ML16123A331

From kanterella
Jump to navigation Jump to search
Post-Approval Site Inspection for License Renewal Report 05000346/2016007, March 28, 2016 � April 8, 2016
ML16123A331
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 05/02/2016
From: Dave Hills
NRC/RGN-III/DRS/EB1
To: Boles B
FirstEnergy Nuclear Operating Co
References
IR 2016007
Download: ML16123A331 (12)


See also: IR 05000346/2016007

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, IL 60532-4352

May 2, 2016

Mr. Brian D. Boles

Site Vice President

FirstEnergy Nuclear Operating Co.

Davis-Besse Nuclear Power Station

5501 N. State Rte. 2, Mail Stop A-DB-3080

Oak Harbor, OH 43449-9760

SUBJECT: DAVIS-BESSE NUCLEAR POWER STATION - POST-APPROVAL SITE

INSPECTION FOR LICENSE RENEWAL REPORT 05000346/2016007

Dear Mr. Boles:

On April 8, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed the outage

segment of the Post-Approval Site Inspection for License Renewal at your Davis-Besse Nuclear

Power Station. The enclosed report documents the results of this inspection, which were

discussed on April 8, 2016, with Mr. B. Kremer and other members of your staff.

This inspection was an examination of activities conducted under your renewed license as they

relate to the completion of commitments made during the renewed license application process

and compliance with the Commissions rules and regulations and the conditions of your

operating license. Within these areas, the inspection involved examination of selected

procedures and representative records, observations of activities, and interviews with

personnel. On the basis of the sample selected for review, there were no findings of

significance identified during this inspection.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public

Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy

of this letter, its enclosure, and your response (if any) will be available electronically for public

inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)

component of the NRC's Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html

(the Public Electronic Reading Room).

Sincerely,

/RA/

David E. Hills, Chief

Engineering Branch 1

Division of Reactor Safety

Docket No. 50-346

License No. NPF-3

Enclosure:

IR 05000346/2016007

cc w/encl: Distribution via LISTSERV

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket No:

50-346

License No:

NPF-3

Report No:

05000346/2016007

Licensee:

FirstEnergy Nuclear Operating Company

Facility:

Davis-Besse Nuclear Power Station

Location:

Oak Harbor, OH

Dates:

March 28 - April 8, 2016

Inspectors:

S. Sheldon, Senior Reactor Engineer (Lead)

T. Bilik, Senior Reactor Engineer

Approved by:

D. Hills, Chief

Engineering Branch 1

Division of Reactor Safety

2

SUMMARY

Inspection Report 05000346/2016007, 03/28/2016 - 04/08/2016; Davis-Besse Nuclear Power

Station; Post-Approval Site Inspection for License

The inspection was conducted by two regional based inspectors. No instances were noted

of incomplete license renewal commitments with respect to timeliness or adequacy. No

findings were identified by the inspectors. The significance of inspection findings is indicated

by their color (i.e., greater than Green, or Green, White, Yellow, Red) and determined using

Inspection Manual Chapter 0609, "Significance Determination Process," dated April 29, 2015.

Cross-cutting aspects are determined using Inspection Manual Chapter 0310, "Aspects Within

the Cross-Cutting Areas," dated December 4, 2014. All violations of U.S. Nuclear Regulatory

Commission (NRC) requirements are dispositioned in accordance with the NRCs Enforcement

Policy, dated February 4, 2015. The NRC's program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process,"

dated February 2014.

No findings were identified.

3

REPORT DETAILS

Summary of Plant Status

The unit was in a refueling outage during the period of this inspection.

4.

OTHER ACTIVITIES

4OA5 Other Activities

.1

Post-Approval Site Inspection for License Renewal (Phase I) - Inspection

Procedure 71003

a.

Inspection Scope

(1) Review of Newly Identified Systems, Structures and Components

The inspectors discussed the identification of new systems, structures, and components,

under the purview of Title 10 of the Code of Federal Regulations (CFR), Part 54.37(b),

with the licensees license renewal staff. The licensee personnel indicated that no new

components have been identified to date that should have been within the scope of the

License Renewal Program.

