15, 1992, Step 3.1.2.1, requires -in

part that all

radioactive materials removed from the RCZ shall be labeled.

The inspector performed radiological surveys both inside and

outside the RCA. No discrepancies were noted outside the RCA,

however, a high volume portable air sampler outside of the Unit 2

HP office was found to have a reading of 10,000 ccpm and was not

labeled. HPTs were notified and immediately surveyed and properly

labeled the piece of equipment. During a tour of the primary

chemistry laboratory, Room 329 of the Auxiliary Building, the

inspector noted a tool box in the clean area of the laboratory.

The unlabeled tool box contained a screwdriver with levels of

radioactivity greater than 1,200 ccpm. HPTs were called and

confiscated the screwdriver providing proper controls as described

in ORPMP 5.1.

This is a repeat of a non-cited violation

documented by IR 92-06, dated March 6, 1992, when a contaminated

pair of needle nose pliers was found in the same tool box. Since

this was -a

repeat problem, the inspector informed the licensee

that the failure to control and label radioactive materials in

accordance with T.S. 6.4.1 and ORPMP 5.1 was an apparent violation

(50-269/92-17-02, 50-270/92-17-02, and 50-287/92-17-02). A tour

of the primary chemistry laboratory showed that radiological

controls were lax. Contamination was detected in many areas on

counter tops and on equipment that was not labeled or posted as a

contamination zone. For example, greater than 100,000 ccpm were

detected on equipment used to measure the pH of primary samples.

This equipment was not labeled or inside a controlled

contamination zone. Earlier in the year, the NRC found that a

contaminated lead brick that was being used as a laboratory door

stop had contaminated the floor. The inspector also noted that

there were no requirements posted for personnel to frisk after

completing work in a contaminated zone or when leaving the primary

chemistry laboratory. The licensee was informed that this was the

second example of apparent violation for failure to post

(50-269, 270, 287/92-17-01) (see Paragraph 6).

7.

Description of Events Surrounding an Unplanned Exposure (83524)

a.

Description of the Event

On August 14, 1992, the Resident Inspector notified the Region

about a potential overexposure that had occurred in July 1992. On

August 17,

1992, the licensee issued a Problem Investigation

Process Report #3-092-0347, Potential Technical Overexposure of an

Individual Based on a Thermoluminescent Dosimeter (TLD) Readout.

The beta (skin) exposure was reported as 10.002 rem, which

exceeded both the 10 CFR Part 20 limit of 7,500 mrem per quarter

and the Duke Power Company Administrative Skin Dose Limit of

6,000 mrem per quarter. Data from the licensee was subsequently

submitted to the Region concerning the dosimetric aspects of the

13

event.

However, some important radiological aspects did not reach

the Region for evaluation. The licensee's investigation showed

that a Radwaste Operator (RO)

and a Primary Chemist (PC)

had

anomalies on their TLDs for July and focused their investigation

on the overlay of a Unit 3 Deborating Demineralizer in the

auxiliary building on July 14,

1992.

The licensee assigned the

following doses based on their TLD analysis of the data and beta

correction factors. The RO's TLD read 4,959 mrads and 0 mrem

gamma,

and the PC's TLD read 653 mrad beta and 67 mrem gamma.

The

EDC system was implemented primarily to keep track of radiation

dose and maintain a record of a person's access on a RWP. It

showed that July 14,

1992, was the only time that month that the

RO and PC worked together, to add resin to a Unit 3 Deborating

Demineralizer.

TLDs were reviewed to determine if they had been physically

altered, surveyed to determine if contamination had occurred, and

other experiments were conducted to simulate the beta/gamma

component ratios of 50:1. Air samples conducted at the end of the

2-2.5 hour5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> overlay operation showed eight MPC with the primary

isotopes noble gasses (Krypton and Xenons).

Two HPTs provided

continuous radiological coverage during the job and stated that no

unusual incidents occurred.

Following the job, both individuals

alarmed the PCMs near the job location.

It was determined to be

noble gas after performing a manual frisk with an RM-14 and a

pancake probe.

The RO and PC went to their respective shops after

degassing in front of fan.

After-making a shift turnover, gate

house portal monitors alarmed on both individuals when the RO and

PC attempted to exit the site. They were subsequently released

based on a manual frisk with a RM-14 and pancake probe.

In each

case, HPTs performed the manual frisk and each individual was

determined to be less than 150 ccpm.

b.

