L-2015-304, RAI Reply for the Application for Technical Specifications Changes to Remove Communications and Manipulator Crane Requirements and Relocate to Licensee-Controlled Documents

From kanterella
(Redirected from ML16005A146)
Jump to navigation Jump to search

RAI Reply for the Application for Technical Specifications Changes to Remove Communications and Manipulator Crane Requirements and Relocate to Licensee-Controlled Documents
ML16005A146
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 12/15/2015
From: Costanzo C
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
CAC MF5835, CAC MF5836, L-2015-304
Download: ML16005A146 (2)


Text

0December FPIL U. S. Nuclear Regulatory Commission 15, 2015 L-2015-304 10 CFR 50.90 Document Control Desk Washington, DC 20555-0001

Subject:

St. Lucie Units 1 and 2 Docket Nos. 50-335 and 50-389 RAI Reply for the Application for Technical Specifications Changes to Remove Communications and Manipulator Crane Requirements and Relocate to Licensee-Controlled Documents

References:

1. FPL Letter L-2015-030 dated March 10, 2015, "Application for Technical Specifications Changes to Remove Communications and Manipulator Crane Requirements and Relocate to Licensee-Controlled Documents," ADAMS Accession No. ML15084A141
2. NRC email dated November 4, 2015, "Request for Additional Information - St. Lucie Units 1 & 2 LAR of March 10, 2015 regarding Communications and Crane TS relocation

- CACs MF5835/MF5836," ADAMS Accession No. ML15313A548 In Reference 1 Florida Power & Light (FPL) submitted a Technical Specification (TS) license amendment request (LAR) that would relocate the TS LCOs associated with the refueling manipulator crane and communication requirements to licensee controlled documents.

Reference 2 the NRC requested additional information for their review of the LAR. The response to the RAI is contained in the attachment.

The no significant hazards consideration determination within Reference 1 bounds the scope of these changes. If you should have any questions, please contact Mr. Ken Frehafer at (772) 467-7748.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on December 5,* ,2015.

Sincerely, Christopher R. Costanzo Site Vice President St. Lucie Plant CRC/KWF Attachment cc: NRC Region II Administrator St. Lucie Plant NRC Senior Resident Inspector / )0 Florida Power &Ught Company 6501 S. Ocean Drive, Jensen Beach, FL 34957

L-2015-304 Attachment Page 1 of 1 RAI-MF5835/MF5836-APHB- 1:

In the License Amendment Request submitted on March 10, 2015 (ML15084A141), the licensee proposed deleting technical specifications relating to communications systems and the manipulator crane used during refueling operations. The application indicates that the FSAR and other administrative controls will be used to ensure that refueling communications and manipulator crane operations are conducted safely, however the LAR does not clearly identify what information will be put into the FSAR, procedures, or other administrative controls.

Please provide a description of the content to be relocated from the technical specifications to the FSAR/other administrative documents. Describe and justify any changes to aspects of the technical specifications that will be changed or deleted (if the content will be relocated in its entirety, please indicate this). Alternatively, you may provide marked up draft copies of the FSARladministrative controls/procedures that show how specific elements of the technical specifications will be controlled.

FPL Response:

FPL will relocate the existing TS LCOs and their associated actions without change into Chapter 13 of the St. Lucie Unit 1 and Unit 2 UFSARs, where configuration will be maintained consistent with the requirements of 10 CFR 50.59.