(2) Review of Revised Commitments

Based on discussion the inspectors had with licensee staff, at the time of the inspection

there were no revised commitments.

(3) Review of Commitments

The inspectors reviewed supporting documents including completed surveillance

records, conducted interviews, observed non-destructive examination activities,

performed visual inspection of structures and components, including those not

accessible during power operation, and observed the activities described below

that the licensee completed to comply with the license conditions associated with

the renewed operating license. The inspectors verified the licensee implemented

the outage-related Aging Management Programs included in, Safety Evaluation

Report Related to the License Renewal of Davis-Besse Nuclear Power Station,

dated September 2013 (ML13248A267) in accordance with 10 CFR Part 54,

Requirements for the Renewal of Operating Licenses for Nuclear Power Plants.

b.

Findings and Observations

The inspectors reviewed portions of the activities listed below, which are referenced

to the Aging Management Programs from the licensees License Renewal Application

(LRA) and the commitments noted in Appendix A of the Safety Evaluation Report where

applicable. Activities observed related to these commitments are also listed.

(1) (B.2.8) Closed Cooling Water Chemistry Program (Commitment Item 32)

The Closed Cooling Water Chemistry Program is intended to mitigate damage due to

loss of material, cracking, and reduction in heat transfer of components that are within

the scope of license renewal and contain closed cooling water. The program manages

4

the relevant conditions that could lead to the onset and propagation of a loss of material,

cracking, or reduction in heat transfer through proper monitoring and control of corrosion

inhibitor concentrations consistent with the current Electric Power Research Institute

water chemistry guideline.

Commitment item 32 states the licensee will make the following enhancements to the

Closed Cooling Water Chemistry Program prior to October 22, 2016:

Document the results of periodic inspections of opportunity, performed when

components are opened for maintenance, repair, or surveillance;

Ensure that a representative sample of piping and components will be inspected on

a 10-year interval, with the first inspection taking place prior to entering the period of

extended operation; and

Ensure that component cooling water radiochemistry is sampled on a weekly interval

to verify the integrity of the letdown coolers and seal return coolers.

The inspectors reviewed records from a sample of completed inspections. Specific

records are listed in the list of documents reviewed. The inspectors identified no

concerns with these inspections.

The inspectors also observed the licensee perform a visual examination (VT-1,

direct/remote using video probe) of CC-150 valve and adjacent piping, for component

cooling water to decay heat pump 2 alternate source, per Work Order (WO) 200638210.

The inspectors had no concerns with the observed activities.

(2) (B.2.23) Inservice Inspection Program - IWF (Commitment Item 50)

The Inservice Inspection (ISI) Program - IWF establishes responsibilities and

requirements for conducting American Society of Mechanical Engineers (ASME)

Code Section XI, Subsection IWF inspections as required by 10 CFR 50.55a. The

ISI Program - IWF includes visual examination for supports based on sampling of the

total support population. The sample size varies depending on the ASME class.

Commitment item 50 states the licensee will make numerous enhancements to the

ISI Program - IWF prior to October 22, 2016.

The inspectors observed the licensee perform VT-3 direct visual examinations of

DG-JKY WTR HTXCHR-1-1-AW, diesel generator jacket water heat exchanger E10-1

supports, per WO 2000616036. One of the examiners failed to properly perform the

ASME Code required illumination verification check. The exams were concurrently

performed by another examiner who found no recordable indications. The licensee

captured this issue in CR-2016-04439. Except for the minor issue noted, the inspectors

had no concerns with the observed activities.

5

(3) (B.2.24) Inservice Inspection Program

The ISI Program manages cracking of reactor coolant pressure boundary components

and once-through steam generator secondary side components. The program includes

periodic visual, surface, or volumetric examination and leakage (pressure) testing of

ASME Class 1, 2, or 3 components, and their integral attachments, as well as repair,

modification, or replacement of same.