Inspection of the Event

On September 1, 1992, after reviewing recent developments based on

the licensee's investigation, the Resident Inspector requested

assistance from the Region. Three Region-based inspectors

responded with the intent of verifying licensee data, root cause

determination, and corrective actions. In addition, the

inspectors were to review aspects of the licensee's program to

prevent a radiation exposure in excess of regulatory limits.

The licensee.provided the inspector with a,

tour of the Unit 3

areas frequented by ROs and PCs in the performance of their

duties. The inspector also interviewed the RO and both HPTs that

participated in overlaying the resin bed in the Unit 3 Deborating

Demineralizer.- The methods used to add resin to the resin bed

were discussed as well as radiological considerations, locations

of airborne and gas radiation monitors, and frisking stations.

14

Based on interviews with licensee personnel who participated in

the resin bed overlay and a review of data, the inspector found

that a number of radiological discrepancies occurred during the

operation. The PC was assisted by the RO since the operation was

physically taxing.

The PC was signed in on RWP 13, Revision 0,

Routine Primary Chemistry Sampling/Analysis (includes

transportation and preparation). The licensee determined that the

PC should have been signed in on RWP 12, Revision 0, Spent Resin

Operations (includes recirculation, sampling, and transfers).

The

RO was not signed in on any RWP at the time the overlay was

performed but subsequently signed in on RWP 12.

RWP 12 required

in the special instructions/precautions section, a pre-job

briefing to be performed.

The licensee was not able to show that

a pre-job briefing had been conducted since neither individual was

on the correct RWP.

This is identified in Paragraph 7.c. as an

apparent violation.

This meant that to determine where the ROs unplanned exposure

occurred, the licensee had to rely solely on the RO's memory to

reconstruct the RO's movements and whereabouts for the month of

July. The inspectors, as well as the licensee, reviewed data for

all personnel in the Radwaste and Primary Chemistry departments to

determine if the EDC system was utilized properly.

Several

individuals did not appear to utilize the system properly,

frequently enough (this included the RO).

However, the inspectors

determined that the majority of the department was checking in on

the EDC system at the start of their shift and checking out on the

EDC system at the end of the shift. The inspector found that two

things contributed to this: 1) the PC group had RWP 13 and the RO

group had RWP 31, Liquid Radwaste Operations, that were almost

always used to perform their required tasks; and 2) Station

Directive 3.3.1 dated November 20, 1991, Personnel Dose-Control,

was not clear on the requirement to use the EDC system on each

individual entry and exit.

While it was determined that July 14, 1992, was the only day that

the RO and PC worked together on a job with the potential for a

significant exposure, the licensee has not been able to state with

any assurance that the unplanned exposure occurred on this date.

As a result of the unusual beta' dosimetry values obtained on TLD

  1. 400011728 an investigation was performed by the licensee to

determine the most probable cause of the dose and the amount of

the dose.

The inspector independently reviewed the following documents and

conducted independent interviews and event walk through to

evaluate the licensee's final beta dose assignment:

Memorandum to File dated August 16, 1991, Beta Half Value

Layer Determination File No: OS-752-01; OS-752.05

15

Enclosure 5.7 of Procedure HP/O/B/1010/04 titled,

"Respiratory Evaluation" dated August 27,

1992

Memorandum to File dated August 25, 1992, Beta Half Value

Layer Determination File No: 05-752.01; OS-752.05

Memorandum to C. T. Yongue, dated August 31, 1992, TLD Beta

Correction Factor File OS-756.00

Radiation Protection Manual Section 6.6 titled, "Measurement

and Control of External Dose Due to Beta Radiation,"

revision September 8, 1989

Procedure HP/O/B/1008/03 titled,"Procedure. for

Thermoluminescent Dosimeter Quality Assurance Check,"

undated

Performance Summary Report for Third Quarter 1989 Through

Fourth Quarter 1990 by Atlan-Tech, Inc., dated April 1991

National Voluntary Laboratory Accreditation Program (NVLAP)

Current Certificates of Accreditation for ANSI-N13.11

Categories I, II, III, IV, V, VI, and VII

Undated Research Reported titled, "Development of Dose

Algorithms for Low and Intermediate Energy Photons-Using the

Teledyne Isotopes PB-3 Badge Case and CA-S04:

DY Personnel

Dosimetry by E. A. Ballinger"

Computer program Listing for Calculating Personnel Gamma and

Beta Dose Equations written September 29, 1981 with

subsequent revisions including October 18, 1991

Report titled, "Oconee Nuclear Station Units 1, 2, 3, Docket

Nos. 50-269, 270, 287, Unusual Beta Radiation Exposure,"

dated September 30, 1992.

On August 12, 1992, the Oconee Nuclear Station RP staff was

notified of an unusually high beta exposure as read on the above

mentioned TLD badge from the July monitoring period.

The

individual who had been assigned that badge (TLD #400011728) for

July is an Oconee Nuclear Station employee in the Rad Waste

Section of the chemistry group. As part of the investigative

process, the individuals involved were interviewed and various

station documents, records, and logs were reviewed.

Beta dose is determined by the licensee using an in-house TLD

processing facility. As part of this process, the value seen on

the badge that is determined to be from beta radiation is a

fraction of the actual beta dose. To arrive at the actual beta

value, the initial output of the badge, that is determined to be

S

due from beta radiation, must be multiplied by a correction

16

factor. The correction factor is determined from the beta half

value layer (HVL).

The HVL is a density thickness measurement of

the amount of material necessary to reduce a beta dose rate by

one-half. By procedure this measurement is made at the beginning

of each major outage and may vary from one :unit to another and one

fuel cycle to another.

The current beta c6rrection factor used in

processing Oconee's TLDs is 4.8 (a conservative value) and based

on a HVL of 16 mg/cm2 measured from Unit 1 beta activity. A

previous HVL for Unit 3, measured in March of 1991, was 25 mg/cm 2.

The latest value measured for Unit 3, following an extended period

of operation with failed fuel, was determined to be 57 mg/cm

The corresponding correction factor as determined by procedure for

that HVL is 2.38.

The licensee investigation process revealed that tasks performed

by the individual in question, during July, limited their work

locations to the Unit 3 area of the plant and in particular the

Rad Waste Facility. One specific task places the individual in

question working with a Chemistry technician who also received a

beta dose for the month of July.

This beta dose was above the

normal range for Oconee Nuclear Station personnel, although many

times lower than the Rad Waste Technician.

The licensee

established various test conditions to determine if the high beta

to gamma ratio observed on the individual's TLD badge could be

reproduced. These tests revealed that radiation sources

originating from Unit 3 could produce such ratios.

Based on the interviews with the individuals involved, historical

data and TLD testing, the licensee has concluded that the most

probable cause of this beta exposure resulted from a hot particle

or a very small, localized area of surface contamination from

Unit 3.

Based on the licensee's investigations a determination was made

that the beta dose most likely resulted from a hot particle or a

very small, localized area of surface contamination from Unit 3

and the fact that the beta energies for Unit 3 were elevated due

to the presence of failed fuel from January 1992 through the end

of the cycle in July 1992.

The licensee has therefore applied a

beta correction factor of 2.38 to determine a record skin dose of

4.959 Rad to be assigned to the individual.

This correction

factor (2.38) was based on the most current HVL for Unit 3 and was

felt to be more accurate than the previously measured Unit 3 HVL

from March 1991 which does not reflect the activity in the reactor

coolant as a result of the failed fuel.

The inspector, after a review of the supporting data and after an

independent assessment of the event, believes the 4.959 Rad skin,

dose assignment is plausible and technically supportable.

Therefore, there was no regulatory overexposure nor was there an

administrative overexposure.

17

The inspector was concerned as to what extent plant personnel were

not using the EDC system.

A subsequent review of the EDC system

records showed that the RO routinely did not use the dose/RWP

tracking system.

This was identified as an apparent violation in

Paragraph 7.c. The inspector expanded the review of EDC system

records to the Chemistry department which includes radwaste and

primary/secondary chemistry. The review showed that the majority

of the chemistry department checked in on the EDC system at the

beginning of their shift and out at the end of their shift. These

actions would not support the tracking of a person in performing

their duties or maintaining a "real time" record of their dose.