The inspectors observed ultrasonic examination of reactor coolant pump cover to case

studs, RC-RCP-1-1-1-STUDS; per WO 200616040, and RC-30-CCA-8-1-SWB through E,

per WO 200629210. The inspectors also observed dye penetrant examinations of reactor

coolant system (RCS) pipe-to-elbow weld, RC-CCA-23-S-CV030, per WO 20061038, and

RCS pipe-to-elbow weld, RC-MK-A-93-SW51, per WO 200616038. The inspectors had

no concerns with the observed activities.

(4) (B.2.28) Nickel-Alloy Management Program (Commitment Item 49)

The Nickel-Alloy Management Program manages primary water stress corrosion

cracking and stress corrosion cracking/intergranular attack for nickel-alloy pressure

boundary components, other than reactor vessel closure head nozzles and steam

generator tubes, exposed to reactor coolant. Mitigative actions include replacement

of Alloy 600/82/182 components with materials known to be less susceptible to primary

water stress corrosion cracking and stress corrosion cracking/intergranular or repair of

those components through weld overlay, weld inlay (also known as weld underlay),

mechanical stress improvement process or surface conditioning. The condition

monitoring portion of the program uses a number of inspection techniques to detect

cracking, including volumetric and bare metal visual examinations.

Commitment item 49 states the licensee will enhance the Nickel-Alloy Management

Program to:

Provide for inspection of dissimilar metal butt welds in accordance with the

requirements of ASME Code Case N-770-1, Alternative Examination Requirements

and Acceptance Standards for Class 1 PWR [Power Water Reactor] Piping and

Vessel Nozzle Butt Welds fabricated with UNS N06082 or UNS W86182 Weld Filler

Material With or Without Application of Listed Mitigation Activities,Section XI,

Division 1, as modified by the 10 CFR 50.55a(g)(6)(ii)(F).

The inspectors observed a manual phased array ultrasonic examination of a RCS

10 branch connection-to-pipe overlay, per WO 200616038. The inspectors had no

concerns with the observed activities.

(5) (B.2.30) One-Time Inspection Program (Commitment Item 13)

The One-Time Inspection Program is a new program that is intended to provide

assurance that aging which has not yet manifested itself is indeed not occurring, or

that the age-related degradation is so insignificant that an Aging Management Program

is not warranted.

6

The inspectors observed the licensees activities to implement Commitment Item 13, of

the license renewal Safety Evaluation Report. This commitment documents the licensee

will implement the One-Time Inspection Program, as described in LRA Section B.2.30,

prior to October 22, 2016.

The inspectors observed the licensee perform a visual examination of MS891A Steam

Generator 2 Drain Line valve per WO 200635583, MS109A, MS109B Main Steam

System Pressure Indicator Valves per WO 200631009, the fuel transfer tube 2 isolation

valve per WO 200636246, and the FW145 Steam Generator 1 Feedwater Header Vent

per WO 200639572. The inspectors had no concerns with the observed activities. The

inspectors reviewed a sample of completed inspections. Specific records are listed in

the list of documents reviewed.

The licensee stated that overall results will be evaluated once all of the inspections

have been completed. This evaluation should be reviewed during the 71003 Phase II

inspection.

(6) (B.2.31) Open-Cycle Cooling Water Program

The Open-Cycle Cooling Water Program manages loss of material due to crevice,

galvanic, general, pitting, and microbiologically-influenced corrosion, and also due to

erosion for components located in the Service Water (SW) System, and for components

connected to or cooled by the SW System, and also in the Circulating Water System.

The program also manages fouling due to particulates (e.g., corrosion products) and

biological material (micro- and macro-organisms) resulting in reduction in heat transfer

for heat exchangers within the scope of the program. The program includes of

inspections, surveillances, and testing to detect and evaluate fouling, loss of material,

combined with chemical treatments and cleaning activities to minimize fouling and loss

of material.

The inspectors observed visual inspection of the SW cross tie to auxiliary feedwater per

WO 200606738 including records of as found condition and direct observation of as left

condition. During a direct visual inspection, an NRC inspector observed a section of

pipe that still had a thick layer of silt and tubercles. The inspector conveyed this

observation to the licensee, and in response, the licensee initiated CR 2016-04754,

SW261 Clean/Inspect piping - NRC inspectors post cleaning piping walkdown

observed that the SW piping segment had not yet been cleaned. The licensee

subsequently cleaned the pipe before reassembly. Except for the work in progress

issue noted, the inspectors had no concerns with the observed activities.

(7) (B.2.37) Small Bore Class 1 Piping Inspection (Commitment Item 19)

The Small Bore Class 1 Piping Inspection is intended to detect and characterize

cracking of small bore ASME Code Class 1 piping less than 4 inches nominal pipe size

(NPS 4), which includes pipe, fittings, and branch connections. The inspection will

consist of volumetric examination of a representative sample of small bore piping

locations that are susceptible to cracking. The inspection sample includes both socket

welds and butt welds.

Commitment item 19 states the licensee will implement the Small Bore Class 1 Piping

Inspection, as described in LRA Section B.2.37, prior to October 22, 2016.

7

The inspectors observed phased array volumetric inspections of 1 elbow-to-pipe RC

welds RC-FSK-M-CCA-19-1-24a and RC-FSK-M-CCA-19-1-29, and pipe-to-elbow weld

RC-FSK-M-CCA-19-1-23a, per WO 200629207.

The inspectors had no concerns with the observed activities.

(8) B.2.39 Structures Monitoring Program (Commitment Item 20)

The Structures Monitoring Program is part of the Maintenance Rule Program. It is

an existing program that is designed to ensure age-related degradation of the plant

structures and structural components within its scope are managed such that each

structure and structural component retains the ability to perform its intended function.

The program includes period inspections of structures.

Commitment item 20 states the licensee will make numerous enhancements to the

Structures Monitoring Program prior to October 22, 2016.

The inspectors observed visual inspection of the auxiliary building, 643 elevation

main steam pipe rooms 601 and 602 in accordance with EN-DP-01511, Structures

Monitoring. The inspectors had no concerns with the observed activities.

(9) Service Level III Coatings and Linings Monitoring Program (Commitment Item 51)

The Service Level III Coatings and Linings Monitoring Program is a plant-specific

condition monitoring program for Davis-Besse. The program consists of periodic visual

inspections of all Service Level III coatings and linings on the internal surfaces of piping,

piping components, and tanks in mechanical fluid systems that are within the scope of

license renewal. The program includes organic (e.g., elastomeric or polymeric) and

inorganic (e.g., zinc-based) coatings and linings (e.g., rubber, cementitious).

The program is intended to manage loss of coating integrity due to blistering, cracking,

flaking, peeling, delamination, or physical damage of coatings and linings to ensure

that degradation does not result in loss of intended function due to unanticipated or

accelerated corrosion or flow blockage of in-scope mechanical components.

Commitment item 32 states the licensee will implement the Service Level III Coatings

and Linings Monitoring Program prior to October 22, 2016.

The inspectors observed visual inspection of the SW60 containment air cooler service

water header cross connect butterfly valve (WO 200423706). The inspectors had no

concerns with the observed activities.

4OA6 Management Meetings

.1

Exit Meeting Summary

April 8, 2016 the inspectors presented the inspection results to Mr. B. Kremer and

other members of your staff. The licensee acknowledged the issues presented.

The inspectors confirmed that none of the potential report input discussed was

considered proprietary.