Another contributing factor in not being able to track Radwaste or

Chemistry personnel easily in performing their duties was that

Radwaste primarily used one RWP (#31) and 'Chemistry another (#13)

for the majority of their duties. The inspector reviewed the

controlling procedure for the EDC System Station Directive 3.3.1,

dated November 20, 1991, and found that the procedure was not

clear on whether to use the EDC system on each individual entry

and exit. The inspector concluded that the procedure did not

require or specify EDC system usage necessary to maintain either

real time dose tracking or access on RWPs for jobs. The procedure

was determined to be inadequate and was characterized as an

apparent violation in Paragraph 7.c. As part of the concern about

EDC system usage, the inspector compared monthly thermoluminescent

(TLD) results with monthly pocket dosimeter (PD) doses accumulated

by the EDC system. The intent of the comparison was to identify

individuals whose TLD dose exceeded the PD dose entered in the EDC

system, indicating that the individual may not have been properly

using the EDC system. The inspector noted that the licensee

generallymaintained a 0.6 to 0.7 TLD-to-PD ratio. Also, on

average, only 2-4 individuals per month were indicated to have TL

eand

PD doses that did not correlate within an acceptable range.

Those that were identified were investigated as required.

However, the inspector also noted that PD doses were allowed to

differ by as much as -45% to +70% of the TLD dose before the dose

was isolated and "flagged" for investigation. For example, with a

TLD reading of 100 millirem (mrem), the EDC system could indicate

55-170 mrem for the same time period without a "flag."

Likewise,

for a TLD reading of 2000 mrem, the allowable PD dose was 1900

2500 mrem. In addition, the inspector noted that an individual

could receive 50 mrem per month on a TLD and never have-signed in

on the EDC system because the lower PD dose limit for that TLD

dose was 0 mrem. The inspector informed the licensee that the

wide PD dose ranges limited the usefulness of the system,

especially at the "lower" end of TLD doses. The licensee

indicated that- the ranges were appropriate and did not perceive a

problem with the correlation methods or the EDC system as a whole.

The inspector reviewed licensee procedure.HP/D/B/1000/04,

Change 24, dated December 17, 1991, Issuance, Revision, and

Termination of Radiation Work Permits and Standing Radiation Work

Permits, partly due to a concern that related to the overlay of

18

resin in the Unit 3 Deborating Deminerzlizer; specifically, why

was this operation not performed on a special rather than a

standing RWP. Upon review of the procedure, the inspector found

that the only criteria for requiring a RWP was that the task was

expected to exceed one. person-rem.

The inspector noted that the

overlay of resin in the potentially spent Unit 3 Deborating

Demineralizer was performed on a standing- RWP and that there were

no instructions in the procedure to direct when a special RWP

would be used. In fact, there were no directions in the procedure

for differentiating a special RWP from a standing RWP.

The

inspector found other shortcomings in the procedure and discussed

these observations with licensee management.who agreed to consider

any necessary changes.

The inspector also reviewed the licensee's !instrumentation and

equipment program.

The following procedures were reviewed and

appeared adequate:

HP/O/B/1003/1 6, Procedure for Calibration of Automated

Personnel Monitors, dated January 14,' 1992

HP/O/B/1003/ 22, Calibration Procedure for the Automated

Laundry Frisker, dated June 7, 1988;

HP/O/B/1004/58, Procedure for Calibration of Portable

Instrumentation, dated July 27, 1992. The inspector also

reviewed the licensee's area monitoring system and discussed

its current and future uses. The licensee's equipment

appeared to effectively meet their needs and was maintained

as required.

The inspector discussed the licensee's use of frisking devices for

site release purposes upon receiving portal monitor alarms.

Licensee procedure HP/O/B/1005/11, Response to Personnel and

Clothing Contaminations, allowed-for the use of friskers to clear

individuals for release once they had alarmed the portal monitors.

However, based on discussions with licensee personnel, it appeared

that frisking devices (i.e. RM-14 with pancake probe) were less

sensitive overall than the gatehouse portal monitors that act as

the licensee's "last defense" against unauthorized radioactive

material leaving the site.

In addition, the same procedure:

(1)

recommended that a multi-channel analyzer (MCA) be utilized

when noble gas was suspected to be causing the alarm to verify and

quantify the radioisotope; and (2)

did not require any

documentation of events believed to be noble gas-related.

According to the licensee, due to the relatively high numbers of

apparent noble gas contaminations, an MCA was not routinely

utilized nor were the events documented.

19

c.

Regulatory Implications

TSs 6.4.1 and 6.4.1.g requires that the station shall be operated

and maintained in accordance with approved procedures. Written

procedures with appropriate check-off list and instructions shall

be provided for personnel radiation protection procedures.