ATTACHMENT: SUPPLEMENTAL INFORMATION

Attachment

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

B. Boles, Site Vice President

D. Saltz, Plant Manager

K. Zellers, License Renewal Project Manager

S. Dort, Aging Management Coordinator

G. Clark, License Renewal

C. Daft, License Renewal

D. Munson, License Renewal

A. Scheanwald, ISI Program Owner

G. Wolf, Regulatory Affairs

LIST OF ITEMS OPENED, CLOSED AND DISCUSSED

Opened, Closed and Discussed

None

LIST OF ACRONYMS USED

ADAMS

Agencywide Documents Access and Management System

ASME

American Society of Mechanical Engineers

CFR

Code of Federal Regulations

ISI

Inservice Inspection

LRA

License Renewal Application

NRC

U.S. Nuclear Regulatory Commission

PARS

Publicly Available Records System

RCS

Reactor Coolant System

SW

Service Water

WO

Work Order

2

LIST OF DOCUMENTS REVIEWED

The following is a partial list of documents reviewed during the inspection. Inclusion on this list

does not imply that the NRC inspector reviewed the documents in their entirety, but rather that

selected sections or portions of the documents were evaluated as part of the overall inspection

effort. Inclusion of a document on this list does not imply NRC acceptance of the document or

any part of it, unless this is stated in the body of the inspection report.

Condition Reports Initiated During the Inspection

- CR 2016-04754; SW261 Clean/Inspect piping - NRC inspectors post cleaning piping

walkdown observed that the SW piping segment had not yet been cleaned; dated 04/06/16

- CR-2016-04439; NRC Observation of Visual Examination Acuity Verification; dated 04/02/16

Completed Work Orders and Inspections

- 200499963; Auxiliary Building Room 601 4" Floor Drain (TDF-4-1) A-2356 (601F-95);

dated 05/06/15

- 200542646; SBO DG Primary Fuel Filter; dated 02/16/15

- 200630441; MDFP Lube Oil Filter Housing; dated 09/09/15

- 200631602; Boric Acid Evaporator 1 Outlet To Condensate Tank Steam Trap Body;

dated 12/02/15

- BOP-VT-15-115; E144-2 (Post-Accident Sample Cooler 1-2); dated 08/18/15

- BOP-VT-15-177; SH289 & HX Tubing (Radwaste Heating Coil Inlet Isolation); dated 09/30/15

- BOP-VT-15-201; P95, SH326 (Secondary Hot Water Fuel Handling Pump); dated 10/08/15

- BOP-VT-15-220; Emergency Diesel Generator 1-2 Lube Oil Heat Exchanger; dated 11/09/15

- BOP-VT-15-227; FE1476 (DG Jacket Cooling Water HX 2 CC Outlet Flow Element);

dated 11/10/15

- BOP-VT-15-256; AC302 Computer Room AC Inlet Valve; dated 12/07/15

- BOP-VT-16-031; CC496A (Reactor Coolant Pump 2-2 Pump Seal CCW Return Line Vent);

dated 03/31/16

- BOP-VT-16-032; CC496 (Reactor Coolant Pump 2-2 Pump Seal CCW Return Line Vent);

dated 03/31/16

- BOP-VT-16-033; CC494 (Reactor Coolant Pump 2-2 Pump Seal CCW Supply Line Drain);

dated 03/31/16

- BOP-VT-16-034; CC494A (Reactor Coolant Pump 2-2 Pump Seal CCW Supply Line Drain);

dated 03/31/16

- SW256-2016; DB-SW256; dated 03/30/16

- SW60-2016; DB-SW60; dated 03/31/16

- BOP-VT-16-059; FW145 SG 1 Feedwater Header Vent; dated 04/04/16

- BOP-UT-16-019; SW261; dated 04/07/16

- BOP-VT-16-043; Fuel Transfer Tube 2 Isolation Valve; dated 04/01/16

Miscellaneous

- DBRM-ER-0001; One-Time Inspection Program Components; Rev. 00

- Structures Monitoring Inspection Worksheet; auxiliary building, 643 elevation, rooms 601 and

602; dated 04/07/16

- ACI 349.3R-02; Evaluation of Existing Nuclear Safety-Related Concrete Structures

3

Observed Inspections

- WO 200635583; MS891A Steam Generator 2 Drain Line; dated 03/30/16

- WO 200631009; MS109A, MS109B Main Steam System Pressure Indicator Valves;

dated 03/30/16

- WO 200423706; SW60 Containment Air Cooler Service Water Cross Connect Valve;

dated 03/31/16

- WO 200636246; Fuel Transfer Tube 2 Isolation Valve; dated 04/01/16

- WO 200639572; FW145 SG 1 Feedwater Header Vent; dated 04/04/16

- WO 200606738; Service Water Cross Tie to AFW; dated 04/05/16

Procedures

- 54-ISI-369-003; VT-1, VT-3, General and Detailed Visual Examinations; Rev. 3

- 54-ISI-615-001; Procedure for Manual and Semi-Automated Phased Array Ultrasonic

Examination of Socket Fillet Welds; Rev. 1

- 54-ISI-864-003; Manual Phased Array Ultrasonic Examination of Weld Overlaid Similar and

Dissimilar Metal Welds; Rev. 3

- 54-ISI-864-005; Manual Phased Array Procedure for Weld Overlaid Similar and Dissimilar

Metal Welds; Rev. 5

- EN-DP-01511; Structures Monitoring; Rev. 04

- EN-DP-01515; Service Level III Coatings and Linings Condition Assessment Inspection;

Rev. 00

- NA-QC-05560; Visual Examination Procedure for VT-1, VT-3, and General Visual

Examinations; Rev. 11

- NG-EN-00551; Service Level III Coatings and Linings Monitoring Program; Rev. 00

- NG-EN-00552; One-Time Inspection Program; Rev. 00

- NOP-ER-2006; Service Water Reliability Management Program; Rev. 02

- Program Basis Documents

- LRPD-05 Att 2.16; Service Level III Coatings and Linings Monitoring Program; Rev. 1

- LRPD-05 Att 2.11; One-Time Inspection Program; Rev. 7

- LRPD-05 Att 2.6b; Closed Cooling Water Chemistry Program; Rev. 4

- LRPD-05 Att 2.12; Open-Cycle Cooling Water Program; Rev. 3

Mr. Brian D. Boles

Site Vice President

FirstEnergy Nuclear Operating Co.

Davis-Besse Nuclear Power Station

5501 N. State Rte. 2, Mail Stop A-DB-3080

Oak Harbor, OH 43449-9760

SUBJECT: DAVIS-BESSE NUCLEAR POWER STATION - POST-APPROVAL SITE INSPECTION FOR

LICENSE RENEWAL REPORT 05000346/2016007

Dear Mr. Boles:

On April 8, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed the outage segment of the

Post-Approval Site Inspection for License Renewal at your Davis-Besse Nuclear Power Station. The

enclosed report documents the results of this inspection, which were discussed on April 8, 2016, with Mr.

B. Kremer and other members of your staff.

This inspection was an examination of activities conducted under your renewed license as they relate to

the completion of commitments made during the renewed license application process and compliance

with the Commissions rules and regulations and the conditions of your operating license. Within these

areas, the inspection involved examination of selected procedures and representative records,

observations of activities, and interviews with personnel. On the basis of the sample selected for review,

there were no findings of significance identified during this inspection.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections,

Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the NRCs

Public Document Room or from the Publicly Available Records (PARS) component of the NRC's

Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the

NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

David E. Hills, Chief

Engineering Branch 1

Division of Reactor Safety

Docket No. 50-346

License No. NPF-3

Enclosure:

IR 05000346/2016007

cc w/encl: Distribution via LISTSERV

DISTRIBUTION:

Jeremy Bowen

RidsNrrDorlLpl3-2 Resource

RidsNrrPMDavisBesse Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Darrell Roberts

Richard Skokowski

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

Jim Clay

Carmen Olteanu

ROPreports.Resource@nrc.gov

ADAMS Accession Number ML16123A331

Publicly Available

Non-Publicly Available

Sensitive

Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE

RIII

RIII

RIII

RIII

NAME

SSheldon:cl

DHills

DATE

04/29/16

05/02/16

OFFICIAL RECORD COPY