Oconee Nuclear Station Directive (ONSD) 3.3.1, Personnel Dose

Control, dated November 20, 1991, requires in Step 3.2, in part,

that work done in a radiation controlled zone or RCA shall be

performed under a SRWP or a RWP.

Contrary to the above, on July 14, 1992, an RO and PC performed

the resin overlay of the Unit 3 Deborating Demineralizer without

being signed on the correct RWP or SRWP. The licensee was

informed that this was an apparent violation of ONSD 3.3.1 and

TS 6.4.1 (50-269, 270, 287/92-17-03).

Duke .Power Company, Oconee Nuclear Station Procedure (ONSP)

HP/0/B/1000/0 4, Issuance, Revision, and Termination of Radiation

Work Permits, and Standing Radiation Work Permits, Change 24,

dated December 17, 1991, is inadequate in that the procedure is

not specific as to when a RWP or a SRWP is needed. The procedure

does not differentiate in criteria for the two. In addition,

field personnel may make changes to the SRWP without

authorizations from supervision and the procedure does not

adequately define what is meant by continuous coverage or

intermittent coverage. This issue was discussed with the licensee

at the exit interview.

ONSD 3.3.1 in Step 3.7 requires that the EDC system shall be used,

when in operation, by individuals to record the pocket dosimeter

dose he/she received for entry or work done under each RWP or

SRWP.

Thorough investigations into the July 14, 1992, job revealed that

two individuals in the Radwaste Chemistry department did not

routinely use the EDC system which is contrary to the above

requirement. This issue was also discussed with the licensee.

The licensee indicated that appropriate changes would be

considered for both issues.

8.

Information Notices (92701)

The inspector determined that the following Information Notices (INs)

had been received by the licensee, reviewed for applicability,

distributed to appropriate personnel, and that action, as appropriate,

was taken or scheduled.

90-48: Enforcement Policy for Hot Particle Exposures

20

88-63, Supp.

1:

High Radiation Hazards from Irradiated Incore

Detectors and Cables

91-36: Nuclear Plant Staff Working Hours

91-37: Compressed Gas Cylinder Missile Hazard

91-39: Compliance with 10 CFR Part 21,

"Reporting of Defects and

Noncompliance"

88-63, Supplement 2:

High Radiation Hazards from Irradiated

Incore Detectors and Cables

91-60: False Alarms of Alarm Ratemeters Because of Radiofrequency

- Interference

91-76:

10 CFR Part 21 and 50.55(e) Final Rules

92-25:

Potential Weakness in Licensee Procedures for Loss of

Refueling Cavity Water

92-30: Falsification of Plant Records

92-37:

Implementation of the Deliberate Misconduct Rule

9. Exit Meetings

a.

August 6, 1992

The inspector met with licensee representatives denoted with a (*)

in Paragraph 1 on August 6, 1992. The inspector discussed the

examples of inadequate posting of radiation controlled zones as an

apparent violation.

As well, the failure to control radiological

operations adequately during cavity drain line piping

decontamination was also discussed.

The inspector also discussed

the increase in hot particle skin contaminations.

The inspector

did not receive any proprietary material or dissenting comments.

Item Number

Description or Reference

50-269, 270, 287/92-17-01

VIO - Two examples of failure to

adequately post RCZs

(Paragraph 6.a).

50-269, 270, 287/92-17-02

VIO - Failure to label Radioactive

Material (Paragraph 6.c).

b.

September 9, 1992

As the result of an unplanned personnel exposure, a second

inspection was conducted. The inspector met with licensee

representatives denoted with a (+)

on September 9, 1992. The item

21

listed below is characterized as an apparent violation of NRC and

TS requirements. Since the licensee investigation was not

complete, the inspector requested a copy upon completion. The

inspector did not receive any proprietary material nor dissenting

comments.

Item Number

Description or Reference

50-269, 270, 287/92-17-03

VIO - Primary Chemist and Radwaste

Operator failed to access a RWP

(Paragraph 7.c).

On October 6, 1992, the inspector received a copy of the completed

licensee investigation. On October 30, 1992, Messrs A. Herdt,

W. Rankin, P. Skinner, and R. Shortridge of the NRC contacted

J. Hampton, D. Sweigart, C. Yongue, M. Patrick and S. Perry at

Oconee Nuclear Station via telephone and discussed the likely

characterization of the inspection report findings.